Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
1
Plum IslandShoreline Protection & Management
A Review of Current Design & Construction InitiativesBy David Vine, Vine Associates, Newburyport, MA
David Lager, NETCO, Lexington, MA
PRESENTATION TOPICS• Introduction• Coastal Conditions• Shoreline Changes• Community Response• Design Issues• Construction Progress• Plum Island Coir Envelopes, Anchors
• Other Recent CoirApplications
3
INTRODUCTIONCase Study• Short Term Dune
Stabilization• Community Alliance to Deal
With Beach Management• Still Going On
4
COASTAL GEOLOGICAL FACTORS
• Jetty Construction
• Active Ebb Tidal Delta (Sandbar)
• “Reversal”Northern Littoral Drift
• Stone Groin Impact
5
COASTAL PROCESSES
• Groin Limiting Northern Sand Flow
• Degraded Jetty• Refraction• Funneling into Area
Causing “Hot Spots” per Particular Storm
6
COASTAL PROCESSES
7
SHORELINE CHANGES• Long-Term Shoreline
Changes Since 1928• About 3 – 4 feet per
Year 1928-1994
8
SHORELINE CHANGES• Shorter Term 2000-2007• 13.3 Feet per Year• Most Significant at Town Center • Circa 1995• Order of 100 Foot Shoreline
Erosion• Groin Fully Covered
9
FORMATON OF MERRIMACK RIVER BEACH ALLIANCE
• Newbury• Newburyport• Salisbury• State Senators/Representatives• Seaport Bond Council• Department of Conservation &
Recreation• State Regulatory Agencies
DEPCZM
• Federal Regulatory Agencies• Local Citizens Groups• Newspapers• Local Residents• Privately Retained Lobbyist• Monthly Meetings – Totally Open Process
10
DESIGN CONSIDERATIONS• Protect Public
Infrastructure• Sand Nourishment• Less than 3 Ton Sand
Bags• Geotube (High Strength
Plastics)• Bio-Degradable Fabrics• Stone/Timber/Steel• Plantings (Limited)REGULATORY REQUIREMENTS• Off Site Sand Source• Must be Bio-Degradable
11
LIMITED SOLUTIONS/FUNDS• Design had to be of large Bio-Degradable Sand Bags or
Envelopes• Considered Placement of Fabric Covered in Sand and
Covering it with Fabric• Considered Pre-Fabricated Coir Forms Placing sand and
then stitching together (Netco Product)
12
PLUM ISLAND DESIGN• Investigating Past Coir Projects
How Past Designs Evolved• Consider more like Design of
Revetment• 5 Terrace System• Buried First Terrace 4’ Below Grade• Second Terrace 6’ Wide Section 90°
to Dune• Upper 3 Terraces Paralleled to Dune• Helical Anchors• To be Covered with Sand and
Planted
13
OCTOBER/NOVEMBER 2008• Design Set• Permit Approvals Received• Bid Project• Award/Fund Project• Start Construction• November 26, 2008 Storm
14
NOVEMBER 28 THRU END OF DECEMBER
• Construction Continues (Accelerated)
15
CONSTRUCTION COMPLETED• Mid January Construction Completed
(Though tested along the way)
16
MARCH/APRIL 2009SAND NOURISHMENT
17
DIFFICULT SPRING/SUMMER• Wave Activity• Several Eastern
Storms• Some Damage
Encountered
18
THE PRESENT• Presently USACE Sand Nourishment
to start January 2010• Modest Repairs Scheduled for 6’ Bags• Hope for Mild Fall/Winter Awaiting
Nourishment
19
LIMITED REPAIR TO APPROXIMATELY TEN SIX FOOT BAGS
20
Coir “Soft Technology”
• Biodegradable Material
• Renewable Resource• Relatively High
Tensile Strength• Imported From Far
East• Custom Fabricated
For Each Project In Massachusetts
21
Building Block – Matsof Different Weights, Dimensions
22
Mats Fabricated In MA Into Different Sizes, Shapes
23
Plum Island Application
24
Key – Bottom “Foundation”Terrace
• Bottom Terrace Below Beach Face, Avoid Wave, Surf Undercutting
• 4’ Wide Terrace – Add. Mass, Weight
• 2 x Layers Coir Mat, 1 x Layer Jute Liner
• Helical Tie Down Anchors• Continuous Sand Filled
Envelope 500 Feet Long
25
Bottom Foundation Terrace
26
Plum Island Application – 2nd
Terrace
27
2nd Terrace Level
• 3’ x 3’ x 6’ Envelopes• Attached to Bottom
Terrace and to Adjacent Envelopes
• Imported Sand• Slowest Part of the
Project• 2 x Layers Coir Mat,
1 x Layer Jute Liner
28
3rd, 4th, 5th Terraces
29
3rd, 4th, 5th Terrace Levels• Coir Envelope Tubes• 3’ x 3’ x 500’• Imported Sand• Attached on All Sides
to Form Continuous Envelope
• Minimize Possible Beach Debris
30
Upper Level Terraces In Progress
31
Completed Project – January, 2009
32
Conclusions• Permit Allowed Excavation Below Beach Face
– Minimized Potential for Undercutting By Waves/Surf• Second Terrace Level Used 6’ Envelopes –
Robust/Durable Design, Repairs Easier• Terraced Stepped Back 3 Feet, Natural Slope
Face Maintained, Increase Stability • Helical Tie Down Anchors Installed @ 50’
Spacing, Decrease to 25’ Spacings• No Recent TV News Coverage of Plum Island
Homes Taken By Ocean• Allowed Time To Develop Longer Term Beach
Nourishment Program With U.S.A.C.E. and Local Communities
33
Eastham Toe Protection Design(Engineering/Permitting – LEC Environmental)
34
Eastham – Existing Conditions –December, 2006
35
Coir Envelope Construction
36
Coir Envelope Solution - 2006
37
Completed Toe Protection –Ready for Vegetation
38
Vegetated Bank – Sep., 2009