125
Proposed Subdivision of Erf 177476, St James, Cape Town SLR Consulting (South Africa) (Pty) Ltd Comments Report 1 COMMENTS AND RESPONSES REPORT 1. INTRODUCTION The purpose of this Comments and Responses Report is to record comments received from Interested and Affected Parties (I&APs) on the Background Information Document (BID) review and comment period from 20 July to 21 August 2017 and the Draft Basic Assessment Report (BAR) review and comment period from 7 January to 6 February 2019. It should be noted that all significant changes and/or additions to the Comments and Responses Report that was included in the Draft BAR are underlined and in a different font (Times New Roman) to the rest of the text. 2. COMMENTS RECEIVED The following I&APs submitted written comments during the above-mentioned comment and review periods: SUBMITTED BY: METHOD, DATE RECEIVED: Authorities and/or Organs of State 1. Department of Water and Sanitation - Melissa Lintnaar - Strauss 24 July 2017 2. Heritage Western Cape - Zwelibanzi Shiceka 25 July 2017 3. South African National (SAN) Parks - Michael Slaylen 21 August 2017 and 6 February 2019 4. Department of Environmental Affairs and Development Planning – Rondine Isaacs 29 January 2019 5. Cape Nature - Rhett Smart 6 February 2019 6. Department of Transport and Public Works: Road Network Management – Alvin Cope 6 February 2019 7. City of Cape Town – Dimitri Georgeades (Acting Manager) 25 February 2019 General I&APs and/or Organisations 1. Andy Paige 25 July 2017 2. Zusiphe Kapa 25 July 2017 3. Mnoneleli Mlobeli 25 July 2017 4. Andrew Swain 31 July 2017 5. Gavin Brown 31 July 2017 6. Nick Steytler 31 July 2017 7. Tommy Brummer 31 July 2017 8. Bert Stafford 31 July 2017 9. Cheri Scholtz 1 August 2017 10. Simon Draper 2 August 2017 11. Norman Malcolm 2 August 2017

COMMENTS AND RESPONSES REPORT 1. INTRODUCTION · Applicant and the Environmental Assessment Practitioner (EAP) in the BAR. The signed declarations from the Applicant and the EAP have

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report 1

    COMMENTS AND RESPONSES REPORT

    1. INTRODUCTION

    The purpose of this Comments and Responses Report is to record comments received

    from Interested and Affected Parties (I&APs) on the Background Information Document

    (BID) review and comment period from 20 July to 21 August 2017 and the Draft Basic

    Assessment Report (BAR) review and comment period from 7 January to 6 February 2019. It

    should be noted that all significant changes and/or additions to the Comments and Responses

    Report that was included in the Draft BAR are underlined and in a different font (Times New

    Roman) to the rest of the text.

    2. COMMENTS RECEIVED

    The following I&APs submitted written comments during the above-mentioned comment and

    review periods:

    SUBMITTED BY: METHOD, DATE RECEIVED:

    Authorities and/or Organs of State

    1. Department of Water and Sanitation - Melissa Lintnaar - Strauss 24 July 2017

    2. Heritage Western Cape - Zwelibanzi Shiceka 25 July 2017

    3. South African National (SAN) Parks - Michael Slaylen 21 August 2017 and 6

    February 2019

    4. Department of Environmental Affairs and Development

    Planning – Rondine Isaacs

    29 January 2019

    5. Cape Nature - Rhett Smart 6 February 2019

    6. Department of Transport and Public Works: Road Network

    Management – Alvin Cope

    6 February 2019

    7. City of Cape Town – Dimitri Georgeades (Acting Manager) 25 February 2019

    General I&APs and/or Organisations

    1. Andy Paige 25 July 2017

    2. Zusiphe Kapa 25 July 2017

    3. Mnoneleli Mlobeli 25 July 2017

    4. Andrew Swain 31 July 2017

    5. Gavin Brown 31 July 2017

    6. Nick Steytler 31 July 2017

    7. Tommy Brummer 31 July 2017

    8. Bert Stafford 31 July 2017

    9. Cheri Scholtz 1 August 2017

    10. Simon Draper 2 August 2017

    11. Norman Malcolm 2 August 2017

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report 2

    12. Steve Doidge 4 August 2017

    13. Ashleigh Sandes: Praesidium Family Trust 7 August 2017

    14. Barrie Gasson: Kalk Bay - St James Ratepayers Association 14 August 2017 and 6 February 2019

    15. Bev Russell 18 August 2017

    16. Patrick Morris 18 August 2017

    17. Barbara Elshove 18 August 2017

    18. Dawn Friend 19 August 2017

    19. Andy Rice 21 August 2017

    20. Neil Fraser and John Fraser 21 August 2017

    21. William Wiley 9 January 2019

    22. P.F.P Morris 6 February 2019

    23. Nick Steytler - Khula Environmental Consultants on behalf of

    Kevin Hodgson and Karl and Gina Leinberger

    6 February 2019

    Copies of the written submissions are attached as Attachment A. The comments received

    are presented, and responded to, in the tables below and have been categorised as

    follows:

    1. General and procedural issues;

    2. Flooding risks;

    3. Impacts on heritage resources;

    4. Site access issues;

    5. Biophysical impacts;

    6. Visual impacts; and

    7. I&AP registrations.

    No importance should be given to the order in which the categories are presented. As far

    as possible, comments are presented verbatim from written submissions.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    3

    Table 1: Summary table of comments received from Authorities, with responses from the project team � = Letter/Fax/Post � = E-mail

    NO. ISSUE COMMENT RESPONSE

    1. DEPARTMENT OF ENVIRONMENTAL AFFAIRS AND DEVELOPMENT PLANNING (DEA&DP)

    1.1. Public

    Participation

    You are required to submit proof of the Public Participation Process being

    conducted for the draft BAR. This will include (but is not limited to):

    • Proof that the BAR was made available to registered Interested and

    Affected Parties;

    • All comments received from Interested and Affected Parties (including

    comments from Heritage Western Cape and the Department of Water

    and Sanitation);

    • A Comments and Responses Report, indicating all the comments

    received from Interested and Affected Parties on the BAR and the

    responses thereto; and

    • A complete list of registered Interested and Affected Parties.

    The requested information has been included

    in Section F and Appendix F of the revised

    Basic Assessment Report (BAR).

    1.2. Declarations by

    applicant and

    Environmental

    Assessment

    Practitioner

    You are hereby reminded to include the signed declarations from the

    Applicant and the Environmental Assessment Practitioner (EAP) in the

    BAR.

    The signed declarations from the Applicant

    and the EAP have been included in the revised

    BAR.

    1.3. Heritage Western

    Cape comments

    Final comment from Heritage Western Cape (HWC) must be obtained

    prior to submitting the final BAR to the Department. Where applicable,

    any comments or requirements from Heritage Western Cape must be met

    and incorporated into the final BAR and Environmental Management

    Programme.

    The Heritage Specialist has submitted the

    Heritage Impact Assessment Report to HWC

    and requested final comment. Once a response

    has been received, it will be provided to

    DEA&DP.

    1.4. Comment from

    Department of

    You are required to obtain comment from the Department of Transport

    with regards to access to the proposed site.

    Comment from the Western Cape

    Government: Department of Transport has

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    4

    NO. ISSUE COMMENT RESPONSE

    Transport been included in the revised BAR (see

    Appendix E3).

    1.5. Confirmation of

    availability of

    services

    Since electricity supply will be provided by the City of Cape Town, you

    are requested to provide this office with written proof that the municipality

    has sufficient unallocated capacity to provide the necessary service to the

    proposed development. Confirmation of the availability of the service from

    the service provider must be provided together with the BAR.

    Confirmation that adequate electrical supply

    capacity is available for the proposed project

    has been obtained from the Energy Directorate

    of the COCT (see Appendix E3).

    1.6. General You are required to indicate the correct departmental reference number on

    pages i and ii of the BAR. The site layout plan (Appendix B) has not been

    attached.

    The reference number included in the draft

    BAR was provided by the Department in

    response to the submission of the Notice of

    Intent application. Subsequently, the

    Application for Environmental Authorisation

    was submitted to DEA&DP and an updated

    reference number was received. The updated

    reference number has been included on pages i

    and ii of the revised BAR.

    1.7. Submission of

    final BAR

    In accordance with Regulation 19(1) of Government Notice No. R. 982,

    the final BAR must be submitted to this Department within a period of 90

    days of receipt of the application by this Department, i.e., the final BAR

    must be submitted by 8 April 2019.

