Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
Community Action for Nutrition Project (Sunaula Hazar Din)
(IDA Credit No. 5137-NP and IDA Grant No. H786-NP)
Implementation Review and Support Mission
June 2-13, 2014
Aide-Memoire
A. Introduction
1. A World Bank team1 led by Manav Bhattarai (Task Team Leader) carried out an implementation
review of the Sunaula Hazar Din - Community Action for Nutrition Project from June 2-13, 2014.
The objectives of the consultation were to assess the overall implementation progress and identify
key steps in order to move forward to ensure accelerated implementation of the project activities.
2. The team would like to express its sincere thanks to the officials of the Ministry of Federal Affairs
and Local Development (MOFALD) which include Mr. Reshmi Raj Pandey (Joint Secretary, Project
Director), Mr. Tekraj Niraula (Under Secretary, Project Coordinator), Mr. Baburam Shrestha (Chief
Controller), Mr. Tula Raj Sunuwar (M & E Officer), Mr. Mahesh Pokharel (Procurement Consultant)
and Mr. Indra Bhujel (Social Mobilization Consultant), Mr. Dhananjaya Poudyal (Nutrition
Specialist) and Mr. Bishnu Bahadur Rayamajhi (Accounts officer) for organizing the consultations
and for the courtesies and cooperation extended to the World Bank team. The team had the
opportunity to visit Sunsari and Saptari districts to see communities implementing Rapid Results
Initiatives. The list of people met is included in Annex 1.
3. This Aide Memoire (AM) summarizes the discussions and agreements reached during the
consultations. The team’s findings, summarized in this AM, were discussed at a wrap-up meeting,
chaired by Mr. Shanta Bahadur Shrestha, Secretary, (MOFALD) on June 13, 2014. As agreed at the
wrap up meeting, this AM will be classified as a public document under the World Bank’s Access to
Information Policy.
B. Key Project Data
Project Data Project Performance Ratings
Board Approval: June 26, 2012
Effectiveness Date: August 24, 2012
Original Closing Date: June 30, 2017
MTR Date: (Planned) January 2015
Original Cr. Amount: USD40 million
Amount Disbursed: 2.04 million (5.1%)
(As of June 30, 2014)
Summary Ratings: Last Now
Achievement of PDO MU MU
Implementation Progress MU MS
Project Management MU MS
Procurement MU MS
Financial Management U MS
Safeguards MS MS
M&E MS MS
Counterpart Funding S S
HS=Highly Satisfactory; S=Satisfactory; U=Unsatisfactory; HU=Highly Unsatisfactory; NA=Not Applicable;
NR=Not Rated
1 The team consisted of : Manav Bhattarai, Health Specialist and Task Team Leader) Albertus Voetberg, Lead
Health Specialist; Preeti Kudesia, Senior Health Specialist; Tekabe Belay, Senior Health Economist; Phoebe Folger,
Operations Officer; Silvia Kaufmann, Senior Nutrition Specialist; Daniel Stein, DIME; Gogi Grewal. DIME, Timila
Shrestha, Financial Management Specialist; Annu Rajbhandari, Environmental Specialist; Ramesh Raj Bista,
Procurement Specialist and Jasmine Rajbhandary, Social Protection Specialist.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
C. Achievement of Development Objectives Status
4. The Project Development Objective (PDO) is to improve attitudes and practices known to improve
nutritional outcomes of women of reproductive age and children under the age of 2. The project will
achieve this development objective by creating demand for nutrition related services and products.
There has been an accelerated implementation of rapid results for nutrition initiatives in the last few
months in 94 VDCs of 10 districts as was agreed during the last implementation support visit. Out of
831 such initiatives more than 90% have already received budget and have started working. Although
progress has been noted in the last four months, the project team still needs to focus on
implementation in order to make up for the implementation delays suffered earlier to ensure the
likelihood of achieving the PDO. The PDO, therefore, has been retained as “Moderately
Unsatisfactory”. Detailed status of the PDO and its indicators are included in Annex 2.
