Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Clines Corner-Four Corners 262 MW (TSR 84736305 – 62 MW, TSR 73111347- 100 MW, and TSR 73111363- 100 MW)
Transmission Service Facilities Study
September 2017
Work Performed by: Public Service Company of New Mexico
Foreword
This report is prepared for Avangrid, Inc. (Transmission Customer) by Public Service Company of New Mexico Transmission Planning and Contracts Department in response to a 262 MW long term firm point–to-point transmission service facilities study agreement executed in June 1, 2017. This document was prepared by PNM. PNM does not:
(a) make any warranty or representation whatsoever, express or implied, (i) with respect to the use of any information, apparatus, method, process, or similar item disclosed in this document, including merchantability and fitness for a particular purpose, or (ii) that such use does not infringe on or interfere with privately owned rights, including any party's intellectual property, or (iii) that this document is suitable to any particular user's circumstance; or
(b) assumes responsibility for any damages or other liability whatsoever (including any consequential damages, even if PNM or any PNM representative has been advised of the possibility of such damages) resulting from your selection or use of this document or any information, apparatus, method, process, or similar item disclosed in this document. Any correspondence concerning this document, including technical and commercial questions should be referred to:
Director, Transmission/Distribution Planning and Contracts Public Service Company of New Mexico
2401 Aztec Road NE, MS-Z220 Albuquerque, NM 87107
Table of Contents
1. Executive Summary .......................................................................................................................... 1
2. Required Network Upgrades ........................................................................................................... 3
2.1 New 42 mile 345 kV line from Diamond Tail to Clines Corners .................................................... 4
2.2 Existing BA – Clines Corners and BA – Norton 345 kV Line loop in into Diamond Tail Switching Station 4
2.3 New 2.5 mile double circuit 345 kV line from BA – Norton 345 kV transmission line .................. 5
2.4 Diamond Tail Switching Station .................................................................................................... 5
2.5 Clines Corners Switching Station Expansion ................................................................................. 5
2.6 Expansion of Eastern New Mexico RAS and relay upgrades at Norton and BA 345 kV stations .. 6
3. Summary of Cost Estimate and Work Schedule .............................................................................. 7
Appendix A: Cost Estimate Detail ............................................................................................................... 11
Appendix B: Detailed Switching Station layout and one line diagrams ...................................................... 21
List of Figures
Figure 1 —General location and surrounding transmission of Second BA – Clines Corners 345 kV line ..... 2 Figure 2 —Transmission Interconnection Project and nearby PNM Transmission System .......................... 4 Figure 3 - Diamond Tail Switching Station Layout ........................................................................................ 5 Figure 4 - Clines Corners Switching Station Expansion ................................................................................. 6 Figure 5 - One Line Diagram of Diamond Tail Switching Station ................................................................ 22 Figure 6 - Electrical Plan Layout of Diamond Tail 345 kV Switching Station ............................................... 23 Figure 7 - One Line Diagram of Clines Corners 345 kV Switching Station................................................... 24 Figure 8 - Electrical Plan Layout of Clines Corners 345 kV Switching Station ............................................. 25 List of Tables
Table 1: List of contingencies and corresponding proposed action from remedial action scheme ............. 6 Table 2: Second BA -Clines Corners 345 kV Line and Network upgrade Cost Estimate ............................... 7 Table 3: Second BA - Clines Corners 345 kV Line Construction Schedule ..................................................... 9 Table 4: Detailed total Cost Estimate of Second BA - Clines Corners 345 kV Line and Network Upgrade . 11 Table 5: New 345 kV Line from Diamond Tail to Clines Corners Detail Cost Estimate ............................... 12 Table 6: Norton - BA 345 kV Line Loop in into Diamond Tail Detail Cost Estimate .................................... 14 Table 7: Diamond Tail Switching Station including RAS Detail Cost Estimate ............................................ 15 Table 8: Clines Corners 345 kV Station Expansion Detail Cost Estimate .................................................... 17 Table 9: Relay Upgrades at BA Switching Station Detail Cost Estimate ...................................................... 19 Table 10: Relay upgrade at Norton Switching Station Detail Cost Estimate............................................... 20
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
1
1. Executive Summary Public Service Company of New Mexico (“PNM”) performed this Transmission Service Facilities Study
(“Study Report”) based on results from a completed System Impact Study (“SIS”) for the Second BA –
Clines Corners 345 kV line dated May 20171 in response to a 262 MW Transmission Service request by
Transmission Customer. The purpose of this Study Report is to provide cost and construction schedule
estimates for facilities needed to fulfil the Transmission Customer 262 MW Transmission Service
Request for the transfer of energy at Clines Corner 345 kV (Point of Receipt) to Four Corners 345 kV
(Point of Delivery). The Study Report is being developed in accordance with the Transmission Facilities
Study Agreement executed in June 1, 20171. The project timeline is based on complete energization by
the end of November 2020, this is contingent on the date the Transmission Customer provides PNM an
executed Transmission Service Agreement and associated security.
