Upload
randall-richardson
View
131
Download
0
Embed Size (px)
Citation preview
1 Johnson Controls, Inc. © June 2007
ASG-NA Automotive NorthwoodProcess Owner: Brian KrugerGREENBELT: Randall RichardsonMaster Black Belt: Fernando BuchholzSigma Trac ID # 200807163834
Project Schedule
Definition: 08/15/08 09/24/08 09/27/08 Measure: 09/19/08 11/05/08
11/25/08Analyze: 10/10/08 01/10/09
01/23/09Improve: 11/10/08 02/18/09 04/10/09 Control: 11/28/08 04/29/09 04/29/09Validation: 07/29/09 07/29/09
07/29/09
Original Revised ActualCompletion Completion
Completion
BUILD COCKPITS – Reduce the number of Cluster Bezel Repairs in the Tester area
2 Johnson Controls, Inc. © June 2007
• Problem Statement:There is non value added work being performed at the end of line testers.
For the month of June 2008 there were 12 cluster bezel repairs made to the Cockpits. This resulted in a scrap cost of $155.64 (annualized at $6225.6), and a downtime cost of $256 (annualized at $10,240) in man hours. This information is gathered from the repair logs.
• Project Objective:YC1 = (Number of Cockpits that should have been repaired or contained but
were sent to the testers)YB1 = cost of downtime due to repairs in testersYB2 = cost of scrap due to repairs in testersYp1 = proportion of bezels repaired / week
Define
3 Johnson Controls, Inc. © June 2007
Drill Down Pareto
Count 112 4 4 2 2 2 1 1Percent 3.441.4 13.8 13.8 6.9 6.9 6.9 3.4 3.4Cum % 100.041.4 55.2 69.0 75.9 82.8 89.7 93.1 96.6
Tester Repairs
302520151050
100
80
60
40
20
0Co
unt
Perce
nt
Pareto Chart of Tester RepairsCount 31 8 8
Percent 66.0 17.0 17.0Cum % 66.0 83.0 100.0
REPAIREQ TESTER 6 DOWNRP
50
40
30
20
10
0
100
80
60
40
20
0
Coun
t
Perc
ent
Pareto Chart of TESTER JUNE DOWNTIME
Total repairs at tester June 2008
Count 12 5 5 5 2Percent 41.4 17.2 17.2 17.2 6.9Cum % 41.4 58.6 75.9 93.1 100.0
Cluster Bezel Repair Types
30
2520
1510
50
100
80
60
40
20
0
Coun
t
Perc
ent
Pareto Chart of Cluster Bezel Repair Types
Scratches #1 repair
4 Johnson Controls, Inc. © June 2007
Statement of Work
CI Statement of WorkDate printed: 9/9/08
Form rev.: 2007-0328a
Project Title:
Location:
Phase Definition Project # 200807163834Originator: Jay LewisCustomer Quality Focus: YesCreate Date: 7/31/08
Rollout Type:
PROJECT DESCRIPTIONProcess / Product Being Improved: Project Scope and Boundaries: Customer Y (s):
Business Y (s):
Problem Statement:
Project Objective / Suspected Root Cause: Primary BBP metric impacted:BBP Product Line:
ESTIMATED SAVINGS (from COPQ)Est. Hard Savings: Est. Soft Savings: 78
TEAMProcess Owner: Denise Stinson Black Belt:
CI Manager: Jay Lewis Green Belt: Randall R Richardson
Yc1 = Number of Cockpits that should have been repaired but were sent to customer.
Interiors: Instrument Panels
Yb1 = Cost of doing repairs in testers.
There is non value added work being performed at the end of line testers. For the month of June 2008 there were 34 repairs made to the Cockpits. The information is gathered from the repair logs. Reduce the number of repairs being sent to the testers by 85%.
10 - Total Labor Hours Per EQU
2009 Q1 BUILD COCKPITS - Reduce Number Of Cockpits Needing Repair At TestersUSA - Northwood OH
Cockpit assembly process.
AG - NAJ IT - DCBU - Northwood - Cockpit Line
Standard
200807163834
Type: Green Belt
#N/A#N/A
Objective: Reduce number of defective cluster bezels being sent to the Testers by 100%.
Process: Build Cockpits
Problem: There is non value added work being performed at the end of line testers. For the month of June 2008 there were 12 cluster bezel repairs made to the Cockpits. This information is gathered from the repair logs.