    The final BAR has been completed for

    submission to DEA&DP by 8 April 2019.

    1.8. Compliance with

    NEMA

    Please note that the proposed activity must not be commenced with prior to

    an environmental authorisation being granted by the Department. It is

    prohibited in terms of Section 24F of the NEMA for a person to commence

    with a listed activity unless the competent authority has granted an

    environmental authorisation for the undertaking of the activity. A person

    convicted in terms of this prohibition is liable to a fine not exceeding R10

    The Applicant is aware of the requirement for

    Environmental Authorisation for listed

    activities in terms of NEMA and is committed

    to adhering to the legal requirements in this

    regard.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    5

    NO. ISSUE COMMENT RESPONSE

    million or imprisonment for a period not exceeding ten years, or to both

    such fine and imprisonment.

    1.9. Reference

    number

    Kindly quote the above-mentioned reference number in any future

    correspondence in respect of this application.

    This is noted.

    2. DEPARTMENT OF WATER AND SANITATION

    2.1. Requested hard

    copy of

    documentation

    Please send us a hard copy of the document. Only then will we be able to provide

    comment.

    A hard copy of the Draft Basic Assessment Report

    (BAR) was sent to the Department of Water and

    Sanitation for review and comment on 6 January

    2019. SLR has undertaken regular follow-up

    with DWS in order to obtain comment on the

    draft BAR. To date no comments have been

    received.

    3. SANPARKS

    Comments dated 21 August 2017

    3.1. Objection Having reviewed the Background Information Document, SANParks objects to the

    proposed sub-division for the following reasons:

    Your objection to the proposed subdivision has

    been noted and is recorded here for consideration

    by the Department of Environmental Affairs and

    Development Planning (DEA&DP).

    3.2. Disruption of natural

    watercourse

    The proposal to sub-divide the property unnecessarily disrupts and re-routes what

    appears to be a natural and productive watercourse flowing across the property.

    The potential impact on natural vegetation and the

    seasonal watercourse are assessed in Section F of

    the BAR and the specialist freshwater and botanical

    assessments (refer to Appendix G1 and G2,

    respectively).

    A 10 m development setback buffer is proposed

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    6

    NO. ISSUE COMMENT RESPONSE

    along Portion 2 and the upper half of Portion 1 in

    order to accommodate the seasonal watercourse.

    In addition, the setback would maintain a corridor of

    natural vegetation between future houses and the

    neighbours adjacent to this boundary. Of the total

    length of the watercourse located below Boyes

    Drive (180 m), approximately 30 m would be

    lost through the implementation of the

    proposed diversion of the watercourse.

    3.3. Development on

    slopes steeper than

    1:4

    The proposed sub-division will facilitate development on slopes steeper than 1:4

    which is generally considered inappropriate.

    The suburb of St James was established on the

    mountain slope and there are numerous existing

    residences located adjacent to Erf 177476. Thus,

    the precedent for development on the slopes has

    already been established.

    With reference to the geotechnical

    investigation which was undertaken for the

    house currently under construction, it is noted

    that: “changes to the current slope geometry,

    such as … cuts and fills in a bulk excavation,

    will adversely affect overall slope stability

    unless appropriate stabilisation (remedial)

    measures are taken timeously at the

    engineering design stage”.

    In this regard, the engineer (Eward Grobler of

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    7

    NO. ISSUE COMMENT RESPONSE

    Grobler & Associates) has indicated that such

    remedial measures would include:

    • Self-drilling anchors (micro piles) and

    ground beams to transfer loads deep into

    the soils and reduce surface loading. This

    is deemed to have a positive impact on the

    overall slope stability when compared to

    the current status quo; and

    • In areas where platforms would be created,

    it is recommended that the fill areas are

    contained using gabion retaining structures

    at near vertical slopes, thereby constraining

    the area of fill placement. This would also

    include soil anchoring which forms part of

    gabion retaining wall construction.

    It is further noted that as part of the current

    house construction, Boyes Drive has been

    secured laterally by installing pile and

    shotcrete walls deep into the natural ground

    during the construction of the access road.

    Thus, the technical requirements for

    construction on the steep slopes associated

    with the site are understood and would be

    considered as part of the detailed engineering

    design for the future houses.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    8

    NO. ISSUE COMMENT RESPONSE

    3.4. Disturbance of

    indigenous

    vegetation

    The established indigenous vegetation on the property will be unnecessarily

    disturbed.

    As noted above, the potential impact on natural

    vegetation and the seasonal watercourse are

    assessed in Section F of the DBAR and the

    specialist freshwater and botanical assessments

    (refer to Appendix G1 and G2, respectively).

    A 10 m development setback buffer is proposed

    along Portion 2 and the upper half of Portion 1 in

    order to accommodate the seasonal watercourse.

    In addition, the setback would maintain a corridor of

    natural vegetation between future houses and the

    neighbours adjacent to this boundary.

    3.5. Development above

    Boyes Drive

    The proposed garage is located on the steep mountainside above Boyes Drive

    and will unnecessarily disturb the indigenous vegetation and a potentially unstable

    slope and will have both visual and traffic impacts. This mountainside portion of

    the property should not be developed. The proposed garage should rather be

    located below Boyes Drive.

    No garage or any other development associated

    with the proposed subdivision is planned above

    Boyes Drive. Accordingly, no vegetation would be

    removed and no changes to slope would occur

    above Boyes Drive.

    3.6. Request to register

    as an I&AP

    SANParks requests to be registered as an interested and affected party.

    SANParks reserves the right to request further information and make additional

    comments on any additional information that might be received.

    SANParks was registered on the project database

    (see Appendix F1).

    Comments dated 6 February 2019

    3.7. Objection Your email dated 7 January 2017 refers. Having reviewed the Basic

    Assessment Report, SANParks objects to the proposed sub-division for the

    following reasons:

    This objection is noted and is recorded here for

    consideration by DEA&DP during the

    decision-making process.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    9

    NO. ISSUE COMMENT RESPONSE

    3.8. Loss of

    endangered

    vegetation and

    current stream

    In response to SANPark’s previous comment (letter dated 17 August

    2018) that “The proposal to sub-divide the property unnecessarily disrupts

    and re-routes what appears to be a natural and productive watercourse

    flowing across the property” and that “The established indigenous

    vegetation on the property will be unnecessarily disturbed”, the applicant

    states in the Comments and Responses Report (Annexure F5, Pg. 4) that:

    “A 10 m development setback buffer is proposed along Portion 2 and the

    upper half of Portion 1 in order to accommodate the seasonal watercourse.

    In addition, the setback would maintain a corridor of natural vegetation

    between future houses and the neighbours adjacent to this boundary”.

    However, SANParks is of the view that a narrow, partial and reconstructed

    water course and corridor of 10 m and does not mitigate the loss of

    endangered vegetation due to the extent of the proposed development.

    Notably, the massive earthworks, excavation and re-shaping that will be

    required to create the two building platforms (as evidenced by the

    construction of the upper platform and access driveway), will result in the

    permanent loss of the current stream and the destruction of the riparian

    forest.

    This comment is noted. While the loss of

    existing indigenous vegetation within the

    future building footprints of each subdivided

    portion cannot be avoided, this loss can be

    mitigated to a degree through the use of

    existing indigenous vegetation for landscaping

    on completion of construction.

    Furthermore, the proposed 10 m buffer would

    allow for the preservation of a large portion of

    the seasonal watercourse and associated

    existing riparian vegetation (over and above

    the remaining upper part of the seasonal

    watercourse located adjacent to the approved

    dwelling). Of the total 180 m length of the

    watercourse located below Boyes Drive,

    approximately 30 m of the existing

    watercourse would be lost through the

    implementation of the proposed diversion of

    the watercourse. However, an allowance has

    been made for the continuation of overland

    flow along this section and a 3 m building line

    would be incorporated along this section of the

    property boundary. Thus some vegetation

    establishment and modified ecological

    functioning along this portion of the

    watercourse could still occur.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    10

    NO. ISSUE COMMENT RESPONSE

    3.9. Does not support

    loss of Peninsula

    Sandstone Fynbos

    vegetation

    In addition, the botanical specialist report states that: “The proposed

    development of Erf 177476 would result in the loss of mostly intact

    ENDANGERED Peninsula Sandstone Fynbos” and that “The vegetation is

    likely to survive, although not optimally, without fire even though some

    species may be lost over time”. (Annexure G1 pg.36).

