34
Rob Pether B.E.(Mech) Commissionin g

Commissioning. What is Commissioning? And the word Authority?

Embed Size (px)

Citation preview

Page 1: Commissioning. What is Commissioning? And the word Authority?

Rob Pether B.E.(Mech)

Commissioning

Page 2: Commissioning. What is Commissioning? And the word Authority?

What is Commissioning?The origin of the word comes from:-commission (n.)mid-14c., “authority entrusted to someone,” from Latin commissionem (nominative commissio) “delegation of business,” noun of action from past participle stem of committere. Meaning “body of persons charged with authority” is from late 15c.commission (v.)1660s, from commission (n.). Related: Commissioned; commissioning.

Page 3: Commissioning. What is Commissioning? And the word Authority?

And the word Authority?

authority (n.)early 13c., autorite "book or quotation that settles an argument," from Old French auctorité "authority, prestige, right, permission, dignity, gravity; the Scriptures" (12c.; Modern French autorité), from Latin auctoritatem (nominative auctoritas) "invention, advice, opinion, influence, command," from auctor "master, leader, author".

Usually spelled with a -c- in English till 16c., when it was dropped in imitation of the French. Meaning "power to enforce obedience" is from late 14c.; meaning "people in authority" is from 1610s. Authorities "those in charge, those with police powers" is recorded from mid-19c.

Page 4: Commissioning. What is Commissioning? And the word Authority?

So a Commissioning Authority is:

A leader that has been entrusted to ensure that the facility is fit for purpose

Page 5: Commissioning. What is Commissioning? And the word Authority?

What is Health Facility Commissioning?The ASHE Health Facility Commissioning Guidelines (HFCx Guidelines) defines “commissioning” as a process intended to assure that all building systems in a facility, including sustainable building technologies, are installed and perform in accordance with the design intent, that the design intent is consistent with the owner’s project requirements, and that operations and maintenance staff are adequately prepared to operate and maintain the completed facility. The LEED-New Construction (NC) Reference Guide states that “a commissioned building provides optimized energy efficiency, indoor air quality and occupant comfort” and goes on to say that “conventional commissioning has limited the focus to HVAC systems but that coordinating other building sustainable design systems in the commissioning process results in higher performance, sustainable buildings.”

Page 6: Commissioning. What is Commissioning? And the word Authority?

What Systems are there for Commissioning ?CIBSE – UK Based SchemeFocus is predominantly on the construction phase

ASHRAE – USA Based SchemeTakes a more holistic view of the facility over the life of the project

Page 7: Commissioning. What is Commissioning? And the word Authority?

What is Commissioning as per CIBSE?

Commissioning is:The advancement of an installation from the state of static completion to full working order to the specified requirements. It includes the setting to work of an installation, the regulation of the system, and the fine tuning of the system.

Page 8: Commissioning. What is Commissioning? And the word Authority?

What is Commissioning as per ASHRAE?Commissioning is:A quality-focused process for enhancing the delivery of a project. The process focuses upon verifying and documenting that the facility and all of its systems and assemblies are planned, designed, installed, tested, operated and maintained to meet the owner’s project requirements.

Page 9: Commissioning. What is Commissioning? And the word Authority?

What Platforms Enforce Commissioning ?Estidama – Abu Dhabi Based (CIBSE Basis)IDP-R3 – Basic Commissioning (This is a mandatory credit)

IDP-5: Re-Commissioning (This is an optional credit)

LEED – USA Based (ASHRAE Basis)EA Prerequisite 1: “Funadmental Building Systems Commissioning” (This is a mandatory credit)EA Credit 3: “Additional Commissioning” (This is an optional credit)

Page 10: Commissioning. What is Commissioning? And the word Authority?

Are these Systems Similar?Credit Requirement Estidama

IDP-R3LEED EAP 1

Engage a Commissioning Authority

Review design intent and basis of design documentation

Include commissioning requirements in the construction documents

Develop and utilize a commissioning plan

Verify installation, functional performance, training and documentation

Complete a commissioning report

Page 11: Commissioning. What is Commissioning? And the word Authority?

