Fred James Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 [email protected] October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British Columbia Utilities Commission Suite 410, 900 Howe Street Vancouver, BC V6Z 2N3 Dear Mr. Wruck: RE: Project No. 1598975 British Columbia Utilities Commission (BCUC or Commission) British Columbia Hydro and Power Authority (BC Hydro) Supply Chain Applications Project (SCA Project) CONFIDENTIAL Semi-Annual Progress Report No. 1 October 2018 to September 2019 (Report) BC Hydro writes to provide its confidential Report in compliance with BCUC Order No G-78-19. The Report is consistent with other project-specific progress reports filed with the BCUC, and provides an update on the SCA Project’s scope and activities, cost, benefits, risks, and schedule, as applicable, over the period from October 1, 2018 to September 30, 2019. BC Hydro is providing the confidential Report to the Commission only. A public version of the Report is being filed under separate cover redacting commercially sensitive and contractor-specific information and is available at www.bchydro.com. BC Hydro seeks this confidential treatment pursuant to section 42 of the Administrative Tribunals Act and Part 4 of the Commission’s Rules of Practice and Procedure. British Columbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver BC V6B 5R3 www.bchydro.com

Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

Fred James Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 [email protected] October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British Columbia Utilities Commission Suite 410, 900 Howe Street Vancouver, BC V6Z 2N3 Dear Mr. Wruck: RE: Project No. 1598975

British Columbia Utilities Commission (BCUC or Commission) British Columbia Hydro and Power Authority (BC Hydro) Supply Chain Applications Project (SCA Project) CONFIDENTIAL Semi-Annual Progress Report No. 1 October 2018 to September 2019 (Report)

BC Hydro writes to provide its confidential Report in compliance with BCUC Order No G-78-19. The Report is consistent with other project-specific progress reports filed with the BCUC, and provides an update on the SCA Project’s scope and activities, cost, benefits, risks, and schedule, as applicable, over the period from October 1, 2018 to September 30, 2019.

BC Hydro is providing the confidential Report to the Commission only. A public version of the Report is being filed under separate cover redacting commercially sensitive and contractor-specific information and is available at www.bchydro.com.

BC Hydro seeks this confidential treatment pursuant to section 42 of the Administrative Tribunals Act and Part 4 of the Commission’s Rules of Practice and Procedure.

British Columbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver BC V6B 5R3

www.bchydro.com

Page 2: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British Columbia Utilities Commission Supply Chain Applications Project (SCA Project) CONFIDENTIAL Semi-Annual Progress Report No. 1 October 2018 to September 2019 (Report) Page 2 of 2

For further information, please contact Geoff Higgins at 604-623-4121 or by email at [email protected].

Yours sincerely,

Fred James

Chief Regulatory Officer cu/tl Enclosure Copy to: BCOAPO

Attention: Leigha Worth [email protected]

CEC Attention: Christopher Weafer [email protected]

Page 3: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

BC Hydro Supply Chain Applications Project

Progress Report No. 1

October 1, 2018 to September 30, 2019

PUBLIC

Page 4: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Table of Contents

1 Background ........................................................................................................ 1 2 Project Status ..................................................................................................... 2 3 Project Scope & Activities .................................................................................. 3

3.1 Major Accomplishments and Work Completed ......................................... 4 3.1.1 Configuration .............................................................................. 4 3.1.2 Detailed Design and Writing of Custom Program Code .............. 4 3.1.3 Data Migration ............................................................................ 5 3.1.4 “Go-live” Planning ....................................................................... 5 3.1.5 Testing ........................................................................................ 6 3.1.6 End-User Documentation & Training .......................................... 6

3.2 Plans for Next Six Months ......................................................................... 7 3.3 Quality Assurance Advisor’s Monthly Report ............................................ 8

4 Project Cost ........................................................................................................ 8 4.1 Project Cost Summary .............................................................................. 8 4.2 Project Contingency Draws ..................................................................... 14 4.3 Summary of Individual Contracts Exceeding $3.0 million ........................ 15

5 Project Benefit Realization Plan ....................................................................... 15 6 Project Risks .................................................................................................... 16 7 Project Schedule .............................................................................................. 24

List of Tables

Table 1 Project Status Dashboard .................................................................. 2 Table 2 Identified Changes in Activities and Impact on the SCA Project ........ 3 Table 3 Project Expenditure Summary – Forecast and Actual Cost ................ 9 Table 4 Identified Changes in Activities and Impact on Scope and

Contingency ..................................................................................... 14 Table 5 Summary of Contracts exceeding $3.0 million ................................. 15 Table 6 Implementation Phase – Risks and Risk Mitigation Summary ......... 18 Table 7 Project Schedule Change Components ........................................... 25 Table 8 Project Milestones ............................................................................ 25

BC Hydro Supply Chain Applications Project

Page i

Page 5: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Appendices

Appendix A Quality Assurance Advisor’s Monthly Project as of September 19, 2019

Appendix B Project Benefit Realization Plan Update Appendix C Risk Register Appendix D Project Schedule

BC Hydro Supply Chain Applications Project

Page ii

Page 6: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

1 Background 1

British Columbia Hydro and Power Authority (BC Hydro) must procure materials and 2

services on a day to day basis in order to maintain safe and reliable electric service 3

to customers. Third party materials and service acquisitions are expected to be in 4

the order of $2 billion annually for at least the next ten years. To meet BC Hydro’s 5

current and future business needs, reduce risk, and provide benefits for supply chain 6

activities, BC Hydro is replacing its current supply chain IT platform with the Supply 7

Chain Applications Project (SCA Project or Project). 8

The new supply chain software and business processes to be put in place by the 9

SCA Project are expected to provide the necessary supply chain tools for BC Hydro 10

to more efficiently and effectively manage its third party materials and service 11

acquisitions. The benefits of SCA Project will include improved efficiency, risk 12

reduction, and cost savings for materials and services procured over the life of the 13

new SAP supply chain system. 14

In October 2017, BCUC issued Order No. G-158-17 accepting the SCA Project’s 15

capital expenditure schedule of $22.5 million to $29.7 required to complete work up 16

to the end of the Definition Phase and directed BC Hydro to file a Phase Two 17

Verification Report (Verification Report) at the end of the Definition Phase. 18

BC Hydro filed the Verification Report in October 2018, and in April 2019 the BCUC 19

issued Order No. G-78-19 accepting the capital expenditure schedule of 20

$38.5 million to $45.4 million to complete the Implementation Phase. 21

BC Hydro was directed to file semi-annual progress reports on the SCA Project. The 22

first progress report is being filed approximately six months from the date Order 23

No. G-78-19 was issued, but will also cover the six months prior to that date. 24

Progress Report No. 1 covers the period from October 1, 2018 to September 30, 25

2019 (the reporting period), and reflects the work undertaken in the Implementation 26

Phase. 27

BC Hydro Supply Chain Applications Project

Page 1

Page 7: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

2 Project Status 1

As discussed in the Verification Report, BC Hydro’s Board of Directors authorized 2

the SCA Project to proceed with Implementation Phase activities in September 3

2018. These activities commenced in October 2018 and work continues to date. 4

Prior to April 2019, the SCA Project completed the detailed design and system 5

configuration activities, and began work on the technical solution build (i.e., 6

development of custom programs). From April 2019 to the end of September 2019, 7

work on the following major activities has progressed: technical solution build, data 8

migration, “go-live” planning, system testing, and development of end-user training 9

materials. 10

This section discusses the status of the Project as at the end of the reporting period. 11

Table 1 Project Status Dashboard 12

Green: No Concerns; Amber: Some Concerns but in Control; Red: Serious Concerns 13

Status as of: September 30, 2019 Overall:

Overall Assessment The project continues to progress on budget, on scope, with an improving level of risk, and anticipates delivery of the planned benefits. The planned in-service date for the new SAP based system is now February 18, 2020, which is within the Target and Committed In-Service dates of November 2019 to March 2020 established in the Verification Report. However, some critical path tasks and deliverable elements are delayed, resulting in an amber rating for the schedule dimension and causing the overall amber rating for the project. The Project team is currently assessing the impact of the schedule slippage on the key project milestones, including the current target In-Service date.

Scope & Activities There have been no material changes to the Project scope since the start of the Implementation Phase. Please refer to Section 3 for more information on the changes to planned Project activities.

Cost The Project’s forecast cost at completion is within the range of the accepted capital expenditure schedule. There have been no approved draws against the project’s $8.0 million reserve amount. Please refer to section 4 for more information on the Project cost.

Benefits There are no changes in the Project’s planned baselines, metrics, measures, and / or the tracking plan in this reporting period. Please refer to Section 5.

BC Hydro Supply Chain Applications Project

Page 2

Page 8: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Status as of: September 30, 2019 Overall:

Risk While the risk profile of the project continues to improve as development progresses and the number of unknown elements within the solution continues to be reduced, ongoing delays with some activities have resulted in new project delivery risks. These new risks are the reasons for the amber rating for risk. Please refer to Section 6 for an updated assessment of the Project’s risks.

Schedule The current Target In-Service date is within the Target and Committed In-Service dates of November 2019 to March 2020 established in the Verification Report. In May 2019, the Project Steering Committee authorized a change to the project schedule, establishing a Target In-Service date of February 2020. Overall, the Project has progressed on schedule for key milestones; however, a number of critical path activities are currently progressing behind schedule placing the target in-service date at risk and resulting in the amber rating. Please refer to Section 7 for further information on the changes to the Project schedule.

3 Project Scope & Activities 1

There were no material changes in project scope in the reporting period. This 2

section covers the major accomplishments and work completed in the reporting 3

period as well as provides updates on planned activities in the next reporting period. 4

There were a few changes in project activities as outlined in Table 2 below. Table 2 5

provides a summary of the identified changes in project activities and the impact of 6

those changes. The cost and schedule implications of these changes are also 7

discussed in the Sections 4 and 7, respectively. 8

Table 2 Identified Changes in Activities and 9 Impact on the SCA Project 10

Description of Change Identified Impact Increased Ariba license fees and implementation services. Negotiated fees exceeded budgeted amount.

Additional cost

Additional BC Hydro IT testing support resources Additional resources and cost BC Hydro Project Coordinator role (unplanned) Additional resources and cost Funding for overtime worked by salaried BC Hydro staff Additional resources and cost System Integrator costs for additional training courses to be developed

Additional resources and cost

Additional BC Hydro (non-System Integrator) costs resulting from the schedule change and additional detailed design work

Schedule change and additional cost

BC Hydro Supply Chain Applications Project

Page 3

Page 9: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Description of Change Identified Impact

Additional System Integrator costs resulting from the schedule change and additional detailed design work

Schedule change and additional cost

Additional Quality Assurance Advisor costs resulting from the schedule change

Schedule change and additional cost

Access to Ariba via single sign-on Additional cost

3.1 Major Accomplishments and Work Completed 1

The following sections describe the major accomplishments completed during the 2

current reporting period. 3

3.1.1 Configuration 4

System configuration includes making entries and settings in pre-defined SAP 5

administration tables, which control the operation of the SAP application. 6

Configuration of the SAP system has been completed and is currently being tested 7

to ensure that the numerous configuration settings effectively support the new 8

business processes. 9

3.1.2 Detailed Design and Writing of Custom Program Code 10

Development of the solution detailed design was completed during this reporting 11

period. This included the writing, review, and approval of the various functional and 12

technical specification documents used to detail the design of 135 custom programs 13

included in the solution. 14

Writing of the custom program code was materially completed this period with 130 of 15

135 custom programs completed, and the remaining five still in progress. Of the 16

required 135 custom programs, 36 are modifications to existing programs and 99 are 17

entirely new custom programs required to support the solution. Examples include 18

modifications to the existing interfaces between PassPort and SAP, and new mobile 19

applications to enable warehouse management tasks to be processed on iPhone 20

and tablet devices. 21

BC Hydro Supply Chain Applications Project

Page 4

Page 10: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

3.1.3 Data Migration 1

During the current reporting period, the project completed the development of all 24 2

custom programs required to extract migration data from the legacy systems, to 3

transform the data into the required format for loading, and to load the data into the 4

new SAP system. Also during this period, detailed plans were developed and 5

execution started on data cleansing and enrichment activities for 56 unique data 6

elements. Examples of these activities include: cleansing existing vendor records, 7

capturing additional data to support enhanced quality management processes, 8

classification and enrichment of existing contract information, and cleansing and 9

enriching of inventory management data. 10

3.1.4 “Go-live” Planning 11

In May 2019, the project started to perform a series of practice or “mock” data 12

conversion exercises as part of the process to fully detail the cutover plan and to test 13

the conversion exercise. To date, three such mock conversions have been 14

completed with 21 of 24 data conversion items being tested in all three mock 15

conversion exercises, and all data conversion items being tested in at least one 16

mock conversion exercise. 17

In July 2019, and in preparation for moving into the testing stage of the project, the 18

initial detailed cutover plan was developed and then executed to create the project 19

testing environment. The results of this initial execution of the plan led to additional 20

details being added to a refined version of the cutover plan. The cutover plan is in 21

process of being executed a second time as the project prepares a second test 22

environment to be used in the second cycle of system testing. Information gathered 23

from this second conversion exercise will be used to further refine the cutover plan. 24