YC1= Number of Cockpits that should have been repaired but were sent to the testers
YB1 = Downtime cost due to repairs in testers
YB2 = Scrap cost due to repairs in testers
YP1 = proportion of cluster bezels repaired / week
5
Baseline Performance
Level
Description(with unit of measure) Before
Project Target After % Improve
YC panels repaired/each 12 0
YB1
Annualized cost of dow ntime due to repairs in testers in dollars $10,240.00 0
YB2
Annualized cost of scrap due to repairs in testers in dollars $6,225.60 0
Avg:0.009 Avg:0 Avg:St.Dev:.005 St.Dev:0 St.Dev:Cpk or P pk:N/A
Cpk or P pk:N/A
Cpk or P pk:
Proportion of bezels repaired per day (p bar)
YP
6
Customer Y
YC1 = No. of unacceptable cluster
bezel scratches found in tester area
12/29 unacceptable repairs for scratched
bezels(41.4% of total occurrences)
FY08 data from the month of June scrap report
Count 12 5 5 5 2Percent 41.4 17.2 17.2 17.2 6.9Cum % 41.4 58.6 75.9 93.1 100.0
Cluster Bezel Repair Types
3025
20
1510
50
100
80
60
40
20
0
Coun
t
Perc
ent
Pareto Chart of Cluster Bezel Repair Types
7
Business Y
YB2= Cost of scrap due to repairs (cluster bezels) in testers Process in statistical control. Operating within control limits
YB1= Cost of downtime due to repairs in testers
Process in statistical control.Operating within control limits
06/0806/0706/0606/0506/0406/02
$250.00
$200.00
$150.00
$100.00
$50.00
$0.00
-$50.00
-$100.00
Date
Indi
vidu
al V
alue
_X=$56.20
UCL=$235.58
LCL=-$123.17
I Chart of Cost of scrapped bezels
06/0806/0706/0606/0506/0406/02
$150.00
$100.00
$50.00
$0.00
-$50.00
Date
Indi
vidu
al V
alue
_X=$42.65
UCL=$147.01
LCL=-$61.71
I Chart of Downtime Cost
8 Johnson Controls, Inc. © June 2007
Concentration Chart
scuff marks on A surface
scratches on A surface
KA chart of scratch location
on A surface
KK chart of scratch location
on A surface
9 Johnson Controls, Inc. © June 2007
Initial Process FlowCluster Bezels are received from
shipping and stored in storage area
panel moves to stn 25 (steering shroud installed) and then to the tester area to be tested and stored in th
HK system waiting to be shipped to customers
material handler retrieves and scans
part
Places part on belt
Finds correct part and scans it
stn 20 operator retrieves part from
belt
stops line and finds correct
part
places part in tote box
stn 24 operatro retrieves part from
tote and scans label on part
installs cluster bezel to IP shell
Yes
No
No
Yes
stops line and retrieves correct part
and scans it
No
Yes
Finds correct part and
scans it for verification
Stops line and retrieves correct
part and then scans for
verification
Stops line and retrieves correct part
and then scans for verification
Project focuses on this part of the process
10
Yp1 Current Defective
Level = 4603 PPM
Historical Data
Acceptable MSA
Process YYC1 = Number of Cockpits that should have been repaired but were sent to customer
YP1 = (proportion of bezels repaired / week)Between Appraisers
Assessment Agreement
# Inspected # Matched Percent 95 % CI 30 28 93.33 (77.93, 99.18)
# Matched: All appraisers' assessments agree with each other.
11
View of Process Before Changes
Stacking parts on top of each other
Station 20 bezel kit area
12 Johnson Controls, Inc. © June 2007
4 Identify causes (Xs) of variation and defects.Yp1 = No. of defective cluster bezels being sent to testers
People
MachinesMethods
Materials
Scratched cluster bezels
Operators in a hurry
Operators tossing bezel in tote
New tasks added to process
Material/operator Handlers stacking parts on top of each other during part change out
Height of torque gun stn 24
Shipments received from supplier
Potential Causes
Tote is close to empty, time to change out tote for more
parts
Replacing stripped unuts
Operator drove screw into bezel incorrectly
Bit from torque gun scratching after torque process
X1
X3X2
13
Potential CauseNull
HypothesisAlternative Hypothesis Verification Data
Data Type (Attribute/Variable)
Verification Method (Test)
Results (P=) Conclusion
(Reject Null?)