    SANParks does not support the loss of this remnant portion of endangered

    vegetation and maintains its concern in this regard in the light of the

    enhanced rights that are being applied for.

    In Section F1(b) of the BAR it is indicated that

    while the proposed project would require the

    clearance of the Peninsula Sandstone Fynbos

    located on the property, this vegetation type is

    exceptionally well conserved, with 95% of its

    total original extent remaining, of which

    approximately 98% of this being formally

    protected (mostly within the TMNP). Thus,

    the proposed project would not have a

    significant impact on the overall conservation

    requirement for this vegetation type.

    3.10. Disturbance of the

    watercourse

    The Freshwater Assessment Report states that “the extant development of

    this site has already substantially impacted on the ravine, stream and forest

    environment. The proposed additional development will result in the near

    complete loss thereof”. (Annexure G2 pg. 8). Our previous comments in

    this regard stating that “the proposal to sub-divide the property

    unnecessarily disrupts and re-routes what appears to be a natural and

    productive watercourse flowing across the property” have clearly not been

    adequately addressed.

    Refer to the response provided in Section 3.8

    above.

    3.11. Development on

    slopes steeper than

    1:4

    Likewise in response to SANParks comments that “the proposed sub-

    division will facilitate development on slopes steeper than 1:4 which is

    generally considered inappropriate, the applicant states “The suburb of St

    James was established on the mountain slope and there are existing

    residences located adjacent to Erf 177476. Thus, the precedent for

    development on the slopes has already been established”. To our

    understanding, each application needs to be assessed on its merits and in

    No rationale has been provided by SANParks

    as to why it is of the view that subdivision or

    development on steep slopes may not take

    place – there are numerous locations along the

    Cape Peninsula where similar development on

    steep slopes has been undertaken. As noted in

    Section 3.3, the technical requirements for

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    11

    NO. ISSUE COMMENT RESPONSE

    this case the visually exposed and steep slopes should not be subdivided or

    developed as proposed.

    construction on the steep slopes associated

    with the site are understood and would be

    considered as part of the detailed engineering

    design for the future houses.

    3.12. Right to provide

    additional

    comment

    SANParks reserves the right to request further information and make

    additional comments on any additional information that might be received.

    This is noted.

    4. COMMENTS FROM CAPENATURE

    4.1. Desktop

    Information

    The subject property is classified as No Natural according to the

    Biodiversity Network (BioNet) for the City of Cape Town and the

    Western Cape Biodiversity Spatial Plan. A watercourse is mapped on the

    watercourse layer on City of Cape Town Map Viewer along the north

    eastern boundary of the site flowing in a south easterly direction, and

    entering the site in the eastern section. It is also mapped on Surveys and

    Mapping along a slightly more easterly alignment. The natural vegetation

    occurring over the site is Peninsula Sandstone Fynbos, listed as

    Endangered.

    This information is noted and was included in

    the Basic Assessment Report, where relevant.

    4.2. Application

    The proposal is for subdivision of the subject erf into three erven (initially

    five) for residential purposes. While subdivision would require a planning

    approval and in itself does not require environmental authorisation, the

    application is to allow for authorisation for the listed activities related to

    excavation or deposition of material within a watercourse or buffer and

    clearing of endangered vegetation, which is likely to be relevant to the

    future development of the proposed erven.

    It must be noted that planning approval was provided for the construction

    of a dwelling on the largest northernmost erf, which is currently underway.

    This information is correct.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    12

    NO. ISSUE COMMENT RESPONSE

    The Department of Environmental Affairs and Development Planning

    (DEA&DP) determined that no listed activities would be triggered for this

    activity, as indicated in the correspondence dated 5 November 2014

    (DEA&DP ref. no. 16/3/1/6/1/A6/82/2219/14). The determination was in

    terms of the DEA&DP Circular regarding the term “commencement” and

    it was determined that the development of a single dwelling had

    commenced in terms of the original subdivision of the suburb and the

    related commencement of earthworks (clearing of vegetation, excavation

    and deposition) which would relate to the relevant NEMA listed activities.

    4.3. Botanical

    Assessment

    A botanical assessment was undertaken and identified the presence of

    intact and semi-intact vegetation occurring across the site which is typical

    of the south-east facing slopes above this coastline. The presence of the

    watercourse and associated ravine results in a higher presence of thicket

    and forest species, and which is further enhanced by fire exclusion at this

    location. The addendum to the botanical assessment includes an evaluation

    of the reference in the freshwater assessment to the vegetation adjacent to

    the stream as riparian forest. CapeNature wishes to express that we do not

    consider there to be a discrepancy between the two reports in this regard,

    as within all vegetation types, riparian/riverine vegetation would differ

    from the surrounding vegetation due to increased moisture availability,

    however this can only be mapped at a national scale for the larger

    watercourses with more extensive riparian/riverine vegetation and not

    smaller watercourses such as the stream on site.

    This comment is noted, however it is unclear

    how the national scale mapping of larger

    watercourses is relevant with respect to the

    information provided by the Botanical

    specialist.

    4.4. BioNet

    Classification

    In terms of the mapping on the BioNet for the site, CapeNature is

    assuming that the No Natural classification was based on the existing

    rights and the assumption that the site would be developed, because based

    This comment is noted. Given that the

    applicant has existing land use rights to

    develop property, the assumption that the site

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    13

    NO. ISSUE COMMENT RESPONSE

    on the botanical (and freshwater) assessments there is natural vegetation

    present on the site, which does not concur with the current classification.

    would be developed in the future is considered

    reasonable.

    4.5. Watercourse

    buffer zone

    The botanical assessment mapped the intact and disturbed vegetation on

    site and indicated a 10 m buffer from the stream as a no-go area, which

    was subsequently reduced to 3 m based on the cut and fill requirements as

    a result of the steep slope. CapeNature wishes to query this reduction and

    whether the buffer should not remain at 10 m as originally recommended.

    The overall assessment is that the impact is considered of low negative

    significance both before and after mitigation, however certain species and

    specimens thereof are listed as of importance.

    The 3 m buffer referred to in this comment

    relates to a project layout alternative that was

    determined to not be feasible and was screened

    out of the BAR (refer to the discussion of

    alternatives presented in Section E of the

    BAR). The preferred project alternative

    includes a diversion of approximately 30 m of

    the existing watercourse and a 10 m

    development setback buffer along Portion 2

    and the upper half of Portion 1 in order to

    accommodate the seasonal watercourse.

    Furthermore, allowance has been made for the

    continuation of overland flow along this

    section of the watercourse diversion and a 3 m

    building line would be incorporated along this

    section of the property boundary, vegetation

    establishment and ecological functioning

    along this portion of the watercourse can still

    occur, albeit in a modified way.

    4.6. Freshwater

    Assessment

    findings

    The freshwater assessment has delineated the centreline of the stream

    which more or less aligns with the mapping of the City of Cape Town

    Map Viewer. The assessment reveals that the stream channel is

    geomorphologically intact and is typical of a steep sloped mountain stream

    flowing through a narrow ravine with an intact riparian forest zone. It

    The summary of the freshwater assessment

    findings is noted. However, it is pointed out

    that, as per the Botanical Assessment

    Addendum, no remnant coastal forest

    vegetation is located on the site.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    14

    NO. ISSUE COMMENT RESPONSE

    should be noted that the freshwater assessment has included several

    additional riparian tree species to those listed in the botanical assessment.

    The recommendation provided was that a minimum of a 10 m buffer from

    the centreline of the stream is required.

    4.7. Development

    alternatives

    The initial development proposal for five erven is that the stream will flow

    above ground in the uppermost proposed erf (containing the existing

    dwelling) after which it will enter a below ground box culvert and be

    piped to where it joins with the existing underground culvert which exits

    into the sea, with the remainder of the run-off from the site channelled to

    the same underground culvert. The revised proposal for three erven allows

    for above ground flow in the natural channel until halfway down the

    lowermost third erf after which it is channelled underground as above.

    This information is correct.

    4.8. Concerns raised in

    freshwater

    assessment

    Several concerns are raised in the freshwater assessment:

    • Firstly, the precedent set by the existing dwelling which has

    encroached into the riparian area of the stream with evidence of

    material within the streambed and the associated impacts.

    • The steep slopes of the site are a general concern and steeper than the

    generally recognised maximum gradient permissible for development.

