Common Cause/PA Website Project. Common Cause of Pennsylvania. Who are they? Volunteer based nonpartisan nonprofit advocacy organization What do they do? Inform constituents of PA of the issues that affect Pennsylvanians Work to strengthen public participation in the political process Goals - PowerPoint PPT Presentation
Citation preview
Common Cause/PA Website Project
Common Cause of Pennsylvania
• Who are they?• Volunteer based
nonpartisan nonprofit advocacy organization
• What do they do?• Inform constituents of
PA of the issues that affect Pennsylvanians
• Work to strengthen public participation in the political process
• Goals• Continuing growth and
spreading their message across the state
The Problem
• CC/PA would like to have control of their own website
• Currently run by national chapter of CC• Would like maintain a new website in
house which can be controlled by volunteers
• New website will support their goals by increasing their visibility
Stakeholder Analysis
• Team 8Project Managers SME - Suzanne Cummings
• James Eisenstein Project Sponsor
• Barry Kauffman CC Executive Director
• Ruth Frits Web Developer
• Entry Level & InternsResources
Initial Financial Analysis
Final Financial Analysis
Earned Value Chart
AC
BACEAC
EVPV
0
50000
100000
150000
0 3 6 6.45
Month
$
• Under Budget
• Behind Schedule
Cost variance = Earned Value – Actual Cost = $62,181.28 - $55,519.00 = $6662.28
Schedule Variance = Earned Value – Planned Value = $62,181.28 - $66,622.80 = -$4441.52
Cost performance Index = Earned Value / Actual Cost = $62,181.28 / $55,519.00 = 1.12
Schedule Performance Index = Earned Value / Planned Value = $62,181.28 / $66,622.80 = 0.933
Estimate at Completion = Budget at Completion / Cost Performance Index = $111,038.00 / 1.12 = 99141.07
MilestonesMilestone Date
Initiating
Completed scope draft 10/27/05
Assemble project teams, define roles completed
10/20/05
Completed initiating stage 10/20/05
Planning
Completed schedule 11/10/05
Completed planning stage 11/11/05
Executing
Completed CMS development 11/25/05
Completed Templates 11/14/06
Completed site design 11/23/05
Completed website construction 11/30/05
Completed security development 1/19/06
Completed executing stage 1/19/06
Deployment
Completed deployment stage 2/2/06
Milestones ContinuedRollout Date
Modify items as necessary 2/13/06
Completed Pilot 2/13/06
Completed stakeholder review 2/14/06
Deploy production system complete 2/20/06
Completed rollout 2/21/06
Completed deployment stage 2/21/06
Controlling
Status reports 16th of every month
Stakeholder status report Every Wednesday
Status reports to client Every other Wednesday
Completed external testing 3/13/06
Completed unit testing 3/13/06
Completed external testing 3/17/06
Completed integration testing 3/17/06
Completed external testing 3/20/06
Completed testing stage 3/21/06
Training materials complete 3/28/06
Completed documentation 3/28/06
Completed controlling stage 3/28/06
Closing
Project concluded 4/4/06
Project Risk Management• Technology Risk
Medium Probability / High Impact / Risk Factor of 4
No confirmation to see approval of hardware
No relationship between sponsor and Kintera
• Financial RiskHigh Probability / High Impact / Risk Factor of 7.2
Non profit organization / Not certain of volunteer’s experience
No budget could make the project unfeasible
• People RiskMedium Probability / High Impact / Risk Factor of 3.2
Working on project without getting to know clients
Manager and team realize misunderstanding of customer’s expectations
Project Risk Management (cont’d.)
• Market RiskMedium Probability / High Impact / Risk Factor of 3.2
Displeased over the control of their presence on the Internet
Website draws more users and members to organization
• Structure/Process RiskHigh Probability / Low Impact / Risk Factor of 2.4
National level of organization take over CC/PA website
Customized website distinguish unique identity
Project Quality Management
Standards:• Website works on all browsers• Accessible to all users: website can be used by
the disabled
Requirements:• Completed project meets all specifications
and satisfies all needs: the website must accomplish the desired goal and meet all expectations
• System available 24/7: the website is available at all times, except during updates or reconstruction
• System available to all users: anybody can use and view the website
• System is easy to find/navigate: website is linked to the main Common Cause website; website is easy to find through web searches and easy to navigate
Lessons Learned
• Contact stakeholders early in the project and stay in contact
• Define scope more clearly• Have resource availability
defined in writing