Community Consultation July 18, 2018

Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

Community ConsultationJuly 18, 2018

Page 2: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

2

At Waterfront Toronto, we work with our partners at the City of Toronto, Province of Ontario and Government of Canada.

Page 3: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

Chris GlaisekSVP Planning & Design, Waterfront Toronto

Julius GombosVP Project Delivery, Waterfront Toronto

3

Page 4: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

4

Insert map from Port Lands 101 context board

Page 5: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

5

Page 6: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

6

Keating Channel

Page 7: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

7

Page 8: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

8

Page 9: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

The Port Lands Flood Protection Project

9

Page 10: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

10

Keating Channel

Port Lands Flood Protection Project Boundary

Page 11: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

11

What are we building?

Page 12: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

12

Earthworks/Flood Protection

Page 13: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

Bridges and Structures

Page 14: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

14

Roads and Municipal Services

Page 15: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

15

Parks

Page 16: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

Where are we now?

16

Page 17: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

A decade of planning

2006Don Mouth

Naturalization and Port Lands Flood Protection Project Environmental

Assessment (DMNP EA) began

2007International design

competition

2011Port Lands

Acceleration Initiative

2015DMNP EA and Lower

Don Lands EA approved

2016Due Diligence report for Port Lands Flood Protection completed

2017$1.25 billion funding for

Port Lands Flood Protection

Port Lands Framework Plan and Villiers Island Precinct Plan approved

2012Port Lands

Framework Plan and Villiers Island

Precinct Plan began

Page 18: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

Where are we now?

Feb 2018Port Lands Flood Protection (PLFP)

Community consultation #1

May 2018Design river, parks,

roads & bridges is 30% complete

July 2018PLFP community consultation #2

Fall 2018River excavation begins

Design for parks & river is 50% complete

Design complete on Cherry Street & Cherry

Street Bridge North

Spring 2019Design for parks & river

is 60% complete

we are here

Fall 2019Design for

Commissioners Street is complete

Page 19: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

19

Construction Progress

Page 20: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

20

Page 21: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

21

Page 22: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

22

Page 23: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

23

Construction Schedule

Page 24: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

24

Construction Schedule: July 2018 – September 2018

Page 25: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

25

Construction Schedule: September 2018 – December 2018

Page 26: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

26

Construction Schedule: January 2019 – April 2019

Page 27: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

27

Construction Schedule: May 2019 – July 2019

Page 28: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

28

Construction Schedule: August 2019 – October 2019

Page 29: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

29

Construction Schedule: November 2019 – December 2019

Page 30: Community Consultation July 18, 2018 · Port Lands Flood Protection (PLFP) Community consultation #1. May 2018. Design river, parks, roads & bridges is 30% complete. July 2018. PLFP

Matthew Urbanski, Principal, MVVA

Herb Sweeney, Associate Principal, MVVA

James Roche, Partner, DTAH

Michael Meschino, Principal, Entuitive

30