    The steep slope significantly increases the risk of impacts associated

    with erosion and sedimentation and substantially increases the

    footprint size for development due to cut and fill requirements.

    • The loss of the stream habitats in the lower parts and most of the

    • It is noted that any impacts associated with

    the construction of the existing house will

    be rehabilitated on conclusion of the

    construction phase. Any material located

    within the seasonal watercourse would be

    removed and landscaping of disturbed

    areas would take place.

    • Refer to the response provided in Section

    3.3 above regarding development on steep

    slopes.

    • This comment is noted. As highlighted in

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    15

    NO. ISSUE COMMENT RESPONSE

    riparian habitat is still a concern associated with the preferred

    alternative, even although the revised proposal for three erven is an

    improvement on the original proposal for five erven in this regard.

    The addendum to the freshwater assessment which assesses the revised

    proposal of three erven as opposed to five erven provides a good summary

    of the concerns with the proposal and is supported by CapeNature.

    Section E of the BAR, the rationale for

    selecting the preferred alternative included

    the fact that the proposed layout would

    have a lower impact on the seasonal

    watercourse.

    This comment is noted.

    4.9. Support of the

    freshwater

    assessment

    In conclusion, CapeNature supports the findings of the freshwater

    assessment, and recommends that that the proposed 10 m buffer must be

    implemented to allow for the persistence of the natural stream and

    associated riparian vegetation. We do not support the proposal of

    tunnelling the stream underground, despite the poor historical precedents

    downstream of the site. CapeNature in general does not support the

    artificial canalisation (above ground or underground) of natural

    watercourses supporting natural habitat.

    This comment and the position of CapeNature

    against the planned underground diversion of

    the seasonal watercourse is noted. However, it

    is pointed out that of the total 180 m length of

    the watercourse located below Boyes Drive,

    approximately 30 m would be lost through the

    implementation of the proposed diversion of

    the watercourse into an underground culvert.

    Furthermore, in addition to the proposed

    diversion, allowance has been made for the

    continuation of overland flow along this

    section of the watercourse diversion and a 3 m

    building line would be incorporated along this

    section of the property boundary. Vegetation

    establishment and ecological functioning

    along this portion of the watercourse can still

    occur, albeit in a modified way.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    16

    NO. ISSUE COMMENT RESPONSE

    4.10. Objection In terms of the application, CapeNature therefore objects to the current

    proposal. While we do not object to the principle of three erven, the 10 m

    buffer as indicated in Figure 5 of the freshwater assessment must be

    implemented as a minimum, and should the remaining development

    envelope not allow for feasible development options for the proposed

    erven, the subdivision proposal must be revised. The approved

    development envelope and no-go area must be binding on the title deeds

    of the subdivided erven. Ideally there should be no subdivision of the

    existing erf.

    This objection is noted and is recorded here

    for consideration by DEA&DP during the

    decision-making process.

    However, in response to the statement that

    there should be no subdivision of the existing

    erf, it must be pointed out that the current erf

    represents a recent consolidation of two erven

    and that the project proposal would entail the

    subdivision of the current erf into three

    portions. Thus, when compared to the status

    quo prior to the consolidation only one

    additional erf would be created.

    4.11. Landscaping

    recommendations

    The recommendation is that landscaping should utilise locally indigenous

    species, and includes those species which already occur on site. We wish

    to query if the recommendation should rather be to keep as many of the

    existing specimens as possible in particular mature specimens. We do also

    wish to express that although fire exclusion may result in a different

    vegetation community, however, it is still of biodiversity value as habitat,

    particular as riparian habitat. We also wish to note that the Leucospermum

    conocarpodendron specimen which was the only threatened species listed

    (Endangered) was present on the already developed footprint of the

    approved dwelling.

    This recommendation has been updated to

    reflect the requirement to keep as many of the

    existing indigenous plant specimens (in

    particular mature specimens) as possible for

    use in site landscaping.

    4.12. Comments relating

    to the construction

    of the existing

    With regards to the existing large dwelling which has already been

    constructed on the site, CapeNature does not support the use of “legal

    loopholes” to enable activities which will have a significant negative

    It is pointed out that the applicant has followed

    due process and obtained all relevant

    approvals from COCT to facilitate the

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    17

    NO. ISSUE COMMENT RESPONSE

    dwelling. impact on biodiversity. While we will not interrogate the legal

    interpretations, other aspects of the National Environmental Management

    Act (NEMA) such as Duty of Care (Section 28) and application of the

    mitigation hierarchy (Section 2) remain relevant.

    construction of the existing house.

    4.13. Rehabilitation of

    watercourse

    The encroachment of the existing dwelling into the riparian area of the

    watercourse is not supported due to the impacts on the riparian and in-

    stream habitat. Although not within the ambit of an authorisation in terms

    of the NEMA EIA Regulations, CapeNature recommends that a setback

    line/no-go boundary from the stream needs to be established adjacent to

    the dwelling which is being constructed and that a rehabilitation plan is

    compiled following completion of construction.

    This comment is noted. While not related to

    the planned subdivision, rehabilitation of

    impacts associated with the construction of the

    current house will be undertaken on

    completion of the construction of the current

    house.

    4.14. Right to provide

    additional

    comment

    CapeNature reserves the right to revise initial comments and request

    further information based on any additional information that may be

    received.

    This is noted.

    5. HERITAGE WESTERN CAPE

    5.1. Requirement for the

    submission of a

    Notice of Intent to

    Develop

    The email below and the letter attached have reference. Kindly be informed that

    Heritage Western Cape (HWC) has received the letter as indicated above. As

    such, HWC cannot comply with the due date mentioned. Kindly note HWC

    requires a Notice of Intent to Develop (NID) in order to start this application.

    Aikman Associates has been appointed as the

    independent specialist heritage consultant. A Notice

    of Intent to Develop (NID) form was compiled by the

    heritage specialist and submitted to HWC. On 5

    October 2017, HWC confirmed that a Heritage

    Impact Assessment would be required.

    The potential impact on heritage resources are

    assessed in Section F of the BAR and the specialist

    Heritage Impact Assessment (refer to Appendix

    G3).

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    18

    NO. ISSUE COMMENT RESPONSE

    6. DEPARTMENT OF TRANSPORT AND PUBLIC WORKS: ROAD NETWORK MANAGEMENT

    6.1. Previous approval of access off

    Boyes Drive

    NOTE: This email correspondence was addressed to Mr Marlyn Botha of

    the City of Cape Town: Transport Impact Assessment & Development

    Control and copied to SLR.

    Erf 177476 (JN 24891) is a consolidation of Erven 88268 and 88273 (JN

    20155). We approved the access (Section 17 of the Roads Ordinance)

    based upon the COCT’s support – it appears as though it was indeed an

    existing carriageway crossings (CWC) access.

    Your previous approval of the access off

    Boyes Drive is noted here for consideration by

    DEA&DP during the decision-making process

    (a copy of this approval has been included in

    Appendix E3).

    6.2. No foreseeable

    issue to support

    proposed access

    off Main Road

    One extra dwelling unit using the PMR 106 (Boyes Drive) access – should

    be no problem for you to support – I would suggest that it be made clear

    that only single residential use will be allowed – no Bed & Breakfast or

    other consent uses [sic] should be allowed.

    This comment is noted.

    6.3. Safe access A new access on Main Road (PMR 101) is proposed - safe? There is an existing servitude located on the

    south-western section of the erf that links to

    Main Road. Erf 88308 currently obtains access

    of Main Road from this servitude and is thus

    deemed to be safe.

    6.4. No requirement for

    Department to

    comment

    Please note that the COCT is the Regulatory Authority for both PMR 101

    and PMR 106 in this area and no further input is required from this branch

    - assuming there is an existing access to PMR 101, if not, with your

    recommendation we will approve it in terms of Section 17.

    This comment is noted.

    6.5. It appears as though the reason why this branch has not received any

    official request for comment on the subdivision is that there is no legal

    requirement for us to comment. The same applies to the NEMA

    application for subdivision – no official request for comment.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    19

    NO. ISSUE COMMENT RESPONSE

    6.6. No objection to the

    subdivision

    As stated previously (for the PMR 106 access), this branch will offer no

    objection to the subdivision, if requested to do so, both in terms of your

    legislation as well the NEMA.

    This support of the application is noted here

    for consideration by DEA&DP in decision-

    making.