This process will be repeated for a third time in early December 2019 to create the 25

environment in which user-acceptance testing will be performed. Repeating the 26

process a number of times helps to ensure that the team will be well practiced and 27

able to successfully execute the system cutover during the go-live weekend. 28

BC Hydro Supply Chain Applications Project

Page 5

Page 11: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

3.1.5 Testing 1

On July 26, 2019, the Project’s Steering Committee approved the project to move 2

into the testing stage. The first round of formal system testing started on July 29, 3

2019. To date, the team successfully completed over 100 test scripts. The testing 4

process, which included the tracking of defects that are identified through test 5

execution, is managed with a testing tool called “ALM”. As of September 30, 2019, 6

the team had logged over 1,200 system defects. Of these, over 800 had been 7

successfully fixed and roughly 400 remain open. Of the current open defects, 2 are 8

listed as having a critical impact (i.e. they prevent the further execution of testing) 9

and 115 are listed as having a high impact (i.e. they seriously impair the system’s 10

ability to operate). Defects are expected to be identified and addressed through all 11

stages of testing. 12

Testing activities are currently tracking approximately four to six weeks behind 13

schedule. 14

3.1.6 End-User Documentation & Training 15

In this reporting period, the detailed planning for the development of the end-user 16

training materials was completed, the team of 10 instructional designers was on-17

boarded, and the development of training materials was started. The project team 18

identified roughly 80 courses to be delivered to end-users. The courses range from 19

short on-line courses to instructor led “hands on” classroom based courses. 20

Development of the training delivery schedule was also started this period, focusing 21

on the roughly 1,600 employees who will attend classroom training. Initial planning 22

for training delivery logistics was also started this period, including identifying 23

trainers, booking facilities, and planning for required equipment. 24

Training material development activities are currently tracking roughly one month 25

behind schedule. 26

BC Hydro Supply Chain Applications Project

Page 6

Page 12: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

3.2 Plans for Next Six Months 1

Work to be completed in the next reporting period includes the following: 2

• Completion of system testing, including execution of user-acceptance testing. 3

• Completion of the development of end-user training materials, finalization of 4

training delivery plans, and delivery of the initial rounds of end-user training 5

(focusing on training required prior to the system go-live); 6

• Completion of data cleansing and enrichment activities; 7

• Establish pre-go live baseline measures for tracking the realization of benefits, 8

as identified in Appendix I of the Verification Report; 9

• Finalization of cutover planning activities and execution of additional “mock” 10

cutover events in preparation for the go-live weekend; and 11

• Execution of the system go-live event. 12

BC Hydro Supply Chain Applications Project

Page 7

Page 13: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

3.3 Quality Assurance Advisor’s Monthly Report 1

KPMG remains the Quality Assurance Advisor on the Project and continues to 2

provide reports on the Project’s performance and progress on a monthly basis to the 3

Project’s Steering Committee. The report provides ongoing assessments on the 4

governance structure, financial controls, benefits structure, project schedule and 5

deliverables, and decision making, amongst other key areas. 6

Please see the latest monthly report submitted by KPMG attached as Appendix A. 7

4 Project Cost 8

4.1 Project Cost Summary 9

The actual total cost for the pre-Implementation phase was $25.5 million. The BCUC 10

accepted the capital expenditure schedule of $38.5 million to $45.4 million to 11

complete the Implementation Phase, and the estimated operating cost to complete 12

the Implementation phase is $7.4 million to $8.5 million. This results in a total Project 13

Forecast Cost Range of $71.3 million to $79.3 million. 14

Table 3 shows the current Project forecast cost and the actuals-to-date. Also 15

included in this section are variance explanations. 16

BC Hydro Supply Chain Applications Project

Page 8

Page 14: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Table 3 Project Expenditure Summary – Forecast and Actual Cost

Line #

Description

A B C D E F G H I J K L Verification Report Cost

Estimate Current Forecast Cost Forecast Cost Analysis Actual Cost Analysis

CapEx Cost

OpEx Cost

Total Cost

CapEx Cost

OpEx Cost

Total Cost

$M [F - C]

% [F / C]

Notes

Actual Cost-

to-Date $M

% of Current Forecas

t [K / I ]

% of Verificat

ion Report Cost

Estimate

[K / C] 1 Pre-Implementation Costs 2 Supply Chain Transformation Blueprint (Early Design

Costs) 7.3 0.0 7.3 7.3 0.0 7.3 0.0 100.0% 7.3 100.0% 100.0%

3 Identification Phase Costs 0.0 1.2 1.2 0.0 1.2 1.2 0.0 100.0% 1.2 100.0% 100.0% 4 Definition Phase Costs 15.3 1.6 16.9 15.4 1.5 16.9 0.1 100.3% 16.9 100.0% 100.3% 5 Total Pre-Implementation Phase Cost 22.6 2.8 25.4 22.7 2.7 25.5 0.1 100.2% 1 25.5 100.0% 100.2%

6 Implementation Phase Costs 7 System Integrator's Direct Costs 8 Realization 9 Final Preparation

10 Stabilization 11 Total System Integrator's Estimated Cost 12 BC Hydro's Internal Direct Cost 13 Realization 14 Final Preparation 15 Stabilization & Extended Onboarding 16 Total BC Hydro's Internal Estimated Cost 17 Total Implementation Phase Direct Costs 18 Contingency (% * Direct Future Costs) 19 Interest During Construction 2.3 0.0 2.3 1.9 0.0 1.9 -0.3 82.6% 10 1.1 57.2% 48.5% 20 Total Implementation Phase Expected Cost Estimate 38.5 7.4 45.9 38.3 7.4 45.7 0.0 99.5% 28.6 62.6% 62.3% 20 Total Project Expected Cost Estimate 61.1 10.2 71.3 61.1 10.2 71.3 0.0 100% 54.0 75.8% 75.8%

BC Hydro Supply Chain Applications Project

Page 9

Page 15: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Line #

Description

A B C D E F G H I J K L Verification Report Cost

Estimate Current Forecast Cost Forecast Cost Analysis Actual Cost Analysis

CapEx Cost

OpEx Cost

Total Cost

CapEx Cost

OpEx Cost

Total Cost

$M [F - C]

% [F / C]

Notes

Actual Cost-

to-Date $M

% of Current Forecas

t [K / I ]

% of Verificat

ion Report Cost

Estimate

[K / C] 21 Project Reserve - Reserve For Known Risks 1.3 0.0 1.3 1.3 0.0 1.3 0.0 100% 0.0 0.0% 0.0% 22 Project Reserve - Incremental Contingency 5.4 1.1 6.5 5.4 1.1 6.5 0.0 100% 0.0 0.0% 0.0%

23 Incremental Interest During Construction on project reserve 0.2 0.0 0.2 0.2 0.0 0.2 0.0 100% 0.0 0.0% 0.0%

24 Total Project Reserve 6.9 1.1 8.0 6.9 1.1 8.0 0.0 100% 11 0.0 0.0% 0.0% 25 Total Project Authorized Cost Estimate 68.0 11.3 79.3 68.0 11.3 79.3 0.0 100% 54.0 68.1% 68.1%

Numbers may not add up due to rounding

BC Hydro Supply Chain Applications Project

Page 10

Page 16: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Notes refer to notes 1 to 11 in Column I of Table 3: 1

Changes in Pre-Implementation Phase Costs: 2

1. The actual costs incurred in completing the pre-Implementation phase activities 3

were $100,000 higher than reported in the Verification Report. This was 4

primarily due to an unplanned $250,000 for BC Hydro employee’s overtime pay 5

for additional work performed during the Definition Phase. This unplanned 6

amount was partially offset by several tasks being completed under budget. 7

Changes in System Integrator Implementation Phase Direct Costs: 8

2. xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx9

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx10

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx11

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx12

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx13

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx14

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx15

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx16

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx17

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx 18

3. xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx19

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx20

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx21

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx22

xxxxxxxx 23

4. xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx24

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx 25

BC Hydro Supply Chain Applications Project

Page 11

Page 17: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Changes in BC Hydro Direct Costs: 1

5. xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx2

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx3

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx4

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx5

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx6

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx7

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx. 8

6. Xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx9

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx10

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx11

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx12

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx13

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx14

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx15

xxxxxxxxxxxxx . 16

7. xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx17

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx18

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx19

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx20

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx21

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx. 22

Changes in Total Implementation Phase Costs & Indirect Costs: 23

8. xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx24

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx25

xxxxxxxxxxxxxxxxxxxxx 26

BC Hydro Supply Chain Applications Project

Page 12

Page 18: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

9. The Implementation Phase contingency amount has been reduced by xxxx 1

xxxxxxxxxxxxxxxx of operating cost contingency and xxxxxxxxxx of capital cost 2

contingency) as a result of the contingency draws approved by the project 3

Steering Committee and outlined in Table 4 below. Of the original $5.7 million in 4

contingency, the project has xxxxxxxxxxx of contingency remaining. This 5

represents approximately xxxx per cent of the remaining future direct costs on 6

the project. 7

10. The forecast Interest during Construction (IDC) for the Implementation Phase 8

has decreased by $300,000 due to the difference in the method used to 9

forecast IDC and the more detailed daily calculation used to assign actual IDC. 10

11. The total Project Reserve amount remains unchanged from the Verification 11

Report. 12

BC Hydro Supply Chain Applications Project

Page 13

Page 19: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

4.2 Project Contingency Draws 1

A summary of the changes to Project activities and the identified impacts are 2

outlined in Section 3. Some of the changes in Project activities had a cost impact 3

due to an extension of the schedule or the need for more than the planned amount 4

of resource hours. Project contingency draws are approved by the Project Steering 5

Committee, and none of the approved contingency draws are as a result of changes 6

in the project scope. 7

The extension to the Project schedule resulted in three draws on contingency of 8

xxxxxxxxxxxx to cover the additional costs associated with the increased resource 9

time as follows: to cover the additional BC Hydro costs, to cover the additional 10

System Integrator’s costs, and to cover the additional Quality Assurance Advisors’ 11

costs. Please see section 7 for a discussion on the extension to the Project 12

schedule. The balance of xxxxxxxxxxxx was generally due to additional resources 13

being required to complete the planned activities. 14

Table 4 Identified Changes in Activities and 15 Impact on Scope and Contingency 16

Description of Change Identified Impact

Impact

Capital Contingency

($’000)

Operating Contingency

($’000) Increased Ariba license fees and implementation services. Negotiated fees exceeded budgeted amount.

