Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Commissioning for Robustness in a High-Tech Hospital in the Caribbean
Kelly Adighije, Ajit Naik & Marc Harks
AIA Quality Assurance
The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of the Completion for both AIA members and non-AIA members are available upon request.
This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.
Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
BCxA Conference – Chicagoland, IL – 2019 2
Learning Objectives
BCxA Annual Conference – Chicagoland, IL – September 2019 3
• Project History• Facts and Figures• Project Team Organigram• Owner Project Requirements (OPR)• Basis of Design (BOD)• Defining Robustness in the Caribbean (Periodic Design Reviews)• Synergizing the Prefunctional Checklists (PCx) with Submittals Reviews and Site Acceptance Tests
(SAT)• Synergizing the Functional Performance Tests (FPTs) with Site Acceptance Tests (SAT) and Site
Integration Tests (SIT)• Planning for System Future-Proofing (Ongoing Commissioning)
Project History
BCxA Annual Conference – Chicagoland, IL – September 2019 4
Project History
BCxA Annual Conference – Chicagoland, IL – September 2019 5
By Kmusser - Own work, all data from Vector Map., CC BY-SA 3.0, https://commons.wikimedia.org/w/index.php?curid=14857874
• Country of Curacao• Dutch Lesser Antilles Islands
• 150,000 population• Unusually high incidence of obesity• Unusually high incidence of kidney
diseases and kidney failure• High incidence of diseases of joints
and heart conditions
Project History
BCxA Annual Conference – Chicagoland, IL – September 2019 6
• St. Elisabeth Hospital (SEHOS)• 1855 (164 years)• Breedestraat (O) 193, Willemstad,
Curacao• Center for basic and clinical care• Diagnostic research and specialist
medical care• Serves Leeward Islands and the
wider region
Personal administrativo de SEHOS no ...noticiascurazao.com
http://curacaochronicle.com/politics/new-hospital-on-same-location-as-old-one/
https://curacaochronicle.com/local/a-lot-of-unrest-among-patients-there-is-need-for-an-organization-that-takes-this-seriously/
https://images.app.goo.gl/Ykf3iPxL5qrPAPBp7
Project History
BCxA Annual Conference – Chicagoland, IL – September 2019 7
Facts and Figures
BCxA Annual Conference – Chicagoland, IL – September 2019 8
• Willemstad, Curacao • €130,000,000• Operator - Foundation for the Development of the Netherlands Antilles (SONA)• General Contractor - Ballast Nedam - Contract to Design, Construct and Maintain for 15 years• Commissioning Authority, Building Energy Simulation - Baumann Consulting• November 2013 - December 2019 Project Schedule• 60,000 m2 including 3 levels of parking garage• 40,000 m3 of poured concrete• 90% Local Labor Force• LEED Gold Certification Sort• Large Education and Training Component
BCxA Annual Conference – Chicagoland, IL – September 2019 9
Project Team Organigram
BCxA Annual Conference – Chicagoland, IL – September 2019 10
Netherlands Government
Curacao Government
SONA - Foundation for the Development of the
Dutch Antilles -(Operator)
Ballast Nedam Infra B.V. / Rönesans
(General Contractor)
Baumann Consulting (Energy
Modeler & LEED Commissioning)
SONACommissioning
Team(Medical Devices)
Ballast Nedam Commissioning
Team(MEP Systems)
REME Technik Controls
Contractor (MEP Systems)
Berenschot International
(Project Manager)
Valstar Simonis Rijswijk
(SMEP Designer)
BCxA Annual Conference – Chicagoland, IL – September 2019 11
Owner Project Requirements (OPR)
BCxA Annual Conference – Chicagoland, IL – September 2019 12
Owner Project Requirements (OPR)
BCxA Annual Conference – Chicagoland, IL – September 2019 13
• 300 beds• 90 FTE Medical Specialists• Distributed across 20 specialisms • All rooms and facilities sufficiently flexible to meet further growth • Act also as a training hospital• 20 specialist registrars and 20 interns
Owner Project Requirements (OPR)
BCxA Annual Conference – Chicagoland, IL – September 2019 14
BCxA Annual Conference – Chicagoland, IL – September 2019 15
Basis of Design (BOD)
BCxA Annual Conference – Chicagoland, IL – September 2019 16
Basis of Design (BOD)
BCxA Annual Conference – Chicagoland, IL – September 2019 17