D. Current Implementation Status
5. The team reviewed with the government the progress made till date including the progress on the
actions agreed during the implementation review and support mission in February, 2014. Since the
team observed sufficient progress in most of the pending activities of individual project components,
project management, financial management and procurement including compliance to legal
covenants like finalization of the Operations Manual and Sub-grant guidelines, the implementation
progress has been upgraded to “Moderately Satisfactory”. The progress needs to further accelerate
to create adequate basis to increase the likelihood of achieving the PDO.
The attached table shows the status of actions agreed during the last mission:
Actions Date Agreed Status
1. First round of sub-projects will be completed in 50%
of the wards of 94 VDCs July 15, 2014 Ongoing. Of agreed 243
initiatives, 831 were
initiated and 770 have
received money to conduct
activities and are expected
to finish on time.
2. BER for Laptop computers to be submitted to the
World Bank February 15, 2014 Completed, and goods
procured
3. Coaches for 90 VDCs to be hired
March 7, 2014 Completed
4. Firm for training/orientation of FSNSC to be hired
May 15, 2014 Delayed, Contract
evaluation phase
5. Procurement process for consulting and non-
consulting services related to additional activities in
IEC to be completed
May 30, 2014 IEC materials printed
6.
Project Operations Manual will be finalized and
submitted to the Bank
February 28, 2014 Completed
7. Capacity assessments of project DDCs from a
financial management perspective to be completed June 30, 2014 Delayed
8. A dedicated and full time accounts officer as
member of core PMT team to be assigned February 28, 2014 Completed
3
E. Project Components
6. Component 1 (estimated US$34.86 million) Rapid Results for Nutrition Initiatives (RRNI) at
the ward level. The team congratulates the government for progress made under this component. Of
the 423 initiatives agreed to be complete by July 15, 2014, 831 RRNI have been grounded. Of these,
more than 90% of the communities have received the funds and have started working. The team
observed during field visits the excitement and enthusiasm in those communities to successfully
complete the first cycle of initiatives on time.
7. The team expressed concern regarding the slow pace of fund flow to communities and encouraged the
government to expedite the fund flow to those remaining communities which have not yet received
the funds. In order to make up for implementation delays of one year, we are pleased to note that the
government is considering allowing multiple initiatives in the communities beginning with the next
cycle. This would not only accelerate disbursement but also help to more rapidly produce a
developmental impact on nutrition behaviors. In the communities visited, the team observed a great
deal of community interest to implement multiple initiatives and their confidence that they could do
so. However, the team agreed to allow multiple initiatives only in those communities which were
successful in their first cycle. It is expected that successful communities achieve 80% of the targets
set in their proposals.
8. National Service Providers (NSPs) contracted by the Ministry recruited coaches who facilitate the
communities to choose goals and prepare proposals for sub-projects and help them to implement
activities in 94 VDCs. During the field visits, it was observed that the coaches will need constant
supervision and mentoring in order for them to help the communities to implement the sub-projects.
The government agreed that such provisions will be made to mentor the coaches.
9. The team also pointed out that the work to be done by coaches is comparable to the work done by
existing social mobilizers of Local Governance and Community Development Program (LGCDP),
and given that the government has decided to increase the salaries of social mobilizers from NRs.
7,000.00 to NRs. 10,000.00 per month, the project should also explore the possibility of raising the
salaries of the coaches to the same amount.
Agreed Actions:
• During the second round of sub-projects, only communities which have achieved 80% of their
targets will be allowed to undertake multiple initiatives.
• The remaining communities which have not received funds for the first cycle will receive the
funds by June 30, 2014.
• Every three months, the coaches will receive mentoring and supervision support.
10. Component 2 (estimated US$5.14 million) Project Management, Capacity Building, Monitoring
and Evaluation (M&E). This component relates to procurement and financial management activities
which include procurement of goods and consultation services for capacity enhancement and district
financial capacity assessment, finalization of operations manual and establishment of Management
Information System (MIS). Based on the good progress observed in this component as detailed
below, the rating for project management has been upgraded to “Moderately Satisfactory”.