Are these Systems Similar?Credit Requirement Estidama

IDP-5LEED EA 3

Complete a focused design review prior to the construction documents phase (3rd party commissioning authority must be used)

Complete a focused design review of the construction documents

Complete a selective submittal review for commissioned equipment

Create a recommissioning management manual

Contract for a warranty or post occupancy review

Page 12: Commissioning. What is Commissioning? And the word Authority?

Specific Requirements

Estidama –Currently Version 1.0 is applicableVersion 2.0 has been issued as information only, but not yet enforcedThe guidelines are generic for all building types

LEED –Currently LEED V4Healthcare projects have been specifically addressed

Page 13: Commissioning. What is Commissioning? And the word Authority?

What Systems should be Considered for Commissioning?

HVAC systems ControlsPlumbing systemsElectrical systems

Interior lighting Exterior lightingRefrigeration

Page 14: Commissioning. What is Commissioning? And the word Authority?

What Systems should be Considered for Commissioning?

Building envelope Life safety systemsHVAC systems ControlsPlumbing systems Medical gas systemsElectrical systems Fire alarm systemsInformation technology Fire protection systemInterior lighting Exterior lightingRefrigeration Vertical transportMaterial handling

Page 15: Commissioning. What is Commissioning? And the word Authority?

Does the CxA do all of these?

The short answer is that nobody is a specialist in everything.Normally the CxA has specific areas that they are well experienced in. For the areas that they are not experienced in they manage the process and specialists are brought in for the actual verification works to be undertaken.

Page 16: Commissioning. What is Commissioning? And the word Authority?

So which areas need additional specialists?

Building envelope Life safety systemsHVAC systems ControlsPlumbing systems Medical gas systemsElectrical systems Fire alarm systemsInformation technology Fire protection systemInterior lighting Exterior lightingRefrigeration Vertical transportMaterial handling

Page 17: Commissioning. What is Commissioning? And the word Authority?

This will differ between companies based on their specific strengths and specialties. Currently within EKO Engineering we utilize additional specialists for:

Building envelope Life safety systems

Medical gas systemsFire alarm systemsFire protection system

Refrigeration Vertical transportMaterial handling

Page 18: Commissioning. What is Commissioning? And the word Authority?

So Commissioning is Just Testing and Balancing isn’t it?• Commissioning is far more than testing and

balancing.• Testing and Balancing is one element of

commissioning• Commissioning is the process of ensuring that the

facility operates in accordance with the design requirements (which hopefully match the client’s brief!) while minimising the energy consumption of the facility.

• It is a process that can be undertaken throughout the life cycle of the project/ facility.

Page 19: Commissioning. What is Commissioning? And the word Authority?

Commissioning is:• Documenting the owner’s goals and

requirements• Keeping the project team focused on the

owner’s goals• Identification and correction of problems as

cost effectively as possible and as early as possible

• Reducing the overall costs for the owner• Improve profitability by decreasing costs

Page 20: Commissioning. What is Commissioning? And the word Authority?

And the Role of the Commissioning Authority (CxA) is to:• Determine what the owner REALLY wants• Work with the design team to implement a

Basis of Design (BOD) document and the Owner’s Project Requirements (OPR) document

• Develop a plan to implement the BOD and OPR into the construction documents

• Verify that the right systems are being installed• Verify the operation of the systems• Document the entire project

Page 21: Commissioning. What is Commissioning? And the word Authority?

When Should Commissioning Start?

• There are no rigid timeframes regarding the commencement of commissioning; however, if compliance with LEED or Estidama is required a CxA needs to be appointed during the design phase.

• Beyond this it is up to the discretion of the owner and a cost-benefit analysis should be undertaken to determine when to appoint the CxA.

Page 22: Commissioning. What is Commissioning? And the word Authority?
Page 23: Commissioning. What is Commissioning? And the word Authority?

The Importance of Design Reviews• Design reviews help to resolve issues before the

project moves to the construction phase.• It is far cheaper to change ink on paper than to make

a change during or after construction.• For healthcare the design needs to manage the

infection control risks associated with air and water. For air this involves maintaining pressure differentials.

• A commissioning design review considers how to maintain the facility in addition to whether the system can be commissioned effectively from a controls perspective.

Page 24: Commissioning. What is Commissioning? And the word Authority?

