Common Reasons for Delays and Rejection of CDM Projects

Embed Size (px)

Citation preview

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    1/25

    UNFCCC secretariat, programmeFirstname Lastname, Job Title

    Main reasons for delay and rejection ofCDM projects during registration and

    issuance

    Workshop on Enhancing the Regional Distribution of CDM Projects in

    Asia and the Pacific

    Kathmandu, Nepal. 7 September 2011

    Mr. Miguel NaranjoUNFCCC secretariat, SDM/ OSD

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    2/25

    REGISTRATION

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    3/25

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    4/25

    COMPLETENESS CHECK

    Source: Information note on the results of the completeness checks (1 February 2011 30 April 2011)

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    5/25

    Main issues raised during CC

    Issues related to Modalities of Communication:

    Example 1: Two focal points are appointed with the same sole role.

    Example 2: No party is mentioned in the Annex 1 of the MoC.

    Use of an expired version of the methodology (please refer to paragraph 14 of EB48

    Annex 60 for extensions of the validity period of the methodology)

    Replicable spreadsheets: Example 1: Existence of debugs or circular references.

    Example 2: Sensitivity analysis is not replicable.

    Example 3: Some rows/cells in the spreadsheets provided do not contain formulas (only

    typed figures), most of the time in the calculation of the income tax

    Inconsistencies (mainly related to PPs and Parties)

    Documents submitted without any translation

    Bundling form not provided

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    6/25

    INFORMATION AND REPORTING CHECK

    Source: Information note on the results of the completeness checks (24 October 2010 31 January 2011)

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    7/25

    Main issues raised during I&R Check

    Investment analysis - Validation of input values:

    Example 1: No explanation on the application of annual escalation to O&M cost and notto other input values.

    Example 2: No validation of each component of the project and/or O&M costs.

    Example 3: Validation on why no salvage value was considered is missing.

    Example 4: No justification of investment breakdown and electricity schedule is

    provided.

    Common practice analysis

    Example 1: The list of the similar activities considered (including their details) is not

    provided in the PDD.

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    8/25

    Main issues raised during I&R Check

    Baseline:

    Example 1: The Validation Report does not validate the baseline assumptions or doesnot contain the values of such parameters.

    Example 2: Evidence of the assessment of the elimination of the alternatives to the

    baseline scenario is not provided.

    Example 3: Assessment on the increase in capacity for Small Scale projects is not

    provided.

    Applicability condition of the methodology

    Monitoring

    Example 1: Monitoring parameters are not in line with the methodology or tools.

    Issues related to closure of CARs

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    9/25

    REVIEW STAGE

    Registration

    142 (66%)

    55 (25%)

    19 (9%) 1 (0%)

    Additionality

    Application of baselinemethodology

    Application of the

    monitoring methodology

    Project description

    Source: Appendix 2 (Annex 2 to Annotations to the agenda of EB)

    Monitoring period from 1 January to 20 June 2010

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    10/25

    Main issues raised during the Review stage

    Additionality

    114 (80%)

    10 (7%)

    11 (8%)

    7 (5%) Prior consideration

    Investment analysis

    Barrier analysis

    Common practice analysis

    Application of baseline methodology

    20 (36%)

    23 (42%)

    4 (7%)8 (15%) Project boundary

    Baseline identification

    Algorithms and/or formulae to

    determine emiss ion reductions

    Compliance with applicability

    conditions

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    11/25

    Main issues raised during the Review stage

    Investment analysis:

    Example 1: Simple cost analysis is not applicable as there is evidence that the project

    activity generate some revenues. Example 2: Suitability of input values at the time of investment decision not validated.

    Example 3: Input values not cross-checked against independent sources

    (contracts/quotations/purchase orders/price indexes/appropriate literature)

    Barrier analysis (project-specific) Example 1 - Investment barrier: The financial situation of the PP and its difficulty to

    receive loan is not confirmed.

    Example 2 - Technological barrier : Training cost (or other resources) have a direct

    impact on the financial returns of the project activity and were not assessed by investment

    analysis.

    Example 3 - Prevailing practice: No information was provided on whether there are

    industries with similar or comparable technologies to the project activity that have installed

    similar technologies in the country/region and how the application of the technology differs

    between such industries and the projects sector.

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    12/25

    Main issues raised during the Review stage

    Continuing and real actions:

    Example 1: The type of evidence used to justify the gap between the project starting date

    and the commencement of validation is not appropriate or has not been justified (i.e.

    termination contracts, minutes of meetings).

    Example 2: The specific CDM deliverables and/or actions carried out under the different

    consultancy agreements is not explained (in cases where more than one consultant is

    involved)

    Baseline:

    Example 1: The baseline scenario does not take into account the projected increase

    in (processing) capacity in line with General Guidance forSSCmethodologies

    Example 2 Investment comparison: Different construction period, investment

    breakdown and schedule and amount of electricity generation is considered for thebaseline and project scenarios but they are not justified.

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    13/25

    ISSUANCE

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    14/25

    COMPLETENESS CHECK

    Source: Information note on the results of the completeness checks (1 February 2011 30 April 2011)

    A total of 429 submissions for Issuance were made.

    2%

    15%65%

    17%

    Projects Rejected

    at CC (step 1) =

    40/429 =

    9%

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    15/25

    Main issues raised during CC

    Inconsistency of Information:

    The documents submitted are not internally and mutually consistent (EB48 - Annex 68

    paragraph 7(b)).Example 1: In the monitoring line diagram for Line II (page 13 of the monitoring report), the

    tag number for the monitoring equipment of "P_HNO3" is stated as 322-FT-2-513 whereas

    page 43 of the monitoring report states 322-FT-512 inconsistency.