4
F. Procurement, Financial Management (FM) and Disbursement
Procurement
11. The team reviewed the implementation of the procurement plan and noted that most of the
procurement activities planned for the year have been completed. Some procurement activities in
consulting services and goods categories have been delayed and are now planned for the next fiscal
year. The team suggested preparing an updated procurement plan for the next fiscal year while
preparing the proposed annual work program and budget and submitting it to the World Bank for its
review by July 31, 2014. Selection of Service Providers for clusters 1 and 3 are in place and
reselection process for Cluster 2 has been initiated and the technical evaluation has been submitted to
the World Bank for review. This is a critical activity for meeting the project objectives. Procurement
of laptops and computers and services for printing materials has been completed. The contract for
vehicles has been signed. Based on the significant progress made on procurement activities and its
positive impact in project implementation, procurement performance rating has been upgraded to
“Moderately Satisfactory”.
Agreed Actions:
• An updated Procurement Plan for FY 2014/15 to be submitted to the World Bank by July 31,
2014.
• Hiring of National Service provider for cluster 2 to be completed by August 15, 2014.
• Hiring of a firm to train/orient district and VDC level stakeholders by July 15, 2014.
Financial Management and Disbursement
12. The review noted good progress in financial management with most agreed actions being completed,
and setting a good ground for continuing good financial information system. The mission is pleased
to note that an Accounts Officer as well as an Accounts Assistant has been assigned for the project.
The mission is also pleased to see that the Project Operations Manual has been approved and
disseminated to the concerned offices. The required books of accounts have also been maintained
except for ledgers as per the approved programs/activities which the project has been advised to
maintain. The mission appreciated the project’s efforts in submitting the financial reports on time.
There were no major issues raised in the external audit report of FY2012/13. The mission, however,
reminded one pending action which was agreed during appraisal which relates to carrying out the
capacity assessments of project District Development Committees (DDCs) from a financial
management perspective. The mission noted that the Request for Proposal (RFP) has been issued and
the contract is expected to be awarded by July 2014 and capacity assessment completed by October
2014. Some internal control deficiencies identified during the mission were recommended for
rectification.
13. Out of the approved budget of NPR 590.6 million for FY 2013/14, only 1.98% expenditure has been
incurred up to May 14, 2014. The mission noted that the budget was approved with the expectation
that the communities will be able to undertake at least two cycles of sub-projects in 15 districts but
due to delay in establishing institutional arrangement for rolling out the sub-projects, expenditures
could not be incurred as expected. As of the review date, only one cycle of sub-projects had been
initiated in 10 out of 15 districts. The sub-projects will be implemented as per the recently adopted
Project Operations Manual. The corresponding expenditures for those sub-projects will be reflected in
the last trimester. The implementation of the project is therefore expected to improve, especially in
the Sub-Grants category which is the main component of the project.
14. Disbursement is running very slow. As of June 30, 2014, the disbursements comprise of initial
advance to the Designated Account of USD 2 million and a replenishment of USD 40,795.67, which
5
is only about 11.3% of the allocated funds under IDA Grant. There has been no disbursement against
IDA Credit. With the improvement in implementation, the disbursement is expected to pick up in
FY2014/15.
15. Based on the completion of most of the agreed actions and the progress observed, the financial
management of the projects is upgraded to “Moderately Satisfactory”
Agreed Actions:
• Complete the capacity assessment of project DDCs from a financial management perspective by
October 30, 2014.
• Submit third trimester Implementation Progress Report of FY2013/14 by August 31, 2014.
• Submit unaudited accounts of FY2013/14 by October 15, 2014.
G. Safeguards
16. As agreed in the last mission, Operation Manual of the project includes provision made in the
Environment and Safeguard Management Framework (ESMF) including environmental screening for
safeguard compliance. During the field visits in Sunsari and Saptari districts, the team observed
initiatives like Sanitation and Hygiene in a school, creating open defecation free communities,
encouraging exclusive breastfeeding and encouraging increased consumption of animal sourced
protein among pregnant women and children. The visit to the few wards revealed that toilets have
been constructed in schools considering the safeguard aspects for improving the hygiene and
sanitation in the school premises. Similarly, at the household level toilets have been constructed
considering proximity from the water sources, appropriate location for soak pit and septic tank and
water availability. The coaches are using the developed manuals which also include the safeguard
concerns (which was shared to the WB safeguard specialists) are being used for monitoring purposes.
