46
Closure Design and Construction of Contaminated Soft Sludge Lagoons: A Tale of Innovation, Poor Field Execution and Final Redemption David Espinoza Washington DC, USA April, 2013 West Lafayette, Indiana PURDUE GEOTECHNICAL SOCIETY

Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

Closure Design and Construction of

Contaminated Soft Sludge Lagoons:

A Tale of Innovation, Poor Field

Execution and Final Redemption

David Espinoza

Washington DC, USA

April, 2013 West Lafayette, Indiana

PURDUE GEOTECHNICAL SOCIETY

Page 2: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

AVTEX SUPERFUND SITE

Located in the Shenandoah valley

(62 miles west of DC)

Page 3: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

A LITTLE HISTORY…

Page 4: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

ONCE UPON A TIME…

Plant built

in 1937

Page 5: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

AVTEX FIBERS

Page 6: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

SUPERFUND RECIPE

Ingredients:

• Caustic soda

• Sulfuric acid

• Carbon disulfide

1950s

Page 7: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

PRODUCE SOME MORE…

1970s

Page 8: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

ET VOILÀ (1990’s)…

Page 9: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

Sludge Basins

( 21 Hectares)

Fly Ash Stockpile

(500,000m3)

PROJECT BACKGROUND

Fly ash was recommended to close the lagoon (260,000 m3)

Page 10: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

REMEDIATION

• Leave in place and cap 5 sulfate sludge basins (~50 acres)

• Capping implied: 4 ft – 10 ft surcharge

Natural Soil

0.5 - 1.5 ft

3 - 20 ft

Crust (200 - 400 psf)

Soft (10-100 psf)

Page 11: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

CHARACTERIZATION

• Perm 10-7 to 10-8 cm/s

• Unit Weight: 10 pcf to 50 pcf

• Moisture Content: 90% to 800%

• Shear Strength: 10 psf to 100 psf

Page 12: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

HOW SOFT IT IS 10-100 PSF?

An average person weighs 180 lb

Average shoe size: 10 (~ 0.75 ft2) 240 psf

Page 13: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

CLOSURE APPROACH

Soil-Geosynthetic Cover

Sulfate Sludge

Fly Ash

Surplus of fly ash available on site (240,000 m3)

1-7 m

0.5-2 m

1 m

Use fly ash as grading fill

Place soil-geomembrane cap on the top

Page 14: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

THE $1M QUESTION IS:

How to over build a 10 PSF soft sludge lagoon?

Page 15: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

ANSWER: BROMS (1987)

Stabilization of Very Soft Clay using Geofabric

Geotextiles and Geomembranes Vol. 5, pp 17-28

Page 16: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

A. Lagoon Filled with Soft Sludge

LAGOON TO BE STABILIZED

(SOFT SLUDGE)

LAGOON TO BE STABILIZED

(SOFT SLUDGE)

HOW DOES IT WORK?

Page 17: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

A. Lagoon Filled with Soft Sludge

GEOTEXTILE SEAM (TYP)

STABILIZING BERM (TYP)

B. Install Geotextile over Lagoon

and Place Stabilizing Berms

CONSTRUCTION SEQUENCE

Page 18: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

A. Lagoon Filled with Soft Sludge

B. Install Geotextile over Lagoon

and Place Stabilizing Berm

INTERMEDIATE BERM

PERPENDICULAR TO SEAMS (TYP)

C. Construct Intermediate Berms

CONSTRUCTION SEQUENCE

Page 19: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

A. Lagoon Filled with Soft Sludge B. Install Geotextile over Lagoon and

Place Stabilizing Berm

D. Widen Intermediate Berms C. Construct Intermediate Berms

CONSTRUCTION SEQUENCE

Construction involves a step-wise procedure to be followed in the field

Page 20: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

SOFT SLUDGE

STABILIZING BERM HIGH STRENGTH GEOTEXTILE

CLOSURE METHOD

SOFT SLUDGE

LOCKING BERM

SOFT SLUDGE

INTERMEDIATE BERM

Page 21: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

BROMS (1987)

2

2

1

1

l

h

l

h

Hypothesis:

12

12

5

5

hh

ll

For example:

Excerpts from Page 23:

ft5)ft1(5 ft;1

ft50)ft10(5 ;ft10

21

21

hh

ll

Page 22: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

NEW APPROACH (2000)!

