    CONSTRUCTION MTP-006

    MANAGEMENT Rev.: 0

    GUIDELINE Rev. Date: 12-03-1999

    Page 1 of 8

    This document contains information which is confidential and proprietary to Sargent & Lundy (S&L). It shall not

    be reproduced in whole or in part or released to any third party without the prior written consent of S&L.

    Copyright Sargent & Lundy 1999 all rights reserved. Standards located on the Intranet at

    http://SLWEB.SARGENTLUNDY.COM are to be considered as the official version of the Standard.

    CMTP006.DOC

    MECHANICAL TEST PROCEDURE

    HANGERS AND SUPPORTS: SETTINGS AND INSPECTIONS

    APPROVED: Signature on File

    1. PURPOSE

    1.1. To provide uniform guidelines for the inspection of piping system hangers and supports, and

    ductwork system hangers, supports, and slide plates prior to initial system operation.

    1.2. To verify hanger, support, and slide plate COLD and HOT set positions, damage during

    construction, and that supports are correctly installed.

    2. TEST EQUIPMENT REQUIRED

    2.1. Ladders, scaffolding, and staging, as applicable, for access.

    2.2. Measuring devices, as applicable.

    3. NOTES AND PRECAUTIONS

    3.1. The client's Work Permit Program shall be followed during the performance of the work activities

    required by this procedure.

    3.2. The client's Safety and Tagging Program shall be followed during the performance of the work

    activities required by this procedure.

    3.3. Prior to inspection, review system Piping & Instrumentation Drawings, Piping Isometric

    Drawings, Large/Small Bore Pipe Spool Drawings, Hanger and Support Detail Drawings,

    Ductwork Hanger and Support Detail Drawings, and Vendor Component and Assembly Drawings

    for installation requirements.

    3.4. Metering & Test Equipment (M&TE), Certification Sheets shall be retained by the client. M&TE

    device identification, serial number, and calibration due date shall be reviewed prior to use and

    recorded on Form MTP-006-01, "Hanger and Support Checklist."

    4. PREREQUISITES

    4.1. For Initial Inspection At Construction Completion, (Section 6), the systems are not required to

    be filled and vented to an operational condition.

    4.2. For Final Inspection (COLD) - Prior to Initial System Operation, (Section 7), verify the system

    associated with each hanger, support, and slide plate to be inspected is in a cold state, filled

    and vented for liquid systems and drained for steam systems.

  • 7/27/2019 CMTP006

    2/8

    CONSTRUCTION MTP-006

    MANAGEMENT Rev.: 0

    GUIDELINE Rev. Date: 12-03-1999

    Page 2 of 8

    This document contains information which is confidential and proprietary to Sargent & Lundy (S&L). It shall not

    be reproduced in whole or in part or released to any third party without the prior written consent of S&L.

    Copyright Sargent & Lundy 1999 all rights reserved. Standards located on the Intranet at

    http://SLWEB.SARGENTLUNDY.COM are to be considered as the official version of the Standard.

    CMTP006.DOC

    4.3. For HOT Inspection System in Service at Operating Temperature (Section 8), verify the

    requirements of Section 6., "Initial Inspection At Construction Completion," and Section 7,

    "Final Inspection (COLD) - Prior to Initial System Operation," have been met and all documented

    unresolved, incomplete, and discrepant issues have been adequately addressed.

    4.4. For HOT Inspection System in Service at Operating Temperature (Section 8) verify system

    normal operating parameters have been established for a minimum of two (2) hours prior to the

    start of inspections.

    4.5. Review hanger, support, and slide plate equipment/component drawings, detail drawings,

    principal drawings, project specifications, and contract requirements as applicable, prior to

    conducting walk downs and inspections to identify applicable hanger, support, and slide plate

    location, design, clearance, and installation requirements.

    4.6. Verify system hydrostatic testing, as applicable, has been performed and hydrostatic test

    results are included in the Construction Turnover Package.

    4.7. Ensure adequate scaffolding, staging, ladders, and safety harnesses are available for use duringthe required inspections of this procedure.

    4.8. Review the Construction Turnover Documentation Package to ensure construction testing is

    complete and appropriate test data has been reviewed for accuracy and completeness.

    5. GENERAL INSPECTION METHOD

    5.1. Perform a general visual status inspection to verify the state of the system to be inspected or

    walked-down, (empty, filled and vented, system in service with flow, etc.), and that it is safe and

    meaningful to conduct the inspection.

    5.2. Verify areas requiring access for inspection have been prepared and proper staging is in place.

    5.3. Upon completion of the work activities detailed by this procedure, assemble all inspection

    documentation and review for accuracy and completeness. Final disposition of documents will

    be in accordance with the Project Instructions.

    6. INITIAL INSPECTION - AT CONSTRUCTION COMPLETION

    6.1. Verify that the piping system is complete as identified by system boundaries and that it is

    installed in accordance with the drawings, (P&ID's, flow diagrams, isometrics, etc.), and project

    specifications.

    6.2. Verify hanger, support, and slide plate locations, orientation, and installations are correct as

    noted on the drawings.