Additional cost

xxxx

Additional BC Hydro IT testing support resources Additional resources

xxxx

BC Hydro Project Coordinator role (unplanned) Additional resource

xxxx

Funding for overtime pay for BC Hydro employees for additional work in the Definition and Implementation phases

Additional resource time

xxxx

System Integrator costs for additional training courses to be developed

Additional resources

xxxx

Additional BC Hydro (non-System Integrator) costs resulting from the schedule change and additional detail design work

Schedule change and additional cost

xxxx xxxx

BC Hydro Supply Chain Applications Project

Page 14

Page 20: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Description of Change Identified Impact

Impact

Capital Contingency

($’000)

Operating Contingency

($’000) Additional System Integrator costs resulting from the schedule change and additional detail design work

Schedule change and additional cost

xxxx xxxx

Additional Quality Assurance Advisor costs resulting from schedule change

Schedule change and additional cost

xxxx

Access to Ariba via single sign-on Additional cost

xxxx

Total draws: xxxxxxx xxxx

4.3 Summary of Individual Contracts Exceeding $3.0 million 1

The table below provides a summary of the total contract with PwC, the System 2

Integrator, as reflected in the Statements of Work (SoW). There are no other 3

contracts exceeding $3 million. 4

Table 5 Summary of Contracts exceeding 5 $3.0 million 6

No. Supplier and Scope of Supply Initial Contract

Value ($ million)

Forecast Contract

Cost ($ million)

Actuals to Sept

30, 2019 ($ million)

1 PwC System Integrator Costs – Design Stage

xxx1 n/a xxx2

2 PwC System Integrator Costs – Implementation Phase

xxx3 xxxx xxx4

1 Total fixed fee as of Statement of Work #2 signed on February 9, 2018 7 2 This is the final contract amount for the work completed in the Design Stage. 8 3 Total fixed fee as of Statement of Work #3 signed on October 19, 2018. 9 4 Actual costs to date based on PwC’s accrued amount. 10

5 Project Benefit Realization Plan 11

BC Hydro is finalizing the baselines and metrics and measures in the 12

Implementation Phase by iteratively assessing business impacts. There are no 13

changes in planned baselines, metrics, measures, and / or the tracking plan in this 14

reporting period. The Benefit Tracking Sheets filed as Appendix I-1 with the 15

BC Hydro Supply Chain Applications Project

Page 15

Page 21: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Verification Report reflects the most up-to-date information on the expected benefits 1

and the tracking plan. 2

6 Project Risks 3

In this section, BC Hydro provides updated mitigation plans and status, and updates 4

on the probability and impact assessments for risks as identified in the Phase Two 5

Verification Report in Table 6. Project risks continue to be managed through the risk 6

management process, and identification of new risks is supported by the ongoing 7

quality assurance assessments provided each month by the Project’s Quality 8

Assurance Advisor. Please refer to Appendix C for the Project Risk Register 9

Our current assessment of the overall Project risk is lower than at the beginning of 10

the Implementation Phase. This is due to the progression in Project activities, the 11

decrease in the number of unknown elements, and the fact that the impact of the 12

solution is better defined. However, there are ongoing delays with some activities 13

that have resulted in new project delivery risks identified in Table 6. 14

BC Hydro has grouped the risks into the following four categories: 15

1. Business risk: These risks have the potential to impact BC Hydro’s ability to 16

realize business benefits from the project. They include: how the extent of 17

change required to current business processes impacts BC Hydro’s ability to 18

realize the benefits upon which the project is justified (the supporting of the 19

Supply Chain Business Requirements, the closing of the capability gaps and 20

the achievement of monetized benefits); and the risk the business experiences 21

a reduction in productivity during the transition period from the existing to new 22

supply chain; 23

2. Technology risk: The technology risk assessment considers the maturity of 24

the technologies used to deliver the technical solution. Overall, the SAP supply 25

chain IT configuration that BC Hydro plans to implement is very mature and 26

BC Hydro Supply Chain Applications Project

Page 16

Page 22: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

considered low risk from both a probability and consequence perspective. 1

However, there are a few elements included in the project design which are 2

less mature and for which limited deployment experience exists at BC Hydro; 3

3. Project Delivery risk: The project delivery risk assessment considers the key 4

project delivery related risks that have been identified as having the potential to 5

impact BC Hydro’s ability to deliver the project on time, on budget and with 6

quality; and 7

4. Readiness risk: The readiness risk assessment considers the key risks related 8

to organizational readiness that has the potential to impact BC Hydro’s ability to 9

successfully undertake the project.10

BC Hydro Supply Chain Applications Project

Page 17

Page 23: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Table 6 Implementation Phase – Risks and Risk Mitigation Summary

No. Risk Category

Current Risk

Status

Risk Event / Threats Updated Mitigation Plans & Mitigation

Assessment

Verification Report

Report No. 1

Mitigation Status

Probability and Impact

Mitigation Status

Probability and Impact

1 Business Active, Updated

Risk that the scale of business process changes is too large to be absorbed successfully by BC Hydro.

Change management business engagement activities continue to be executed according to plan. Impacted business groups highly engaged in development of detailed transition and readiness plans.

In Progress Medium probability; medium impact.

In Progress Medium probability; medium impact.

Governance processes continue to function effectively.

In Progress In Progress

Previous plans regarding the extended stabilization period and the development of detailed benefits realization plans remain unchanged.

In Progress In Progress

2 Business Active, Updated

Risk that reduced productivity is experienced by the business while it transitions to the new supply chain

Change management business engagement activities continue to be executed according to plan. Impacted business groups highly engaged in development of detailed transition and readiness plans.

In Progress High probability; low impact.

In Progress High probability; low impact.

Previous plans regarding the extended stabilization period remain unchanged.

Planned Planned

3 Technology Inactive Risk that integration between SAP Fiori and UI5 screens is more costly to develop than anticipated

Development completed within budget. Monitoring Low probability: Low impact

Complete Risk has passed

BC Hydro Supply Chain Applications Project

Page 18

Page 24: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

No. Risk

Category Current

Risk Status

Risk Event / Threats Updated Mitigation Plans & Mitigation

Assessment

Verification Report

Report No. 1

Mitigation Status

Probability and Impact

Mitigation Status

Probability and Impact

4 Technology Active, Updated

Risk that interfaces to be developed between SAP and Unifier Construction Contract Management are new to BC Hydro, leading to unclear business needs

Confirmed that the additional interface is most likely not required. Will continue to monitor through stabilization to confirm this is the case.

Monitoring Low probability: Impact estimated at $0.3 million.

Monitoring Very Low probability: Impact estimated at $0.3 million.

5 Project Delivery

Inactive Risk of adverse or delayed British Columbia Utilities Commission Order

Complete Risk has passed

Complete Risk has passed

6 Project Delivery

Inactive Risk of requirement to undertake a protracted regulatory process in order to proceed with Implementation phase work

Regulatory process completed without disruption to project timeline.

Monitoring Low probability: High impact

Complete Risk has passed

BC Hydro Supply Chain Applications Project

Page 19

Page 25: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

No. Risk

Category Current

Risk Status

Risk Event / Threats Updated Mitigation Plans & Mitigation

Assessment

Verification Report

Report No. 1

Mitigation Status

Probability and Impact

Mitigation Status

Probability and Impact

7 Project Delivery

Active, Updated

Risk that the proposed offshore development model is determined to be impractical or ineffective. As discussed in section 2.3.2.1 [of the Verification Report], the benefits of offshore development include, but not limited to, lower cost and a 24-hour development cycle due to having resources in another time zone.

Some residual risk remains that off-shore development will prove to be ineffective or produce low quality outputs. Reserve of $1 million included in Implementation Phase estimate to cover cost of completing additional development on-shore.

Monitoring Low probability; impact estimated at $1 million.

Monitoring Very Low probability; impact estimated at $1 million.

8 Project Delivery

Inactive Risk of unsuccessful System Integrator Request for Proposal

9 Project Delivery

Active, Updated

Risk of weak project governance

KPMG continues to be engaged and working closely with the project team. Risk has materially passed as governance processes continue to function effectively.

In Progress Low probability: high impact

Monitoring Very Low probability: high impact

10 Project Delivery

Active, Updated

Risk of poor project management

KPMG continues to be engaged and working closely with the project team.

Monitoring Medium probability; high impact

Monitoring High probability; medium impact BC Hydro’s project governance

processes continues to work effectively

BC Hydro Supply Chain Applications Project

Page 20

Page 26: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

No. Risk

Category Current

Risk Status

Risk Event / Threats Updated Mitigation Plans & Mitigation

Assessment

Verification Report

Report No. 1

Mitigation Status

Probability and Impact

Mitigation Status

Probability and Impact

The probability of this risk has increased as reflected by having to repeatedly re-plan work due to schedule slippage. The impact of the risk is reduced from high to medium as the project has progressed further along thorugh implementation phase.

11 Project Delivery

Active, Updated

Risk of lack of clear Supply Chain Business Requirements

Business requirements further detailed through early Implementation Phase detailed design activities and recorded in realization deliverables Updated Functional and Non-functional Requirements List and Requirements Traceability Matrix.

Monitoring Low probability: Medium impact

Monitoring Low probability: Medium impact

12 Project Delivery

Active, Updated

Risk of scope creep, unnecessary complexity and customization

Project change control processes functioning effectively for managing minor design changes. No material scope changes requested or approved. No significant scope risks exist currently.

Monitoring Low probability: medium impact

Monitoring Low probability: medium impact

13 Project Delivery

Active Updated

Risk of unforeseen PassPort functionality issues

BC Hydro PassPort support team fully engaged in project activities, including testing of new solutions and assessing impacts on remaining PassPort functions.

Monitoring Low probability, high impact

Monitoring Low probability, medium impact

BC Hydro Supply Chain Applications Project

Page 21

Page 27: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

No. Risk

Category Current

Risk Status

Risk Event / Threats Updated Mitigation Plans & Mitigation

Assessment

Verification Report

Report No. 1

Mitigation Status

Probability and Impact

Mitigation Status

Probability and Impact

14 Project Delivery

Active, Updated

Risk of poor quality of delivery by SI

The probability of this risk has increased, as the project has not yet met the quality threshold to exit the first formal test cycle. As project progresses, the impact of this risk is reduced as BC Hydro’s resources are more knowledgeable and less dependent on the System Integrator’s expertise.

In Progress Medium probability, high impact

Monitoring High probability, medium impact

15 Project Delivery

Active, Updated

Risk of low data quality and or data not being ready according to Project Schedule

Detailed data clean-up and enrichment plans development and being executed.

In Progress Medium Probability, medium impact

In Progress Low probability, medium impact

16 Readiness Active, Updated

Risk of lack of availability of BC Hydro non-technology resources

Project continues to operate effectively with planned resource levels.

In Progress Low probability: high impact

In Progress Low probability: high impact

17 Readiness Active, Updated

Risk of lack of availability of BC Hydro technology functional sustainment resources

Project continues to operate effectively with planned resource levels.

In Progress Low probability, medium impact

In Progress Low probability, medium impact

18 Project Delivery

New Risk that reporting is not developed in time for initially planned testing dates

Build into Project schedule plans for ITC2 execution to align with report delivery.

In Progress High probability, medium impact Manage scope closely through change

control process to ensure build phase does not overrun.

In Progress

BC Hydro Supply Chain Applications Project

Page 22

Page 28: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

No. Risk

Category Current

Risk Status

Risk Event / Threats Updated Mitigation Plans & Mitigation

Assessment

Verification Report

Report No. 1

Mitigation Status

Probability and Impact

Mitigation Status

Probability and Impact

19 Project Delivery

New Risk that training materials are not developed in time for initially planned training delivery dates

Monitor the effectiveness of updated plans and corrective actions presented to the PMO.

In Progress High probability, medium impact

Assess options to modify training delivery schedule to allow additional time to complete material development by delaying start of initial pre-go live training.

In Progress

BC Hydro Supply Chain Applications Project

Page 23

Page 29: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

7 Project Schedule 1

In this section, BC Hydro provides the updated Project schedule and explains 2

changes in the project’s schedule. The current Target In-Service date for the Project 3

is now in February 2020. This date falls before the Committed In-Service date 4

identified in the Verification Report. 5

In May 2019, the Project Steering Committee approved an update to the project 6

schedule, setting the Target In-Service date to February 2020. This extended the 7

system build and testing schedule by 13 weeks from the previous Target In-Service 8

date in November 2019. The decision to place the Project into service in February 9

2020 was driven by a number of considerations, including: 10

• Roughly six weeks of schedule slippage on some critical path activities early in 11

the Implementation phase such as the completion of detailed design and the 12

development of custom program code; 13

• Required calendar year-end activities to apply mandated tax and payroll 14

updates to the current SAP production system which restricts the SCA Project 15

from being placed into service between late November and early January; 16

• Allowing time in late December–early January period for the project team to 17

have a break prior to the expected heavy workload of the go-live and early 18

stabilization period early in the following year; and 19

• Providing time to allow for the “hands on” training on the new system to be 20

delivered in January 2020, thereby enabling the training to be delivered as 21

close to the go-live event as possible. 22

The 13 week overall extension is comprised of the components outlined in Table 7 23

below: 24

BC Hydro Supply Chain Applications Project

Page 24

Page 30: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

Table 7 Project Schedule Change Components 1

Item Project Stage Description Extension 1 Realization Additional time to complete build activities prior to

the start of integration testing. The delay is a result of the additional work and review required to complete and close out the detailed design decisions, functional specifications, and delays in the planned completion of various technical items (i.e. programming).

6 weeks

2 Realization Additional time between integration test cycles to allow for additional time for defect resolution and preparation of test environments as based on a revised evaluation of project risks.

2 weeks

3 Final Preparation Non-working time through the Christmas Holiday period.

2 weeks

4 Final Preparation Additional time per BC Hydro’s request to not have user-acceptance-testing (UAT) activities overlap with the delivery of end-user training, and additional UAT time and pre-go live training time to allow proper review by the BC Hydro business groups as per BC Hydro standards and reduce overall project risk.

