Coking 101 Coking 101 An Introduction to Delayed Coking Prepared By: Jack Adams, Adams Project Managers, Inc. Email: [email protected] JLAdams com & Email: info@ProcessEngr.com www.JLAdams.com www.ProcessEngr.com

Coking 101

Embed Size (px)

Citation preview

Page 1: Coking 101

Coking 101Coking 101An Introduction to Delayed Coking

Prepared By:

Jack Adams,Adams Project Managers, Inc.Email: [email protected]

JLAdams com

&

Email: [email protected] @ gwww.ProcessEngr.com

Page 2: Coking 101

Delayed Coker Process & Systems OverviewDelayed Coker Process & Systems Overviewy yy y

This presentation provides an overview of the delayed coking system found in modern refineriesrefineries.

I. Process Schematics (various sources)II. Delayed Coker Feed Material

III. The Coker Fractionator unitIV. The Coker Furnace

V. The Coke Drumse Co e u sVI. Coke Drum Opening

VII. Coke Drum Cutting, Coke HandlingVIII Coke Drum Cycle Time comparisonVIII. Coke Drum Cycle Time comparison

Adams Project Managers, Inc.2

Page 3: Coking 101

I. I. Delayed Coker Process SchematicsDelayed Coker Process Schematicsyy

Adams Project Managers, Inc.3

Page 4: Coking 101

ehi

llips

Bro

chur

enc

e: C

onoc

oPh

Ref

eren

4

Page 5: Coking 101

bsite

nce:

CB

&I w

ebR

efer

en

5

Page 6: Coking 101

ehe

eler

Bro

chur

enc

e: F

oste

r Wh

Ref

eren

6

Page 7: Coking 101

7

Page 8: Coking 101

II. Delayed Coker Feed MaterialII. Delayed Coker Feed Materialyy

Delayed Coker (Coker)Delayed Coker (Coker) feedstock is material from the refinery vacuum unit, which is otherwise used as road asphalt. The objective of the Coker is to process the asphalt-like material to produce higher value productsproduce higher value products, such as gasoline, diesel fuel, LPG, and petroleum coke.

Adams Project Managers, Inc.8

Page 9: Coking 101

III. Delayed Coker III. Delayed Coker FractionatorFractionatoryy

The Coker Fractionator receives and separates the f d t k d ‘ k d’feedstock and sour ‘cracked’ gas and liquids from the operating Coke Drum and Coker Furnace.

•Fuels Gas and LPG are recovered for fuel or other productsproducts.

•Naptha is recovered and sent to the other refinery units for gasoline production.

•Light Coker Gas Oil (LCGO) and Heavy Coker Gas Oiland Heavy Coker Gas Oil (HCGO) are sidedraws from the Fractionator and are sent to hydrotreating for processing into diesel and other products.

The Coker Gas Plant further separates the productsseparates the products.

Adams Project Managers, Inc.9

Page 10: Coking 101

IV. Delayed Coker FurnaceIV. Delayed Coker Furnaceyy

The Coker Furnace heats the heavy liquid material from the bottom of the Fractionator to about 900 to 945o F. (482 to 507o C). This heating causes the heavy liquid material to “crack” or change into a combination of smaller molecule gas and liquid products. Steam is injected to minimize the cracking until it is in the Coke Drum.

Adams Project Managers, Inc.10

Page 11: Coking 101

V. Delayed Coker Coke DrumsV. Delayed Coker Coke Drumsyy

The Coker typically has 2 or more Coke Drums which operate in pairs in a semi-batch mode:batch mode:

•In the Operating Coke Drum, the material from the Coker Furnace, at high temperature and low pressure, is injected into the bottom of the drum and is further ‘cracked’ into (1)and is further cracked into (1) gaseous products which are returned to the Fractionator for product recovery and (2) into the petroleum coke that solidifies in the drum.

•The other offline drum isThe other offline drum is steamed, vented, and cooled prior to the drum being opened to atmosphere. After the drum is opened, the petroleum coke is cut from the drum using high pressure water. Petroleum coke or simply “coke” is similarcoke or simply coke is similar to coal and is typically used for fuel in power plants.

Adams Project Managers, Inc.11

Page 12: Coking 101

VI. Coke Drum DeheadingVI. Coke Drum Deheadinggg

The modern Coker has automatic deheading valves

th t d b tt kon the top and bottom coke drum flanges to allow the coke drums to be opened safely for “cutting” the coke from the drum. Historically, the flanges were opened manually.

