Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
CM 26 – Riverside
24th – 27th March 2010
Engineering Summary
Presented by Wing Lau
RF Power by Andy Moss
EMR Installation by Alain Blondel
Window fabrication by Don Summers
Diffuser by John Cobb
Solid Absorber clamping arrangement by Wing Lau
Radiation Shield by Andy Nichols
Discussion on the TOF Shield support bracket
production problems
Contributions
The system as it
is at DL currently
RF Power status
•Connected to its test
load, tested water
flows - no leaks !
•Manufactured input
sliding short for input
tuning
•tested operation of
grid and anode tap
moving circuits
The done list on the TH116 Amplifier
The done list on the TH116 Amplifier
•Connected to its test
load, tested water
flows - no leaks !
•Manufactured input
sliding short for input
tuning
•tested operation of
grid and anode tap
moving circuits
Test TH116 triode in
amplifier HT tank
Water connections
HT connection
visible, water feed
and return are inside
this connectionPTFE insulation
116 HT Tank
The done list on the TH116 Amplifier
This part of the amplifier is up at 40kV,
arcing will damage silver plated
components – takes months to fix!
•Connected to its test
load, tested water
flows - no leaks !
•Manufactured input
sliding short for input
tuning
•tested operation of
grid and anode tap
moving circuits
Test TH116 triode in
amplifier HT tank
Water connections
HT connection
visible, water feed
and return are inside
this connectionPTFE insulation
116 HT Tank
The done list on the TH116 Amplifier
This part of the amplifier is up at 40kV,
arcing will damage silver plated
components – takes months to fix!
Installed arc detector, smoke alarm
and camera to monitor conditions
inside the HT tank remotely
Will run up the amplifier gently so as
to understand how to operate it.
•Connected to its test
load, tested water
flows - no leaks !
•Manufactured input
sliding short for input
tuning
•tested operation of
grid and anode tap
moving circuits
HT Power supply -The done list
•PLC controller tested
•Filament heater tested to full power on the test triode
•Cathode bias unit tested to operation levels
•System earthing assessed and corrected to promote
return current path back through monitor circuits
HT Power supply -The done list
•PLC controller tested
•Filament heater tested to full power on the test triode
•Cathode bias unit tested to operation levels
•System earthing assessed and corrected to promote
return current path back through monitor circuits
Still to do list
Some wiring between amp and HV rack / Aux rack
Built & Test Cathode modulator
Test Crowbar circuit
HV pressure test of amplifier & HV components
HT Power supply -The done list
•PLC controller tested
•Filament heater tested to full power on the test triode
•Cathode bias unit tested to operation levels
•System earthing assessed and corrected to promote
return current path back through monitor circuits
Still to do list
Some wiring between amp and HV rack / Aux rack
Built & Test Cathode modulator
Test Crowbar circuit
HV pressure test of amplifier & HV components
• Altronic Reaserch water
load, already tested to
3MW pulse
• Load (smaller!)
• Water cooling plant
• Much smaller than our
current test load - a
positive design change
for the hall installation
• Possibility to have one
cooling plant for
multiple waveguide
loads -ideal for MICE
due to low average
power
RF Load
Model 43200
(back view)
• Altronic Reaserch water
load, already tested to
3MW pulse
• Load (smaller!)
• Water cooling plant
• Much smaller than our
current test load - a
positive design change
for the hall installation
• Possibility to have one
cooling plant for
multiple waveguide
loads -ideal for MICE
due to low average
power
RF Load
Model 43200
(back view)
Hall implementation
Will use 3D CAD
drawings to understand
how to fit RF equipment
under the floor system
build up;
Need to look for phase
shifter and hybrid
devices to reduce the
size
N2 pressure will be
used for whole
waveguide system to
raise voltage stand off
and provide a “W/guide
complete” interlock.
Amplifier to cavity installation 1 – using
amplifier with DL/LBNL typical layout
RF Loads
Amplifier to cavity installation 1 – using
amplifier with CERN typical layout
RF Load
Summary on RF work
• Large amplifier ready for testing, connected to water,
test load and checked with network analyser as far as
possible
• Some work remains on the power supply, this will
continue as staff effort allows
• Hall design in progress and components being
identified that will be better for the installation, need to
progress to 3D CAD models as soon as possible
• Committed RF effort for this year to fully test amplifier
system
Module M0 prototype under testing
First test module (2 crossed planes,
2 x 0.8mm dia. Fibre / bar)
EMR production status
Module M0 prototype under testing
First test module (2 crossed planes,
2 0.8mm dia. Fibre / bar)
New modules now in production
Guide for fibre insertion and
gluing (20 bar in a row)
EMR production status
Go
ing to
te
st
roo
m s
oo
nR
ea
dy fo
r p
lan
e a
sse
mb
ly
1 stand for plane assembly1 stand for Module
assembly & storage
Module M0 prototype under testing
First test module (2 crossed planes,
2 0.8mm dia. Fibre / bar)
New modules now in production
Module assembly awaiting PMT
connector gluing & electronic
integration - 1st one with 1mm dia
fibre will be tested soon with
cosmic!