3 weeks

Total 13 weeks

The extension to the project schedule resulted in draws on contingency to cover the 2

additional costs associated with the increased resource time. Refer to Section 4.2 for 3

further information on the resulting contingency draws. 4

Table 8 below provides an update on the key milestones for the Project as of May 5

2019 and the status of these milestones as of September 2019. Please refer to 6

Appendix D for the latest approved Project schedule. 7

Table 8 Project Milestones 8

No. Stage Planned Date Actual or Forecast Date

Status

1 BC Hydro releases Implementation Phase work to System Integrator and Quality Assurance Advisor

October 2018 October 2018 Completed as scheduled

2 Implementation - Build Solution October 2018 to November 2019

October 2019 to February 2020

Expected late completion

3 Target In-Service Date November 2019 February 2020 Target in-service date is at risk of further delay.

4 Committed In-Service Date March 2020 March 2020 No change

BC Hydro Supply Chain Applications Project

Page 25

Page 31: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

PUBLIC Progress Report No. 1

October 1, 2018 to September 30, 2019

No. Stage Planned Date Actual or Forecast Date

Status

5 Implementation – Stabilization March 2020 to Mid July 2020

March 2020 to Mid July 2020

Expected on-time Completion

6 Implementation – Onboarding March 2020 to March 2021

March 2020 to March 2021

Expected on-time Completion

7 Project Completion March 2021 March 2021 Expected on-time Completion

Since the Project schedule was revised in May 2019, several project activities have 1

progressed behind schedule, including the development of custom programs, 2

system testing, and the development of end-user training materials. The Project is 3

currently four to six weeks behind schedule due to delays in the completion of the 4

first cycle of integration testing and development of training materials. This delay 5

may result in another revision to the Target In-Service date as a result of impacts to 6

downstream activities. The project team is currently assessing techniques to 7

possibly recover the schedule time lost due to the delay. In addition, the project team 8

is also reviewing the impact of placing the system into service during the busy fiscal 9

year-end period, which could result in a further delay. A forecast of the In-Service 10

date is expected in late November 2019, and will be provided in the next progress 11

report to be filed in April 2020. 12

BC Hydro Supply Chain Applications Project

Page 26

Page 32: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

BC Hydro Supply Chain Applications Project

Progress Report No. 1

Appendix A

Quality Assurance Advisor’s Monthly Project as of September 19, 2019

Page 33: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

Monthly Project Update

Prepared for BC Hydro SCA Steering Committee—

September 19, 2019

Appendix A

BC Hydro Supply Chain Applications Project Page 1 of 20

Page 34: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

2© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Activities Completed December August 22 – September 19 2019

September 19, 2019We are here

RM7

Interviews conducted

• Project Directors – Zaheer Shivji, Hugh Smith• PMO – Steven Purvis, Ivette Rico• Solution Integration – Maryna Korsei• Project Integration – Fred Jongeneel, Cory Lanovaz• Work Management Integration – Wayne Martell, Victor Galina• Purchasing & Contracts – Brian Wong, Oliver Garsault• Inventory Management & Quality – Darren Gebert, Mario Ortega• Data Management – Tim Kikkert, Greg Turnbull• Change Management – Daniel Watt• Technology – Sandeep Paul, Michel Maurivard• Reporting – Wendy Cachero, Diego Mendez, Kent Jarvie• Testing – Ross Hunter• Training – Souli Vohradsky, Sarah Low, Daniel Watt

List of documents reviewed

• Project Schedule (August 29th & August 9th

versions)

• Subordinate project plans

• 2.17.01 RICEFWU Tracker_Realization

• Reporting development tracker

• HPQC ALM environment (string test progress, integrated test scenario progress, defect instances and resolution progress)

• ITC1 testing kickoff document

• Updated ITC1 test scripts

• Testing status report graphs

• Data prep list

• Data conversion issue list

• SCA_CourseDevelopmentTracker

• Training Critical Path

• SCA Design Training Deliverables

• Weekly Status Report_ALL_20190903

• Weekly Status Report_ALL_20190909

• Weekly Status Report_ALL_20190916

Appendix A

BC Hydro Supply Chain Applications Project Page 2 of 20

Page 35: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

3© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Accountability and responsibility

Scope and change control

Project plan, deliverables, and resourcing

Cost management (financial model)

Change approach and strategy

Change leadership

Change capability

Business case

Benefit management

Incentives to deliver

Independent assurance

People strategy and design

Role design

Skills and competencies

Training and development Target operating model

Process design

Requirements management

Data management and reporting

Project governance Project management Change management Performance management People Process Technology

Enterprise architecture

System design

Data conversion / migration

Interfaces and legacy systems

Portfolio management Lifecycle management Business readiness High performing culture People performance management Security Transition and support

Structure and capabilityRisks, assumptions,

issues and dependencies management

Engagement and communication KPIs / metrics Business process controls

and BCP System buildOrganizational design

Monitoring and controls Quality standards management Change impact assessment Performance improvement Functional testing Non-functional testingCulture and behaviors

Project Delivery Functional Dimensions

Strategic alignment

Leadership

Delivery principles and policies

Vendor management (SI Selection Process Review)

Case for change

Adequate Project elements are appropriately addressed and meet expectations for current stage of the SCA project

Partial Project elements partially address requirements and mitigation actions have been identified by the Project Team

Inadequate Project elements are not addressed and mitigation actions have not been identified

Out of Scope Project elements that are out of scope for this assessment period

GETT Assessment Dimensions for This Period

Below highlights the assessment dimension for August 22, 2019 to September 19, 2019 and the associated findings.

Bolded outline denotes assessment dimensions detailed in executive summary.

`

Appendix A

BC Hydro Supply Chain Applications Project Page 3 of 20

Page 36: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

4© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

For this period the assessment identified the following key observations and recommendations.

Executive summary

ITC 1: Based on KPMG's assessment, the risk for functional testing has increased. ITC 1 is currently behind schedule. As of Sep 17, HP ALM indicates that for the Integrated Scenarios, ~72% of test scripts under integrated scenarios have been executed, ~ 52% of test scripts have been executed and passed.

KPMG observed that the project team had challenges executing against the test plan. Several key assumptions used for the testing plan did not hold true:

• Development objects: A number of RICFEWU objects were not completed and available for testing at the original planned date. As of the final week of ITC 1 (Sep 9), the RICFEWU tracker indicated that 14 objects had not yet passed FUT: 7 ARIBA objects, 5 non-ARIBA objects which had been planned for promotion during ITC 1, and 2 other non-ARIBA objects. As of Sep 16, the Weekly Status report indicates that 9 objects have not yet passed FUT (ARIBA and non-ARIBA).

• Script detail: Test scripts were not sufficiently detailed and required further re-work before tests could be executed.• Unclear data dependencies: Data dependencies for running test scripts were unclear, and as a result in some cases data was

not staged and ready for testing.• Integrated scenarios: For some integration scenarios, entry and exit requirements for string tests between streams did not line

up, which blocked testing for the scenario and required additional work to revise the test scripts.

ITC 2• Resource capacity KPMG is concerned that the delay for ITC 1 could impact the completeness for ITC 2 testing, as the project

team will need to simultaneously close ITC 1 and prepare for ITC 2.• Development completeness KPMG is also concerned that as FUT might not be completed for some reporting and ARIBA

objects in advance of ITC 2, defects from these two objects could block testing to a greater degree than anticipated and create further schedule risk.

Functional Testing

Func

tiona

l Tes

ting

Appendix A

BC Hydro Supply Chain Applications Project Page 4 of 20

Page 37: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

5© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

For this period the assessment identified the following key observations and recommendations.

Executive summary – cont’d

Proj

ect M

anag

emen

t

Project plan, deliverables

and resourcing

ScheduleBased on KPMG's observations, schedule risk is increasing. ITC 1 consumed significantly more time from business resources than was estimated, which has created workload balancing issues resulting in bottlenecks. Stream leads have indicated that business resources have reduced capacity to support other activities on the critical path including communication and engagement, training material development and report validation.

KPMG is concerned that this schedule risk could have an impact on completing business readiness activities.

RecommendationKPMG recommends that the project:1. Where required, identify dependencies between deliverables to sequence completion dates and identify deliverable

requirements;2. Validate that the assumptions used to identify resource requirements, activity duration and planned completion dates

continue to be appropriate; and3. Identify and assess contingency scenarios if effort and duration requirements are greater than expected compared to the

base case. Develop recovery plans if required.

The SI PMO has indicated that the project is in the process of re-assessing effort requirements for key resources and will adjust

the project plan accordingly to better balance workload and reduce bottlenecks.

Appendix A

BC Hydro Supply Chain Applications Project Page 5 of 20

Page 38: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

6© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Executive summary – cont’d

For this period the assessment identified the following key observations and recommendations.

Development schedule (Aug 22nd)

• Progress against plan The reporting dimension continues to indicate as yellow due to schedule pressure. Progress for

completing the reporting functional specification is tracking behind plan. The reporting team has indicated that this is the result

of the complexity of reporting requirements and unforeseen resource availability challenges.

• As the functional specifications have been written to meet “fit to proceed” criteria, KPMG is concerned that there is insufficient

time until ITC 2 begins to iterate the reports to fully meet business requirements and allow for the complete planned scope of

testing to take place for reports.

Development schedule (Sep 19th)• Progress against plan Based on KPMG’s observation, progress for reporting continues to track behind plan. The reporting team

indicated that ~6 objects (reports and dashboards) will not be fully completed in time for the start of ITC 2.• Validation: As BCH business resources were largely dedicated to supporting the execution of ITC 1, KPMG is concerned that

there was insufficient time for the business to validate the reports against business requirements. As a result, more effort could be required during ITC 2 than anticipated to address reporting defects.

• Data dependencies: At this time, based on KPMG’s observations the data requirements necessary to validate and test reporting

effectiveness have not yet been explicitly defined. Additional effort will be required to stage data to allow for testing to take place.

Recommendations• Test approach: KPMG recommends the project incorporate testing for reporting into the integrated scenarios. This will help

make sure that reporting dependencies required to support business processes are validated as part of the test cycle. • Data dependencies KPMG recommends that that project team complete analysis to identify data requirements necessary to

validate reporting and formally assign members on the project team to make sure this data is staged to allow for testing to takeplace.

Reporting

Dat

aM

anag

emen

t & R

epor

ting

Appendix A

BC Hydro Supply Chain Applications Project Page 6 of 20

Page 39: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

7© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Appendix AKey Findings

Appendix A

BC Hydro Supply Chain Applications Project Page 7 of 20

Page 40: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

8© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Key FindingsGETT

DimensionAssessment

Area Trend Expectation Findings Follow UpPr

ojec

t Man

agem

ent

Pro

ject

Pla

n, D

eliv

erab

les,

R

esou

rcin

g Project Plan and

ResourcePlan

• Project and resource plans are responsive to project changes (e.g. design decisions affecting project deliverables, dependencies, effort requirements, etc.) and feedback fromProject Team.

• The updated project plan reflects the findings of the SCA team and integrates lessons learned regarding timing, effort and resource requirements; areas of the project experiencing challenges are outlined to a greater level of detail to provide clarity and direction to team members.

Please refer to executive summary section

for full details.

Please refer to executive summary

section for full details.

Appendix A

BC Hydro Supply Chain Applications Project Page 8 of 20

Page 41: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

9© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Key Findings – Cont’dGETT

DimensionAssessment

Area Trend Expectation Findings Follow UpC

hang

e M

anag

emen

t

Cha

nge

Lead

ersh

ipChange

Leadership

• Roles and responsibilities have been identified for Change Leaders.

• The Engagement and Communication Plan is suitably detailed (e.g. plan identifies: communication channels, detailed activities, roles and responsibilities, target completion dates, and progress tracking).Progress against the Engagement and Communication Plan is tracked and documented consistently.

• An approach has been identified to assess effectiveness of communication campaigns.

BAR• Based on KPMG’s observations, the

Change Team is continuing to address feedback captured during BAR 1 and are communicating outcomes to the business through various channels (e.g. emails, Hydroweb)

• BAR 2 logistics have been arranged and invites distributed. The Change Team is finalizing the agenda, content and deliverables.

• KPMG will continue to monitor the outcomes of BAR 1 and development of BAR 2 materials.

Enga

gem

ent&

C

omm

unic

atio

n

EngagementActivities

Busi

ness

Rea

dine

ss

BusinessTransition

Plan

• Project has identified an approach to develop a transition plan which will address go-live, and post go-live; business, and technical, requirements,and dependencies by stream.

• The project has completed on-boarding the new BTP lead. The Change Team has indicated that with the new leadership and support from the Business Strategy Advisor, activity execution and progress has consistently improved.

• On-boarding has begun for Transition Point People and transition packages have been prepared to varying levels of detail depending on the impact to each TPP’s KBU.

• KPMG will continue to monitor the development of the transition planand TPP on-boarding material.