    7. CITY OF CAPE TOWN

    INTEGRATED URBAN MANAGEMENT - LAND USE MANAGEMENT – KEVIN MCGILTON

    7.1. Requirement for

    environmental,

    heritage and visual

    assessments and

    public

    participation

    process

    The property in question is zoned Single Residential Zone 1 and is within

    a Heritage Protection Overlay Zone. Any proposed subdivision the

    property would require an application which, given the nature of the

    property with its watercourse, would require an environmental assessment

    and heritage assessment including a visual assessment as the property is

    visible from the Main Road as well as Boyes Drive.

    A process of public participation would be required before the

    adjudication of the proposal.

    This Basic Assessment process has been

    undertaken for the proposed subdivision. The

    requested specialist studies (heritage and

    visual) were included in the draft Basic

    Assessment Report (BAR) which was

    circulated for a 30-day comment and review

    period (see Appendix G).

    A public participation process has been

    undertaken as part of the Basic Assessment

    process (see Section F of the BAR)

    WATER AND SANITATION (RIVERS, STORMWATER AND CATCHMENT MANAGEMENT) – JUSTIN SMIT

    7.2. Requirements for

    Stormwater

    Management Plan

    A Stormwater management plan is to be submitted to this office for water

    quality only, due to the size of the Erf. Water quantity is not required due

    to the close proximity of this site to the ocean. Although Stormwater

    detention for water quantity is not required, the volume of water generated

    during the different scenario storms must be calculated and accommodated

    for and therefore the Stormwater management plan must also clearly

    indicate (with details) all required Stormwater overland escape routes to

    cater for flood water not piped underground. No runoff from this site must

    cause a nuisance to neighbouring properties, including Main Road. It must

    This comment is noted. A preliminary

    stormwater management plan has been

    prepared by the project engineer. This will be

    submitted to the COCT for approval as part of

    the relevant town-planning application that

    would be undertaken should the proposed

    project receive Environmental Authorisation.

    A copy of the Stormwater Management Plan

    has been also appended to the Engineering

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    20

    NO. ISSUE COMMENT RESPONSE

    be further noted that due to the steep nature of this site, critical velocities

    must be designed for and if so required, energy dissipaters will be required

    as well as a device/devices that will prevent the blocking of any

    Stormwater intakes/headwalls. Best management principles are to be

    applied to this site regarding the Stormwater management.

    Services Report (refer to Appendix G).

    7.3. Support for

    freshwater

    specialist

    recommendations

    This office supports the recommendations of the Fresh Water Specialist. Your support of the freshwater specialist

    recommendations are noted.

    ROADS AND STORMWATER (ASSET MANAGEMENT AND MAINTENANCE) – HEUPPSCHENNE LEKAY

    7.4. Engineering design

    drawing approval

    Civil Engineering drawings pertaining roads and storm water to be

    submitted for approval should municipal services be affected. Civil

    Engineering drawings demonstrating combined engineering services must

    also be submitted for perusal. This approval must be obtained prior to

    building plan approval.

    Engineering design drawings will be submitted

    for approval to the relevant office as per the

    normal building plan approval process.

    The approved civil engineering plans shall be implemented to the

    satisfaction of Asset Management and Maintenance before building plan

    approval or clearance application in case of sub division or taking

    occupancy.

    This requirement is noted.

    7.5. Comply with

    conditions issued

    by Transport

    Impact Assessment

    and Development

    Control

    Department

    Prior to submitting a full set of detailed engineering drawings to this office

    (Roads and Stormwater) for approval, the applicant shall ensure that all

    conditions relating to engineering requirements stipulated by Transport

    Impact Assessment and Development Control (TIA & DC) are met and

    depicted on the drawings. Consent given by TIA & DC must accompany

    submission of the engineering drawings.

    This comment is noted.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    21

    NO. ISSUE COMMENT RESPONSE

    7.6. Development of a

    Stormwater

    Management Plan

    Prior to submitting a full set of detailed engineering drawings to this office

    (Roads and Storm water) for approval, the applicant shall submit detailed

    Stormwater Management Plan to Catchment, Stormwater and River

    Management for approval. Consent from Catchment, Storm water and

    River Management must accompany submission of the detailed

    engineering drawings that depict the SMP.

    As indicated in Section 7.2, the stormwater

    management plan will be submitted to the

    Catchment, Stormwater and River

    Management for approval as part of the

    relevant town-planning application that would

    be undertaken should the proposed project

    receive Environmental Authorisation.

    7.7. Development

    contribution

    Development contribution will be applicable and payable prior to or

    clearance application.

    This requirement is noted.

    WATER AND SANITATION (WATER SECTION) – GAIRONESSE VAN WYK

    7.8. Provision of

    standard approval

    conditions on

    application for

    water connection

    No objections to the proposed subdivision.

    Standard approval conditions will be provided when a water connection is

    applied for to the respective properties. In addition, confirmation from

    Water Planning will be required that there is sufficient capacity in the

    existing water reticulation systems to accommodate the proposed

    development or units before approvals can be granted for water

    connections.

    This comment is noted.

    TRANSPORT IMPACT ASSESSMENT & DEVELOPMENT CONTROL – MARLYN BOTHA

    7.9. No objection Please note that this branch offers no objection in principle to the proposed

    subdivision of Erf 177476, St James. However, due to the fact that Boyes

    Drive is classified as a Provincial Main Road (PMR 106), this branches

    final comment on this application which will be issued at LUMS stage of

    the process will be subject to the final approval being issued by the

    Provincial Roads Engineer.

    This comments is noted, however, it is pointed

    out that the current access of Boyes Drive was

    approved as part of the approval process

    associated with the development of a house on

    the site.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    22

    NO. ISSUE COMMENT RESPONSE

    SOLID WASTE MANAGEMENT – CHANTAL ERLANK

    7.10.Residential

    properties required

    to use council

    refuse removal

    services

    The council wishes to ensure that all new developments, that require

    planning permission, contain suitable accommodation for the storage and

    disposal of waste to a licenced landfill site. Council reserves the right to

    service all residential properties that falls within its boundaries for refuse

    removal services. In terms of the Waste Management Tariff Policy,

    Section 18.2.1 all residential properties are compelled to use council

    refuse removal services and may not use private contractors directly. Non-

    residential properties may opt to use either Council services or a private

    contractor directly.

    The requirement for all residential properties

    to use council refuse removal services is

    noted.

    7.11.No objection In connection with the above proposal / development, I confirm that Solid

    Waste (Collections) as the Service Provider in the St James Area has no

    objection to the Proposed Subdivision and has sufficient unallocated

    capacity to accept and collect and dispose of all types of waste to a

    designated licence landfill site.

    A good waste management system must be in place to handle all waste

    generated by the activities and to mitigate against negative impact on the

    environment. The generation of construction waste and waste during the

    operation phases should be recycled on site or reused to fill up other sites

    and clean builder’s rubble can be disposed of at the nearest licenced

    facility under the guidance of the City of Cape Town. The waste generated

    by the construction personnel e.g. lunch remains and packaging etc. must

    be placed in approved refuse bins on site during the construction phases.

    The proposed development will not have any implications on the

    infrastructure of the area provided that the contractors identify a permitted

    refuse disposal site for various categories of waste, provided that a refuse

    This comment is noted.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    23

    NO. ISSUE COMMENT RESPONSE

    room is included in the planning stages of the development for the storage

    of waste to the satisfaction of the Director: Solid Waste Management.

    ENVIRONMENTAL MANAGEMENT: HERITAGE RESOURCES SECTION (HRS) – SJANEL MARTIN

    7.12.Site development

    plan

    Site Development Plan:

    The response to the Notification of Intent to Develop, (NID) requested a

    detailed site development plan (SDP). The submitted SDP only indicates

    the proposed subdivision lines and although these are generally in keeping

    with the pattern of subdivision in the immediate surrounds, it does not

    indicate proposed building platforms, proposed building massing/envelope,

    proposed access roads or existing mature trees to be retained.

    This comment is noted. As the application

    only relates to the proposed subdivision of Erf

    177476, the location of the building platforms

    or the proposed building massing/envelope of

    the future houses are not required at this stage.

    Thus, they are not indicated at present.

    If Environmental Authorisation is granted for

    the proposed subdivision, any future building

    plans for proposed dwellings on the

    subdivided portions would have to be

    submitted to the COCT for approval before

    they could be constructed.