    Example 3: The deviation number I-DEV0XXX stated by the DOE in page 5 of verification

    report refers to another project activity.Example 4: The default value has only been applied from 01/02/2008 till 01/09/2008 for Site 2

    in the Excel spreadsheet whilst the monitoring report Table B5 states that the default value has

    been applied from 01/02/2008 till 20/10/2008.

    Example 5: The verification report states that the calorific value of Diesel is monitored from

    the latest CEA CDM data base and is in line with the registered PDD while the monitoring

    report states that the value is taken from IPCC as per registered PDD.

    The signed form contains inconsistent number of CERs as compared to the verified value.

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    16/25

    Main issues raised during CC

    Other issues:

    Some spreadsheets are missing Inconsistencies between diagrams and monitoring instruments

    Different grid name or grid conection in different documents

    Different grid emission factor in different documents

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    17/25

    INFORMATION AND REPORTING CHECK

    Source: Information note on the results of the completeness checks (1 February 2011 30 April 2011)

    A total of 429 submissions for Issuance were made.

    Projects Rejected

    at I&RC (step 2) =

    39/429 =

    9%

    15%

    5%

    10%

    27%

    24%

    5%

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    18/25

    Main issues raised during the I&RC (step 2)

    Calibration information not provided:

    The verification report does not contain information on how the DOE verified the calibration of

    monitored equipments with the calibration requirements.

    Calibration Delay:

    The verification report does not contain an assessment on how the DOE verified the

    calibration delay of monitoring equipments against the requirements of EB52, Annex 6

    The information on calibration of monitoring instruments reported is not in accordance with

    that specified by the monitoring methodology/ monitoring plan.

    Calibration Frequency Requirement:

    The verification report does not contain information on how the DOE verified the calibration

    frequency of monitored equipments with the calibration requirements.

    Calibration Information not provided and no explanation for increase of ERs:

    The monitoring report and excel file provided do not contain clear information on monitoring

    instruments and related calibration.

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    19/25

    Main issues raised during the I&RC (step 2)

    Incomplete Monitored Parameters:

    The verification report does not list each parameter required by the monitoring plan

    and clearly state how the DOE verified the information flow (from data generation,

    aggregation, to recording, calculation and reporting) for these parameters including the

    values in the monitoring reports (VVM 1.2. para 206).

    The MR does not contain all parameters required to be monitored as per the monitoring

    plan/applied methodology (EB48 - Annex 68 paragraph 10 (a) (iii)).

    Compliance with the monitoring plan / revised monitoring plan:

    The VR does not have a statement on whether the monitoring has been carried out in

    accordance with registered or the accepted revised monitoring plan (VVM v.1.2 para 203).

    Cross-checking with other sources: The Verification Report does not indicate how the information provided in the monitoring

    report has been cross-checked with other sources (VVM v.1.2 para 208 (b)).

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    20/25

    Main issues raised during the I&RC (step 2)

    Inappropriate Calculation of ERs:

    The monitoring report does not contain the formulae for Baseline Emissions and/or ProjectEmissions and/or emission reductions calculations, including reference to formulae and

    methods used.

    The emission reductions spreadsheet does not contain the formulae of calculation.

    No sufficient explanation for Increase of ER:

    The MR does not contain an explanation of any significant increase of actual emission reduction

    claimed in the monitoring period in relation to the estimated in the registered PD.

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    21/25

    Review Stage: Issuance

    Reasons for Review of Request for Issuance

    Sourced from Appendix 2 (Annex 2 to Annotations to the agenda of EB61)

    Monitoring period from 1 Jan- 30 June 2010

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    22/25

    Main issues raised during the Review stage

    Implementation of Project Activity:

    MR & VR does not mention reasons for higher PLF than the one in the registered PDD

    The DOE has not requested either approval or notification of changes from project

    design, if there is a permanent change in the plant load factor from the PDD.

    Turbines model number and capacity are different from those described in the registered

    PDD.

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    23/25

    Main issues raised during the Review stage

    Assessment of data and calculation of greenhouse gas emission reductions:

    The DOE to clarify how it verified that there were no leakage emissions due to electricity

    consumption from Site A considering that the MR indicated that this site was in operation

    during the monitoring period even though there was no gas generation.

    How DOE checked that the calibration of the 7 individual meters was done following the

    Guidance for SSC project activities.

    The DOE shall clarify how it confirmed that the guidelines for small scale project activities

    which require recalibration of meters at least once in three years was complied with

    considering that after the initial calibration of the meters.

    Incorrect IPCC values.

    Inconsistent input values.

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    24/25

    Main issues raised during the Review stage

    Compliance of the monitoring plan with the monitoring methodology:

    The DOE is required to clarify how it verified that the calibration of all measurement

    instruments, except for the HFC23 flow-meter, was done according with the requirements from

    the methodology (i.e., monthly frequency).

    The DOE is required to clarify how it verified the reported values of electricity consumed from

    the grid by the clinker production and by the blended cement grinding units as the existing

    electricity-meter, located in the main feeder, monitors the total electricity imported.

    The methodology requires the measurement of the volume of auxiliary fuel Qi used by the

    project activity to determine project emissions. Since the project emissions had been calculated

    in respect of the steam supplied to de-oxygenation process rather than measured, the DOE is

    requested to clarify: 1) how it verified that the monitoring of project emissions is in accordance

    with the methodology and, 2) if they were not monitored in accordance with the

    methodology why the DOE did not submit a request for deviation.

  • 8/4/2019 Common Reasons for Delays and Rejection of CDM Projects

    25/25

    SDM programme

    UNFCCC secretariat

    THANK YOURegional Meeting of the DNA Forum for Asia and the Pacific

    Kathmandu, Nepal. 5 September 2011

    Mr. Miguel Naranjo