The Top 10 Commissioning Issues in Hospitals• Building pressurization is incorrect. This results in

wasted energy and infection control issues.• Theatres have incorrect air balance, humidity and

temperature control• Incorrect operation of fuel oil systems leading to

generator failure• Incorrect sequencing and operation of generators

leading to failure of critical equipment• Incorrect load shed sequencing leading to failure of

critical equipment

Page 25: Commissioning. What is Commissioning? And the word Authority?

The Top 10 Commissioning Issues in Hospitals• Cause and effect strategy for chiller plant/

boiler plant has not been developed• Short cycling of HVAC equipment leading to

premature equipment failure• Incorrect installation and set up of sensors

leading to incorrect control• Incorrect balancing/ set up of isolation rooms• Lack of training for building operators and/ or

service contractors on complex systems

Page 26: Commissioning. What is Commissioning? And the word Authority?

Example of Issues Identified in a Design Review

Page 27: Commissioning. What is Commissioning? And the word Authority?

Design Intent

Design Philosophy

Room Register No.

Design Actual% Design Within

Spec.(L/s) (L/s)

Toilet E1 -40 -40 100% a

           Patient Room D2 170 170 100% a

  D2 100 100 100% a

  B1 -300 -300 100% a

Balance -30 -30    

Cumulative Balance -70 -70    

Ante Room D2 100 100 100% a

  F3 -80 -80 100% a

Balance 20 20    

Cumulative Balance -50 -50    

Page 28: Commissioning. What is Commissioning? And the word Authority?

Tolerance 0% to -10%

Specification nominates tolerance of 0 to -10 percent

Room Register No.

Design Actual% Design Within

Spec.(L/s) (L/s)

Toilet E1 -40 -36 90% a

           Patient Room D2 170 170 100% a

  D2 100 100 100% a

  B1 -300 -270 90% a

Balance -30 0    

Cumulative Balance -70 -36    

Ante Room D2 100 100 100% a

  F3 -80 -72 90% a

Balance 20 28    

Cumulative Balance -50 -8    

Page 29: Commissioning. What is Commissioning? And the word Authority?

Tolerance +/-10%

What if we consider tolerance +/-10%?

Room Register No.

Design Actual% Design Within

Spec.(L/s) (L/s)

Toilet E1 -40 -36 90% a

           Patient Room D2 170 187 110% a

  D2 100 110 110% a

  B1 -300 -270 90% a

Balance -30 27    

Cumulative Balance -70 -9    

Ante Room D2 100 110 110% a

  F3 -80 -72 90% a

Balance 20 38    

Cumulative Balance -50 29    

Page 30: Commissioning. What is Commissioning? And the word Authority?

Other Issues Identified from CxA Review

Low Level Exhaust introduces lint to the system which will block HEPA filters after approx. 2 weeks of useHEPA filter bank is only accessible in roomHEPA terminal outlets must be accessed in room.Filters will load at different rates and disrupt the air balanceSplitter configuration will be difficult to balance thereby impacting on the pressure differentials in the roomsDoors appear too small to facilitate bed access. Larger doors will impact the pressure differential of the rooms.Large penetrations cannot be effectively sealed (site observation) thereby impacting pressure differential

Back to back wall mounted TV sets will result in air transfer through the wall (power receptacles, data points) thereby affecting the pressure differentialTemperature sensors appear to be in close proximity to heat source and also subject to direct sunlight making control of the room problematic

Page 31: Commissioning. What is Commissioning? And the word Authority?

But How Much Does Commissioning Cost?

• There are a number of studies available regarding the cost of commissioning and associated pay back periods.

• As a rule of thumb commissioning will cost approximately 1% of the project value.

• Pay back periods in the USA are typically between 1 and 5 years for retrospective commissioning (depending on the energy savings that can be realized).

Page 32: Commissioning. What is Commissioning? And the word Authority?

But How Much Does Commissioning Cost?New Construction Retrospective Pay Back Period

Building Commissioning, A Golden Opportunity for Reducing Energy Costs and Greenhouse Gas Emissions

Mills, E, Lawrence Berkeley National Laboratory, Berkeley, CA, USA 2009

Page 33: Commissioning. What is Commissioning? And the word Authority?

A Parting Thought….

Good commissioning forces good construction and thereby raises the bar as to what is acceptable.