Verified Cause? (Y/N)
Y1 X1 Operator tossing besel into tote P > 0 P < 0Collected data for 1 shift to determine # of bezels returned for scratches Attribute
2 Proportion Test P=1 No
Y1 X2Material Handler/Operator stacking parts on top of each other P > 0 P < 0
Collected data for 1 shift to determine # of bezels returned for scratches Attribute
2 Proportion Test P=0.000 YES
X3Bit from torque gun scratching bezel after torqueing process P > 0 P < 0
Collected data for 1 shift to determine # of bezels returned for scratches Attribute
2 Proportion Test P=0.158 NO
Verified Causes
Verified XsX1 P value above .05X2 proved to be significant (P value 0)X3 P value above .05
YP1 = proportion of bezels repaired/week
14
Very effective, easy to implement, low costModerately effective, Moderately easy to implement, Moderate cost
Not very effective, Hard to implement, High cost
LEGEND
YP1 = Proportion of bezels repaired/per week
Cause Possible Counteractions
Effectiveness
Ease to Im
plement
Cost
SafetyY1 X2 material
handler/operator stacking parts on top of each other
Using empty spaces in other totes to lodge excess bezels during changeoutsI9 Cross-train managers to take food orders (second back-up)
X2 material handler/operator stacking parts on top of each other
Fast Tube Rack
X2 material handler/operator stacking parts on top of each other
Corrugated Sleeve Rack to store bezels during changeout
I12 Simplify/standardize abbreviations on print-out
X2 material handler/operator stacking parts on top of each other
Training, making operators aware of the problems associated with staking bezels on top of each other
X10 Slammed (restaurant extremely busy)
Cross training identified for X7 and X8
X12 Inadequate prep (not enough items prepared ahead of time)
I14 Modify computer programming to bucket "prepared" items into lunch and dinner groups, head cook to publish schedule 1 day in advance
Potential Counteractions
X Counteractions
Operator stacking corrugated sleeve
parts on top of each Rack
other
15
New Process FlowBefore After
X2
Cluster Bezels are received from shipping and stored in storage
area
panel moves to stn 25 (steering shroud installed) and then to the tester area to be tested and stored in th
HK system waiting to be shipped to customers
material handler retrieves and scans
part
Places part on belt
Finds correct part and scans it
stn 20 operator retrieves part from
belt
stops line and finds correct
part
places part in tote box
stn 24 operatro retrieves part from
tote and scans label on part
installs cluster bezel to IP shell
Yes
No
No
Yes
stops line and retrieves correct part
and scans it
No
Yes
Cluster Bezels are received from shipping and stored in storage
area
panel moves to stn 25 (steering shroud installed) and then to the tester area to be tested and stored in th
HK system waiting to be shipped to customers
material handler retrieves and scans
part
Places part on belt
Finds correct part and scans it
stn 20 operator retrieves part from
belt
stops line and finds correct
part
places part in tote box
stn 24 operatro retrieves part from
tote and scans label on part
installs cluster bezel to IP shell
Yes
No
No
Yes
stops line and retrieves correct part
and scans it
No
Yes
Utilizing corrugated sleeve rack in preparation for cluster bezel part change outs
Finds correct
part and scans it for verification
Stops line and retrieves
correct part and then scans for verification
Stops line and retrieves correct
part and then scans for
verification
Finds correct
part and scans it for verification
Stops line and retrieves
correct part and then scans for verification
Stops line and retrieves correct
part and then scans for
verification
16
View of area after improvementCorrugated sleeve rack
built/installed
Rack creates a buffer from the time the operator calls for new parts to the time the forklift operator actually arrives to replace empty totes. This way operator is not forced to stack parts on top of each other.
17 Johnson Controls, Inc. © June 2007
Before/After Charts
Improve
YC1 = Number of Cockpits that should have been repaired but were sent to customer
YP1 = (proportion of bezels repaired / week)
100% improvement
18 Johnson Controls, Inc. © June 2007
Before/After Charts
Improve
YB1 (Cost of downtime due to repairs in testers)
04/0804/0704/0604/0204/0106/0706/0606/0506/0406/02
$150.00
$100.00
$50.00
$0.00
-$50.00
Date
Indiv
idual
Value
_X=$0.00UCL=$0.00LCL=$0.00
before afterI Chart of Downtime Cost by Condition
100% improvement
19 Johnson Controls, Inc. © June 2007
Before/After Charts
Improve
YB2 (Cost of scrap due to repairs in testers)
$250.00
$200.00
$150.00
$100.00
$50.00
$0.00
-$50.00
-$100.00
Date
Indiv
idual
Value
_X=$0.00UCL=$0.00LCL=$0.00
Before AfterI Chart of Cost of scrapped bezels by Condition
100% improvement
20 Johnson Controls, Inc. © June 2007
PFMEA
Control
RPN Lowered from 294 to 42 based on occurrence score going from 7 to 1
21 Johnson Controls, Inc. © June 2007
Control Plan
Control
Instructions on staging rack added to ODS
22 Johnson Controls, Inc. © June 2007
ODS
Control
KK KA
Process Steps
Class Photos
× × 1 Scan track sheet.