Appendix A

BC Hydro Supply Chain Applications Project Page 9 of 20

Page 42: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

10© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Key Findings – Cont’dGETT

DimensionAssessment

Area Trend Expectation Findings Follow UpPe

ople

Trai

ning

& D

evel

opm

ent

Training Plan

• Training plans and trackers are kept up to date and are leveraged as a source of truth for progress and upcoming activities.

• Course outlines are being developed with input fro various stakeholders (BSL’s, KBU leads, etc.) and

• Courses are being developed based on outlines and cover both technical and business training requirements.

• The Training Team has communicated that course development has not progressed according to plan, citing two main reasons: 1. Constraints on business resourced

due to ITC 1 and custom development priorities

2. Delayed completion of development reference material (i.e. PDD section 3 documents)

• Based on KPMG’s observations, there is

an emerging risk that training will fall behind schedule as the stated factors continue to remain a challenge for the project.

• Business training resources are being identified and actively on-boarded; the Training Team have indicted there is strong and positive engagement from the business.

• KPMG will continue to observe the development of training materials and monitor the risk status of the stream.

Org

aniz

atio

nal

Des

ign

OrganizationAlignment

• Plans have been created to identify changes in role descriptions and employees impacted by the SCA Project.

• The Change Management Lead is continuing to work with the HR department to finalize the two new roles being created.

• KPMG to will follow up with the Change Team on the status of the HR review.

Appendix A

BC Hydro Supply Chain Applications Project Page 10 of 20

Page 43: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

11© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Key Findings – Cont’dGETT

DimensionAssessment

Area Trend Expectation Findings Follow UpPr

oces

s

Dat

aM

anag

emen

t & R

epor

ting

Reporting

• Reporting requirements have been identified and consistently documented.

• Disposition for reporting requirements have been identified. Requirements needing custom development have been identified and planned for.

• Progress is monitored and tracked in a consistent and timely manner.

• Development progresses on schedule

Please refer to executive summary section

for full details.

Please refer to executive summary

section for full details.

Appendix A

BC Hydro Supply Chain Applications Project Page 11 of 20

Page 44: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

12© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Key Findings – Cont’dGETT

DimensionAssessment

Area Trend Expectation Findings Follow UpPr

oces

s

Secu

rity

Security Plan

• The security approach considers access requirements for Data, System Transactions, and Reporting.

• Progress is tracked for configuring and testing solution to meet security requirements.

• Security profiles have completed unit testing and fully loaded into environment for ITC 2.

• Security unit tests have been executed independently in ITC 1, but the PMO have indicated they will be integrated with process scripts in ITC 2 for full scenario testing.

• KPMG will continue to monitor progress with security document development and unit testing.

Tech

nolo

gy

Dat

a C

onve

rsio

n / M

igra

tion

Data Requirements

and Quality Assessment

• Data requirements have been suitably documented including: data object description, scope inclusion, criticality for go-live, source system, target system, and quality.

• A suitable plan has been developed for data conversion, enrichment, and cleansing and is updated regularly.

• Master data governance processes have been planned for based on requirements identified.

ITC 1• Due to the development delays with

MDG development, the Data Team has indicated that the full MDG load will likely extend beyond the scoped ITC 1 end date.

ITC 2• The Data Team has indicated that a the

draft ITC 2 load plan will allow for ITC 1 testing progression at the same time as ITC 2 prep activities in order to mitigate schedule impacts.

• Data prep for ITC 2 objects is ongoing and progressing according to plan. Based on KPMG’s observations, data

specific entry criteria will be met by the scoped ITC 2 start date (100% of master data, 80% transactional data).

• KPMG will continue to monitor progress against data prep activities for ITC 2

Appendix A

BC Hydro Supply Chain Applications Project Page 12 of 20

Page 45: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

13© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Key Findings – Cont’dGETT

DimensionAssessment

Area Trend Expectation Findings Follow UpTe

chno

logy

Syst

emBu

ild

Custom Development

• Custom development follows a consistent process for sequencing and prioritizing activities.

• Progress is monitored and tracked in a consistent and timely manner.

• Development progresses on schedule.

Schedule Impacts• Based on KPMG’s observations,

delayed completion of custom development and FUT has blocked string test and integrated test scenario execution in many cases. The Technology Team and PMO have communicated that all lagging development objects are being tracked and mitigation strategies are being defined to limit further schedule impact.

Development Quality• Based on KPMG’s observations,

although considerable improvement has been made, offshore development quality continues to cause challenges for the Project.

• The Technology Team raised a potential risk around the consistent updating of Technical Specification Documents following the resolution of defects; a reconciliation process will likely be required by the Project to ensure all TSDs are up to date.

• KPMG will continue to monitor development and FUT progress.

• KPMG will follow-up with the Technology Team during the next assessment period to discuss any updates with the internal review of development quality.

Appendix A

BC Hydro Supply Chain Applications Project Page 13 of 20

Page 46: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

14© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Key Findings – Cont’dGETT

DimensionAssessment

Area Trend Expectation Findings Follow UpTe

chno

logy

Func

tiona

l Tes

ting

Detailed TestPlan

• A consistent process is followed to track test outcomes, manage defects, and assess solution progress.

• Defects are triaged, escalated and resolved in-line with the testing plan and any existing BC Hydro testing and defect management strategies.

• The testing team and work stream leads have identified a suitable level of detail for test scripts.

Please refer to executive summary section

for full details.

Please refer to executive summary

section for full details.

Non

-Fun

ctio

nal

test

ing

Appendix A

BC Hydro Supply Chain Applications Project Page 14 of 20

Page 47: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

15© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Appendix BAugust – September 2019 Meeting Agendas

Appendix A

BC Hydro Supply Chain Applications Project Page 15 of 20

Page 48: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

16© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Meeting AgendasMeeting` Date Attendees Topics

Project Directors Sept 13 Zaheer Shivji, Hugh Smith Key messages from stream meetings, Project risk rating adjustments

Project Management Office Sept 12 Steven Purvis, Ivette Rico Schedule risks, project progress updates, ITC1 progress, development objects, reporting functional specifications and development effort,

Project Integration Team Lead Sept 16 Fred Jongeneel PDDs, string and integrated testing, BAR, customer development, security testing

Purchasing & Contracts Team Leads Sept 10 Brian Wong, Olivier Garsault PDDs, string and integrated testing, BAR, customer development, security testing

Work Management Team Leads Sept 11 Wayne Martell, Victor Galina PDDs, string and integrated testing, BAR, customer development, security testing

Inventory Management & Quality Team Lead and support Sept 10 Darren Gebert , Mario Ortega PDDs, string and integrated testing, BAR, customer development, security testing

Data Management Team Leads Sept 11 Greg Turnbull, Tim Kikkert Data prep and conversion progress, testing environments, MDG development and FUT

Technology Team Leads Sept 11 Sandeep Paul, Michel Maurivard Technical spec development, defect management and risks, offshore team capacity, testing environments

Reporting Team Leads Sept 16 Kent Jarvie, Wendy Cachero, Diego Mendez

Project plan, functional spec development, development efforts, technical design documents, testing approach, backend development

Change Management Team Lead Sept 13 Daniel Watt BAR debrief, training, HR role assessment

Solution Integration Leads Sept 11 Maryna Korsei ITC1, development objects, reporting functional tests, defect management, PDDs, security documents

Appendix A

BC Hydro Supply Chain Applications Project Page 16 of 20

Page 49: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

17© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Meeting AgendasMeeting Date Attendees Topics

Testing Lead Sept 12 Ross Hunter Integrated testing execution and test status, HPQC ALM test environment and progress reports, defect management

Training Leads Sept 10 Souli Vohradsky, Sarah Low, Daniel Watt

Training outline and course development progress, Instructional designer on-boarding, schedule and deliverables

Appendix A

BC Hydro Supply Chain Applications Project Page 17 of 20

Page 50: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

18© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Appendix CPlanned Assessment Activities

Appendix A

BC Hydro Supply Chain Applications Project Page 18 of 20

Page 51: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

19© 2017 KPMG LLP, a Canadian limited liability partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved. The KPMG name and logo are registered trademarks or trademarks of KPMG International.

Planned Assessment Activities for Next Period

Week of Activities

September 30 • Review progress in ITC 1 completion, PDD completion, reporting front end development, ITC 1 exit and ITC 2 entry criteria compliance, and training course development

October 7• Interview Key Stakeholders (Work-stream Leads, Functional Leads, PMO, Project Directors)• Review progress of ITC 1 completion, ITC 2 data prep and mock loads, reporting functional specifications, development of

training materials, and general project schedule progress

October 10 • Prepare Project Update to the Steering Committee

The planned quality assurance assessment for the period of September 19th to October 17th will include the following items. This list is not meant to be exhaustive or comprehensive .

Appendix A

BC Hydro Supply Chain Applications Project Page 19 of 20

Page 52: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

kpmg.ca

Appendix A

BC Hydro Supply Chain Applications Project Page 20 of 20

Page 53: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

BC Hydro Supply Chain Applications Project

Progress Report No. 1

Appendix B

Project Benefit Realization Plan Update

Page 54: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

There are no changes in planned baselines, metrics, measures, and / or the tracking

plan in this reporting period.

Appendix B

BC Hydro Supply Chain Applications Project Page 1 of 1

Page 55: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

BC Hydro Supply Chain Applications Project

Progress Report No. 1

Appendix C

Risk Register

Page 56: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

ID Title CreatedCurrent Status Risk Score Impact Likelihood Risk Owner

Treatment Strategy Risk Response/Mitigation

97 Reporting Timeline 2019-05-29

30. Mitigation Strategy Defined 12 3 4 Hunter, Ross

Treat (or Reduction)

Build into Project schedule plans for ITC2 execution to align with report delivery.Manage scope closely through change control process to ensure build phase does not overrun.

105Training materials not developed in time for initially planned training delivery dates 2019-09-25

30. Mitigation Strategy Defined 12 3 4 Hunter, Ross

Treat (or Reduction)

Updated plan and corrective actions presented to PMO Oct 1, 2019. Will continue to monitor effectiveness of corrections. Decision timing on late November 2019 to fully assess impact of delay and corrective actions. Assessing options to modify training delivery schedule to allow additional time to comlete material development by delaying start of initial pre-golive training.

63 Capacity of Business Solution Leads 2018-10-25

30. Mitigation Strategy Defined 8 2 4 Shivji, Zaheer

Treat (or Reduction)

Each BSL has been asked their strategy to deal with potential conflicts including identifying other project and business resources that can build solution knowledge in order to take on some CM activitiesChange Advisors have been assigned to each workstream to establish well planned focused activities to maximize BSL impact Establish Influencer/Relationship Steward tactic to identify influential business resources in each impacted area to act as conduits for communication & engagement. Influencers are actively supported by Relationship Stewards (including BSLs) to build/channel solution knowledge to impacted Stakeholders

20 Residual risk to "turn off” supply chain functions in PassPort. 2018-02-20

30. Mitigation Strategy Defined 6 2 3

Peachey, Tanya

Treat (or Reduction)

Regression test 1 has been completed and second regression test will be performed during ITC2.An integrated project plan has been created by SI, Trinoor and BC Hydro sustainment team to ensure a comprehensive testing and conversion approach.

30 Interdependencies between SCA and other ongoing initiatives 2018-04-03

30. Mitigation Strategy Defined 6 2 3 Rico, Ivette

Treat (or Reduction)

SCA project established as a key priority by the Executive Team. A Solution Alignment forum has been established to manage system changes and environment availability. This body has representatives from each of the major ongoing projects.

37 Performance issues SAP ECC-Transaction CJ20N 2018-05-1130. Mitigation 6 2 3

Gupta, Abhinav

Treat (or Reduction) To be reviewed as part of the results of planned system performance testing.

67 Central Warehouse Renovation Project 2018-11-19

30. Mitigation Strategy Defined 6 3 2

Gebert, Darren

Treat (or Reduction)

Warehouse renovation project are changing the sequence of work to focus on the rebuilding of the main warehouse building ahead of the construction of the new Critical Spares storage building. This should allow the work in the main warehouse building to be completed in time to not impact SCA. SCA has asked that the main warehouse building to be completed by Sept 1, 2019. Some risk remains that their schedule will slip as they do not have final permitting yet. Bi-weekly touch base meetings to continue to monitor risk.

76Change in BC Hydro external auditor could introduce additional testing or review requirements 2019-01-23

30. Mitigation Strategy Defined 6 2 3 Shivji, Zaheer

Tolerate (or Acceptance)

Project has no option but to accept this risk. Will continue to connect with the Controller's office to better understand any potential requests of the project so they can be accommodated into plans as early as possible.