• Spare capacities for spatial, functional and technical to be included in building design• 15% extra floor area included in design of shafts, and technical spaces• Maximum power usage x 0.9 simultaneity factor + 20% additional capacities• Main power distribution boards with 20% spare groups• Cable trays, ladders and ducts dimensioned with 20% spare capacities• 4 x Chillers sized at 25% maximum cooling load • Distribution pumps are redundantly included with spare capacity of 20% each• Flow rate speed in main cooling pipework reduced to allow for higher cooling capacity in the future• Group distributors in all technical areas with a space connection to create additional cooling networks • AHUs and RCUs dimensioned with spare capacity of 10%• Ventilation airspeeds sized at 20% lower than required for future capacity increases• Control cabinets segmented in 3 sections – VFDs, Conventional Control Circuits, Substations
▪ Conventional Control Circuits sized to provide spare capacity of 15%
BCxA Annual Conference – Chicagoland, IL – September 2019 18
Wing DWing C
Wing B
Wing A
Wing H1
Wing H2
Wing H3
Atrium
Building F
Basis of Design (BOD)
BCxA Annual Conference – Chicagoland, IL – September 2019 19
• 27 Air Handling Units• Wings A, B, C, & D with 50% on
Emergency Power – 8 AHUs• Wings H1, H2 & H3 with 100% on
Emergency Power – 13 AHUs in H2 alone• 6 Transformers, 4 Generators, 4 Chillers
BCxA Annual Conference – Chicagoland, IL – September 2019 20
BCxA Annual Conference – Chicagoland, IL – September 2019 21
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 22
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 23
• External shading devices were modelled as prescribed in design documentation• Shades are fixed but angled differently dependent on floor height and surface orientation • Designed to only provide 90 minutes of direct sunlight per day to patient rooms• Material is corrosive resistant to endure the harsh marine environment
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 24
• Atrium prescribed initially to be naturally ventilated all year round
• Thermal shock between conditioned spaces and atrium resulted in a revised design with some mechanical ventilation now to be integrated
• Louvers motorized and designed to withstand Category II Hurricane
• Designed to only provide 90 minutes of direct sunlight per day to patient rooms
• Metal components treated with a special coating to minimize the effects of corrosion from the abrasive marine environment
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 25
• Chiller spacing and pipework arrange to adhere to manufacturer’s access and maintenance requirements
• Chiller and pipework design including insulation to withstand marine environment
• Chiller evaporation fans retrofitted to reduce air contamination by diesel generator fumes
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 26
• Chiller water pump, valve, and sensor arrangement evaluated during design and via submittal reviews
• Access and maintenance requirements evaluated for conformity with manufacturer’s requirements
• Insulation selection also reviewed. Although this plant room is enclosed, there is no vestibule between this room and the exterior
• Test was performed with the dooropen for a period of time toevaluate condensation risk
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 27
• Switch gear and transformer design were part of the scope
• Switchgear called for factory acceptance tests for circuit breakers, ammeter, voltmeter to be included in the specifications
• Access and maintenancerequirements were alsoevaluated
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 28
• Specific requirements by the utility company or AHJ (Aqualectra) were incorporated
• Transformer winding resistance,ratio, and vector group tests forthe transformers were evaluated
• Submittals of transformers werereviewed to ensure that the measurements of impedancevoltage / short circuit impedanceand load losses could beperformed during construction
• Access and maintenancerequirements were alsoevaluated including security requirements
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 29
• Diesel generators are utilized as back for the emergency systems to keep the hospital running during loss of power
• Submittals of generators were reviewed to ensure that safety checks, fuel delivery, ventilation, attenuation and exhaust systems tests were included in the submittals
• Access and maintenance requirements were also evaluated including security requirements.• Distribution boards were also evaluated during normal and emergency operation with the
sequence of operation thoroughly narrated
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 30
• Exterior Air Handling Unit equipment design was evaluated for additional capacities, material specification, performance data, including access and maintenance requirements
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 31