× × 2
Verify remote start is connected to WCM, observe correct plug orientation as shown and scan "YES" bar code. Load WCM onto steering column (Option).
× × 3 Retrieve and scan SCCM switch.
× × 4 Make (3) connections to bottom of SCCM.
× × 5 Torque down WCM with (1) 6508440AA torx screw.
× × 6 Load SCCM onto steering column.
× × 7 Drive the first torque into the front of the SCCM.
× × 8 Drive (2) torques in order 'a' then 'b' as shown in picture.
× × 9 Make (1) connection to the top of the SCCM.
× × 10 Retrieve the cluster bezel either from conveyor or lineside ropak, then lay on kit tote.
× × 11 In preparation for cluster bezel part change out use staging rack.
× × 12 Release Cart
5 "S" Checklist
ALL Operators have the authority to STOP the line for NON-CONFORMING PRODUCT, or if there is a SAFETY ISSUE. The Operator must contact Supervisor immediately.Do Not Try and Retrieve anything dropped into the equipment without following the proper safety procedures including stopping the equipment and asking for assistance when needed.
ApprovalsDuring each rotation. . . Materials________________________ Date
1) Straighten out parts, and put all tools in their proper places. Quality Date
2) Dust all equipment.Total Productive Maintenance -- Notify your Supervisor if any issues are foundVisually check and inspect all tools and equipment for any visable damage. Verify that all work surfaces including belt conveyors are clean to prevent dirt getting on seats.
Safety Date
3) Clean and sweep floor around work area.
Engineering Date
4) Dispose of all scrap & trash in proper containers.
Production Date
5) When complete call line supervisor for inspection. "Continually Exceed Our Customer's Increasing Expectations"
Revision Date: 05/05/2009
Utilizing the staging rack implemented into the ODS
23
Results Summary
Scrap Cost calculation $12.97 * # of scrapped bezels
Description(with unit of measure) Before
Project Target After % Improve
YC panels repaired/each 12 0 0 100%
YB1
Annualized cost of dow ntime due to repairs in testers/dollars $10,240.00 0 0 100%
YB2
Annualized cost of scrap due to repairs in testers/dollars $6,225.60 0 $0.00 100%
Avg: .009 Avg:0 Avg: 0St.Dev:.005 St.Dev:0 St.Dev: 0Cpk or P pk:N/A
Cpk or P pk:1.33
Cpk or P pk:N/A
proportion of bezels repaired per week/dollars
YP
Downtime cost calculation formula – [1.71 minutes * 18 *# of Ops]/60 *18.5
24 Johnson Controls, Inc. © June 2007
Before/After Charts
3 Month Validation
YC1 = Number of Cockpits that should have been repaired but were sent to customer
YP1 = (proportion of bezels repaired / week)
08/2808/2408/1108/0507/3004/1904/1504/0904/0206/0605/23
0.035
0.030
0.025
0.020
0.015
0.010
0.005
0.000
Date
Prop
ortio
n
_P=0UCL=0LCL=0
Before After1
Cluster Bezel ScratchesBefore and After
Tests performed with unequal sample sizes
100% improvement continues
25 Johnson Controls, Inc. © June 2007
Before/After Charts
3 Month Validation
YB1 (Cost of downtime due to repairs in testers)
100% improvement continues
08/2808/2508/1308/1008/0507/3107/2804/0704/0106/0606/02
0:03:00
0:02:00
0:01:00
0:00:00
-0:01:00Date
Indiv
idual
Value
_X=0:00:00UCL=0:00:00LCL=0:00:00
before afterI Chart of Downtime by Condition
26 Johnson Controls, Inc. © June 2007
Before/After Charts
3 Month Validation
08/3108/2508/1208/0607/3107/2704/1604/1004/0604/0606/0706/02
20
15
10
5
0
-5
-10
Date
Indiv
idual
Value
_X=0UCL=0LCL=0
Before AfterI Chart of Scrapped bezels by Condition
100% improvement continues
YB2 (Cost of scrap due to repairs in testers)