    6.3. Verify rod hangers have sufficient (at least 1-1/2"), showing on all rods at turnbuckles and that all

    rods are double nutted and tight.

    6.4. Verify design clearance is present between U-Bolts and their associated piping for axial

    movement, as applicable.

  • 7/27/2019 CMTP006

    3/8

    CONSTRUCTION MTP-006

    MANAGEMENT Rev.: 0

    GUIDELINE Rev. Date: 12-03-1999

    Page 3 of 8

    This document contains information which is confidential and proprietary to Sargent & Lundy (S&L). It shall not

    be reproduced in whole or in part or released to any third party without the prior written consent of S&L.

    Copyright Sargent & Lundy 1999 all rights reserved. Standards located on the Intranet at

    http://SLWEB.SARGENTLUNDY.COM are to be considered as the official version of the Standard.

    CMTP006.DOC

    6.5. Verify welds to structural steel members are installed parallel to the web or length of the

    structural members.

    6.6. Verify all temporary support devices (wire slings, wood wedges, etc.), have been removed.

    6.7. Verify all variable spring hangers have stops installed prior to cold position setting.

    6.8. Verify that the material for hangers, supports, and slide plates attached to alloy piping/ductwork

    are proper at the interface point.

    6.9. Verify all hangers, supports, and slide plates are hung from/mounted to appropriate structure and

    not from other pipes, equipment, or cable tray.

    6.10. Verify steam line hangers and supports have hydrostatic test pins/stops removed as a result of

    hydrostatic test completion and the lines are drained.

    6.11. Verify ductwork hangers, supports and associated slide plates are installed in accordance with

    the project drawings and specifications.

    6.12. Verify proper installation of insulation and lagging per contract requirements. Verify proper

    insulation and lagging clearance exists at each hanger, support, and slide plate.

    6.13. Document the installed state of the system hangers, supports, and slide plates including air

    gaps, shims, and baseplate concrete expansion anchors installed, as applicable, on Form MTP-

    006-01, "Hanger and Support Checklist." Attach list(s) of incomplete, unresolved, and/or

    discrepant items as applicable.

    7. FINAL INSPECTION (COLD) PRIOR TO INITIAL SYSTEM OPERATION

    7.1. Verify all items of Section 6, "Initial Inspection - At Construction Completion," have been

    inspected and documented. Review inspection sheets and verify that all incomplete/unresolvedissues have been adequately addressed.

    7.2. Verify the system is in a cold state, (filled and vented for liquid systems and drained for steam

    systems).

    7.3. Verify hangers, supports, and slide plates are plumb and their associated rods are vertical,

    (offset only as shown on specified hanger and support drawings allowed).

    7.4. Verify spring hanger travel stops are removed and properly stored.

    7.5. Verify spring cans are set at COLD position with the pipe filled and vented for liquid systems and

    drained for steam systems.

    7.6. Verify hanger and support travel stops do not obstruct position-setting markers.

    7.7. Inspect all system piping hangers and supports and their associated piping systems for proper

    clearance. Document any hangers and supports appearing overloaded or having insufficient

    clearance. Attach documentation to Form MTP-006-01, "Hanger and Support Checklist."

  • 7/27/2019 CMTP006

    4/8

  • 7/27/2019 CMTP006

    5/8

    CONSTRUCTION MTP-006

    MANAGEMENT Rev.: 0

    GUIDELINE Rev. Date: 12-03-1999

    Page 5 of 8

    This document contains information which is confidential and proprietary to Sargent & Lundy (S&L). It shall not

    be reproduced in whole or in part or released to any third party without the prior written consent of S&L.

    Copyright Sargent & Lundy 1999 all rights reserved. Standards located on the Intranet at

    http://SLWEB.SARGENTLUNDY.COM are to be considered as the official version of the Standard.

    CMTP006.DOC

    9.4. Remove all ladders, staging, and scaffolding, installed for the inspection processes of this

    procedure, as applicable.

    10. REFERENCES

    All references listed must be the latest approved issues applicable to the equipment being

    commissioned.

    10.1. Vendor Instruction Manual(s) and Drawing(s) (as applicable)

    10.2. Project Mechanical Piping and Instrumentation Drawings (P&ID's)

    10.3. Project Flow Diagrams

    10.4. Project Piping Isometrics

    10.5. Project Specifications

    10.6. Project Hanger/Support Drawings

    10.7. Client Safety and Tagging Program

    10.8. Client Confined Space Entry Program

    10.9. Client Foreign Material Exclusion Program

    11. ATTACHMENTS

    11.1. Form MTP-006-01, Hanger and Support Checklist

  • 7/27/2019 CMTP006

    6/8

    CONSTRUCTION MTP-006

    MANAGEMENT Rev.: 0

    GUIDELINE Rev. Date: 12-03-1999

    Page 6 of 8

    This document contains information which is confidential and proprietary to Sargent & Lundy (S&L). It shall not

    be reproduced in whole or in part or released to any third party without the prior written consent of S&L.

    Copyright Sargent & Lundy 1999 all rights reserved. Standards located on the Intranet at

    http://SLWEB.SARGENTLUNDY.COM are to be considered as the official version of the Standard.