EMR production status
Module M0 prototype under testing
First test module (2 crossed planes,
2 0.8mm dia. Fibre / bar)
New modules now in production
Module assembly awaiting PMT
connector gluing & electronic
integration - 1st one with 1mm dia
fibre will be tested soon with
cosmic!
Design work on the parts close
to PMT (PMT, FEB electronics,
shielding block etc) is being
finalised
EMR production status
Module M0 prototype under testing
First test module (2 crossed planes,
2 0.8mm dia. Fibre / bar)
New modules now in production
Module assembly awaiting PMT
connector gluing & electronic
integration.
1st one with 1mm dia fibre will be
tested soon with cosmic!
Design work on the parts close
to PMT (PMT, FEB electronics,
shielding block etc) is being
finalised
Here is the whole EMR assembly –
but the shielding is an issue!
Shielding tubes
EMR production status
There was an issue with magnetic
stray field ….. Up to 1200 Gauss
No individual shielding tube could
withstand this.
EMR simulation study
There was an issue with magnetic
stray field ….. Up to 1200 Gauss
No individual shielding tube could
withstand this.
Then, the blondel’s plate came along
and halts back the stray field invasion
EMR simulation study
There was an issue with magnetic
stray field ….. Up to 1200 Gauss
No individual shielding tube could
withstand this.
Then, the blondel’s plate came along
and halts back the stray field invasion
Further iteration gives this
EMR simulation study
Mumetal
There was an issue with magnetic
stray field ….. Up to 1200 Gauss
No individual shielding tube could
withstand this.
Then, the blondel’s plate came along
and halts back the stray field invasion
Further iteration gives this….
….and this
EMR simulation study
Virostek & Blondel plate at PMT2
Due to s
atu
ratio
n w
ith M
um
eta
l
(Arm
co g
ives b
etter
results)
There was an issue with magnetic
stray field ….. Up to 1200 Gauss
No individual shielding tube could
withstand this.
Then, the blondel’s plate came along
and halts back the stray field invasion
Baseline for EMR shielding now:-
-1 global plate (50mm thk in Armco or
equivalent);
- Individual tube for each PMT (1mm
thk in Armco)
EMR simulation study
There was also an FEA study on the mechanical behaviour of the
assembly due to transportation, gravity and handling loads – Blondel
plate not included so far
EMR simulation study
Requires a clear envelop of
1.9x1.9x1m
Need to check if this fouls with
hall building structures etc
EMR integration at MICE Hall
Requires a clear envelop of
1.9x1.9x1m
Need to check if this fouls with
hall building structures etc
EMR outer box must comply
with the different STEPS
(moving downstream) to ensure
no interference with platform.
EMR integration at MICE Hall
Question from the floor
A question was raised by Mike Courthold:
Would the newly added EMR shielding plate, which is 50mm thick, undermine the effectivity of the existing magnetic shielding wall in constraining the stray magnetic field at the boundaries of the MICE Hall to less than 5 gauss, according to regulations imposed on us by RAL Safety group?
Question from the floor
A question was raised by Mike Courthold:
Would the newly added EMR shielding plate, which is 50mm thick, undermine the effectivity of the existing magnetic shielding wall in constraining the stray magnetic field at the boundaries of the MICE Hall to less than 5 gauss, according to regulations imposed on us by RAL Safety group?
It was agreed that Frank Cadoux and Mike Courthold should check this. Or, Frank could check by how much the magnetic shielding wall modifies the magnetic field in the vicinity of the EMR shield.
