44
Code Analysis Presentation September 2014

Code Analysis Presentation - TTU College of … Analysis Presentation ... •Requirements for glazing ... Grading Criteria/Rubric Grade will be determined by 4 categories 1

Embed Size (px)

Citation preview

Code Analysis Presentation

September 2014

TTU College of Arch graduate

Architect with 30 + years experience

Expertise in:

o Higher Education

o Municipal

o Medical

Taught this studio last fall

Earliest bldg/Life Safety code dates from 1772 BC

Modern era bldg codes

o Rebuilding London Act 1666 after 1666 Great Fire

o Ist systematic code- London 1844

o Baltimore passed it’s 1st bldg code in 1859

*Source: Wikipedia

National Bldg/Life Safety Codes

o Eliminated most cities having their own codes

Most common building code:

o International Building Code

Multiple codes often required for a building:

o IBC- building code

o NFPA- Fire/Life Safety code

o Local amendments to the above

o Local Zoning- building setbacks, height restrictions

o Project Specific codes

• TDH&HS- Hospitals, Outpatient Surgery Centers,

Nursing Facilities

o Accessibility requirements- TAS/TDLR, ADA not code

The most restrictive of each generally required

International Codes Council - Family of codes:

o International Building Code

o International Residential Code

o International Fire Code (competes with NFPA 101)

o International Plumbing Code

o International Mechanical Code

o International Energy Code

o International Green Building Code

We will use IBC – 2009 edition

o Currently adopted by City of Lubbock

o San Antonio uses 2012 edition

Most IBC versions available at:

www.archive.org

IBC 2009 Available at:

https://law.resource.org/pub/us/code/ibr/icc.ibc.2009.pdf

Non Plan Code impacts (examples):

o Selection of building materials

o Shear wall connections and locations

o Minimum air exchanges in a mechanical system

o Maximum sizes of windows in a rated wall

o Rating of walls between 2 different kinds of occupancies

o Heights of railings

o And on and on……..

Our efforts will focus on life safety elements that

most impact:

o Site plan- building set backs, etc.

o Floor plan arrangement

o Possible limitations of doors/windows on exterior walls

Out of 35 chapters; we will investigate portions of 5

Occupancy Classification

Allowable Height and Area allowed

Area Increase due to:

o Frontage of land

o Sprinklers

Type of Construction Planned

Room Occupancies

Room Exiting Requirements

Occupant Load for each floor and the buildings

Number of Exits per floor

Travel Distance allowed

Determine minimum width of:

o Corridor

o Stairs

Dead-end corridors

Number of plumbing fixtures

Energy Requirements

Accessibility

Building Occupancy Classification - 302 (p. 23)

o Determine which Classification

• A, I

• B, M

• E, R

• F&I, S

• H, U

• Others: such as Malls, Atriums and High-rises

A building may have multiple occupancies

Most classifications have subsets, example:

Assembly - 303 (p. 23)

o A-1: uses with fixed seating

o A-2: uses with food/drink

o A-3: uses not classified elsewhere

o A-4: uses for indoor sporting events

o A-5: uses for outdoor events

Allowable Increases to SF & # of Floors:

o Frontage- 506.2 (p. 82)

• Based on setback of building from public way

• Percentage of building faces accessible to public way

• Maximum allowable SF increase of 75% if:

• If building faces public way all 4 sides

OR

• Building sets back at least 20 feet all sides

o Sprinklers –

• 504.2: 1 story increase (p. 81)

• 506.3: 200% SF increase (p. 82)

Determine your allowable percentage increase

SF & # of Floors allowed by Occupancy-

• Table 503

Types of Construction – Table 601 (p. 89)

o Type I – IV

• I : non-combustible (steel)

• II: Non-Combustible exterior(steel),

• III: Wood framing

• IV: Heavy Timber

• A : Fire Resistive

• B : Not Fire Resistive, but lower SF

Evaluate Building Types based on

o SF in Table 503 (p. 80)

o SF increase allowed based on setbacks and sprinkler

use

o Type of Construction allowed per type

o Decide which Construction Type appropriate for project

maximum SF allowed for Types IB, IIA & IIB?

Rule of Thumb:

o Select Type of Construction with lowest fire resistive

requirements

o As desired by client- TTU as an example

Determine Occupant Load @ room –

o Table 1004.1.1 (p.220)

o Based on types of occupancy

• Offices

• Lobby

• Meeting room

• Storage

o If fixed seating, # of fixed seats is occ. load 1004.7

o Notice some factors are net and some are gross

• When net-

• Use the interior face of the room walls to calculate SF

• What spaces have no occupant load:

• Restrooms, mechanical, electrical, stairs,

elevators

o Outdoor courtyards have occupant load - 1004.8 (p. 220)

Determine Occupant load for @ floor and & building

Calculating width of corridors - 1005.1 (p. 221)

o min width - 1018.2 (p. 242)

Doors:

o Encroachment into corridor width – 1005.2 (p. 221)

o Door size 1008.1.1 (p. 224)

o Direction of Exit Door swing – 1008.1.2 (p. 225)

o When is panic hardware required? 1008.1.10 (p. 229)

Egress through adjoining rooms limited – 1014.2 (p. 237)