80

Residual risk - Fail to reclassify of "SAP Personnel Number" to become non private information may result in Partner Number on PO/OA transactions need to be masked. 2019-03-11

30. Mitigation Strategy 6 3 2

Setiawan, Ben

Treat (or Reduction)

Apply enhancement to mask personnel id in OA/PO transactions if the replacement of personnel number as authentication in other systems cannot be done in time.

84Additional SAP ECC or Ariba licensing may be required to support future state service entry sheet process 2019-03-25

30. Mitigation Strategy Defined 6 2 3 Shivji, Zaheer

Treat (or Reduction)

Conduct analysis of transaction channels and mapping to existing contracts to determine which vendors will transact on each platform (Ariba vs. ECC Fiori). Use the outcome of this analysis to: - refine estimate of future document volumes and compare to benchmarks provided by Ariba and existing commercial arrangements;- estimate number of vendors/users who will need to access ECC;- leverage BCH IT as required to engage in commercial discussions with SAP.

90Missing data elements in SCA/BW data model to meet SCA reporting requirements 2019-05-28

30. Mitigation Strategy Defined 6 2 3

Smith, Hugh (SAP PM)

Treat (or Reduction)

Will continue to monitor development of reporting specs and data model to minimize likelihood of missing key data elements from the reporting model. Deliverable RD51 also added to provide additional understanding / review / sign-off of the BW data model.

94With only one planned comprehensive test cycle (ITC2) we may fall short of Q4 Gate 2019-05-29

30. Mitigation Strategy Defined 6 3 2 Hunter, Ross

Treat (or Reduction)

Start of ITC2 will be delayed by roughly 4 to 6 weeks while propject ensures entry critera are met. This will will reduce the likelihood of ITC2 not executing effectively. Residual risk remains that ITC2 timeline may need to be extended to fully achieve defined exit criteria. Updated approach presented to Steering Committee Oct 4, 2019.

Appendix C

BC Hydro Supply Chain Applications Project Page 1 of 8

Page 57: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

ID Title CreatedCurrent Status Risk Score Impact Likelihood Risk Owner

Treatment Strategy Risk Response/Mitigation

101 Performance of conversion during cutover weekend 2019-06-21

30. Mitigation Strategy Defined 6 2 3 Hunter, Ross

Treat (or Reduction)

1. Data team completes initial loads in S07/SD7.2. Determine the conversion window within the cutover window (based on how long all of the other tasks in the cutover plan take).3. Extrapolate performance in S07/SD7 to better determine impact and probability of risk.4. Determine when in the schedule a full size environment will be available.5. Arrange for Basis support to monitor test runs to look for opportunities for performance improvements.6. Determine when a full size environment will be available for performance testing conversion and advance this schedule if determined necessary by any of the tasks above.

103 Existing Contractor Portal Technology Version 2019-07-24

30. Mitigation Strategy Defined 6 2 3 Barnard, Tys

Treat (or Reduction)

Project to review technology implications of moving forward with current SCA design or look at other optrions.Risk has materially passed. Plan established with sustainment group as to how to proceed with contractor portal development.

26 Potential impact to union roles / job descriptions as a result of the project 2018-02-26

30. Mitigation Strategy Defined 4 2 2

Johnson, Valerie

Treat (or Reduction)

Updated impact assessment completed in Design Stage confirmed there is not likely to be any significant change to union roles or job descriptions as a result of the project. Will keep risk open and continue to monitor as impacts to specific roles continue to be detailed through Realization. Impacted roles will be reviewed as part of the Transition Planning effort via the Transition Planning Teams. HR representation will be on the teams to lead any effort to communicate with the union and make updates to Job Descriptions.

34Level of continued support for scheduled and ad-hoc excel exports on SCA data in Passport & SAP 2018-05-01

30. Mitigation Strategy Defined 4 2 2

Setiawan, Ben

Terminate (or Avoidance)

This risk could be mitigated by a combination of terminate & treat, ensuring all required data is captured in ECC, SharePoint, etc and extracted to the BW with appropriate end user tools or an IT support model for ensuring access to the data when needed.

46 SCA Regression Testing not final testing cycle 2018-05-29

30. Mitigation Strategy Defined 4 2 2 Rico, Ivette

Treat (or Reduction)

SCA project will ask for a freeze of the Pre-Prod environment to ensure other projects are not going live at the same time or impacting SCA. This will greatly reduce the risk of other non-SCA changes impacting SCA after IT Cycle testing where current non-SCA regression testing is planned.

82 Inefficient Partner Assignment if System Performance is Poor 2019-03-24

30. Mitigation Strategy Defined 4 2 2 Barnard, Tys

Treat (or Reduction) Ensure system performance is enough to prevent bottlenecks such as this one.

87SCA project depends on HR mini master for contractors being loaded through systainment 2019-04-16

30. Mitigation Strategy Defined 4 2 2

Setiawan, Ben

Tolerate (or Acceptance) Monitor.

74 No Mass Upload Tool for Updating Material Group on Service Masters 2018-12-14

30. Mitigation Strategy Defined 3 1 3 Wong, Brian

Tolerate (or Acceptance)

Will continue to monitor if proposed solution causes significant issues for the business.Although it wouldn't be ideal. The current LSMW can update values on Service Masters. It would require a request to IT to make a mass change. But it could be done.

95 Pre go-live training cannot be conducted in the planned 4 weeks 2019-05-29

30. Mitigation Strategy Defined 2 2 1 Watt, Daniel

Treat (or Reduction)

Validate the 4 week training assumption with the detailed course schedule.[Update: new schedule contains 5 weeks of training delivery. Final schedule to be validated]Update 2: new schedule has been approved by Steering Committee, which includes 5 weeks of pre-Go Live end user trainingAssessing option to reduce pre-golive training and focus on core activities only. Planning to be completed by mid-October 2019.

12 Extent of use of Service Masters and Services in Design 2018-02-05 40. Closed 16 4 4 Trask, JonTerminate (or Avoidance)

Service masters and use in services will be determined in purchasing workshops, currently mitigating other service related risks through elevation and visibility.

41 Schedule/Quality Risk not to make to Playback in time/quality 2018-05-17 40. Closed 16 4 4Buehner, Carsten

Tolerate (or Acceptance)

Activity focus on critical path activities leading towards Playback and Extend Design duration for 2 weeks to allow completion at current high intensity

44RICEFWU exceeds baseline estimates. Reduction of objects may impact solution design 2018-05-22 40. Closed 16 4 4 Shivji, Zaheer

Treat (or Reduction) Risk has passed. RICEFWU scope confirmed.

25 BC Hydro Dashboard tool running out of support and not user friendly 2018-02-26 40. Closed 15 3 5Buehner, Carsten

Tolerate (or Acceptance) The mandate for the project is not to change existing BC Hydro reporting tools and strategy

66 IT sourcing award in June 2019 conficts with SCA schedule 2018-11-06 40. Closed 15 3 5Dixon, Kiernan

Tolerate (or Acceptance)

Kiernan, Nicole and Hanif will get the right people from Category management and IT to identify all possibilities of expediting the sourcing process in related areas. Plan B: Start the design based on current supplier (Compugen) and twist it later on once the real supplier is confirmed.

Appendix C

BC Hydro Supply Chain Applications Project Page 2 of 8

Page 58: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

ID Title CreatedCurrent Status Risk Score Impact Likelihood Risk Owner

Treatment Strategy Risk Response/Mitigation

93 Technical build not completed before ITC1 2019-05-29 40. Closed 15 3 5 Hunter, RossTerminate (or Avoidance)

Close design decisionsRamp up build throughput (capacity, collaboration across teams)Other mitigating actions: PwC visit to offshore office to manage delivery closer. Re-planning exercise going on now to include CRs and forecast which objects will be completed by Jul 19 and which will not be ready for Jul 29 (official start of ITC1)

98 Ariba Timeline 2019-05-29 40. Closed 15 3 5Dixon, Kiernan

Treat (or Reduction) Escalated to issue 75 as items not delivered per schedule.

13 Meaningful engagement of Business before Workshops 2018-02-05 40. Closed 12 3 4 Trask, JonTolerate (or Acceptance)

Wayne has weekly meeting with Design Group; update meeting was conducted with Field operations group steering committee; conversations had to elevate with working group members (PCM & Generation); ongoing involvement with SME's by teams; regular bi-weekly working group meeting; 2 cycle workshop methodology with mini-playbacks and playbacks; change management team involvement in sessions

21 SCW and SCA Scope 2018-02-20 40. Closed 12 3 4 Trask, JonTreat (or Reduction)

Identify that scope does not include replacement of SCW, workshops must consider interface or integration in solution. We will not replace SCW with SAP/Ariba.Specific workshops in scheduled in Cycle 2 to review and develop solution for how SCW Ariba and ECC interact.

22 Unifier and SCA Scope 2018-02-20 40. Closed 12 3 4 Trask, JonTreat (or Reduction)

Clarification of scope in Leads meeting, workshops to consider implications of unifier in SAP design Specific workshops in scheduled in Cycle 2 to review and develop solution how projects related contracts will be managed going forward between ECC, SCW and Unifier (decommissioning of Unifier being contemplated)

27 Test Tool version, schedule and support dependant on BCH IT PMO team 2018-02-28 40. Closed 12 3 4Charbonneau, Kim

Terminate (or Avoidance)

Work with IT PMO team to get early SCA project set up in existing 11.x version and stay in communication with them on status of 12.x upgrade. Investigate plan B to determine if implementing stand-alone SCA HP ALM is feasible and Plan C to stay on v11.x and not upgrade.

28 BCH Business Lead playing dual roles on the project (old risk 77) 2018-02-28 40. Closed 12 4 3Smith, Hugh (SAP PM)

Treat (or Reduction)

The project will continue to monitor. Consider elevating one of the Business Solution Leads to take on some of the Business Lead role.

42 Resource Risk related to extended high work intensity 2018-05-17 40. Closed 12 4 3Buehner, Carsten

Treat (or Reduction)

Extend Design duration further (1-2 weeks) to allow for some relief on intensity

60 PS Single Network Header Usage 2018-10-18 40. Closed 12 3 4Jongeneel, Fred

Tolerate (or Acceptance)

Explore impact on allowing multiple network headers - in particular for potential risk with the P6 and BW interfaces as well as change impact for end users.

65 BW migration on HANA may result in impact to SCA reporting development 2018-11-02 40. Closed 12 3 4Gupta, Abhinav

Treat (or Reduction)

Immediate next step is to assess the impact and come up with a mitigation strategy

68 Functional Team Resource Constraints for BW Reports 2018-11-21 40. Closed 12 3 4 Rico, IvetteTolerate (or Acceptance) Risk has passed.

75L3 Process Review time is taking longer than expected, impacting project schedule 2019-01-16 40. Closed 12 3 4

Brandes, Michael

Treat (or Reduction)

Darren is scheduling meetings this week for MMQ to clarify requirements including finance for repair and refurbishment. Wayne is bringing in some additional Distribution business resources to assist with the review and approval of Distribution flows. Stations flows have been sent to SWPE project for feedback.Plan still needed for other business areas which are outstanding (e.g. T lines).

77More time and effort to be involved in 'Puchasing Tax Determination' solution design 2019-02-07 40. Closed 10 2 5 Yang, Robbin

Treat (or Reduction)

The system will be design to determine PO Tax code as accurate as possible based on the tax indicator on vendor, plant, and material master/service master/material group. The system will display a warning on PO creation/change if the PO belongs to generation plants so the user can check the tax code and enter the right one. See Decision# 117.

102Requirements for approvals design may not be fully reflected in the current design 2019-06-28 40. Closed 10 2 5 Shivji, Zaheer

Treat (or Reduction) Escalated to CR 163

14 Quality Impact due to Agressive Schedule 2018-02-08 40. Closed 9 3 3Luna, Leonardo

Tolerate (or Acceptance)

Risk has now passed. Schedule extended per Steering Committee approval (PLCN's 27, 28, and 29) to resolve resulting quality impacts of aggressive schedule.

23 Aggresive schedule of Design Stage 2018-02-22 40. Closed 9 3 3Smith, Hugh (SAP PM)

Treat (or Reduction)

Ensure progress tracking and management processes in place. Use escalation processes as needed to resolve any issues / delays that may arise. Schedule extended per Steering Committee approval to reduce workload on team and allow time for deliverable quality.

29 Inability to properly limit access to supply chain information 2018-03-19 40. Closed 9 3 3Simpson, George

Treat (or Reduction) Risk has passed.

32 Extent of Fiori (or similar) user interface ehancement required 2018-04-27 40. Closed 9 3 3Gupta, Abhinav

Treat (or Reduction)

Develop approach to decide on appropriate user experience and decision approach with Working Group.