Window fabrication
Metal at the thinnest part only 180 micron thick
Window machined with a 27” swing ROMI CNC
lathe & CNC Fadal 50” x 20” 5020A Vertical
Machining Centre
Window fabrication
Metal at the thinnest part only 180 micron thick
Window machined with a 27” swing ROMI CNC
lathe & CNC Fadal 50” x 20” 5020A Vertical
Machining Centre
Total of 20 windows – 6 LH2 & 6 Safety Windows;
5 spares & 3 for burst test
Window fabrication
Metal at the thinnest part only 180 micron thick
Window machined with a 27” swing ROMI CNC
lathe & CNC Fadal 50” x 20” 5020A Vertical
Machining Centre
Total of 20 windows – 6 LH2 & 6 Safety Windows;
5 spares & 3 for burst test
11 Windows done & 2 burst tested at room temp. (
burst at 120 & 122psi – FEA shows 115 psi)
Window fabrication
Metal at the thinnest part only 180 micron thick
Window machined with a 27” swing ROMI CNC
lathe & CNC Fadal 50” x 20” 5020A Vertical
Machining Centre
Total of 20 windows – 6 LH2 & 6 Safety Windows;
5 spares & 3 for burst test
11 Windows done & 2 burst tested at room temp. (
burst at 120 & 122psi – FEA shows 115 psi)
QA – Mississippi own measurement using deep
throat micronmeter + non-contact CMM at LBL
Window fabrication
Metal at the thinnest part only 180 micron thick
Window machined with a 27” swing ROMI CNC
lathe & CNC Fadal 50” x 20” 5020A Vertical
Machining Centre
Total of 20 windows – 6 LH2 & 6 Safety Windows;
5 spares & 3 for burst test
11 Windows done & 2 burst tested at room temp. (
burst at 120 & 122psi – FEA shows 115 psi)
QA – Mississippi own measurement using deep
throat micronmeter + non-contact CMM at LBL
Burst test at 77K still to be done. Preparation is
now underway
Window fabrication
Metal at the thinnest part only 180 micron thick
Window machined with a 27” swing ROMI CNC
lathe & CNC Fadal 50” x 20” 5020A Vertical
Machining Centre
Total of 20 windows – 6 LH2 & 6 Safety Windows;
5 spares & 3 for burst test
11 Windows done & 2 burst tested at room temp. (
burst at 120 & 122psi – FEA shows 115 psi)
QA – Mississippi own measurement using deep
throat micronmeter + non-contact CMM at LBL
Burst test at 77K still to be done. Preparation is
now underway
Shipping hats will have transparent top & bottom
cover plate to enable non-invasive custom
inspection
Window fabrication
Metal at the thinnest part only 180 micron thick
Window machined with a 27” swing ROMI CNC
lathe & CNC Fadal 50” x 20” 5020A Vertical
Machining Centre
Total of 20 windows – 6 LH2 & 6 Safety Windows;
5 spares & 3 for burst test
11 Windows done & 2 burst tested at room temp. (
burst at 120 & 122psi – FEA shows 115 psi)
QA – Mississippi own measurement using deep
throat micronmeter + non-contact CMM at LBL
Burst test at 77K still to be done. Preparation is
now underway
Shipping hats will have plastic top & bottom cover
plate to enable non-invasive custom inspection
2 further ultra thin windows (estimated to be about
70 microns thin) using Lithium-Al. alloy still to be
made and burst tested, at 77K &300K for future
design (not MICE)
The 3-step operation:
Carousel – moves disc to position
“30 degree” – transfer disc from carousel to carrier
Carrier – moves disc in/out of solenoid
There are 160 pins & holes to align
a tricky operation!
Diffuser
The 3-step operation:
Carousel – moves disc to position
“30 degree” – transfer disc from carousel to carrier
Carrier – moves disc in/out of solenoid
There are 160 pins & holes to align
a tricky operation!
Progress:
Cool catches made – for ease insert / hard extraction
Mock-up of Disc-holder – Carrier
-- test various ideas for locking pins
-- develop transfer procedure
Diffuser
Invaluable to gain
understanding of
how it works
The 3-step operation:
Carousel – moves disc to position
“30 degree” – transfer disc from carousel to carrier
Carrier – moves disc in/out of solenoid
There are 160 pins & holes to align
a tricky operation!
Progress:
Cool catches made – for ease insert / hard extraction
Mock-up of Disc-holder – Carrier
-- test various ideas for locking pins
-- develop transfer procedure
Learnt a lot from this
Floating carrier developed –
40 springs allow L/R, U/D & BF compliance of 0.5-
1mm
Most components now made!