CE68901

CE48300 MA161000

Page 23: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

DESIGN ANALYSIS

SOFT SLUDGE

INTERMEDIATE BERM

HIGH STRENGTH

GEOTEXTILE

LOCKING BERM STABILIZING BERM

Bearing Capacity Analysis

BERM SPACING INTERMEDIATE

BERM

DEFORMED

SURFACE

INITIAL

SURFACE

RUT DEPTH

Page 24: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

DESIGN ANALYSIS

Ab = Volume of soft sludge displaced under an intermediate berm

Ah = Volume occupied by soft Sludge heave between intermediate berms

BERM AREA Lb

HEAVED AREA Lh

BERM AREA Lb

INTERMEDIATE

BERM

Ab βh βb

Ah

Ab

rh

rb

εh

βb

rb

Ultimate Reinforced Bearing Capacity of Soil, qur

(Membrane Effect from High Strength Geotextile)

DEFORMED GROUND

SURFACE, f(x)

qur = cNc +qgb +qgh

Page 25: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

q + q + N c = q ghgbcur

dxxfxfx L

J = q

b

b

L

Lb

gb

2/

2/

2/12 )('')('1)(

dxxfxfx L

J = q

hb

b

LL

Lcgh

2/2/

2/

2/12 )('')('1)(2

qavg

Reference: Espinoza and Sabatini (2008), Geosynthetics International

Data required: Modulus (J) and shape of deformation f(x)

DESIGN ANALYSIS

Page 26: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

b

h

L

L

+ + = 2J/L

qhhbbavg

b

avg

q

)secln(tan

1)sec(tanln

)(

1

ghgb

avg

Deformed shape approximated by parabolas (Giroud and Noirey, 1981)

ghgbavg qqq

DESIGN ANALYSIS

Page 27: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

GEOTEXTILE CONTRIBUTION

Using this chart, the effect of geotextile contribution can be quantified

Additional Bearing Capacity Provided by Reinforcement

0.000

0.100

0.200

0.300

0.400

0.000 0.050 0.100 0.150 0.200 0.250 0.300

Rutting Factor - rb/Lb

Mem

bra

ne C

on

trib

uti

on

- q

/(2J/L

b)

0.0%

5.0%

10.0%

15.0%

20.0%

Avera

ge R

ein

forc

em

en

t S

train

(%

)

1.00

1.50

2.00

3.00

4.00

5.00

L h /L bReinforcement Strain

Membrane Effect Contribution

Rutting Factor (rb/Lb)

Mem

bra

ne

Co

ntr

ibu

tio

n

λ=

qu

r/(2

J/L

b)

Ave

rag

e

Str

ain

(%

)

Additional Bearing Capacity Provided by Reinforcement

Page 28: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

Sludge Thickness = 0.3m

Undrained shear strength= 0.5 kPa

Equipment CAT D3C-LGP-5II = 29.6 kPa

kPaN c = q cu 5.214.55.0

0.108.06.29

5.2 =

q

qFS

equipment

u

For Berm Deflection rb= 0.45m

Berm spacing Lh= 8.0 m

Berm width Lb= 2.7 m

17.0,0.3 b

b

b

h

L

r

L

L

CALCULATION

Unreinforced Case

Reinforced Case with Berms

Lh=8.0m INTERMEDIATE

BERM

DEFORMED

SURFACE

INITIAL

SURFACE

rb=0.45m

Lb=2.7m

Page 29: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

GEOTEXTILE CONTRIBUTION

Additional Bearing Capacity Provided by Reinforcement

0.000

0.100

0.200

0.300

0.400

0.000 0.050 0.100 0.150 0.200 0.250 0.300

Rutting Factor - rb/Lb

Mem

bra

ne C

on

trib

uti

on

- q

/(2J/L

b)

