Commercial Points for 86th OCC meeting

Page 2: Commercial Points for 86 th   OCC meeting

Requisition of MTOA before 10am

• Some of the MTOAs are not being scheduled • KSK Mahanadi-AP and CPL-AP are not

requisitioned.• Cl 17.a mandates release of such margin for

STOA • Request states to intimate such Under-

requisition well in advance so that Adv / FCFS STOA can be approved

• Atleast before 10am on Day Ahead basis so that it can be released to Px.

Letter

Page 3: Commercial Points for 86 th   OCC meeting

Treatment of Kudankulam infirm injection

• SRPC issued Allocation order dt 30-07-13 on unallocated quota of Kudankulam

• Order specified allocation ratios for 1)prior to CoD and 2) from CoD

• allocation ratios for prior to CoD for accounting purpose of infirm injection

• SRLDC will not Schedule the infirm injection

• Nor give any relief in Real Time O/D messages etc.

Page 4: Commercial Points for 86 th   OCC meeting

NO OF INSTANCES OF DELAY IN WEEKLY SEM DATA RECEIPT DURING July’ 2013

AP KARNATAKA POWERGRID

KTPS(kothagudam)KTPP

2 each Kodasally 2Udumalpet, Kalivanthapattu, Munirabad

1 each

Mamidipally 1 Kadra 1 Hyderabad 2

Yerandahally 1 Talcher Aux 1

GOA Kadakola 1 KSEB

ponda 1 Hoody 1 Edomon 2

Guttur 1

PONDY Sedam 2

vilianur 1 TN

Mettur 1 Others

Theni 1 SEPL 1

Page 5: Commercial Points for 86 th   OCC meeting

TIME DRIFT STATEMENT NOT RECEIVED in the month of July’13

ANDHRAPRADESH:Gajwel, Gooty RS, Kakinada, Kakatheeya, Kothagudom, Karnool & Mehboob nagarKARNATAKA:All stations except Nelamangala & RaichurTAMILNADU: Arni, SP Koil, & Thiruvelam Pondicherry: nil

ISGS STATIONS: nil

CTU STATIONS:Munirabad ,Vijayawada, Hyderabad, Nellore, Nellore PS, kadapa, Kalivanthapattu , Pondy & Udumalpet

Page 6: Commercial Points for 86 th   OCC meeting

•Tamilnadu Rs.2635 Lakhs (TN opened LC for Rs.8.49Cr only in lieu of Rs.32.84Cr)

•APTRANSCO Rs.247.50 Lakhs Due to delay of wk40(31.12.12-06.01.13) UI payment(APTRANSCO opened LC for Rs. 62 Lakhs only )

•LKPPL Rs.2.44 Lakhs Due to delay of wk40(31.12.12-06.01.13) UI payment

•MEPL to enhance LC to Rs. 17.23 Lakhs from Rs.7Lakhs Due to delay of wk41(07.01.13-13.01.13) UI payment

OPENING OF LC DUE TO DELAYED UI PAYMENT

Page 7: Commercial Points for 86 th   OCC meeting

PoC status for Q3 of 2013-14

Page 8: Commercial Points for 86 th   OCC meeting

Status of RRF Mock Exercise

• Implemented from 15-07-13• TNEB started furnishing data

– for 11 pooling stations in full shape. – For 3 stations Scheduling yet to start – For 2 stations Actual Energy to be recd

• AP not submitting data • Karnataka discontinued from week (220713-

280713) and (290713-040813)

Page 9: Commercial Points for 86 th   OCC meeting

Metering Scheme and Accounting methodology for new stations

• Henceforth SRLDC will not be advising the locations of SEMs for new projects or Connection points

• Installation of SEMs to be done by concerned agencies themselves as per CEA Metering regulations 2010

• Data format to be in line with existing SEMs• New stations to get the Metering Scheme and

Accounting methodology finalised in Commercial subcommittee of SRPC

Page 10: Commercial Points for 86 th   OCC meeting

Before amendment

After amendment