When 2 Exits are required –

o Table 1015.1 and 1015.1.1 (p. 239)

Arrangement/Location of Exits –

o 1015.2.1 & 1015.2.1.2 (p. 239)

Determine min. number of Exits per floor -

o Table 1021.1 (p. 243)

Stairways

o Width based on occupancy - 1005.1 (p. 221)

• Minimum 1009.1 (p. 230)

o Maximum tread and riser dimensions 1009.4.2 (p. 230)

• Impacts stair tower size (10’x20’ early rule of thumb)

o Stairway to roof req’d when there are 4 of more stories-

1007.13 (p. 1009.13)

o Stair doors always swing in the direction of egress

o Max. length of stair run w/o landing – 1009.7 (p. 232)

o When do stairs have to be enclosed? 1022.1 (p. 244)

Determine maximum Travel Distance allowed for

Occupancy Type - Table 1016.1 (p. 240)

Dead-End Corridors - 1018.4 and 1018.4.2 (p. 242)

o Maximum length allowed for dead-End corridors

• Varies by occupancy type

• Sometimes by use of sprinkler

o Determine maximum Dead End corridor length:

• Business occupancy with a sprinkler

Assembly is only Occupancy with “specific

requirements in chapter 10

o Due to higher occupancies and concentrated spaces

o Many occupants unfamiliar with the building as visitors

Specific requirements:

o Assembly Occupancy - 1028

o Main Exits when Occupant Load exceeds 300- 1028.2

Number of plumbing fixtures – Table 2901 (p. 550)

o Based on each occupancy type in building

• Generally split 50/50 towards Men and Women

o This is total count for building

• Can be distributed throughout the building

o This is minimum number- can have more

• Client may request additional fixtures

Texas requires compliance with state energy code

o Most requirements do not impact plan layout :

• Requirements for glazing

• Efficiency of mechanical units

• Insulation requirements in walls and roof

o Floor plan impacted by one requirement:

• Vestibules required when entry opens to large area:

• Maximum of 3,000 SF

Texas Accessibility Standards/ADA

Clearances at doors on floor plans

o General rules of thumb at doors: • 18” clear on pull side

• 12” clear on push side

o Door clearance requirement impacts corridor widths

• 5’ corridor width good rule of thumb

Elevator required if there are multiple floors

Restroom accessibility

o Clearances at fixtures

o Maneuvering room – 5’ turning radius

Develop Code Analysis specific to you project

o For each code component, Cite pertinent code section

o When relevant use 1/16” plans (no smaller) of all floors to

illustrate code issue such as travel distances, etc

o For each element indicate compliance with code component

o Analysis should include the following components:

• Identify Building Occupancy Classification that your building falls

under- state what kinds of occupancy is expected in your

building

• Construction Type proposed to be used

• Note type of materials allowable with proposed type of

construction

• indicate allowable number of stories and SF per floor

• note increases allowed (frontage and sprinkler) & resulting GSF allowed on the ground floor

• note your design’s GSF, by floor and total building

Analysis should include the following components (cont’d):

o Determine Occupant Load for each room

• note rooms requiring multiple exits

o Note occupant load per floor and for total building

o Determine minimum # of plumbing fixtures required

o Corridors:

• Determine minimum width of major corridors

• Note maximum travel distance vs distance per floor of your plan

• When corridors could appear to be dead-end note their length

Analysis should include the following components (cont’d):

o Exits- Determine minimum number of exits required per floor

o Stairs:

• Determine number and minimum width for total stairs

• Note if stairs are required to be enclosed or can be open

o Note SF of open areas served by entry-

• is vestibule required?

o Accessibility-illustrate clearances at all doors and in restrooms

Grading Rubric – 5 levels:

o 5 – Superior: Exceeds the requirements in all areas. The highest level of scholarly, discrimination, discernment and innovation in their work.

o 4 - Exceeds the requirements in most areas. Consistently scholarly, discrimination, discernment and innovation.

o 3 - Above Average: Exceeds requirements in a few areas. Often shows scholarly, discrimination, discernment and innovative effort.

o 2 - Average: Work requires minimal corrections. Inconsistently shows scholarly, discrimination, discernment and innovative efforts.

o 1 - Unsatisfactory: Does not meet the requirements of the instructor. Rarely shows scholarly, discrimination, discernment and innovative efforts.

o 0 - Unacceptable: work that is unacceptable, not defined.

Grading Criteria/Rubric

Grade will be determined by 4 categories

1. Competency- is the analysis correct and accurate

2. Process- Each code component presented in a way that clearly illustrates the how the information is derived and citing where it is coming from. Tables/text/graphics show formulas/ratios and calculations specific to your project.

3. Communication/Composition- Organization of the analysis clearly illustrates in a logical and hierarchical manner the code components. Good graphic quality.

4. Completeness- Each code component is completed to the level of detailed needed to convey the information.

Point to Grade Conversion

o 20 - 100 11 - 76

o 19 - 96 10 - 74

o 18 - 94 9 - 72

o 17 - 90 8 - 68

o 16 - 88 7 - 64

o 15 - 86 6 - 62

o 14 - 84 5-1 - 50-10

o 13 - 82

o 12 - 78

This presentation is available at

http://arch.ttu.edu/wiki/Mary_K._Crites