In order to provide the Transmission Service for the Transmission Customer, the following transmission
system reinforcements will be required.
• Build 42 miles of 345 kV transmission line paralleling the existing BA – Clines Corners line that
extends between the Clines Corners 345 kV station (“Clines Corners”) and the proposed
Diamond Tail 345 kV switching station (“Diamond Tail”) eight and a half miles east of the
existing BA 345 kV switching station (“BA Station”).
• Loop in the existing BA – Clines Corners and the BA – Norton 345 kV lines into the Diamond Tail
switching station.
• Build 2.5 miles of double circuit 345 kV transmission line from BA – Norton 345 line into
Diamond Tail switching station
• Build Diamond Tail 345 kV switching station consisting of eight breakers in a breaker-and-half
station configuration
• Expand Clines Corners 345 kV switching station by three breakers and convert it from a ring-bus
to a breaker-and-half station configuration
• Expand Eastern New Mexico RAS and relay upgrades at Norton and BA 345 kV switching
stations
The total estimated cost of the facilities in 2017 dollars required to provide the Transmission Service is $85,000,907. 1 http://www.oatioasis.com/pnm/index.html
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
2
Figure 1 shows the project and its general location on the transmission system.
Figure 1 —General location and surrounding transmission of Second BA – Clines Corners 345 kV line This Study Report provides a list of required system improvements as well as the associated cost and
construction schedule estimates. Section 2 of this Study Report explains the need and scope of the
system improvements. Cost and construction time estimates are summarized in Section 3 of this Study
Report. Appendix A contains additional cost details. Similarly, the detailed switching station electrical
plan layout and one line diagrams are provided in Appendix B.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
3
2. Required Network Upgrades The following transmission system reinforcements were identified in the SIS:
• Build 42 miles of 345 kV transmission line paralleling the existing BA – Clines Corners line that
extends between the Clines Corners 345 kV station (“Clines Corners”) and the proposed
Diamond Tail 345 kV switching station (“Diamond Tail”) eight and a half miles east of the
existing BA 345 kV switching station (“BA Station”).
• Loop in the existing BA – Clines Corners and the BA – Norton 345 kV lines into the Diamond Tail
switching station.