    CMTP006.DOC

    HANGER AND SUPPORT CHECKLIST

    Form MTP-006-01(Page 1 of 3)

    System Identification:

    Hanger/Support Identification:

    Reference Documentation: (attach separate list as required)

    Measuring & Test Equipment Equipment Control Number Calibration Due Date

    Initial Date

    3. NOTES AND PRECAUTIONS

    Section 3, "Notes and Precautions" reviewed and all required

    precautionary issues are adequately addressed

    4. PREREQUISITES

    Section 4, "Prerequisites" reviewed and all required prerequisite

    requirements are in place.

    5. GENERAL INSPECTION

    5.1. State of system agrees with intended purpose of inspection (construction

    complete/cold/hot)

    5.2. Areas requiring access established, staging installed, as required

    5.3. Inspection documentation assembled and reviewed

    6. INITIAL INSPECTION -_AT CONSTRUCTION TURNOVER

    6.1. Piping system installed per project specifications

    6.2. Hangers located and installed properly

    6.3. Threads visible on rods and double nutted and tight

    6.4. Clearance on U-bolts and pipe for axial movement

    6.5. Welds to structural members acceptable

  • 7/27/2019 CMTP006

    7/8

    CONSTRUCTION MTP-006

    MANAGEMENT Rev.: 0

    GUIDELINE Rev. Date: 12-03-1999

    Page 7 of 8

    This document contains information which is confidential and proprietary to Sargent & Lundy (S&L). It shall not

    be reproduced in whole or in part or released to any third party without the prior written consent of S&L.

    Copyright Sargent & Lundy 1999 all rights reserved. Standards located on the Intranet at

    http://SLWEB.SARGENTLUNDY.COM are to be considered as the official version of the Standard.

    CMTP006.DOC

    HANGER AND SUPPORT CHECKLIST

    Form MTP-006-01

    (Page 2 of 3)

    Initial Date

    6.6. All temporary supports removed

    6.7. Variable spring hangers stops installed or removed

    6.8. Proper support material - welded to pipe (same as pipe for saddles,

    clamps, etc.)

    6.9. Hangers and supports hung from structure only

    6.10. Steam line hangers unpinned

    6.11. Ductwork hangers, supports and slide plates correctly installed

    6.12. Insulation/lagging installed per contract requirements with proper

    clearances

    6.13. Hanger/support installation per project drawings/specifications

    7. FINAL INSPECTION (COLD) - PRIOR TO INITIAL OPERATION

    7.1. All items of Section 6. previously inspected

    7.2. System in a cold state (filled and vented for liquid, steam drained)

    7.3. Hangers plumb and rod vertical (except for allowed offsets)

    7.4. Spring hanger travel stops removed and set to cold position

    7.5. Spring cans set at COLD position, system aligned for COLD condition

    7.6. Hanger travel stops do not obstruct setting markers

    7.7. Piping hanger and supports inspected and overload/insufficient

    clearances documented

    7.8. COLD set of hanger and support readings recorded (attach copy)7.9. Ductwork hanger, support, and slide plates inspected and

    overload/insufficient clearances documented.

    7.10. COLD set of ductwork hanger, support and slide plate readings recorded

    (attach copy)

    8. HOT INSPECTION SYSTEM IN SERVICE AT OPERATING

    TEMPERATURE

    8.1. All items of Section 7. previously inspected.

    8.2. System at normal operating conditions for two (2) hours prior to

    inspection.

    8.3. Piping hanger and supports inspected and overload/insufficient

    clearances documented.8.4. HOT set of piping hanger and support readings recorded. Attach copy.

    8.5. Ductwork hanger, support, and slide plates inspected and

    overload/insufficient clearances documented.

    8.6. HOT set of ductwork hanger, support and slide plate readings recorded.

    Attach copy.

  • 7/27/2019 CMTP006

    8/8

    CONSTRUCTION MTP-006

    MANAGEMENT Rev.: 0

    GUIDELINE Rev. Date: 12-03-1999

    Page 8 of 8

    This document contains information which is confidential and proprietary to Sargent & Lundy (S&L). It shall not

    be reproduced in whole or in part or released to any third party without the prior written consent of S&L.

    Copyright Sargent & Lundy 1999 all rights reserved. Standards located on the Intranet at

    http://SLWEB.SARGENTLUNDY.COM are to be considered as the official version of the Standard.

    CMTP006.DOC

    HANGER AND SUPPORT CHECKLIST

    Form MTP-006-01

    (Page 3 of 3)

    Initial Date

    9. RESTORATION

    9.1. Test equipment removed, system access points closed, as required

    9.2. Permanent wiring, pneumatic, and hydraulic connections associated

    with the system correct/tight

    9.3. System piping/ductwork hangers, supports, and slide plates returned to

    pretest condition or as required

    9.4. Ladders, scaffolding, and staging removed

    Remarks: (Attach additional sheets as required):

    Prepared:

    Construction Date

    Reviewed:

    Startup Date

    Approved:

    Owner Date