Appendix C

BC Hydro Supply Chain Applications Project Page 3 of 8

Page 59: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

ID Title CreatedCurrent Status Risk Score Impact Likelihood Risk Owner

Treatment Strategy Risk Response/Mitigation

35Lack of clarity / pre-socilaization with Working Group on design approval process may slow approval timing 2018-05-04 40. Closed 9 3 3 Yang, Robbin

Treat (or Reduction)

To conduct sessions with WG during May to present C2 Playback Methodology, present Approval Flow and Deliverables Templates (Integrated Design Report).Update June 04 - WG session scheduled June 06.Risk has passed. Additional session completed to enable successful completion of Playback and approval of the IDR.

45Impact of the Passport mechanism for Average Unit Pricing calculation versus the SAP Moving Average Pricing 2018-05-22 40. Closed 9 3 3

Martell, Wayne

Treat (or Reduction)

Technical and Functional Team will be assembled to run Use Case simulations between SAP and the Passport to validate the impacts, magnitude of change, configuration options and prepare a findings report that will be assessed by BCH to assess the risk and next actions.

49Plan to use the data leads as the project cutover leads not BC Hydro's standard approach 2018-06-07 40. Closed 9 3 3

Praveen, Roch

Treat (or Reduction)

Risk has passed. Plan has been updated such that the Integration Manager will transition into the role of cutover lead.

51Solutioning for IT will extend beyond Design for Telus TSR replacement project 2018-06-15 40. Closed 9 3 3

Luna, Leonardo

Treat (or Reduction)

Additional review sessions held with IT to confirm solution meets additional requirements. Risk has passed.

57 Overall project budget may exceed upper bound cost estimate of 79.3M 2018-08-14 40. Closed 9 3 3Smith, Hugh (SAP PM)

Treat (or Reduction)

Project team preparing various scenarios for review with Steering Committee. Continue to work through detailed project plans with PwC to confirm project estimates. Process completed and cost estimates aligned.

58Plans for data conversion, data clean-up and data creation not fully detailed as of the end of Design Stage 2018-10-02 40. Closed 9 3 3

Turnbull, Greg

Treat (or Reduction)

High level plan for developing a plan:- Facilitate series of conversion workshops with functional and business teams with the objective to document the approach for each object and uncover hidden assumptions [COMPLETE]- Present high level approach for each object as a slide (for working group signoff in place of approving DTO) [COMPLETE]- Develop conversion estimates, schedule, and resource plan for approved scope. [COMPLETE]- Identify data quality issues that impact the project based on the approved conversion scope. [COMPLETE]- In consultation with the business develop data remediation plans for issues impacting the project - plan exists - approval from accountable WG members in in progress [IN PROGRESS] Most current data prep items (>75% by record count) will be reviewed with the accountable WG member by the end of the month. Initial dashboard showing progress against data prep items will be published by the end of Jan, as originally communicated to WG. Once the dashboard is published and work is underway this risk should be closed.

70Records Managements requirement might require more complex technical solution 2018-11-22 40. Closed 9 3 3 Rico, Ivette

Treat (or Reduction) Risk has passed.

79The design of Purchasing solution in not clearly understood by different stakeholders involved 2019-03-06 40. Closed 9 3 3

Korsei, Maryna

Treat (or Reduction)

1) Review of targeted areas of the design by Senior Procurement Manager (Rob Dodman) during March and April2) Design walk-through sessions with Rob Dodman, Linda Beardsell, Maryna, Zaheer and Purchasing team held on April 12, April 26 & May 32) Review of Purc decisions at the Open design workshops with the broader SCA team3) Integrated L3 review sessions with the broader SCA team4) Involvement of the Business Lead, and external stakeholders (e.g. Linda) into the design or implementation issues as required.

91 Overpayment due to Duplicate Service Entry Sheets 2019-05-28 40. Closed 9 3 3Garsault, Olivier

Treat (or Reduction)

Possible mitigation options, individual or combined: Keep process as-is: SES approvers will be responsible of catching double-entries - this is the whole point of the SES approval process. CON: approvers may not be able to catch this unless they're aware of what has been entered so far.Business areas should be responsible of running reports, such as the ME2S-Planned/Actual Comparison, to check their planned versus actual charges, and do a check for duplicates. CON: It is after the fact, it is unlikely business areas will run this, and if a duplicate is found, it will require reversal efforts.Ask suppliers to always provide a unique reference number in their entry sheets, entered by them or submitted to a BCH administrator via email, and add a custom validation in the SES process to issue an error or a warning. CON: additional custom development, and suppliers can easily ignore this rule.Create an automatic notification to the SES creators and approves when similar SES entries exist in the system. CON: Duplicate check rules would not be 100% reliable and could become a nuisance.

Appendix C

BC Hydro Supply Chain Applications Project Page 4 of 8

Page 60: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

ID Title CreatedCurrent Status Risk Score Impact Likelihood Risk Owner

Treatment Strategy Risk Response/Mitigation

38 No Solution for MRO 2018-05-14 40. Closed 8 2 4 Yang, RobbinTreat (or Reduction)

SCA will support MRO target state (process and roles) with a set of solutions as outlined below. A. Clarity has been established regarding target business process for MRO materials. Anticipated future state is based on the process currently piloted in Vernon (referred as ‘MRO Pilot’) and assumes the following:1) Field Store keeper will manage MRO materials for all BC Hydro organization, ordering from MRO Supplier directly as required:• to maintain a standard compliment of materials "On Hand" [so-called ‘Working Stock MRO’], while• non-standard items will be ordered "On Demand" on behalf of requestors (multiple business users). A back office "cost allocation" would happen via JV cost allocation process afterwards.2) Materials will be delivered by MRO supplier directly to the Field Store. B. Upon such clarifications provided by the Category Management, the following SCA solutions were discussed and deemed to be optimal in order to support future management of MRO materials:1) Ordering :• A range of standard ECC purchasing channels  (PO, Non-PO invoices, Framework PO)  will support transactional activities in ECC for MRO and will provide certain flexibility to accommodate:  anticipated  MRO business processes as per ‘MRO Pilot’ initiative and

  ordering model established under potential  future contract in Q4 F19 – Q1 F20 (upon RFP

completion)• Ariba Punch-out catalogues will support ordering activities with Vendor catalogues integrated into ECC. This will allow FS Keepers to replenish MRO materials stock at the Field Store or satisfy ad-hoc requirements by leveraging supplier online catalogues through ECC instead of placing orders via phone or by logging into the supplier’s website.• If non-PO channel is chosen, ability to pay with the credit card will remain post SCA Go-Live (currently MRO is paid mostly by the credit card)2) Receiving:

39Unexpected Project Costs from Implementation of Online Catalogues via Ariba 2018-05-14 40. Closed 8 2 4 Shivji, Zaheer

Treat (or Reduction) Risk has passed. Use of Ariba confirmed and consistent with project budget.

69 BW Rework and New Reports Post SCA Go Live 2018-11-21 40. Closed 8 2 4 Rico, IvetteTreat (or Reduction)

After completing the Reporting Requirements review we will evaluate the priorities and work only on "Must have" reports (Priority 1 and 2) to reduce potential rework after Go Live.

78Ariba-Advance Ship Notice enhancement needed if MMQ needs Deliveries to be Picking Relevant 2019-02-22 40. Closed 8 2 4

Gebert, Darren

Tolerate (or Acceptance)

Setup interfaces as per current approach (no issues), and if MMQ later decides to make inbound deliveries relevant for picking, we'll investigate where it breaks and how we can resolve the issue. In the meantime, we'll also ask Ariba to explain why the deliveries must be set as not relevant for picking for the ASN interface to work.

81 Customer Build Program - BCH provides Materials to ESPs directly 2019-03-20 40. Closed 8 2 4Gebert, Darren

Treat (or Reduction)

MMQ BSL is currently in conversation with the Proposal lead and will be listed as optional attendee on all upcoming proposal review/assessment meetings. Complete initial rough assessment of proposal's impact to current SCA design/solutions

86Realization of benefit of improved inventory turns may be impacted by poor scheduling compliance 2019-03-29 40. Closed 8 2 4

Sveinson, Laurie

Treat (or Reduction)

Item identified will be addressed through Communications, Training, Key Actions and the Sustainment Plan.

100Training Risk - "Train the BCH Trainer" Effectiveness for Demand/MRP Related Solutions 2019-06-18 40. Closed 8 2 4

Gebert, Darren

Treat (or Reduction)

Continued Knowledge TransferConfirmed Course Outline and Delivery Approach

9 Ability to identify and confirm Business SME’s for planned Kick-Off 2018-01-29 40. Closed 6 2 3 Shivji, ZaheerTreat (or Reduction) PMO considered options and impacts and collectively moved the Kick-Off to 29 Jan 2018.

17Scope Risk related to potential increase of MDG with impact on MDG and broader System Integration Scope 2018-02-16 40. Closed 6 2 3

Schellekens, Harold

Terminate (or Avoidance)

Initial investigations underway, focus topic in Design

24 CDC - Central Distribution Center Decision is made but not implemented yet 2018-02-23 40. Closed 6 2 3Peachey, Tanya

Treat (or Reduction)

Risk has passed. Enterprise structure confirmed through Design Stage. Included in Implementation plans to deploy.

33Timing risk of completing ITDSP Gate 3 approval may become bottleneck on Imp Phase approvals 2018-04-30 40. Closed 6 3 2

Schellekens, Harold

Treat (or Reduction)

Complete Gate 3 approval in two stages. Initially complete approval of as many items as possible prior to special Board meeting then plan for a follow-up approval of any outstanding items . Final Gate 3 approval will take place after the special Board meeting and after the Phase Two regulatory application has been filed. Risk has passed. Gate 3 successfully past September 13, 2018 ahead of special Board Meeting on September 27, 2018.

40 Schedule and scope for UAT and Regression 2018-05-17 40. Closed 6 2 3Charbonneau, Kim

Treat (or Reduction)

Monitor Unit Testing for meeting Q-Gate for Integration Testing, monitor Integration Testing so UAT is not impacted.

47 RICEFW Tracker usage (KPMG item May 18, 2018) 2018-06-01 40. Closed 6 2 3Schellekens, Harold

Treat (or Reduction) Risk has passed per KPMG Design Review Report.

Appendix C

BC Hydro Supply Chain Applications Project Page 5 of 8

Page 61: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

ID Title CreatedCurrent Status Risk Score Impact Likelihood Risk Owner

Treatment Strategy Risk Response/Mitigation

48Proper disposition / documentation of items within Fit / Gap log (KPMG item May 18, 2018) 2018-06-01 40. Closed 6 2 3 Yang, Robbin

Treat (or Reduction)

The Fit/Gap (Requirement) Masterlist is a Deliverable for Design stage closure, disposition of each requirement with an appropriate closing status, assessment comment and a business lead review a defined and KPI tracked key activity. Risk has passed per KPMG Design Review Report

50Potential conflict on QM configuration/design for meters (devices) between SCA and Meter Tracking (MTS) projects during realization phase 2018-06-13 40. Closed 6 2 3 Rico, Ivette

Treat (or Reduction)

Related to risk 30. Projects to continue to coordinate timing and activities to minimize mutual impacts. SCA project takes priority in case of significant conflict.

61 QM Key User Availability during Realization Phase 2018-10-22 40. Closed 6 2 3 Rico, IvetteTreat (or Reduction) PMO: Business has agreed to assign multiple part time resources .

64 A/P workload may increase as a result of the future Ariba scope 2018-10-29 40. Closed 6 2 3Luna, Leonardo

Treat (or Reduction)

Simplify the vendor setup as much as possible by:Allow A/P to enter the Ariba start date directly in ECC.Do not make this an MDG field that will require a CRBuild the system enhancements towards the automation of the Ariba-vendor setup (e.g. automatically detect when a vendor is Ariba or not using the Ariba start date)Adjust the Ariba configuration in ECC as generic as possible so that no vendor-specific configuration is needed (e.g. setup general output conditions that enhancements will override just for Ariba vendors).

71Additional BW net new requirements, could introduce additional scope for custom development 2018-11-22 40. Closed 6 2 3

Brandes, Michael

Treat (or Reduction) PwC will confirm the requirements by end of RM2

72Lack of functional specs will impact dev. teams ability to meet RM2 development targets 2018-12-07 40. Closed 6 2 3

Brandes, Michael

Treat (or Reduction)

Proposed mitigation would be to get all specs. for RM2 approved by Dec. 14th - this is the last date for the tech team to have all RM2 specs approved with CRs

83Transmission Line workflow will not operate correctly if business does not agree to change some current practices 2019-03-25 40. Closed 6 2 3

Martell, Wayne

Treat (or Reduction)

Summarize the changes that T-Lines would need to make to its current practices and present to business stakeholder (Bill Earis). If not willing to make the changes by F21 escalate to Steering Committee for resolution.Since it is not feasible to make the changes part way through a fiscal year, for the remainder of F20, accept that this risk will materialize and include the appropriate mitigating activities as part of the Readiness and Transition Planning activities for T-Lines and Materials Management.Risk has now passed. Future state process agreed to with Transmission and plans incorportaed into change menegement and engangement activities.