The Bank team recommended the project to adhere to ESMF while selecting the site for poultry
farming (for providing animal protein to pregnant women and children) so that the environmental
issues are considered well in advance. Rating for the safeguard has been retained as “Moderately
Satisfactory”.
H. Results Framework and Monitoring & Evaluation
17. Although preliminary baseline data were received four months ago, the final baseline data turned out
slightly different and thus have been updated in the Operations Portal. However, the targets to be
achieved will remain the same. Since some progress on the sub-projects being conducted in the field
have been reported, the intermediate results indicators have now also been updated. The government
is doing its regular monitoring of the performance of the National Service Providers and the coaches
and their work with the communities. The third party monitoring has begun in the field as well and
their independent review will provide the assurance whether the funds are being used for their
intended purpose.
18. The team reviewed the progress on the impact evaluation. The project runs in two phases and the
VDCs are randomized for impact evaluation into two groups. The first group is called an “early
starter” and the VDCs in this group already have ongoing sub-projects. The second group is called a
“late starter” and will have sub-projects beginning FY16. The implementation of sub-projects is
happening as per the randomization with implementation beginning in most of the early starter VDCs
in clusters 1 and 3 districts. The treatment in which VDCs are required to have female leaders of the
RRNI group also seems to have good compliance, as the data shows that 80% of wards in this
category have female leaders as compared to 40% in wards without this requirement. However, the
strategy for promoting specific focus areas appears to have been less successful. In the field visits,
some coaches were aware of focus area promotion and communicated it to their groups, but others
were not at all aware of the policy. The team recommends that all coaches receive refresher training
6
before the next cycle in which the idea and methods of suggested focus areas is reinforced. Finally,
there was a worrisome error rate between data given provided by the National Service Provider (NSP)
(on focus areas chosen and gender of RRNI group leaders) compared to what was observed in the
field. The team recommends that the NSP develops a more rigorous and traceable system for
collecting this data, and re-confirms all data from the first cycle.
19. The team expressed concerns that the a digital Management Information System (MIS) should have
been in place for proper records but the hiring of a firm to establish this has been delayed due to
administrative reasons. A proper MIS in place will reduce errors of reporting.
20. Based on the above progress, the rating for Monitoring and Evaluation has been retained as
“Moderately Satisfactory”
Agreed Action:
• Award of contract for MIS to be completed by July 31, 2014.
21. Access to Information
22. The Government agreed that the Aide Memoire can be disclosed as a public document under the
World Bank’s Access to Information Policy.
Proposed Next Consultation Visit
23. The timing for the next implementation support visit is planned around November/ December, 2014,
with a focus on reviewing the implementation progress creating adequate ground to increase the
likelihood of achieving the PDO within the project period. The mission will also discuss about the
timing for mid-term review planned for the beginning of 2015.
Summary of Agreed Actions
Actions Date Responsible
1. During the second round of sub-projects, only
successful communities will be allowed to
undertake multiple initiatives.
Next cycle onwards MOFALD
2. The remaining communities which have not
received funds for the first cycle will receive the
funds
June 30, 2014. MOFALD
3. Every three months, the coaches will receive
mentoring and supervision support.
On-going MOFALD/World
Bank
4. An updated Procurement Plan for FY 2014/15
to be submitted to the World Bank
July 31, 2014 MOFALD
5. Hiring of National Service provider for cluster 2
to be completed
August 15, 2014 MOFALD
6. Hiring of a firm to train/orient district and VDC July 15, 2014 MOFALD
7
level stakeholders
7. Complete the capacity assessment of project
DDCs from a financial management perspective
October 30, 2014 MOFALD
8. Submit third trimester Implementation Progress
Report of FY2013/14
August 31, 2014 MOFALD
9. Submit unaudited accounts of FY2013/14 October 15, 2014 MOFALD
10. Award of contract for MIS to be completed July 31, 2014 MOFALD
8
Annex 1:
LIST OF PEOPLE MET
Ministry of Federal Affairs and Local Development
1. Mr. Shanta Bahadur Shrestha, Secretary
2. Mr. Reshmi Raj Pandey, Joint Secretary and Project Director
3. Mr. Tekraj Niraula, Under Secretary and Project Coordinator
4. Mr. Baburam Shrestha, Finance Officer
5. Mr. Tula Raj Sunuwar, Monitoring and Evaluation Officer
6. Mr. Mahesh Pokharel, Procurement Expert
7. Mr. Indra Bhujel, Social Mobilization Expert
8. Mr. Dhananjaya Poudyal, Nutrition Specialist, MOFALD
9. Mr. Bishnu Bahadur Rayamajhi, Accounts Officer
Ministry of Finance
1. Mr. Lal Bahadur Khatri, Under Secretary, IECCD
9
Annex 2:
Results Framework and Monitoring
.