• Interior Air Handling Unit equipment design was evaluated for additional capacities, material specification, performance data, including access and maintenance requirements
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 32
• Air Handling Unit filter specification design EU7, EU9, and M4 or EU13• Corrosion ablation in pre-filter section of AHUs was looked at due to the marine
environment
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 33
• Air Handling Unit ductwork design to ensure conformity of ductwork bends, bend angles, insulation selection, joints, hangers and most importantly, linearity of insulation, both for the exterior and interior AHUs
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 34
• Air Handling Unit controller valves, pumps, fans, air dampers, heat exchangers, temperature sensors were also evaluated
• Submittals of these were reviewed to ensure conformity with design drawings, specifications, including the requirements for any casings or protective shroud
• Access and maintenance requirements were also evaluated including security requirements
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 35
• Exhaust fans including for toilets, storage spaces, AHU coupled, parking impulse fans, and kitchen exhaust were also evaluated
• Submittals of these were reviewed to ensure conformity with design drawings, specifications, including the requirements for any casings or protective shroud
• Access and maintenance requirements were also evaluated including security requirements
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 36
• Condensation from chillers, AHUs, ACs were also evaluated • Submittals of these were reviewed to ensure conformity with design drawings, specifications, including
the requirements for any insulation• Access and maintenance requirements were also evaluated including security requirements
Defining Robustness In the Caribbean (Periodic Design Reviews)
BCxA Annual Conference – Chicagoland, IL – September 2019 37
• Chilled beam, chilled ceiling, supply grille, exhaust grille design including condensation risk control were all addressed during the design reviews with feedback and specification updated as the design progressed
Pre-functional Checklists – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 38
• Commissioning daily kickoff meetings – some if offices and others onsite were a stable of the project.• The commissioning plan and the goals for the day were addressed before activities commenced• Commissioning team including members of all stake holders – operator, operator Cx, Baumann, GC
and GC Cx team
Pre-functional Checklists – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 39
• Commissioning team including members of all stake holders – operator, operator Cx, Baumann, GC, GC Cx team and controls contractor
• Attendee sheet to document all members present, date of the test and some information about theday’s tests
Pre-functional Checklists – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 40
• Testing Agenda▪ Alarm Conditions▪ Visual Inspections▪ Sensor Verifications▪ Sequence of Operation Verifications
◦ Equipment Status Confirmations◦ Temperature Controls◦ Volumetric Flow Controls◦ Pressure Drop Controls◦ Enthalpy Controls◦ MCC Panel Verifications◦ Room Conditions◦ Power Draw Evaluations◦ Emergency Power Tests◦ Fire Alarm Tests
Pre-functional Checklists – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 41
• Alarm conditions were clarified before any test to ensure that health and safety issues were clarified and understood
Pre-functional Checklists – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 42
• A visual inspection by all stakeholders is performed to assess the quality and stability of all the installed equipment
• A checklist is created to document all defects and assign timelines for repairs and persons of responsibility
Pre-functional Checklists – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 43
• Sensor verification via a confirmation of the building automation system data readings verified by field measurements
• This initial test was often performed to confirm the status of the equipment and document this before any tests could commence
BCxA Annual Conference – Chicagoland, IL – September 2019 44
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 45
• Functional Performance Tests – Status verification via the BMS and through field visualization tests
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 46
• Sequence of Operation Verification – Temperature controls to verify design intent• Tolerance for acceptable results – +/- 0.5 degrees Celsius for the water systems and +/- 1 degree Celsius