    It is noted that the proposed access roads were

    indicated on the layout plan included in the

    draft BAR. In this regard, the approved access

    road (currently under construction) would be

    used to provide access from Boyes Drive to

    Portion 2, while Portion 1 would obtain access

    from Main Road via the existing servitude

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    24

    NO. ISSUE COMMENT RESPONSE

    adjacent to the south-western section of the erf

    (closest to Main Road).

    7.13.Pattern of new

    building platforms

    New building platforms should follow the existing pattern of development

    to mitigate the impact of the new building in a currently undeveloped

    landscape. Most erven in the Heritage Area are rectangular in shape. This

    is derived from the historic gridiron pattern of subdivision. The

    predominant building form is simple narrow rectangle with attached

    verandhas or stoeps. The houses are almost always situated parallel to the

    boundaries.

    The requirements for new building platforms

    are noted.

    7.14.St James/Kalk Bay

    Heritage

    Protection Overlay

    Zone Design

    Guidelines

    Design indicators in HIA:

    Heritage Resources Section (HRS) agrees in principle with the following

    design indicators in the HIA:

    • The subdivisions should complement the overall gridiron pattern of the

    area;

    • New buildings to be made up of simple rectangular forms parallel to

    the boundaries;

    • New building to be visually recessive with landscaping the dominant

    element. The use of sandstone is recommended together with plastered

    masonry painted with neutral recessive colours;

    • Large areas of glass/windows to be situated in shadow by pergolas

    and/or verandas;

    HRS also draws the developer’s attention to the already established

    design guidelines for the St James/Kalk Bay Heritage Protection Overlay

    Zone (HPOZ), which should be included as a condition of approval to any

    proposed subdivision. These guidelines are currently used as the

    Support of the proposed design indicators

    listed in the Heritage Impact Assessment

    Report is acknowledged.

    The requirement for the future houses to

    comply with the St James/Kalk Bay HPOZ

    design guidelines is noted.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    25

    NO. ISSUE COMMENT RESPONSE

    establishment of ‘best practice’ for all new developments in the St

    James/Kalk Bay HPOZ and are available on the City’s Website.

    7.15.Contradiction of

    the St James/Kalk

    Bay HPOZ

    HOA and Design guidelines:

    Given that the site falls within the HPOZ, HRS already comments on all

    applications in order to obtain approval to do work in the HPOZ.

    Currently, HRS strongly advises applicant to obtain HRS support during

    the design phase as well as input from the local conservation body prior to

    formal submission. The Design Guidelines suggest that the proposed

    Home Owners Association (HOA) would scrutinise plans prior to

    submission to the COCT, which may cause undue conflict with

    applications that meet the HOA’s requirements but not the City’s. This

    needs to be reviewed and all applications need to be in accordance with the

    existing design guidelines for the area.

    Although HRS is not averse to architectural guidelines that are more

    restrictive than the current design guidelines for the St James/Kalk Bay

    HPOZ, any guidelines that are in contradiction to the established

    guidelines need to be removed and are not supported. HRS will review the

    guidelines in detail during the subsequent commenting period on the final

    BAR as well as in HRS comment to HWC on the HIA.

    The requirement for HRS to review all

    applications within the area and the fact that

    the requirements of the HPOZ Design

    Guidelines would supersede the HOA design

    guidelines are noted.

    It is noted that in terms of the EIA Regulations

    2014, as amended, there is no requirement for

    an additional comment period on the BAR.

    Thus, the revised BAR will be submitted to

    DEA&DP for decision-making.

    7.16.Support for Visual

    Impact Assessment

    mitigation

    measures

    VIA

    HRs supports all mitigation measures that are in accordance with the

    design guidelines for St Kames/Kalk Bay HPOZ.

    Support of the mitigation measures contained

    in the Visual Impact Assessment is

    acknowledged.

    7.17.Provide comments

    from Kalk Bay

    • Kalk Bay Heritage Subcommittee

    Please provide the Kalk Bay Heritage Subcommittee’s comment to HRS.

    The comments received from the Kalk Bay

    Heritage subcommittee to date have been

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    26

    NO. ISSUE COMMENT RESPONSE

    Heritage

    subcommittee

    This is also a requirement of HWC’s response to the NID. forwarded to the HRS.

    ENVIRONMENTAL MANAGEMENT DEPARTMENT: ENVIRONMENTAL MANAGEMENT SECTION (EMS) – CRISPIN BARRETT

    7.18.Summary of

    application

    This application is for material exceeding 10 m3 being removed /

    deposited from / in an unnamed watercourse traversing the site and

    clearance of an area exceeding 300 m2 or more of indigenous vegetation.

    The complete table of listed activities that

    would be triggered by the proposed project are

    provided in Section A of the BAR.

    7.19. General comments

    on

    Botanical Report

    The following is garnered from the Botanical Assessment Report:

    • The site contains the Endangered vegetation type Peninsula Sandstone

    Fynbos, which is adequately represented within the Table Mountain

    National Park so the conservation value is sufficiently protected for the

    geographical location, but it is still a loss that should be assessed with

    possible alternative development proposal that could see more

    vegetation protected rather than lost.

    • The 10 m development setback is seen as adequate for the vegetation

    impact but this does not take into consideration the ecological buffer

    for the watercourse corridor, where the indirect impacts are not

    assessed.

    • The impacted and invaded patches have the potential for

    restoration/rehabilitation.

    • Dr David McDonald, states that the proposed development would

    result in the loss of mostly intact ‘Endangered’ Peninsula Sandstone

    Fynbos. While the vegetation type is well-preserved in its ecological

    state with a number of invasive alien species present, there is high

    restoration potential and the seasonal watercourse line is prominent

    and sensitive feature. With particular interest on indirect impacts is the

    loss of vegetation along the seasonal watercourse would reduce the

    This summary is noted.

    This comment is noted. However, it must also

    be recognised that the ecological corridor of

    the watercourse has been restricted by the

    development of Boyes Drive and historic

    diversion of the watercourse located on the

    bottom of the erf. Accordingly, the ecological

    corridor of the seasonal watercourse is

    considered to be restricted to the site itself.

    Nevertheless, allowance has been made for the

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    27

    NO. ISSUE COMMENT RESPONSE

    ecological corridor. continuation of overland flow along the

    watercourse diversion and a 3 m building line

    would be incorporated along this section of the

    property boundary. Thus, vegetation

    establishment and ecological functioning along

    this portion of the watercourse can still occur,

    albeit in a modified way.

    7.20. General comments

    on

    Freshwater Report

    The following is garnered from the Freshwater Assessment Report:

    • The watercourse, together with its riparian zone, constitutes an intact

    ecological entity.

    • The National Environmental Management Act principle ‘sustainable

    development’ requires the consideration of all relevant factors,

    including that a risk-averse and cautious approach should be applied,

    taking into account the limits of current knowledge about the

    consequences of decisions and actions. This is very much applicable

    for this application.

    • Dr Harding’s findings are that although the previous proposed

    application has been amended to reflect fewer portions of subdivision,

    the negative impact on the environment is to a degree the same, if not

    worse. This is due to the accumulative impact from the upper slope

    development and with the proposed removal of virtually all the western

    riparian vegetation, the intact ecological entity, causing it to be

    disaggregated into smaller non-functional components.

    This summary is noted. However, it is pointed

    out that the preferred alternative layout makes

    provision for fewer subdivided portions and

    allows for a 10 m buffer zone along the

    property boundary for Portion 2 and the upper

    part of Portion 1 which incorporates a large

    portion of the seasonal watercourse. The

    second layout alternative considered five

    subdivided portions and entails the complete

    diversion of the seasonal watercourse over the

    proposed additional subdivided portions.

    It is also noted that, as per the Botanical

    Assessment Addendum, no remnant coastal

    forest vegetation is located on the site thus, the

    “western riparian vegetation” delineated by the

    Freshwater specialist falls under the Peninsula

    Sandstone Fynbos vegetation type.

    7.21.Construction of

    approved dwelling

    The construction of the approved dwelling has shown a significant impact

    on the upper slope, which is steeper than 1:4, and requires that DEADP

    Refer to the response provided in Section 3.3

    above regarding development on steep slopes.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    28

    NO. ISSUE COMMENT RESPONSE

    critically assess it in accordance with their ‘Guideline for the Management

    of Development on Mountains, Hills and Ridges of the Western Cape’

    (EIA Guideline Series File NO E12/2/P). The most significant

    environmental attributes on this site are the presence of seasonal

    watercourses, seeps and mostly intact endangered Peninsula Sandstone

    Fynbos.