Country: Nepal
Project Name: Community Action for Nutrition Project (Sunaula Hazar Din) (P125359)
.
Results Framework .
Project Development Objectives .
PDO Statement
The Development Objective for the Project is to improve attitudes and practices known to improve nutritional outcomes of women of reproductive age and children under the age of 2. Changes in
attitudes and practices would address the key risk factors for child malnutrition and create demand for nutrition related services and products. The supply of these services and products will be provided
through existing public sector and donor-funded programs, the private sector and, to a limited extent, financed through the Project. .
Project Development Objective Indicators
Cumulative Target Values Data Source/ Responsibility for
Indicator Name Core Unit of Measure Baseline YR1 YR2 YR3 YR4 End Target Frequency Methodology Data Collection
Percentage of unmet family planning needs
among women 15-25
years of age
Percentage 31.5 (final
data) 25
Baseline, Mid-
term and end-of-Project
Surveys Consulting firms
Percentage of pregnant
women taking iron and folic acid (IFA)
supplements for 180 days
Percentage 20.5 (final
data) 30
Baseline, Mid-
term and end-of-
Project
Surveys Consulting firms
Percentage of children 0-6 months age who are
exclusively breastfed Percentage
69.0 (final
data) 80
Baseline, Mid-term and end-of-
Project
Surveys Consulting firms
Percentage of children 6-
24 months age who
consume a minimum acceptable diet
Percentage 9.3 (final
data) 25
Baseline, Mid-term and end-of-
Project
Surveys Consulting firms
10
Attitude of community
members towards the importance of keeping
girls in school until at
least 20 years of age
Percentage
36.6
favorable
% score
50 Baseline, Mid-term and end-of
Project
Surveys Consulting firms
Attitude of community
members towards the
importance of reducing indoor air pollution
Percentage
32.1
favorable
% score
50 Baseline, Mid-term and end-of-
Project
Surveys Consulting firms
Attitude of pregnant
women towards the
importance of eating
three time a day
including at least one animal-sourced food per
day
Percentage
75
favorable
% score
92
Baseline, Mid-
term and end-of-
Project
Surveys Consulting firms
.
Intermediate Results Indicators
Cumulative Target Values Data Source/ Responsibility for
Indicator Name Core Unit of Measure Baseline YR1 YR2 YR3 YR4 End Target Frequency Methodology Data Collection
Number of wards
carrying out RRNIs Number 0.00 831 2000.00
Trimesterly,
Annually
Routine
monitoring MOFALD
Percentage of wards
carrying out RRNIs per
selected VDC Percentage 0.00 98.2 80.00
Trimesterly, Annually
Routine monitoring
MOFALD
Number of RRNIs per ward per year
Number 0.00 1 2.00 Trimesterly, Annually
Routine monitoring
MOFAFALD
Characteristics of RRNI teams: % females
participating in all RRNIs Percentage 60.1 40.00
Trimesterly,
Annually
Routine
monitoring MOFALD
Characteristics of RRI
teams: % minority
participation (e.g. dalits,
janajatis, sunuwar) in all
RRIs
Percentage 51 40.00
Trimesterly,
Annually
Routine
monitoring MOFALD
Percentage of successful
RRIs / VDC
Percentage
Will be
available
after July
15, 2014
80.00 Trimesterly,
Annually
Routine
monitoring MOFALD
11
Average time between
RRI proposal submission and approval/rejection
Days 35.5 21.00 Trimesterly,
Annually
Routine
monitoring MOFALD
Percentage of RRIs that
could not take off due to
public sector supply side delays
Percentage
Will be
available
after July
15, 2014
20.00 Trimesterly,
Annually
Routine
monitoring MOFALD, VDC, DDC
Semi-annual meetings of
coaches conducted Text No Conducte
d Twice a year Bi-annually
Routine
monitoring MOFALD
RRNI Process evaluation
conducted Text No Planned Yes Once, at Mid-term Mid-term review MOFALD
.
