    Zion: The Gold Standard for Radiological Dose and Project Cost

    John Sauger‐EVP & Chief Nuclear Officer

    1

  • 2

    What is Decommissioning?

    2

    Which Plants/Sites Meet NRC License Termination Criteria?

    This is what a Decommissioning Cost Estimate is Designed to Produce

  • 3

    Is Your Decommissioning Project Successful?

    3

    PlantMW Output

    Decom Costs (2015 $)

    Price to Decommission/MWe 

    Installed ES Role in ProjectZion 2080 $989,000,000 $475,480.7710CFR50 Licensee. Total Decommissioning ScopeTrojan 1100 $740,500,000 $673,181.82Waste Characterization and DisposalMaine Yankee 900 $779,471,000 $866,078.89Site Characterization, Waste transport and DisposalCT Yankee 619 $1,432,862,000 $2,314,801.29Waste Transport & Disposal, Water Processing

    SONGS 2150 $4,500,000,000 $2,093,023.26Decommissioning General Contractor, Waste Transport & Disposal

    LCBWR 50 $124,383,000 $2,487,660.0010CFR50 Licensee. Total Decommissioning Except Spent Fuel

    Yankee Rowe 185 $950,077,000 $5,135,551.35Waste Transport & Disposal, Water ProcessingBig Rock Point 67 $609,049,000 $9,090,283.58

    Spent Fuel Canisters, Large Component Removal, Waste Disposal

    Humboldt Bay 63 $1,080,000,000 $17,142,857.14Waste Disposal

  • 4

    4

  • 5

    Subject to Confidentiality Statement on Front Cover 5

    EnergySolutions Perspective

    Only Non‐Utility Holding Multiple 10CFR50 Licenses Nearing Completion of Zion and Lacrosse Projects Execute Projects Using Multiple Models:

    ‒ License Stewardship‒ Decommissioning General Contractor (DGC)‒ Public/Private Management with IP Provided‒ “Teach Them to Fish”

    Fully Developed “Management Model” with Processes, Procedures, and Templates

  • 6

    Dose Leader

    6

    0

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    Person Rem/MWE

    Person Rem/MWE

  • 7

    Subject to Confidentiality Statement on Front Cover 7

    Lesson Learned #1Premise:Most projects built on a “rip and ship” approach that results in a shorter project schedule thereby reducing project costs as hotel loads are eliminated earlier.

    DCE’s for Zion and LCBWR were off by a factor of 2 for Radwaste Volumes. Managing multiple waste streams from source to disposal is challenging and can 

    result in contaminating “clean” waste streams. Higher volumes require an increase in transportation mobile assets.(Zion required 

    150 railcars in the disposal “loop” between the site and Clive) Waste stockpiles at generation site can result in land surface contamination below 

    piles ($ to remediate) Tracking waste from generation to “loaded for shipment” is problematic.

    Challenge: Decommissioning Cost Estimates prepared for Utilities have not been built using this model.

  • 8

    Subject to Confidentiality Statement on Front Cover 8

    Lesson Learned #1 (Continued)ES Risk Response: Actual field results for Zion were handled as follows: Turbine Building, intake structure, and miscellaneous “clean” buildings concrete were 

    demolished, reduced, and stockpiled away from rad buildings before any rad demo started.

    Entire aux building exterior/interior and containment interior were demolished, packaged, and shipped as Class A waste to Clive

    Containment concrete (exterior to liner) determined to be clean and demolished after all rad materials had been removed and Final Status Survey (FSS) completed

    Application of Lessons Learned: Changes to Management Model and Hardware as follows:

    All stockpile areas will have sacrificial asphalt paving installed Estimating methods being refined to include Lidar and Building Information 

    Management (BIM) systems for comprehensive volume determination and sequence planning.

    RADMAN software being upgraded to automate manifest generation SMART railcar system plan under development to include GPS location, accelerometer, 

    and moisture detection for fleet.

  • 9

    Subject to Confidentiality Statement on Front Cover 9

    Lesson Learned #2Premise: Current practice for removal of large bore stainless steel piping systems utilizes thermal cutting (typically petrogen torches) resulting in the generation of hexavalent chromium gas

    Using Petrogen torches requires the worker to sit in the pipe being cut while it is being cut. Source term in pipes results in rad exposure to the workforce

    Generation of hexavalent chromium gas requires the use of fresh air hoods by workers and monthly physicals to monitor chromium in blood stream.