    7.22.Conservation of

    watercourses

    Conservation and rehabilitation of our watercourses should be at the heart

    of Water Management for Cape Town, being a water stressed area and

    recently having experienced an extreme drought.

    National Environmental Management Act.

    The principles of the National Environmental Management Act of 1998

    clearly state that sensitive, vulnerable, highly dynamic or stressed

    ecosystems, such as water courses and similar systems, require specific

    attention in management and planning procedures, especially where they

    are subject to development pressure.

    These comments are noted.

    7.23.Floodplain and

    River Corridor

    Management

    Policy

    As per the City’s Floodplain and River Corridor Management Policy (27

    May 2009), watercourses and wetlands with their adjacent riparian areas

    and associated fauna and flora must be protected or ‘buffered’ from the

    impacts of adjacent development or activity. Buffers for watercourses can

    be up to 40 m from river edge/bank edge.

    The perennial & non-perennial watercourses in the narrow St James

    valleys are threatened by, inter alia, alien invasion, infilling, increased

    volumes of stormwater runoff and poor water quality. With the recent,

    approved development of the upper slope of the erf, erosion has increased

    and foreign debris has accumulated in the lower stretch of the watercourse.

    These comments are noted. It is also noted that

    in terms of this policy, the adjustment of the

    recommended buffer can take place on a

    site/case specific basis.

    The preferred layout alternative aims to

    balance the right of the applicant to extract

    value from the property with the need to

    conserve the seasonal watercourse through the

    implementation of the proposed 10 m buffer

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    29

    NO. ISSUE COMMENT RESPONSE

    The existing watercourse, although impacted upon, needs to be conserved

    and rehabilitated and there should be no further net loss, particularly

    where alternatives exist.

    zone. As noted in Section 4.8, any foreign

    debris located within the seasonal watercourse

    will be removed on completion of current

    construction activities.

    7.24.Presentation of an

    alternative

    proposal

    EMS requires an alternative proposal to be presented where there is:

    • An additional development setback that is taken from the watercourse

    and determined by the aquatic specialist and not the property

    boundary.

    • In addition to this a registered river servitude that restricts any further

    development/associated infrastructure as well as landscaping with prior

    consent from the relevant Environmental Management department.

    • A Detailed Site Development Plan that shows reduced building

    platforms/massing/envelope and access roads.

    • Condition that no second dwellings will be permissible on the

    subdivided portions.

    It is understood that the requirements listed

    herein fall outside of the mandate of the

    Environmental Management Section. The

    proposed project proposal remains as was

    originally presented in the draft Basic

    Assessment Report.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    30

    Table 2: Summary table of comments received from I&APs, with responses from the project team � = Letter/Fax/Post � = E-mail

    NO. ISSUE NAME METHOD COMMENT RESPONSE

    1. GENERAL

    1.1. Proposed building

    lines/ boundaries.

    Andy Rice �= E-mail dated

    21 August 2017

    Building lines / boundaries. The proposed building lines applicable

    to the subdivided portions will be in

    compliance with the requirements of

    the relevant City of Cape Town

    planning ordinances and/or by-laws, as

    applicable. As noted in the DBAR, a 10

    m development setback buffer would

    be included over Portion 2 and the

    upper part of Portion 1. A standard

    common boundary building line

    restriction of 3 m would be applicable

    to the remaining common boundaries.

    1.2. Withheld comment/objection

    St. James

    Ratepayers

    Heritage Sub-

    committee – Barrie

    Gasson

    �= E-mail

    dated

    6 February

    2019

    After much consideration of this application we

    have decided to withhold any

    comment/objection until such time as the site

    works, which appear to have stalled, are

    completed according to the approved plans and

    to Council’s satisfaction. We are referring to,

    among other things, the stone cladding yet to be

    done to retaining walls, abandoned rock and

    rubble heaps that should either be put to use or

    removed, and the cantilever road curve, that was

    You right to reserve comment on

    the application is noted. However,

    in terms of the EIA Regulations

    2014, as amended, there is no

    requirement for an additional

    comment period on the BAR. Thus,

    the revised BAR, which includes

    this comment, will be submitted to

    DEA&DP for decision-making.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    31

    NO. ISSUE NAME METHOD COMMENT RESPONSE

    not part of the original plans, the underside of

    which requires ‘closing up’ with appropriate

    stone-clad structure. Further, we expect that

    environmental damage to the

    watercourse/ravine, such as accumulation of

    rubble and at least on large boulder, to be made

    good. Once these matters have been attended to

    we will be prepared to reconsider the

    application to subdivide.

    1.3. Legal non-

    compliance

    Khula

    Environmental

    Consultants – Nick

    Steytler on behalf

    of Kevin Hodgson

    and Karl and Gina

    Leinberger

    �= E-mail

    dated

    6 February

    2019

    Over a period of several years numerous

    activities have been undertaken on the lower

    reaches of the site in close proximity and

    directly affecting the watercourse. These

    activities have included clearance of vegetation,

    infilling and excavations in close proximity and

    within the watercourse to create level platforms

    and to re-route the watercourse. Most (if not all)

    of these activities have commenced without

    prior environmental authorisation in terms of

    the National Environmental Management Act

    (NEMA) EIA Regulations (as applicable at the

    time of the commencement of these activities).

    Given the direct impact these activities have had

    on the lower reaches of the watercourse it is

    also likely that a water use authorisation should

    have been applied for in terms of the National

    It is pointed out that the applicant

    took ownership of the property in

    2014. Thus, the applicant was not

    in control of the land prior to this

    date. With respect to the alleged

    activities highlighted in this

    comment, no evidence has been

    provided to show that any of the

    alleged activities took place or that

    such actions would have triggered

    any listed activities that may have

    been in force at the time.

    It should also be noted that the

    residents in this submission applied

    themselves for the right to

    undertake activities in close

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    32

    NO. ISSUE NAME METHOD COMMENT RESPONSE

    Water Act (Act 36 of 1998). These historic

    activities should be investigated by the

    competent authority as these have a direct

    bearing on the lawfulness of the current

    application as no application in terms of the

    NEMA EIA Regulations should be considered

    by the competent authority if the same site is

    associated with unlawful activities. On this

    basis alone the application should be withdrawn

    until the competent authority has investigated

    the allegations and, if found to be true, only

    after the completion of a successful Section 24G

    Rectification Application, can the current

    application be considered.

    proximity to the watercourse,

    including a gabion basket retaining

    wall located within a few meters of

    the watercourse.

    1.4. Impact on the

    provision of

    municipal services

    Khula

    Environmental

    Consultants – Nick

    Steytler on behalf

    of Kevin Hodgson

    and Karl and Gina

    Leinberger

    �= E-mail

    dated

    6 February

    2019

    Subdividing residential property and the

    associated densification of urban areas, while

    being desirable from a spatial planning

    perspective, results in an increase in pressure on

    the Local Authority’s capacity to provide

    adequate municipal services. Potable water

    supply, which is currently strained given the

    recent drought, in particular is likely to be

    impacted with the result that existing residents

    suffer the consequences which range from

    reduced water pressure to dwindling levels of

    household supply.

    Confirmation has been obtained

    from the COCT service

    departments that adequate capacity

    is available for the proposed

    project (see Appendix E3).

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    33

    NO. ISSUE NAME METHOD COMMENT RESPONSE

    1.5. Nuisance impacts Given the location of the site in a dense

    residential suburb the potential for nuisance

    impacts is high and special attention is required

    to ensure that any potential nuisance impacts are

    minimised. The EMP simply states that

    construction activities outside normal working

    hours should be avoided. This is simply not

    sufficient because the Contractor could

    undertake work over weekends and cause

    significant nuisance impacts and motivate that

    the timing was unavoidable. Working outside

    normal work hours should not be permitted

    without the express permission of the

    independent Environmental Control Officer

    (ECO). This would provide greater assurance

    that the nuisance impacts associated with

    working outside normal work hours would be

    satisfactorily minimised.

    The recommendations relating to

    noise control and working hours

    are set out in Section 3.10 of the

    EMP (see Appendix H). In this

    regard, it is specifically noted that a

    permit shall be obtained from the

    local authority for any deviation

    from local by-laws and/or

    regulations with respect to working

    hours.