12
Annex 3:
Financial Management
Budget and Expenditures for FY 2013/14:
As of May 14, 2014, the following expenditures were incurred in FY 2013/14:
NPR in Million
Budget Expenditure
GON IDA Total GON IDA Total
% of
Budge
t
F/Y 2012/13
Recurrent - 560.00 560.00 - 10.85 10.85 1.93%
Capital - 30.60 30.60 - 0.85 0.85 2.76%
TOTAL - 590.60 590.60 - 11.70 11.70 1.98%
Out of the approved budget of NPR 590.6 million for FY 2013/14, only 1.98% expenditure has
been incurred up to May 14, 2014. The mission noted that the above budget was approved with
the expectation that the communities will be able to undertake at least two cycles of sub-projects
in 15 districts but due to delay in establishing institutional arrangement for rolling out the sub-
projects, the expenditures could not be incurred as expected. As of the review date, only one
cycle of sub-projects had been initiated in 10 out of 15 districts. The sub-projects will be
implemented as per the recently adopted Project Operations Manual. The corresponding
expenditures for those sub-projects will be reflected in the last trimester. The implementation of
the project is therefore expected to improve, especially in the Sub-Grants category which is the
main component of the project.
Disbursements: As of June 30, 2014, disbursements comprise of initial advance to the Designated Account of
USD2 million and a replenishment of USD40,795.67, which is only about 11.3% of the allocated
funds under IDA Grant. There has been no disbursement against IDA Credit. With the recent
adoption of the Project Operations Manual, implementation is expected to improve, especially in
the Sub-Grants category which is the main component of the project.
Financial Management:
The review noted good progress in financial management with most agreed actions being
completed, and setting a good ground for continuing good information system. The mission is
pleased to note that an Accounts Officer as well as an Accounts Assistant has been assigned for
the project. The mission is also pleased to see that the Project Operations Manual has been
approved and disseminated to the concerned offices. The required books of accounts have also
been maintained except for ledgers as per the approved programs/activities which the project has
been advised to maintain. The mission, however, reminded one pending action agreed during
13
appraisal which relates to carrying out the capacity assessments of project District Development
Committees (DDCs) from a financial management perspective. The mission noted that the
Request for Proposal (RFP) has been issued and the contract is expected to be awarded by July
2014 and capacity assessment completed by October 2014.
Following are some other observations of the review team:
Direct Payment from Designated Account: The mission noted that the expenditures included in
the financial reports submitted to the Bank for direct payments from the Designated Account
have not been included in the project’s accounting system, as the project’s FMIS is only
configured to record payment through FCGO. The mission advised the project to modify the
FMIS as necessary to include direct payments in the project’s accounting system.
Ledgers: The mission also noted that the required books of accounts have been maintained
except for ledgers as per the approved programs /activities. The mission advised the project to
maintain the required program ledgers.
Internal Control: The mission recommended measures to address internal control deficiencies
that were identified. The mission guided the project on coding the project’s assets and properly
updating the Stock Book. The mission also advised the project to maintain subsidiary ledger to
keep track of each asset.
Implementation Progress Reports:
The mission appreciated the project’s efforts on submitting the first and second trimester
financial reports for FY 2013/14 on time. There are no outstanding financial reports. The team
reminded that the third trimester progress report is due on August 31, 2014.
Audit Reports: The mission noted that there was no major issue raised in the external audit report of FY
2012/13. The auditors had raised concern on slow implementation and the delay in preparing the
Sub-grants guidelines and Operations Manual. With the recent adoption of the Project
Operations Manual, implementation is expected to improve. The team reminded that the
unaudited account for FY2013/14 is due on October 15, 2014 and the audited accounts on
January 15, 2015.
Agreed Actions:
The following actions agreed at the project appraisal were found yet to be completed:
S. No. Agreed Actions Previous Agreed Date Revised Agreed Date
1
Carry out capacity
assessments of project
DDCs from a financial
management perspective
June 30, 2014 October 30, 2014