85 Loss of knowledge continuity due to illness of Finance Lead 2019-03-27 40. Closed 6 2 3 Shivji, ZaheerTreat (or Reduction)

Project team summarizing list of inputs required from Finance, along with estimate of effort and timing.Project team will work with Finance Directors to identify resource(s) for each activity.Andrea Ling has transiitoned into the role to provide suport in Maria's absence.

92 Detailed design is not completed by April 29th 2019-05-29 40. Closed 6 2 3Peachey, Tanya

Treat (or Reduction)

Prep for, engage right participants, closely manage discussion, push for clear decisions

96 Quality Issues (incl. design) may show up in ITC1 2019-05-29 40. Closed 6 3 2 Hunter, RossTreat (or Reduction)

Risk has materially passed. Project continues to work to updated timeline for completing ITC1 activities. Identified defects being resolved based on priority. While some process / design items logged, no signicant design gaps were identified.

99 Inability to sufficiently restrict access to Supply Chain data in BW 2019-05-31 40. Closed 6 3 2 Shivji, ZaheerTreat (or Reduction)

Risk has passed. Reviewed proposed detailed design with key stakeholders and confirmed that approoach is acceptable. CR 176 logged to track addition of new auth objects to control table.

10 BCH Work Management Business Lead not committed full time yet 2018-01-29 40. Closed 4 2 2 Shivji, ZaheerTreat (or Reduction) Confirm the status and pending outcomes with Leadership.

15Start of Implementation Phase may be delayed due to phase funding approval delay 2018-02-15 40. Closed 4 4 1

Smith, Hugh (SAP PM)

Treat (or Reduction)

Seek Executive approval to proceed with some Implementation Phase activities ahead of receiving the BCUC decision / approval of Implementation Phase funding, assuming there is a high level of confidence that a positive decision will be received. Approach approved by ET April 24, 2018.Board resolution approved Sept 27, 2018 to allow project to begin Imp activities while regulatory process completed in parallel. Slight residual risk remains is process extends beyond six months.Residual risk now past as the commission has issued its decision on the Implementation Phase funding.

18 Other Project Risk: Operations Integration Program 2018-02-19 40. Closed 4 2 2Smith, Hugh (SAP PM)

Treat (or Reduction)

Introductory meeting held between SCA and OIP project management offices in October 2018. Regular touchpoints arranged between SCA and OIP Business Leads, Solution Leads and Project Managers. Will continue to monitor key decisions to identify areas of overlap or conflict. Previous mitigation plan (pre Oct 2018): Confirmed approach that SCA is priority over potentially conflicting project plans between the projects. Senior Operations representative involved with the Operating Model added to the SCA Working Group to ensure alignment of future state designs.

Appendix C

BC Hydro Supply Chain Applications Project Page 6 of 8

Page 62: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

ID Title CreatedCurrent Status Risk Score Impact Likelihood Risk Owner

Treatment Strategy Risk Response/Mitigation

19 Other project risk: CLRA VMS development and timing risk 2018-02-19 40. Closed 4 2 2 Rico, IvetteTreat (or Reduction)

Regular communications between CLRA and SCA projects. Interim SCA Tech PM to move to managing the CLRA VMS project. Sustainment specialist working part time on both projects to ensure alignment of design and timing.

31 Access to historic PDW for Supply Chain Reports 2018-04-25 40. Closed 4 2 2Setiawan, Ben

Terminate (or Avoidance)

Current PDW reports will continue to operate for some period post go live while users are transitioned to new SAP and BW reports. Custom reports to be developed post SCA go-live to replace "copy" of PassPort system utilized for supply chain historical data access.

52 Absence of Overall Plan and Owner for Material/Service Group 2018-06-19 40. Closed 4 2 2Peachey, Tanya

Treat (or Reduction)

Risk has materially passed. Resource has been assigned to complete design process. Will continue to monitor for initial months of Realization.

53 Absence of Overall Plan and Owner for Service Master 2018-06-19 40. Closed 4 2 2Peachey, Tanya

Treat (or Reduction)

Assign a single owner from the SCA project who will be accountable for building an overall plan that includes all impacted activities, groups and objects, with a clear timeline and identification of critical path. Risk materially passed. Tania Cernezel assigned to complete this activity. Will continue to monitor through early Realization phase.

54Time in design to fully work through integrated process designs (KPMG item June 15) 2018-06-22 40. Closed 4 2 2

Peachey, Tanya

Treat (or Reduction)

• Internal team end-to-end L3 reviews late November:  I will work with the BAs to organize sessions to walk through the process flows end to end with their own team members to ensure the proper Security Roles (RDD) are noted in the swim lanes, RICEFWU are noted where relevant, process steps and sequence are correct and the steps are understood by the team and ready to be incorporated into PDD, test scripts and training materials. They will also validate that inputs/outputs to other team L3 flows are consistently connected• Integrated team end-to-end L3 reviews in February:  integration team will select a set of integrated process flows to review in cross team sessions over several days to ensure integration between process maps is reviewedAdditional Integrated L3 sessions held in May 2019 as part of the Open Design closure sessions. Team feels key touch points have been reviewed and further sessions in advance of integration testing are not required..• Integration test scripts will be created which test processes end-to-end and by their very nature will test cross team processes, inputs and outputsWill also be setting up a regular “integration” touch base meeting with the BAs to make sure they are aligned, integrated and producing consistent Process deliverables.Risk has now passed. All review activities completed successfully.

59 Material Master MDRS additional activities planned to be finished by Oct 26 2018-10-13 40. Closed 4 1 4

Ortega cardenas, Mario

Tolerate (or Acceptance) Close follow up on decision making and MDRS Documentaiton

62 Demand Management / MRP Consultant is required 2018-10-23 40. Closed 4 2 2Brandes, Michael

Treat (or Reduction)

Currently MRP / Demand Management Activities and Master Data has been split among different members of the teams in order to perform baseline configuration.

73Data team resource plan may be insufficent towards the end of the project risking quality and schedule 2018-12-13 40. Closed 4 2 2

Brandes, Michael

Tolerate (or Acceptance)

No immediate action will be taken to mitigate this risk. Risk will be re-evaluated closer to ITC1 when the resourcing of the Data team is expected to change.

36BW loads taken 10 to 12 hour today. 60% additional load is coming because of SCA 2018-05-10 40. Closed 3 1 3

Cachero, Wendy

Treat (or Reduction)

To be tested through system performance testing per current plan and resolved as required.

11 ECC SAP Access to Prep for SAP 101 Demo 2018-01-29 40. Closed 2 1 2 Trask, JonTreat (or Reduction) Assign Access to SAP Sandbox for Functional Consultants within 5 Days.

104User interface for entering materials from Outline Agreement might not be acceptable for end users 2019-09-10

60. Updates Required 6 2 3

Setiawan, Ben

Treat (or Reduction)

To be tracked through engagement and BAR activities. Will be logged as a CR if raised as a concern by users.

16Scope Risk related to potential increase of Ariba use with impact on Unifier and SC Workspace (closed as duplicate) 2018-02-16 70. Cancelled 12 4 3

Schellekens, Harold

Terminate (or Avoidance)

Duplicate. Risk cancelled.

55 Data conversion scope risk related to other BCH projects (business or IT) 2018-06-27 70. Cancelled 9 3 3Praveen, Roch

Treat (or Reduction) Duplicate of risk 30

43Unrealized Benefits & Procurement Inefficiencies due to Missing Service Master Standards 2018-05-21 70. Cancelled 6 2 3

Praveen, Roch

Treat (or Reduction)

Mitigations overlap with risk 52 and 53 (which are more immediate). Will cancel this risk and track through those items. The Purchasing and Contracts Team, Data Team and the various Business Teams(SME’s) have to develop:- Standards/Display format (E.g. Taxonomy, Upper Case/ Lower Case or mixture of both) for the Required and Optional fields on the Service Master- Material/Service Groups- The list of Service masters to be uploaded for Go-Live- Service Master upload tools for Go-Live- A Service Master maintenance process for the Sustainment team

Appendix C

BC Hydro Supply Chain Applications Project Page 7 of 8

Page 63: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

ID Title CreatedCurrent Status Risk Score Impact Likelihood Risk Owner

Treatment Strategy Risk Response/Mitigation

56 SCA Project Delays due to CLRA Deliverables 2018-06-30 70. Cancelled 4 2 2Schellekens, Harold

Treat (or Reduction)

The general topic of CLRA and SCA has been discussed for a long time, and is well known. There have been meetings with CLRA team and Robbin Yang, and CLRA team and Leo/Kiernan/Anurag. This coordination and collaboration needs to continue into the level of detail that is now available for both projects as they near DEF completion.

Appendix C

BC Hydro Supply Chain Applications Project Page 8 of 8

Page 64: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

BC Hydro Supply Chain Applications Project

Progress Report No. 1

Appendix D

Project Schedule

Page 65: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

ID % Complete Task Name Start

1 71% Realization Mon 19‐04‐01

2 0% SCA Realization Phase Mon 19‐04‐01

4 100% Solution Definition (PFD, Security, FSD) Mon 19‐04‐01

11 94% Solution Development (Development, FUT) Mon 19‐04‐01

12 92% Material Management & Quality Mon 19‐04‐01

13 97% Purchasing & Contracts Mon 19‐04‐01

14 92% Work Management Integration Mon 19‐04‐01

15 100% Projects Integration Mon 19‐04‐01

16 100% Master Data Governance Mon 19‐04‐01

17 85% Ariba Mon 19‐04‐01

18 0% As‐Built Solution Documentation Mon 19‐09‐30

19 0% Material Management & Quality Mon 19‐09‐30

20 0% Purchasing & Contracts Mon 19‐09‐30

21 0% Work Management Integration Mon 19‐09‐30

22 0% Projects Integration Mon 19‐09‐30

23 0% Master Data Governance Mon 19‐09‐30

24 0% Ariba Mon 19‐09‐30

25 88% Reporting Fri 19‐05‐10

26 95% Reporting Definition Fri 19‐05‐10

27 84% Reporting Development Wed 19‐06‐05

28 88% Back end Development Wed 19‐06‐05

29 62% Front end Development Mon 19‐09‐02

30 99% Data Mon 19‐04‐01

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2019 Qtr 1 2019 Qtr 2 2019 Qtr 3 2019 Qtr 4 2020 Qtr 1 2020 Qtr 2 2020 Qtr 3

Task

Split

Milestone

Summary

Summary Progress

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Slippage

Page 1

Project: SC viewDate: Thu 19-10-10

Appendix D

BC Hydro Supply Chain Applications Project Page 1 of 2

Page 66: Commission Secretary and Manager Regulatory Support British … · 2019. 10. 30. · October 30, 2019 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British

ID % Complete Task Name Start

31 100% Data Business Preparation & Conversion Readiness ITC1 Mon 19‐04‐01

32 95% Data Business Preparation ITC2 Mon 19‐07‐29

33 100% Data Conversion Readiness ITC2 Mon 19‐07‐29

34 62% Testing Mon 19‐06‐03

35 100% String Testing Development Mon 19‐06‐03

36 70% String Testing Execution Iteration 1 Tue 19‐07‐02

37 97% String Testing Execution Iteration 2 Mon 19‐07‐29

38 80% String Testing Execution Iteration 3 Tue 19‐09‐03

39 87% Integration Test Cycle 1 Mon 19‐07‐29

40 0% Integration Test Cycle 2 Mon 19‐09‐23

41 78% Change Management and Business Transformation Mon 19‐04‐01

42 40% Training Preparation (Realization) Mon 19‐07‐15

43 0% Final Preparation Mon 19‐11‐25

44 0% User Acceptance Testing Mon 19‐12‐02

45 0% Training Preparation (Final Prep) Mon 19‐11‐25

46 0% Training Delivery Mon 20‐01‐13

47 0% Cutover Mon 20‐02‐17

48 0% Target in‐Service Date Tue 20‐02‐18

49 0% Stabilization Wed 20‐02‐19

02-18

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2019 Qtr 1 2019 Qtr 2 2019 Qtr 3 2019 Qtr 4 2020 Qtr 1 2020 Qtr 2 2020 Qtr 3

Task

Split

Milestone

Summary

Summary Progress

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Slippage

Page 2

Project: SC viewDate: Thu 19-10-10

Appendix D

BC Hydro Supply Chain Applications Project Page 2 of 2