Engineering is required toEngineering is required to replace manual flanges with automatic deheading valves, due to the changes in orientation of the inlet nozzles and due to the size and weight of the deheading valves.

Several images are shown in the following slides showing the automated slide valves. Schematics also following showing key valves in the system and safety interlocks which are common and allowwhich are common and allow the opening of one Coke Drum while having the other one in operation at the same time.

Adams Project Managers, Inc.12

Page 13: Coking 101

Before DeltaGuard

Safe Unheading• Totally enclosed system from the topof the coke-drum to the drain pit railof the coke-drum to the drain pit, railcar or sluice way• Eliminate exposure risk topersonnel, equipment, andthe unheading deck• Remotely operated fromcontrol room• All safety interlocks incorporated

13

Reference: “Automation and Improved Safety of the Delayed Coking Process using Modern Delayed Coking De-Heading Technology”By: Ruben Lah, VP / CTOCurtiss-Wright Oil and Gas Systems Division

All safety interlocks incorporated• Isolation of a tarry drum• Isolation or control of a drum dump

Page 14: Coking 101

14

Page 15: Coking 101

15

Page 16: Coking 101

Pi t / N l Pi t / N l D lt G dD lt G dPicture / Nozzle Picture / Nozzle DeltaGuardDeltaGuard

Adams Project Managers, Inc.16

Page 17: Coking 101

17

Page 18: Coking 101

I D l d C kiI D l d C kiI. Delayed CokingI. Delayed Coking

Adams Project Managers, Inc.18

Page 19: Coking 101

I t l kI t l kInterlocksInterlocks

Reference: “Shot Coke: Design & Operations”By John D. Elliott, Foster Wheeler USA Corporation

Adams Project Managers, Inc.19

Page 20: Coking 101

VII. Coke Drum Cutting, Coke HandlingVII. Coke Drum Cutting, Coke Handlingg, gg, g

As the coke is ‘cut’ by the high pressure water nozzle, the coke and water flow onto a Coke Pad or into the Coke Pit, where the water is separated and recycled back to the cutting water system.

C k i d f h i bCoke is moved from the pit by either a bridge crane or a front end loader for shipment .

Additional schematics and images follow show various components of the system.

Adams Project Managers, Inc.20

Page 21: Coking 101

VII. Coke Drum CuttingVII. Coke Drum Cuttinggg

Drill assembly

Drill Assembly

Cutting BitDrill Stem Guide

Top Slide Valve

Bottom Slide Valve

The Jet Water Pump produces high pressure water to cut the coke

Cutting Deck

Bottom Slide Valve

from the drums.

Switch Valve

Adams Project Managers, Inc.21

Page 22: Coking 101

22

Page 23: Coking 101

FLOWSERVE FLOWSERVE A t ShiftA t Shift C tti T lC tti T lFLOWSERVE FLOWSERVE AutoShiftAutoShift Cutting ToolCutting Tool

Adams Project Managers, Inc.23

Page 24: Coking 101

C k H dli CC k H dli CCoke Handling CraneCoke Handling Crane

Adams Project Managers, Inc.24

Page 25: Coking 101

VIII. Coke Drum Cycle Time ComparisonVIII. Coke Drum Cycle Time Comparisony py p

Reference: “DELAYED COKER REVAMPS: REALIZATION OF OBJECTIVES “AM-04-69 -- By John D. Elliott, Foster Wheeler USA Corporation

Adams Project Managers, Inc.25

Page 26: Coking 101

Additional Reading on Delayed CokingAdditional Reading on Delayed Cokingg y gg y g

We hope this very basic presentation has been informative. Additionalsuggested reading materials are listed below and provide more detail on the subject of delayed coking. We hope you will contact theAPMI/PROCESS Team when a coker revamp study is needed.y

Tutorial: Delayed Coking Fundamentals, http://www.coking.com/DECOKTUT.pdf, by Paul J. Ellis and Christopher A. Paul

of the Great Lakes Carbon Corporation. Presented at the 1998 AIChE Spring National Meeting in New Orleans, LA.

Delayed Coking, http://processengr.com/pdf_documents/co_school_mines_coker_chp5.pdf, by Colorado School of Mines.

Petroleum Coke Petrography, http://mccoy.lib.siu.edu/projects/crelling2/atlas/PetroleumCoke/pettut.html, web page by

Prof. John C. Crelling, Coal Research Center and Department of Geology, Southern Illinois University Carbondale.

Adams Project Managers, Inc.26