0.0%

5.0%

10.0%

15.0%

20.0%

Avera

ge R

ein

forc

em

en

t S

train

(%

)

1.00

1.50

2.00

3.00

4.00

5.00

L h /L bReinforcement Strain

Membrane Effect Contribution

Rutting Factor (rb/Lb)

Mem

bra

ne

Co

ntr

ibu

tio

n

λ=

qr/(2

J/L

b)

Ave

rag

e

Str

ain

(%

)

Calculating factors using the proposed chart

rb/Lb=0.17

λ=0.014

ε=1.9%

Lh/Lb=3.0

With = 1.9% and qr = 27.1 kN/m then J= 2540 kN/m

Geosynthetic Contribution

Working tensile strength = (2,540 kN/m)×1.9% = 48.25 kN/m

For FS =2, u = 3.8%, Tu = 96.5 kN/m

Page 30: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

SPECIFICATIONS

• Develop construction details

• Specifications

• High strength geotextile (Tu = 96.5 kN/m and u = 3.8%)

• Sequence of construction

• Equipment (D5G-LGP)

Page 31: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

CLOSURE IMPLEMENTATION

Fill Placement to slow and

time consuming

Specified Equipment (e.g.,

D5H-LGP) too small for

production

Page 32: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

Interesting but no, thanks

Use large equipment to push fly ash over sludge to

“save” the cost of geotextile and construction time

(2002-2008)

Page 33: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

After all it is just a dirt job…

Mixing lots

of fill with

sludge

Crust

Displacement

Page 34: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

9 Years later (2009)…

Closed 12 hectares

Fly Ash Stockpile

(500,000m3)

Slow rate of closure and fly ash deficit for remaining work

Remaining 9 hectares

Used 400,000 m3 Remaining 100,000 m3

Sludge Basins

(21 hectares)

Page 35: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

FINAL REDEMPTION

Maybe the

consultant is not as

dumb as he looks

Page 36: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

Field panels seamed in accordion manner in the field

SEAMS FOR GEOTEXTILES

J SEAM HAND SEAMING

Page 37: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

Minimal slack following deployment of the seamed geotextiles

FIELD CONSTRUCTION

Geotextile installed rapidly in the field

Page 38: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

Ease of placement of fly ash material over sludge using equipment on site

Fly ash layer placement perpendicular to geotextile seams

FIELD CONSTRUCTION

Page 39: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

Increased bearing capacity due to membrane effect of geotextile

Parallel berms provided confinement to the sludge

FIELD CONSTRUCTION

Page 40: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

Wave Propagation at Leading Edge of Berms Occurred

Approximately 2 Weeks to Cover 2 Acre Area with Initial Lift

of Fly Ash Grading Layer

FIELD CONSTRUCTION

Reduced construction time to one month to cover one hectare of basin

Series of parallel berms were constructed

Page 41: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

Geotextile was torn and patched in place

Problems occurred when the contractor tried to use oversized equipment

FIELD CONSTRUCTION

Page 42: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

FIELD CONSTRUCTION

Fill thickness of 1-3 m was achieved with remaining fly ash

Intermediate space between berms was filled

Page 43: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

LESSONS LEARNED

Printed correct

Page 44: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

LESSONS LEARNED

• Developing good engineering solutions is not always sufficient

• Convey the risks associated with potential alternatives

Page 45: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

TO BE A GOOD CONSULTANT…

We CANNOT focus in our mouse traps…

Remember, our clients don’t care about our

mouse traps…

They care about

having less mice

Page 46: Closure Design and Construction of Contaminated Soft ... · Average shoe size: 10 (~ 0.75 ft2) 240 psf . CLOSURE APPROACH Soil-Geosynthetic Cover Sulfate Sludge Fly Ash Surplus of

THANKS

Questions?

Contact Information: David Espinoza [email protected]

Address: 10220 Old Columbia Road, Columbia, MD 21046

(Ph: 410-381-4333)