1 — Coastal GasLink Monthly Construction Update Construction Update June 16, 2020 Numbers as available at the end of May 2020 16 16 37 97 16 97 37 39 27 29 ALBERTA BRITISH COLUMBIA ALASKA 1 2 3 4 5 6 7 8 Fort St. James Taylor Fort St. John Dawson Creek Tumbler Ridge Prince George Vanderhoof Fraser Lake Burns Lake Terrace Kitimat Prince Rupert Chetwynd Mackenzie Smithers Telkwa Houston Hudson’s Hope Coastal GasLink Metering Facility Coastal GasLink Compression & Metering Facility Coastal GasLink Compression Facilities (TBD) Under Construction Potential Future Facilities LNG Canada Facility (3rd party) Construction highlights With summer construction poised to begin, June has already seen a significant milestone on the Coastal GasLink route with the first pipe weld in the Kitimat area at the beginning of the month. This is the first of many thousands of pipe welds as mainline pipeline installation comes into focus for many sections along the route. In early June, Aecon was named prime contractor for the Wilde Lake Compressor and Meter Station, and the Kitimat Meter Station. Compressor and meter facilities are important pieces of infrastructure that ensure natural gas is delivered safely and efficiently to LNG Canada’s liquefaction facility in Kitimat. Health and safety continue to be our primary focus. We are following Dr. Bonnie Henry’s guidance and work with Northern Health as we progress construction activities through a measured and gradual ramp up of work over the coming weeks and months. Health and safety plans are in place across the project route, in accordance with guidelines issued by the BC Centre for Disease Control. This includes having access to dedicated, 24/7 on-site medical services within lodges and worksites, reduced occupancy at all workforce sites, enhanced mandatory pre-screening, daily temperature checks, and symptomatic testing in consultation with Northern Health. You can learn more about the measures we’re taking by visiting CoastalGasLink.com/Safety. Working together, we are confident that we can continue our important work across the project, while helping to protect the health and safety of our workforce, their families, and local communities. 77% of route cleared *as estimated from field data at end of May 358 workers at accommodation sites as of May 31 Performance at a glance:

Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

1 — Coastal GasLink Monthly Construction Update

Construction UpdateJune 16, 2020 Numbers as available at the end of May 2020

16

16

37

97

16

97

37

39

27

29

ALBERTA

BRITISH CO

LUM

BIA

ALASK

A

1

2

3

4567

8

Fort St. James

Taylor

Fort St. John

Dawson Creek

Tumbler Ridge

Prince GeorgeVanderhoofFraser Lake

Burns Lake

Terrace

Kitimat

Prince Rupert

Chetwynd

Mackenzie

SmithersTelkwa

Houston

Hudson’s HopeCoastal GasLink Metering Facility

Coastal GasLink Compression & Metering Facility

Coastal GasLink Compression Facilities (TBD)

Under Construction

Potential Future Facilities

LNG Canada Facility (3rd party)

Construction highlights With summer construction poised to begin, June has already seen a significant milestone on the Coastal GasLink route with the first pipe weld in the Kitimat area at the beginning of the month. This is the first of many thousands of pipe welds as mainline pipeline installation comes into focus for many sections along the route.

In early June, Aecon was named prime contractor for the Wilde Lake Compressor and Meter Station, and the Kitimat Meter Station. Compressor and meter facilities are important pieces of infrastructure that ensure natural gas is delivered safely and efficiently to LNG Canada’s liquefaction facility in Kitimat.

Health and safety continue to be our primary focus. We are following Dr. Bonnie Henry’s guidance and work with Northern Health as we progress construction activities through a measured and gradual ramp up of work over the coming weeks and months. Health and safety plans are in place across the project route, in accordance with guidelines issued by the BC Centre for Disease Control.

This includes having access to dedicated, 24/7 on-site medical services within lodges and worksites, reduced occupancy at all workforce sites, enhanced mandatory pre-screening, daily temperature checks, and symptomatic testing in consultation with Northern Health. You can learn more about the measures we’re taking by visiting CoastalGasLink.com/Safety. Working together, we are confident that we can continue our important work across the project, while helping to protect the health and safety of our workforce, their families, and local communities.