• Build 2.5 miles of double circuit 345 kV transmission line from BA – Norton 345 line into
Diamond Tail switching station
• Build Diamond Tail 345 kV switching station consisting of eight breakers in a breaker-and-half
station configuration
• Expand Clines Corners 345 kV switching station by three breakers and convert it from a ring-bus
to a breaker-and-half station configuration
• Expand Eastern New Mexico RAS and relay upgrades at Norton and BA 345 kV switching
stations
Figure 2 shows the project and nearby transmission system.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
4
Guadalupe 345 Taiban Mesa345 kV
Clines C
orners 345 kV
42 Miles
70 Miles
BA 345 kV
svc
Black Water 345 kV
Rio Puerco 345 kV
To 115 kVSystem
To Four Corners
To San Juan To W
est Mesa
44 miles
8.5 Miles
62 Miles
Blackwater Converter
Norton 345 kV bus
+250/-100 MVAR
40 Miles
Aragonne Mesa 90 MW
Tiaban Mesa 200 MW
34 miles
20.38 miles
Diam
ond Tail 345 kV Bus
El Cabo
El Cabo 345 kV
Broadview 34.5 kV Bus
34.5 kV/345 kV transformer
Broadview 345 kV Bus
Broadview 497 MW
DSTATCOM
Aragonne 138 kV Bus 3
Aragonne 138/345 kV transformer
Aragonne 34.5kV/138 kV transformer
Aragonne 34.5 kV Bus 2
Aragonne 138 kV Bus 4
2.5 mile double circuit for BA-Norton loop -in to
Diamond Tail
42 Miles
16 miles
La Joya200 MW Wind
Lucia202 MW Wind
15 miles
18 miles
Torrance 345 kV
Existing Facilities
New Facilities
New Customer Facilities
Figure 2 —Transmission Interconnection Project and nearby PNM Transmission System
2.1 New 42 mile 345 kV line from Diamond Tail to Clines Corners The SIS identified the need to build a 42 mile Clines Corners to Diamond Tail 345 kV line in parallel to the
existing BA – Clines Corners 345 kV line. The addition of the new line allows PNM to accommodate the
incremental firm capacity of 262 MW from the Clines Corners area.
2.2 Existing BA – Clines Corners and BA – Norton 345 kV Line loop in into Diamond Tail Switching Station
The SIS identified the need to loop the BA – Norton 345 kV line into the Diamond Tail switching station
to complete the new BA – Clines Corners 345 kV line path parallel to the existing 345 kV line to achieve
the same rating on the existing line. The existing BA – Clines Corners 345 kV line will also be tapped into
Diamond Tail.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
5
2.3 New 2.5 mile double circuit 345 kV line from BA – Norton 345 kV transmission line
The looping in of the existing BA – Norton 345 kV line into Diamond Tail requires building 2.5 miles of
double circuit 345 kV transmission line from BA to Norton 345 kV line into Diamond Tail switching
station.
2.4 Diamond Tail Switching Station The SIS identified the need for a new Diamond Tail switching station located 8.5 miles east of BA
switching station. Per PNM’s Breaker Configuration Policy, installation of a new five position breaker and
a half 345 kV station configuration is required. Figure 3 shows the layout of the new switching station.
Diamond Tail Switching Station
New Facilities
Figure 3 - Diamond Tail Switching Station Layout
2.5 Clines Corners Switching Station Expansion The SIS identified the need for the expansion of Clines Corners to accommodate the second 345 kV line
and to loop in the existing BA – Clines Corners 345 kV line at Diamond Tail. This involves conversion of
the existing Clines Corners three position ring bus configuration to a four position breaker and a half
configuration per PNM’s breaker configuration policy. Figure 4 shows the breaker and a half
configuration of Clines Corners.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
6
B
B
B
B
B B
BGuadalupe
To El Cabo (Torrance)
Diamond Tail (Previously BA)
Diamond Tail
Clines Corners Switching Station Expansion
New Facilities
Existing Facilities
New Customer Facilites
Figure 4 - Clines Corners Switching Station Expansion
2.6 Expansion of Eastern New Mexico RAS and relay upgrades at Norton and BA 345 kV stations
As per the results of the SIS, expansion of the Eastern New Mexico RAS would be required to mitigate
overloads during some critical contingencies. The recommended Eastern New Mexico RAS would cover
the following system conditions/contingencies and the appropriate actions that would be taken when
the Second BA – Clines Corners 345 kV line is in service.
