32
COMBINED DITCH MEETING JD 18 SM JD 17 MS JD 32 SM Sibley CD 65 August 12, 2019 1:30 pm McLeod County North Complex

Combined Ditch Meeting Presentation

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Combined Ditch Meeting Presentation

COMBINED DITCH MEETING JD 18 SM JD 17 MS JD 32 SM Sibley CD 65

August 12, 2019 1:30 pm

McLeod County North Complex

Page 2: Combined Ditch Meeting Presentation

Redetermination

• Background • JD 18 SM completed redetermination in November of 2016 • Concerns with

• Outlet fee for JD 17 MS, paying over 9% of the benefits • Watershed boundaries do not match up to those previously

redetermined • CD 65 boundary was extended to include portions of JD 18 SM

• Redetermination stays in effect until another redetermination is complete

• Total cost of the project was $1,033,395.89 • Cost less seeding and damages was

$92,167.32

Page 3: Combined Ditch Meeting Presentation

Redetermination

• Proposed • Do a redetermination on JD 18 SM, JD 17 MS, JD 32 SM, Sibley CD 65

• Upon completion they are combined into 1 large system

Page 4: Combined Ditch Meeting Presentation

Redetermination

Including: • Process • Cost • Timeframe

Page 5: Combined Ditch Meeting Presentation

Redetermination

RECAP:

• Eliminates current outlet fees • All 4 ditch systems, big or small, pay for the maintenance of the others • All acres are part of the system and watershed boundaries become

seamless • CD65 and JD 18 SM boundary would no longer be an issue • Need to pay for the redetermination again • Drainage authority would be realigned to reflect the new benefit

percentages • All expenses incurred up until ROB is final are spread on current benefits

• Current debt on JD 18 SM is $647,637.50

Page 6: Combined Ditch Meeting Presentation

Repair Projects

Culvert Locations

Page 7: Combined Ditch Meeting Presentation

Repair Projects

Repair 18-176 256th Lane Crossing

Page 8: Combined Ditch Meeting Presentation

Repair Projects

Repair 18-163 Heinz

Page 9: Combined Ditch Meeting Presentation

Repair Projects

Repair 18-081 Frauendienst

Page 10: Combined Ditch Meeting Presentation

Repair Projects

Page 11: Combined Ditch Meeting Presentation

Repair Projects

Page 12: Combined Ditch Meeting Presentation

Repair Projects

Page 13: Combined Ditch Meeting Presentation

Repair Projects

Page 14: Combined Ditch Meeting Presentation

Repair Projects

Contractor with lowest responsible bid: Wuetherich Drainage, Brian Wuetherich Sibley County culvert pieces have been delivered to the Gaylord area and are being

assembled.

Cost of pieces for 3 culverts: $49,551.000

Page 15: Combined Ditch Meeting Presentation

256th Lane Crossing

• Significant flooding most springs • Impacts farm land upstream from

culvert • Impacts farm land downstream

from culvert • Impacts drivability of driveway east

of 256th Lane

Page 16: Combined Ditch Meeting Presentation

256th Lane Crossing

March 20, 2019- looking east down 256th Lane

Page 17: Combined Ditch Meeting Presentation

256th Lane Crossing

March 20, 2019- looking NW into submerged ditch

Page 18: Combined Ditch Meeting Presentation

256th Lane Crossing

March 22, 2019- looking south of 256th Lane

Page 19: Combined Ditch Meeting Presentation

256th Lane Crossing

March 22, 2019- looking east down 256th Lane

Page 20: Combined Ditch Meeting Presentation

256th Lane Crossing

March 22, 2019- looking NW into submerged ditch

Page 21: Combined Ditch Meeting Presentation

256th Lane Crossing

May 28, 2019- looking west along 256th Lane

Page 22: Combined Ditch Meeting Presentation

256th Lane Crossing

• Solutions • Fix current 256th Lane • Reroute the driveway

Page 23: Combined Ditch Meeting Presentation

256th Lane Crossing

• Fix current 256th Lane • 3 options from ISG Culvert Analysis, 2019

Option 1: • Install a 10’ x 8’ dual box culvert

• Pros: • Increase the capacity of the crossing • Lower the peak flood elevations upstream of the crossing by up to 3’ • Will protect the culvert which currently only has .89’ of cover • Total width of channel at culvert will be 22.5’ (currently 20’)

• Cons: • Will not effect frequency of the road overtopping • Will overtop the road with any 25 year rain event • Cost: $152,840

Page 24: Combined Ditch Meeting Presentation

256th Lane Crossing

• Fix current 256th Lane • 3 options from ISG Culvert Analysis, 2019

Option 2: • Leave existing culvert

• Pros: • Culvert is in good condition

• Cons: • Will continue to flood

Page 25: Combined Ditch Meeting Presentation

256th Lane Crossing

• Fix current 256th Lane • 3 options from ISG Culvert Analysis, 2019

Option 3: • Raise the road 2 feet from elevation of 988 to 990 & install box culvert

• Pros: • Increase the capacity of the crossing • Lower the peak flood elevations upstream of the crossing by up to 3’ • Will protect the culvert which currently only has .89’ of cover • Total width of channel at culvert will be 22.5’ (currently 20’) • The lowest spot is the driveway is 300’ east of the culvert location, so

building it up would prevent further flooding • Cons:

• Will overtop the road with any 50 year rain event • Cost: $176,675

Page 26: Combined Ditch Meeting Presentation

• Reroute the driveway • Pros:

• Increase the capacity of the crossing

• Lower the peak flood elevations upstream of the crossing by up to 3’

• The lowest spot is the driveway is 300’ east of the culvert location, so building it up would prevent further flooding

• Cons: • Will overtop the road with

any 50 year rain event • Cost: $60,000 minimum for

construction • Maintain it perpetually

256th Lane Crossing

1895

Page 27: Combined Ditch Meeting Presentation

• Aaron met with Ryan from the Dept of Homeland

Security & Emergency Management in May • Photos and hydraulic analysis have been sent to

FEMA • FEMA hopes to be out as early as September to take

a look at the damage/repairs • Improvements typically aren’t allowed unless it is

more cost effective

FEMA

Page 28: Combined Ditch Meeting Presentation

Delta Feasibility Study

Page 29: Combined Ditch Meeting Presentation

Two-Tier Ditches

Page 30: Combined Ditch Meeting Presentation

Bonding

Remaining principal & interest balance of debt: JD 18 SM – Redetermination: $234,150 (5 year, final payment 2/1/2023) Cleanout: $413,487.50 (20 year, final payment 2/1/2038) JD 32 SM – Improvement: $95,637.50 Call date: February 1, 2025 Bond defeasance is only option prior to this date, but fees/penalties

Page 31: Combined Ditch Meeting Presentation

Bonding

Future Bonding: Based on: $100,000 for redetermination $500,000 for culvert repairs $600,000

5 years at 1.5% up to 20 years at 2.25%

Reimbursement Resolution: Look back 60 days from the date of the resolution & 18 months forward

Page 32: Combined Ditch Meeting Presentation

COMBINED DITCH MEETING JD 18 SM JD 17 MS JD 32 SM Sibley CD 65

August 12, 2019 1:30 pm

McLeod County North Complex