Diffuser
Controls
Fibre optic link – hardware done; prototype still to be developed;
FPGA firmware -- Basic manual control done; remote control to be developed
Labview control – still to be developed
Encoder (must align relative rotation to within 3 microns) – 2 out of 3 tested
Overruns – reproducible to 0.25mm, expected to be only a fraction of mm
Controls
Fibre optic link – hardware done; prototype still to be developed;
FPGA firmware -- Basic manual control done; remote control to be developed
Labview control – still to be developed
Encoder (must align relative rotation to within 3 microns) – 2 out of 3 tested
Overruns – reproducible to 0.25mm, expected to be only a fraction of mm
Still to do
Hardware – Dis-/ re-assemble with new components;
Install alignment rings for disc holder in zero-position;
Guards, installation drawings etc
Firmware – Develop FPGA firmware & RS232 interface
Controls – Develop Labview control
Develop EPICS when Firmware system is developed
Acceptance test – Number of unaided disc transfer & Acceptance criteria
to be agreed;
Have allowed 6 weeks in our schedule
Diffuser
Schedule
Mechanical
Control Hardware &
Firmware
Mechanical & Control
integration
Acceptance tests
Installation drawings
Installation
Quench test
Install in tracker
Integration with EPICS
Ma
rch
Ap
ril
Ma
y
Ju
ne
Ju
ly
Au
g
Se
pt
Oct
Nov
Dec
Ja
n
Feb
Ma
rch
2010 2011
Ap
ril
Solid Absorber clamping arrangement
70
mm
> 500mm
Entrance clearance to the
spool piece: ~ 500 x 70mm
Space constraint
Warm
bo
re
cle
ar
dia
me
ter:
47
0 +
/-2
mm
AFC Warm bore
Solid Absorber clamping arrangement
70
mm
> 500mm
Entrance clearance to the
spool piece: ~ 500 x 70mm
Space constraint
Warm
bo
re
cle
ar
dia
me
ter:
47
0 +
/-2
mm
AFC Warm bore
Overall dimension of clamp with
absorber must be under 468 x 70mm
Solid Absorber clamping arrangement
Space constraint
Three
brackets to
lock tight
the clamp
ring to the
absorber
Solid Absorber clamping arrangement
Space constraint
Three
brackets to
lock tight
the clamp
ring to the
absorber
Dimension check
Mounting it to the AFC
Adaptor connecting the solid
absorber to the Safety Window
mounting flange
Solid Absorber clamping arrangement
Mounting it to the AFC
Adaptor connecting the solid
absorber to the Safety Window
mounting flange
Bolted onto the
underside of the spool
piece cover plate
Solid Absorber clamping arrangement
Mounting it to the AFC
Adaptor connecting the solid
absorber to the Safety Window
mounting flange
Bolted onto the
underside of the spool
piece cover plateThings to do:
• To decide
whether the
clamp band is to
be made of
carbon fibre or
stainless steel –
Alan Bross to
decide and
advise
• To produce
fabrication
drawings –
Oxford to provide
• Fabrication by
Fermilab
Solid Absorber clamping arrangement
Radiation Shield inside the Spectronmeter
Radiation shutter assembly
Is bolted to spectrometer
solenoid #1 prior to Step IV
Two guided lead shutters
Remotely operated, but with
Manual control in reserve
Control rods have to
penetrate MICE vacuum
volume
Design work is nearly
complete
• Shutter doors and guides have been made at
FNAL, awaiting/undergoing fit check before
shipping
• All detail design work is done by Peter Lau
• Some potential manufacturing difficulties need
sorting out, nothing major
• Probably some scope for simplifying the control
rods and actuation
Progress Status
Radiation Shield inside the Spectrometer
• Completion of manufacturing drawings:
– End of April, 2010
• Shipment of shutters & guides to RAL
– Q2/3, 2010?
• Design and manufacture of pre-assembly test stand
– Mid-May, 2010
• Trial assembly and testing prior to installation
– Q4, 2010
• Final installation in MICE
– Difficult to tell just now – linked to Step IV
Remaining work and schedule plans
Discussion session
There were concerns raised on the Iron Shield Support brackets:-
1. The workmanship on the welds is not good. He is concerned at
the weld size on the bracket joints.
2. There was no specification on what the weld size should be,
resulting in fabricators welding the bracket with nominal weld
throat
3. At some of the joints, the fillet weld meant that the Iron Shield
which was machined with no fillet or chamfer can not fit into the
bolt holds...
4. It was not sure what external load the brackets were assessed
to and what the safety margins are on these brackets;
5. No Assembly drawing was available to show where the parts
go....
6. We need to decide if these brackets need to be re-made or re-
welded.....
1. There is a stress report on these brackets.
Apart from the gravity load that hangs on the top and bottom
brackets, there is a total of 8 tons of horizontal loads (magnetic
load)shared between the 4 brackets.
The stress from the FE analysis showed that the stresses on
these brackets are generally very low (about 35 - 40 MPa,
compared to an allowable of 235 MPa), except two areas where
the local stress is about 85 MPa.
2. Design was done based on a full joint efficiency, meaning that the
joints are of fully penetrated welds. Apart from the two brackets
which have slightly higher stresses, a fillet weld of 10mm should be
OK.
Wing Lau agreed to take the FE results and extrapolate them to
see what stress should be if the joints for a 10mm fillet weld.
A meeting was convened afterwards to discuss the issues
3. The drawings made by Oxford were "Design Drawings". Design
drawings only show basic dimensions. They do not list out the details
such as tolerance and weld sizes etc. Such information are normally
shown in "Production Drawings".
4. Production drawings were not done in this case and instead the
design drawings were sent out to manufacturers for fabrication.
5. Of the two brackets need to be re-welded / re-made.
6. The drawings specified that the bracket material to be Stainless
Steel. Yamour to check if they are indeed made of SS, and not
carbon steel.
A meeting was convened afterwards to discuss the issues