11
portmetrovancouver.com Presented by: Stephan Ptatschek December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW

COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

Presented by:

Stephan Ptatschek

December 8, 2015

COMMISSIONER STREET

REALIGNMENT PROJECT

OVERVIEW

Page 2: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

• Introductions

• Project Scope and timelines

• Project Outcomes

• Next Steps

• Questions

AGENDA

Page 3: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

PROJECT SCOPE – PHASE I

JANUARY-MARCH 2016

• Relocation of BC Hydro poles

• Closure of east-bound bypass lane (curb installation marked with the red lines)

Existing BC Hydro poles

Future BC Hydro pole

locations

Curb installation to close

lane

Curb installation to close

lane

Page 4: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

• Realign and shift Commissioner St to the north (south curb line to be moved up to the red line)

• Provides room for one east-bound and two west-bound future traffic lanes.

PROJECT SCOPE – PHASE II (CONT’D)APRIL 2016 – SEPTEMBER 2016

Existing curb line Future curb line

Page 5: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

• Replacing and extending existing ocean-facing retaining wall (4.5m high)

PROJECT SCOPE – PHASE II (CONT’D)APRIL 2016 – SEPTEMBER 2016

Retaining wall

Page 6: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

• Construction of a new retaining wall (1m high) on the outside curve of New Brighton Rd at the Commissioner St – New Brighton Rd intersection.

PROJECT SCOPE – PHASE II

APRIL 2016 – SEPTEMBER 2016

Small retaining wall

Page 7: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

• Demolition of existing grain elevator at Columbia Containers following construction of their new facility.

• Extension of BC Hydro lines (from A to B)

• Construction of new road alignment through the footprint of the Columbia Containers grain elevator.

PROJECT SCOPE – PHASE III (CONT’D)JANUARY 2017 – SEPTEMBER 2017

AB

BC Hydro

Extension

BC Hydro feed

installed during

Phase I

Location of existing

grain elevator

Page 8: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

• Realignment of GVRD sanitary sewer and water main into the footprint of the new road alignment.

PROJECT SCOPE – PHASE III

JANUARY 2017 – SEPTEMBER 2017

Existing location

of utilities

Future location

of utilitiesFuture curb line

Page 9: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

• Improve the overall flow of traffic on Commissioner St

• Reduce possible congestion at McGill VACS gates. May result in reduced truck noise.

• Improve the pavement surface, which may reduce truck trailer noise.

• Removal of existing Columbia Containers grain elevator.

PROJECT OUTCOMES

Page 10: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

• Will undergo Category C (TBD) review under PMV’s Project and Environmental Review (PER) process.

• Under East Vancouver Port Lands – Area Plan -Conditionally Approvable (Yellow) Use

• Public consultation required for PER and EVPL Area Plan, with in-person meeting opportunity, notifications, online outreach (dates to be determined)

NEXT STEPS

Page 11: COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW · December 8, 2015 COMMISSIONER STREET REALIGNMENT PROJECT OVERVIEW. portmetrovancouver.com • Introductions • Project Scope and

portmetrovancouver.com

• QUESTIONS?

CONCLUSION