for the air systems
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 47
• Sequence of Operation Verification – Volumetric flow control verification
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 48
• Sequence of Operation Verification – Pressure drop controls verification
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 49
• Sequence of Operation Verification – Enthalpy controls via run around coils and thermal wheels
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 50
• Sequence of Operation Verification – MCC panel verification
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 51
• Sequence of Operation Verification – Room conditions (temperature, humidity, pressurization were also verified
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 52
• Sequence of Operation Verification – Power draw evaluation of installed equipment
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 53
• Sequence of Operation Verification – Emergency condition was also simulated as part of SIT after SAT• Sequence of Operation Verification – Fire condition was also simulated as part of SIT after SAT
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 54
• Sequence of Operation Verification – Commissioning reports
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 55
• Sequence of Operation Verification – Issues log• Blend of web-based platform (ED Controls, CxAlloy) and paper-based issues sheets• Issues are correlated and assigned to different trades thought the GC
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 56
• Mis-aligned inline CHW pump which resulted in pipework leakage and excessive pump vibration.• Improper sealing of the duct penetration between two fire zones basically negating the fire separation.• Controller damage via glue used to seal insulation. Controller was stuck and stopped modulating.• Improper grounding of AHU to protect against electric shock during power surges or lightning.
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 57
• Pipework corrosion damage due to gluing of the connections during insulation application • Glued insulation improperly installed and not sealing the pipework properly• Excessive vibration from exhaust fan due to misalignment during installation• Exhaust fan BMS communication issues (“off” on BMS, “on” during field observation)
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 58
• Non-functioning room thermostat and thus no signal received in the BMS• Improper labeling or in some occasions, no labelling installed• Improper AHU panel installation – with visible gaps causing leakage and whistling• Leaking chilled water pipework – someone apparently used the lower pipework as a step ladder
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 59
• AHU frame support improperly installed and, in this case, not level• Controller incorrectly installed – opposite signals between 0 to 10v – closes when signaled to open etc.• Duct penetration to roof not properly sealed exposing the equipment below to water penetration and debris• Ductwork support not properly secured resulting in breakage is the ductwork seals
Functional Performance Tests – Site Acceptance Tests
BCxA Annual Conference – Chicagoland, IL – September 2019 60
• Chiller controller bottom plat cover not installed – negating the chiller IP (ingress protection) rating • BMS communication issues with sensors and actuators identified during Site Acceptance Tests• Condensation observed below main CHW pipework due to the high humidity in the plantroom• Corrosion observed on vibration isolation equipment. Repainting necessary
Ongoing Commissioning – Trend Data Analysis
BCxA Annual Conference – Chicagoland, IL – September 2019 61
• Energy Consumption
Ongoing Commissioning – Trend Data Analysis
BCxA Annual Conference – Chicagoland, IL – September 2019 62
• AHU Fan Operation
Ongoing Commissioning – Trend Data Analysis
BCxA Annual Conference – Chicagoland, IL – September 2019 63
• Temperature Controls and Valve / Thermal Wheel Operation
Ongoing Commissioning – Trend Data Analysis
BCxA Annual Conference – Chicagoland, IL – September 2019 64
• Room Temperature Controls via Chilled Beams and Chilled Ceilings
BCxA Annual Conference – Chicagoland, IL – September 2019 65
Kelly AdighijeVice President & Director of the Chicago Office – Baumann Consulting [email protected]+1 202 415 0618
Ajit NaikSenior Commissioning Engineer – Baumann Consulting [email protected]+1 734 276 6539
Marc HarksProject Manager Ballast Nedam: Project HNO [email protected]+0599 662 15 28
66
https://baumann-us.com/ www.ballast-nedam.nl