17
Cnoc Windfarms Ltd Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Embed Size (px)

Citation preview

Page 1: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Cnoc Windfarms LtdCnoc Windfarms Ltd

Presented by Thomas Cooke

Director

Page 2: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Company

• Locally owned and developed

• 4 partners

• 3 are landowners

• Self financed and developed

Page 3: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

LOCATION

Page 4: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

On Tipperary Kilkenny Border

Page 5: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Highest point on Slieveardagh Hills 340 metres elevation

Page 6: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Planning History

• Planning lodged in 2001 for 17 turbines 600 kw each 10.2 MW, full EIS etc by Fehily Timoney.

• Granted by South Tipperary County Council• Refused by ABP in 2002, main reason was

visibility on nearby Cistercian Abbey• (Inspectors report mentioned no need for

onshore wind farms as Ireland could meet its 500MW target from the Arklow Bank offshore wind farm!)

Page 7: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Planning Contd.

• Revised planning application in 2009 for 5 x 2.3MW turbines,4 have 65 metre hub height and 1, 55 metre hub all with 70m diameter blades total installed capacity 11.5MW

• EXTENSIVE consultations with state agencies etc. • Full EIS etc by Eamon O’Domhnaill Aeolas• New EIA guidelines arrived mid planning• Again granted by South Tipperary County Council and

appealed to ABP by third parties• ABP granted planning on a majority decision on March

2011, no onerous planning conditions

Page 8: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Grid Connection

• Applied for Grid in 2005

• Missed Gate 2

• In Gate 3

• H1 Thurles Node

• Got Grid offer March 2011 same week as ABP granted Planning!

• Accepted Grid offer in November 2011

Page 9: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Grid Connection Contd.

• Grid offer connection to Thurles OHL in association with two other wind farms in Blanchfield sub group c.35MW total

• Unfeasible to build OHL due principally to planning timescale, 63 landowners, 24 km, 3 Local Authorities

• Currently applying for modification to UHL with Blanchfield Group

Page 10: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Wind resource

• Two masts on site

• 30 metre radio mast operating for a few years

• 65m lattice mast erected by Lynx Metmasts in 2011

• Wind speed 8.5m/s +

Page 11: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

• Lynx Mast• 65 metre • Lattice • Guyed • Ammonit logger • Web access to

logger data• Theiss

anenometer

Page 12: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

• Head for heights

Page 13: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Projected costs

• C. €15 – €16m

Page 14: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Build date

• Start construction 2014

Page 15: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Current work

• Due diligence

• Land leases

• Engaging with banks

• Access issues

• Wind data analysis

Page 16: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

Consultants

• Aeolas - Planning • Connellan and associates – Planning• Poe Kiely Hogan Lanigan – Legal• O’Neill Foley – Company Accountants• Mullan Grid – Grid Connection• Irish Wind Farmers Cooperative – Financial• EMD - Wind analysis

Page 17: Cnoc Windfarms Ltd Presented by Thomas Cooke Director

The last word

Persistence !