    The significance of general

    nuisance impacts during the

    construction phase was assessed in

    Section G of the BAR. In this

    regard, although intensity of these

    impacts could be high at times

    during construction, the overall

    construction period would be over

    the short-term and would be of

    local extent. Thus, these impacts

    are deemed to be of low to

    medium significance without

    mitigation. With the

    implementation of mitigation, the

    significance would reduce to

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    34

    NO. ISSUE NAME METHOD COMMENT RESPONSE

    LOW.

    1.6. Operational

    management

    Khula

    Environmental

    Consultants – Nick

    Steytler on behalf

    of Kevin Hodgson

    and Karl and Gina

    Leinberger

    �= E-mail

    dated

    6 February

    2019

    The timing and frequency of culvert inspections

    and cleaning of debris, indicated as a key

    operational phase environmental management

    activity, needs to be specified. Given the risk of

    flood-related impacts associated with the

    proposed infrastructure failing, it is important

    that the precise timing of inspections and debris

    removal should be recommended by a

    hydrologist.

    This comment is noted. The timing

    and frequency of such inspections

    and actions would be the same as

    those undertaken by the COCT for

    the existing culvert located on the

    site.

    2. PROCEDURAL ISSUES

    2.1. Flawed public

    participation

    process

    Khula

    Environmental

    Consultants – Nick

    Steytler on behalf

    of Kevin Hodgson

    and Karl and Gina

    Leinberger

    �= E-mail

    dated

    6 February

    2019

    The Public Participation Process (PPP) is

    flawed as it does not satisfy the principle that all

    information submitted for decision-making will

    have been reviewed by the stakeholders (in this

    case the Interested and Affected Parties, I&APs)

    prior to the decision having being reached. The

    flaw has come about as a result of the manner in

    which the process has been designed whereby

    only one opportunity has been provided to

    I&APs to review the Basic Assessment (the

    currently available Draft BAR) and associated

    specialist studies. It is indicated that the

    comment received on the Draft BAR will be

    incorporated into a Final BAR which will be

    It is pointed out that in terms of the

    EIA Regulations 2014, as

    amended, there is no requirement

    for an additional comment period

    on the BAR. Thus, the revised

    BAR, which includes this

    comment, will be submitted to

    DEA&DP for decision-making. As

    is commented, I&APs had the

    opportunity to comments on the

    BID during the pre-application

    phase – this is seen as normal

    practice to inform people and

    provide opportunity to comment

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    35

    NO. ISSUE NAME METHOD COMMENT RESPONSE

    submitted to the competent authority for a

    decision. As such it appears as though no

    opportunity is available for the Registered

    I&APs to review and comment on any

    additional information or significant changes to

    the BAR or specialist studies that may arise as a

    result of the comment on the Draft BAR.

    Circulating a Background Information

    Document (BID) as a precursor to the Draft

    BAR should not be considered as a substitute

    for a comment period on a BAR as the BID

    lacks the detail presented in the BAR and the

    specialist studies, a critical component of any

    EIA process, are not included.

    ahead of the formal application

    procedure.

    2.2. Concern for a need

    of a Water Use

    Licence

    Khula

    Environmental

    Consultants – Nick

    Steytler on behalf

    of Kevin Hodgson

    and Karl and Gina

    Leinberger

    �= E-mail

    dated

    6 February

    2019

    Related to this concern is the very strong

    likelihood that the proposed development will

    require a Water Use Licence Application

    (WULA) in terms of the National Water Act

    (NWA), Act 36 of 1998. The BAR simply

    indicates that the current BAR (which includes

    a freshwater specialist Risk Assessment) has

    been submitted to the Department of Water and

    Sanitation (DWS) for confirmation regarding

    the requirement for a WULA. Given that a

    WULA is highly likely (and this is

    acknowledged by the EAP) and that the project

    This comment is noted. Once

    confirmation has been received

    from DWS that a WULA is

    required, the applicant will have to

    undertake a public participation

    process which complies with the

    legislative requirements for a

    WULA in terms of the NWA.

    Thus, registered I&APs would still

    have an opportunity to review any

    additional information that may be

    required for the WULA.

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    36

    NO. ISSUE NAME METHOD COMMENT RESPONSE

    Khula

    Environmental

    Consultants – Nick

    Steytler on behalf

    of Kevin Hodgson

    and Karl and Gina

    Leinberger

    �= E-mail

    dated

    6 February

    2019

    is associated with the unmitigable loss of

    aquatic habitat that is assessed as having a

    HIGH Risk, it is highly likely that DWS, in

    order to decide on the WULA, will require

    additional information and/or revisions to the

    project design. If additional information or a

    change is project design is required in order for

    the WUL to be issued then the Registered

    I&APs would not have been able to review the

    additional information and the Environmental

    Authorisation (if issued) would not be aligned

    with the WUL. Section 24(4) of NEMA calls

    for the alignment of all environmental

    applications and at present the requirement for

    integrated decision-making is being

    implemented by DEA&DP. Accordingly the

    information submitted as part of the Basic

    Assessment process should also be sufficient for

    fulfilling the information of other environmental

    applications (viz a viz the very likely WULA

    which clearly it is not).

    Where there is a requirement to

    alter the proposed project design

    due to the findings of the WULA,

    these changes would be presented

    to DEA&DP to confirm whether an

    Application to Amend

    Environmental Authorisation (if

    issued) would be necessary.

    2.3. Insufficient

    information

    Certain important information is lacking in the

    application and this also presents a flaw. In

    terms of the layout and design of the proposed

    development no estimate of the development

    footprint is presented in the Draft BAR and the

    As noted in Section 7.2, no detailed

    information pertaining to the

    building footprint of future houses

    is required as this application

    related to the proposed subdivision

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    37

    NO. ISSUE NAME METHOD COMMENT RESPONSE

    Khula

    Environmental

    Consultants – Nick

    Steytler on behalf

    of Kevin Hodgson

    and Karl and Gina

    Leinberger

    �= E-mail

    dated

    6 February

    2019

    Site Layout Plan presented in Appendix B of the

    Draft BAR does not show building footprints.

    No plan is included in the Draft BAR which

    presents a map of the environmental

    sensitivities of the site with an overlay of the

    layout of the proposed development. This is a

    specified requirement as per Appendix 1 of

    Regulation 3 of GN No. R326 of the NEMA

    EIA Regulations 2014 (as amended).

    The proposed engineered containment of the

    seasonal watercourse on the eastern boundary of

    the site (i.e. the proposed headwall, open and

    of the erf. This information would

    only be available if Environmental

    Authorisation is granted for the

    proposed subdivision and once

    building plans have been

    completed for each subdivided

    portion for formal approval by the

    City of Cape Town.

    A plan showing the location of the

    erf in relation to mapped Critical

    Biodiversity Areas is provided in

    Appendix D of the BAR. In

    addition, Figure 10 of the Botanical

    specialist assessment report shows

    the location of intact and semi-

    intact natural vegetation located on

    the site and Figure 4 of the

    freshwater assessment shows the

    location of the seasonal

    watercourse.

    A cross-section of this

    infrastructure was included in

    Figure 3 of the Engineering

    Services Report (see Appendix

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    38

    NO. ISSUE NAME METHOD COMMENT RESPONSE

    closed culverts) is associated with potentially

    significant environmental impacts yet no

    engineering drawings of these structures are

    presented for scrutiny.

    Due to the nature of the receiving environment

    and also the requirement for a Heritage Impact

    Assessment where a key concern is the potential

    visual impact information allowing for the

    satisfactory assessment of visual impacts is

    necessary. However upon review of the

    specialist VIA and the Draft BAR it is evident

    that no elevation drawings or any 3D

    impressions showing the visual appearance of

    the developed site are included. This lack of

    information undermines the credibility of the

    VIA and is considered a significant limitation.

    G5). The engineer has provided

    additional detail flor the proposed

    structure in the Stormwater

    Management Plan appended to the

    Services Report.

    As no detailed information

    pertaining to the building footprint

    of future houses is required at the

    time of the assessment, no 3D

    impressions were prepared.

    However, the Visual Impact

    Assessment practitioner deemed

    that sufficient information was

    available to adequately assess the

    potential visual impact of the

    proposed project on sensitive

    viewers. The implementation of

    design guidelines for the future

    residences (and the required

    approvals of these residences in

    terms of the HPOZ) was deemed to

    be significant mitigation for any

    potential visual impacts (refer to

    Appendix G4).

  • Proposed Subdivision of Erf 177476, St James, Cape Town

    SLR Consulting (South Africa) (Pty) Ltd Comments Report

    39

    NO. ISSUE NAME METHOD COMMENT RESPON