Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
COMBINED DITCH MEETING JD 18 SM JD 17 MS JD 32 SM Sibley CD 65
August 12, 2019 1:30 pm
McLeod County North Complex
Redetermination
• Background • JD 18 SM completed redetermination in November of 2016 • Concerns with
• Outlet fee for JD 17 MS, paying over 9% of the benefits • Watershed boundaries do not match up to those previously
redetermined • CD 65 boundary was extended to include portions of JD 18 SM
• Redetermination stays in effect until another redetermination is complete
• Total cost of the project was $1,033,395.89 • Cost less seeding and damages was
$92,167.32
Redetermination
• Proposed • Do a redetermination on JD 18 SM, JD 17 MS, JD 32 SM, Sibley CD 65
• Upon completion they are combined into 1 large system
Redetermination
Including: • Process • Cost • Timeframe
Redetermination
RECAP:
• Eliminates current outlet fees • All 4 ditch systems, big or small, pay for the maintenance of the others • All acres are part of the system and watershed boundaries become
seamless • CD65 and JD 18 SM boundary would no longer be an issue • Need to pay for the redetermination again • Drainage authority would be realigned to reflect the new benefit
percentages • All expenses incurred up until ROB is final are spread on current benefits
• Current debt on JD 18 SM is $647,637.50
Repair Projects
Culvert Locations
Repair Projects
Repair 18-176 256th Lane Crossing
Repair Projects
Repair 18-163 Heinz
Repair Projects
Repair 18-081 Frauendienst
Repair Projects
Repair Projects
Repair Projects
Repair Projects
Repair Projects
Contractor with lowest responsible bid: Wuetherich Drainage, Brian Wuetherich Sibley County culvert pieces have been delivered to the Gaylord area and are being
assembled.
Cost of pieces for 3 culverts: $49,551.000
256th Lane Crossing
• Significant flooding most springs • Impacts farm land upstream from
culvert • Impacts farm land downstream
from culvert • Impacts drivability of driveway east
of 256th Lane
256th Lane Crossing
March 20, 2019- looking east down 256th Lane
256th Lane Crossing
March 20, 2019- looking NW into submerged ditch
256th Lane Crossing
March 22, 2019- looking south of 256th Lane
256th Lane Crossing
March 22, 2019- looking east down 256th Lane
256th Lane Crossing
March 22, 2019- looking NW into submerged ditch
256th Lane Crossing
May 28, 2019- looking west along 256th Lane
256th Lane Crossing
• Solutions • Fix current 256th Lane • Reroute the driveway
256th Lane Crossing
• Fix current 256th Lane • 3 options from ISG Culvert Analysis, 2019
Option 1: • Install a 10’ x 8’ dual box culvert
• Pros: • Increase the capacity of the crossing • Lower the peak flood elevations upstream of the crossing by up to 3’ • Will protect the culvert which currently only has .89’ of cover • Total width of channel at culvert will be 22.5’ (currently 20’)
• Cons: • Will not effect frequency of the road overtopping • Will overtop the road with any 25 year rain event • Cost: $152,840
256th Lane Crossing
• Fix current 256th Lane • 3 options from ISG Culvert Analysis, 2019
Option 2: • Leave existing culvert
• Pros: • Culvert is in good condition
• Cons: • Will continue to flood
256th Lane Crossing
• Fix current 256th Lane • 3 options from ISG Culvert Analysis, 2019
Option 3: • Raise the road 2 feet from elevation of 988 to 990 & install box culvert
• Pros: • Increase the capacity of the crossing • Lower the peak flood elevations upstream of the crossing by up to 3’ • Will protect the culvert which currently only has .89’ of cover • Total width of channel at culvert will be 22.5’ (currently 20’) • The lowest spot is the driveway is 300’ east of the culvert location, so
building it up would prevent further flooding • Cons:
• Will overtop the road with any 50 year rain event • Cost: $176,675
• Reroute the driveway • Pros:
• Increase the capacity of the crossing
• Lower the peak flood elevations upstream of the crossing by up to 3’
• The lowest spot is the driveway is 300’ east of the culvert location, so building it up would prevent further flooding
• Cons: • Will overtop the road with
any 50 year rain event • Cost: $60,000 minimum for
construction • Maintain it perpetually
256th Lane Crossing
1895
• Aaron met with Ryan from the Dept of Homeland
Security & Emergency Management in May • Photos and hydraulic analysis have been sent to
FEMA • FEMA hopes to be out as early as September to take
a look at the damage/repairs • Improvements typically aren’t allowed unless it is
more cost effective
FEMA
Delta Feasibility Study
Two-Tier Ditches
Bonding
Remaining principal & interest balance of debt: JD 18 SM – Redetermination: $234,150 (5 year, final payment 2/1/2023) Cleanout: $413,487.50 (20 year, final payment 2/1/2038) JD 32 SM – Improvement: $95,637.50 Call date: February 1, 2025 Bond defeasance is only option prior to this date, but fees/penalties
Bonding
Future Bonding: Based on: $100,000 for redetermination $500,000 for culvert repairs $600,000
5 years at 1.5% up to 20 years at 2.25%
Reimbursement Resolution: Look back 60 days from the date of the resolution & 18 months forward
COMBINED DITCH MEETING JD 18 SM JD 17 MS JD 32 SM Sibley CD 65
August 12, 2019 1:30 pm
McLeod County North Complex