77% of route cleared *as estimated from field data at end of May

358 workers at accommodation sites as of May 31

Performance at a glance:

Page 2: Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

2 — Coastal GasLink Monthly Construction Update

Base map source © Mapbox, © OpenStreetMap

Chetwynd Lodge

Sanaata Lodge

MOBERLY LAKE

Highway 52

Chetwynd

Groundbirch

Highway 29

Highway 97Su

kunk

a Rive

r For

est

Servi

ce Ro

ad

46

0

92

SectionLocation: West of Dawson Creek to south of ChetwyndLength: 92 kilometresPrime Contractor: Surerus Murphy Joint Venture Workforce Accommodations: Two Workforce Accommodations – Chetwynd Lodge and Sanaata Lodge

Project Right-of-Way (Section 1)Workforce Accommodation SiteStorage Area (Where construction equipment and materials are stored) Kilometre Post Markings (KP)

1

Section 1: Monthly Construction Update1

Construction progress:• Completed pipe hauling and

stockpiling pipe at section storage areas for this season; pipe hauling to resume in October 2020

• Aecon announced as prime contractor for Wilde Lake Compressor and Meter Station

Upcoming activities*:• Finalizing construction readiness

for summer mainline pipe installation

• Ongoing environment and erosion control monitoring and management

• Re-starting critical road upgrades, clearing works and grading in the Groundbirch area

• Resuming blasting as required from mid-June to end of August

• Drone surveys for environment and construction activities continue until end of the year

• Mainline pipeline construction in the Groundbirch area scheduled to commence mid-August

*All schedules are subject to change

86% of route cleared

Chetwynd Lodge; Saanata Lodge under development

Performance at a glance:

Did you know? Sanaata Lodge will house workers constructing the Wilde Lake Compressor and Meter Station in the Groundbirch area. Visit Map.CoastalGasLink.com to view our interactive map and learn about each workforce accommodation site, including location and recent occupancy.

Page 3: Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

3 — Coastal GasLink Monthly Construction Update

Section 2: Monthly Construction Update2

76% of route cleared

Performance at a glance:

Base map source © Mapbox, © OpenStreetMap

SUKUNKA RIVER

BURNT RIVER

Highwa y 29

Sukunka River Forest Service Road

140

116

92

SectionLocation: South of Chetwynd to east of McLeod Lake Length: 48 kilometresPrime Contractor: Surerus Murphy Joint Venture Workforce Accommodations: Two Workforce Accommodations – Mt. Merrick Lodge and Sukunka Lodge

Project Right-of-Way (Section 2)Workforce Accommodation SiteStorage Area (Where construction equipment and materials are stored)Kilometre Post Markings (KP)

2

Mt. Merrick Lodge

Sukunka Lodge

Construction progress:• Road and bridge upgrades ongoing by road owners

Upcoming activities*:• Preparing construction readiness for summer mainline

pipe installation• Ongoing environment and erosion control monitoring

and management• Anticipating re-start of critical road upgrades, clearing

works and timber hauling in late June 2020, pending ground conditions

• Drone surveys for environment and construction activities continue until end of the year

*All schedules are subject to change

0workers at Sukunka Lodge

Page 4: Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

4 — Coastal GasLink Monthly Construction Update

Section 3: Monthly Construction Update3

77% of route cleared

Performance at a glance:

Base map source © Mapbox, © OpenStreetMap

Highway 97

McLeod Lake

Bear Lake

PARSNIP RIVER

ANZAC RIVER

Parsnip Lodge

244

192

140

SectionLocation: East of McLeod Lake to north of Prince GeorgeLength: 104 kilometresPrime Contractor: SA Energy Group Workforce Accommodations: One Workforce Accommodation – Parsnip Lodge

Project Right-of-Way (Section 3)Workforce Accommodation SiteStorage Area (Where construction equipment and materials are stored)Kilometre Post Markings (KP)

3

Construction progress:• Hand falling of trees along the

route as required

Upcoming activities*:• Ongoing environment and

erosion control management • Preparing construction readiness

for summer mainline pipe installation

• Drone surveys for environment and construction activities continue until end of the year

• Pipe deliveries continue to storage areas until April 2021

*All schedules are subject to change

0 workers at Parsnip Lodge

Did you know? Hand falling — or cutting — trees requires careful planning and highly skilled professionals. It’s a time-intensive clearing technique for larger trees but is used as an important method to ensure safety.