    Industrial gasses used in cutting process are flammable requiring enhanced safety measures in the management of bottles and hoses.

    Firewatches and the use of flame retardant blankets are required to prevent ignition of flammables in the are adjacent to and below cut zones

    Gases generated during cutting process prohibits the access of non protected workers into containment when cutting operations are in progress.

    Challenge: Develop a method that eliminates the generation of hexavalent chromium gas and reduce exposure to the work force.

  • 10

    Subject to Confidentiality Statement on Front Cover 10

    Lesson Learned #2 (Continued)ES Risk Response: Actual field results for Zion were handled as follows:

    Research & Development of an alternative cutting method was initiated before cutting was started on the second unit.

    Application of Lessons Learned: Changes to Management Model and Hardware as follows:

    Diamond Wire Saw application developed. Diamond Wire Saw technique sheets developed and included in decommissioning 

    management model for future projects.

    NOTEThe application of the Diamond Wire Saw resulted in an 80% reduction of dose received by the workforce in cutting large bore stainless steel piping.

  • 11

    Subject to Confidentiality Statement on Front Cover 11

    Lesson Learned #3Premise: Surgical Removal of components and systems in the Auxiliary Building will result in a shorter schedule to open air demo

    Significant amounts of manual labor were devoted to removing systems, structures, and components in the auxiliary building.

    Auxiliary building was worked from the basement up. FSS intended to leave aux building equipment and aux building floor drains behind  Auxiliary building was not electrically isolated early in the project resulting in 

    “workarounds” to ensure worker safety. Use of Brokk mini excavators in aux building was “mixed”

    Challenge: Find methods/approaches that result in the auxiliary building being ready for open air demo earlier in the project

  • 12

    Subject to Confidentiality Statement on Front Cover 12

    Lesson Learned #3 (Continued)ES Risk Response: Actual field results for Zion were handled as follows:

    Extensive review of results from aux building sub project has resulted in a complete change in strategy for aux buildings going forward

    Application of Lessons Learned: Changes to Management Model and Hardware as follows: Institute “Top‐to‐bottom” and “back‐to‐front” strategy for aux buildings Implement cold & dark on aux buildings relying on minimal installed plant circuits. Once entry ways for equipment are cut, remove Brokks and use a CAT 290 or 

    equivalent with shears and hydraulic hammers. Minimize the use of “supersacks” and establish a removal pathway for waste using 

    intermodals. Install “torit” systems earlier in schedule such that plant ventilation systems can 

    be retired. Include removal of aux building drains in estimate and schedule

  • 13

    Subject to Confidentiality Statement on Front Cover 13

    Lesson Learned #4Premise: Experience from Maine and Connecticut Yankee revealed that loading waste outdoors resulted in shipments being sent back from Clive

    Tents were constructed over the rail tracks leading into the turbine building. Tents were extended to reach each Containment building Torit systems were used in each tent to provide negative air flow into the tents 

    when access doors were opened.

    Challenge: Find methods/approaches that allow waste to be loaded around the clock with no impact from weather conditions on site.

  • 14

    Subject to Confidentiality Statement on Front Cover 14

    Lesson Learned #4 (Continued)ES Risk Response: Actual field results for Zion were handled as follows:

    Tent structures improved productivity. 

    Application of Lessons Learned: Changes to Management Model and Hardware as follows:

    Require the use of tents in future decommissionings Consider a tent over the aux building foot print when it is demolished 

    down to grade. Either establish a pathway from the aux building to the tent or 

    construct an additional tent external to the aux building such that waste can be loaded directly into intermodals.

    Provide dust suppression capabilities in tent to improve working conditions.

  • 15

    Strategic Focus Areas• MARSIM Rev 1‐ USDOE centric revision that will have cost impacts to commercial 

    decommissioning industry.• FSS/Construction Interface‐ Two groups with 2 different missions that can create 

    significant “rub” areas in the schedule.• Evaluate explosive demolition for containments designed using post‐tensioned 

    concrete.• Develop standards for risk reduction during the decommissioning life‐cycle.• License Termination Plan (LTP)• Decommissioning Cost Models• Fuel Ownership

    15