Work Instruction CNB2 - JPN - Display PO for Project
PurposeUse this procedure to display the purchase orders per project.TriggerPerform this transaction when you need to display the purchase orders based on its project or WBS element.Menu PathUse the following SAP Easy Access menu path(s) to begin this transaction:
Transaction code CNB2 via the Command or Keycode edit field.
Transaction Code
CNB2
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
1/12
7/28/2019 CO CNB2 JPN Display PO for Project
2/12
Work Instruction CNB2 - JPN - Display PO for Project
Screen Flow
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
2/12
7/28/2019 CO CNB2 JPN Display PO for Project
3/12
Work Instruction CNB2 - JPN - Display PO for Project
Procedure
1. In SAP, start the transaction using the menu path or transaction code.SAP Easy Access
2. As required, complete/review the following fields:
Example:Field
CNB2
R/O/C Description
RCommand
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
3/12
7/28/2019 CO CNB2 JPN Display PO for Project
4/12
Work Instruction CNB2 - JPN - Display PO for Project
3. Click the Enter button .
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
4/12
7/28/2019 CO CNB2 JPN Display PO for Project
5/12
Work Instruction CNB2 - JPN - Display PO for Project
Enter profile
4. Click the Database prof. edit field .5. Click the Database prof . possible entries button .Profile for logical database PSJ (1) 10 Entries found
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
5/12
7/28/2019 CO CNB2 JPN Display PO for Project
6/12
Work Instruction CNB2 - JPN - Display PO for Project
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
6/12
7/28/2019 CO CNB2 JPN Display PO for Project
7/12
Work Instruction CNB2 - JPN - Display PO for Project
6. Double-click the 000000000001 | Standard selection (structure) lineitem .
Enter profile
7. Click the Continue button .Purchasing Documents per Project
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
7/12
7/28/2019 CO CNB2 JPN Display PO for Project
8/12
Work Instruction CNB2 - JPN - Display PO for Project
8. As required, complete/review the following fields:
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
8/12
7/28/2019 CO CNB2 JPN Display PO for Project
9/12
Work Instruction CNB2 - JPN - Display PO for Project
Abusinessundertakinginvolvingapredeterminedgoal toachievewith
prescribed fundsandoperatingresources, to anagreedlevel of quality,and by aparticular
date.Field
Example:I-IC-08003
R/O/C Description
R
Project9. Click the Execute button .Purchasing Documents per Project
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
9/12
7/28/2019 CO CNB2 JPN Display PO for Project
10/12
Work Instruction CNB2 - JPN - Display PO for Project
10.
Click the Exit button .
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
10/12
7/28/2019 CO CNB2 JPN Display PO for Project
11/12
Work Instruction CNB2 - JPN - Display PO for Project
Result
You have successfully displayed PO per project.
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
11/12
7/28/2019 CO CNB2 JPN Display PO for Project
12/12
Work Instruction CNB2 - JPN - Display PO for Project
Scenario
Instructions In this simulation you are required to: Display PO for Project in SAP ECC 6.0.
Required Data This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise.I-IC-08003 Field
Project
Value
CNB2
Command
Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc
12/12