Page 5: Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

5 — Coastal GasLink Monthly Construction Update

Base map source © Mapbox, © OpenStreetMap

Highway 27

Highway 16

Bear Lake

NukkoLake

Vanderhoof

Fort St. James

9A Stockpile Site

337

244

290.5

SectionLocation: North of Prince George to northwest of VanderhoofLength: 93 kilometresPrime Contractor: SA Energy Group Workforce Accommodations: One Workforce Accommodation – Vanderhoof Lodge

Project Right-of-Way (Section 4)Workforce Accommodation SiteStorage Area (Where construction equipment and materials are stored)Kilometre Post Markings (KP)

4

Highw

ay 97

Vanderhoof Lodge

Section 4: Monthly Construction Update4

98% of route cleared

Performance at a glance:

Construction progress:• Vanderhoof Lodge construction ongoing• Stuart River bridge deck landed safely on the piers on

the opposite side• Restoration and clean-up of 9A storage site

Upcoming activities*:• Continue construction of Vanderhoof Lodge, with first

occupancy expected in mid-June• Stuart River bridge construction activities; anticipated

bridge opening in late June• Begin access road construction in mid-June• Complete construction readiness reviews for summer

mainline pipe installation• Drone surveys for environment and construction

activities continue until end of the year

*All schedules are subject to change

Vanderhoof Lodge under development

Page 6: Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

6 — Coastal GasLink Monthly Construction Update

Section 5: Monthly Construction Update5

100% of route cleared

48 workers at Little Rock Lake Lodge

Performance at a glance:

Base map source © Mapbox, © OpenStreetMap

Highway 16

Fort FraserFraser Lake

EndakoFRASER LAKE

Highway 27

420

337378.5

SectionLocation: North of Vanderhoof to south of Burns LakeLength: 82 kilometresPrime Contractor: Macro Spiecapag Joint Venture (MSJV) Workforce Accommodations: One Workforce Accommodation – Little Rock Lake Lodge

Project Right-of-Way (Section 5)Workforce Accommodation SiteStorage Area (Where construction equipment and materials are stored)Kilometre Post Markings (KP)

5

FRANÇOIS LAKE

Little Rock Lake Lodge

Construction progress:• Ongoing erosion and sediment control monitoring • Ongoing site and access preparation at section

storage areas

Upcoming activities*:• Preparing construction readiness for summer mainline

pipe installation• Ongoing erosion and sediment control• Drone surveys for environment and construction

activities continue until end of the year

*All schedules are subject to change

Page 7: Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

7 — Coastal GasLink Monthly Construction Update

Section 6: Monthly Construction Update6

97% of route cleared

113 workers at 7 Mile Road Lodge

Performance at a glance:

Base map source © Mapbox, © OpenStreetMap

Highway 16

Burns Lake

François Lake

Southbank

Houston

Highway 35

TCHESINKUT LAKE

FRANÇOIS LAKE

7 Mile Road Lodge

505

420

462.5

SectionLocation: South of Burns Lake to south of Houston Length: 85 kilometresPrime Contractor: Pacific Atlantic Pipeline Construction Inc. (PAPC) Workforce Accommodations: One Workforce Accommodation – 7 Mile Road Lodge

Project Right-of-Way (Section 6)Workforce Accommodation SiteStorage Area (Where construction equipment and materials are stored)Kilometre Post Markings (KP)

6

Construction progress:• Ongoing erosion and sediment control• Ongoing site preparation at 7 Mile Road Lodge site and

section storage areas

Upcoming activities*:• Begin right-of-way grubbing and construction access

construction and upgrades• Receive pipe at Section 6 storage areas• Begin construction at borrow sites, including blasting• Preparing construction readiness for summer mainline

pipe installation• Blasting activities continuing as required by right-of-

way conditions• Drone surveys for environment and construction

activities continue until end of the year

*All schedules are subject to change

Page 8: Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

8 — Coastal GasLink Monthly Construction Update

Section 7: Monthly Construction Update7

0% of route cleared

Performance at a glance:

Base map source © Mapbox, © OpenStreetMap

Highway 16

Houston

MORICE RIVER

MORICE LAKE

PARROTT LAKES

Huckleberry Lodge583 544 505

SectionLocation: South of Houston to north of Morice Lake Length: 78 kilometresPrime Contractor: Pacific Atlantic Pipeline Construction Inc. (PAPC) Workforce Accommodations: One Workforce Accommodation – Huckleberry Lodge

Project Right-of-Way (Section 7)Workforce Accommodation SiteStorage Area (Where construction equipment and materials are stored)Kilometre Post Markings (KP)

7

Construction progress:• Commenced civil works for Huckleberry Lodge and

associated access

Upcoming activities*:• Preparing construction readiness for summer clearing

and construction• Pipe to arrive at Section 7 storage sites until April 2021• Blasting activities continuing as required by ancillary

site conditions• Drone surveys for environment and construction

activities continue until end of the year• Development of first phase of the Huckleberry

Workforce Accommodation site and access

*All schedules are subject to change

Huckleberry Lodge site under development

Page 9: Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

9 — Coastal GasLink Monthly Construction Update

Construction progress:• Continued road and bridge works in the Kitimat Valley,

District of Kitimat and North Hirsch areas• Commenced civil works for 9A Lodge as part of

renovating this facility• Hunter Creek workforce accommodation operational

Upcoming activities*:• Ongoing site preparation at Kitimat River for under

river pipe installation• Continue clearing on priority work fronts • Blasting activities continuing as required by right-

of-way conditions• General maintenance on North Kitimat, North

Hirsch, South Hirsch and Shea roads• Continue work at Hunter Creek and 9A Lodges• Preparing construction readiness for summer

mainline pipe installation• Pipe deliveries continue in the Kitimat area until

April 2021• Drone surveys for environment and construction

activities continue until end of the year

*All schedules are subject to change

Base map source © Mapbox, © OpenStreetMap

Kitimat

Kitamaat Village MORICE LAKE

Highway 37

667

625

583

SectionLocation: North of Morice Lake to KitimatLength: 84 kilometresPrime Contractor: Macro Spiecapag Joint Venture (MSJV) Workforce Accommodations: Seven Workforce Accommodations – Sitka Lodge, Hunter Creek Lodge, Icy 1 Lodge, Icy 2 Lodge, P2 Lodge, 9A Lodge, P4 Lodge

Project Right-of-Way (Section 8)Workforce Accommodation SiteStorage Area (Where construction equipment and materials are stored) Kilometre Post Markings (KP)

8

Icy 1 Lodge

P4 Lodge

Hunter Creek Lodge

Sitka Lodge

Icy 2 Lodge

P2 Lodge

9A Lodge

Section 8: Monthly Construction Update8

78% of route cleared

Performance at a glance:

197workers at Sitka Lodge and Hunter Creek Lodge

Page 10: Coastal Gaslink Monthly Construction Update · 6/16/2020  · to resume in October 2020 • Aecon announced as prime contractor for Wilde Lake ... 0 workers at Sukunka Lodge. 4 —

Keep in touch and learn moreWe want to make sure you have access to the information you need about the project. Here are the many ways you can reach out, and learn more:

Visit our community office:Prince George 760 Kinsmen Place

Email us: [email protected]

Sign up to receive our Connector Newsletter: CoastalGasLink.com/contact

Follow us on Facebook: @CoastalGasLink

Follow us on Twitter: @CoastalGasLink

Visit our website: CoastalGasLink.com

Photo of the monthAerial view of Section 7 pipe yard

Pipes are stored and organized in preparation for installation at a pipe yard near Houston.

About Coastal GasLink’s Construction UpdatesOur construction updates include information on recent progress, activities that we expect over the next month and detailed section maps, that help communicate where project infrastructure is located and where activities are happening.

Check us out!Find information, such as Construction Updates and an interactive map, on CoastalGasLink.com.