Table 1: List of contingencies and corresponding proposed action from remedial action scheme Contingency Type
Contingency Action from Remedial Action Scheme
N-1 Loss of either Diamond Tail to Clines Corners 345 kV line and the total power flow into BA switching station greater than 1000 MW
Trip a portion of Transmission Customer generation at Lucia and La Joya
N-2 Loss of both BA to Diamond Tail 345 kV lines and the power flow into BA switching station greater than 450 MW
Transfer trip the Taiban to Blackwater 345 kV (TB) line and Avangrid at Clines Corners
Loss of both BA to Rio Puerco 345 kV Lines and the power flow into BA switching station is greater than 750 MW
Transfer trip the Taiban to Blackwater 345 kV (TB) line and Transmission Customer generation tie line at Clines Corners
Loss of BA to Diamond Tail and Norton to Diamond Tail 345 kV lines and power flow into BA switching station greater than 1000 MW
Transfer trip Taiban to Blackwater 345 kV line
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
7
Looping in the existing Norton – BA 345 kV line into the Diamond Tail switching station will require line relay upgrades at both Norton and BA Switching Stations.
3. Summary of Cost Estimate and Work Schedule The total cost and construction schedule estimates are shown below in Table 2. Construction schedule estimates are from the date the Transmission Customer provides written authorization to proceed, provided all agreements and funding arrangements are in place.
It is likely that PNM will incur outage costs during the construction of the identified system reinforcements. The cost of construction outages cannot be estimated at this time. However, in accordance with applicable Federal Energy Regulatory Commission Policy, PNM reserves the right to recover such costs from the Transmission Customer.
Additional Cost Estimate details are contained in Appendix A.
Table 2: Second BA -Clines Corners 345 kV Line and Network upgrade Cost Estimate Summary of Cost and Construction Schedule Transmission Network Upgrade Cost ($M) Construction Time New 42 mile 345 kV Line from Diamond Tail – Clines Corners
$44.737 40 months
Looping the Norton – BA 345 kV line into Diamond Tail including new 2.5 mile 345 kV transmission line
$6.731 40 months
Diamond Tail switching station including Eastern NM RAS
$26.305 40 months
Clines Corners station expansion $6.305 22 months Relay upgrade at BA 345 kV Switching Station, testing and commissioning
$0.462 3 months
Relay upgrade at Norton 345 kV Switching Station, testing and commissioning
$0.462
Retirement - 1 month Total $85.001 41 months
Projects will proceed concurrently. The following general assumptions apply to all PNM Cost Estimates and schedule:
The Cost Estimates and schedule submitted in this Facility Study report are based on the following assumptions:
1. Reasonable system outages can be obtained in the fall of 2020 to test and commission the new system additions.
2. State and local permitting processes are timely with favorable outcomes within acceptable timeframes.
3. Environmental studies result with limited findings that can be reasonably mitigated. National Environmental Policy Act (NEPA) evaluation will not be required.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
8
4. Site engineering studies such as geotechnical and soil resistivity have not been conducted for these estimates but the costs of these studies are very low.
5. Land owners are willing to negotiate with PNM for the station site. 6. Allowance for Funds Used During Construction (AFUDC) is included at a rate of 4.33% of
total costs. AFUDC is based on current projected rates for the 2019-2020 time frame and the estimated project spent by month over the same two years.
7. Estimates include project management, land rights acquisition, public outreach and permitting, environmental studies, design, materials and equipment, site and access development, construction, testing and commissioning, construction management, 10% contingency and utility loads and New Mexico Gross Receipt Tax.
Appendix A contains Cost Estimate details as well as specific assumptions used in preparing the Cost Estimate.
Major activities are presented in the construction schedule estimate in Table 3 below. The schedule is
representative of typical project timelines and activities.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
9
Notes and Assumptions:
1) The project timeline is based on complete energization of all the above projects by the end of November 2020. 2) The issuance of a certificate of public convenience and necessity (“CCN”) is a minimum 9 month process with a likely result in a 6 month
extension for a total of 15 months. The CCN requires outreach and local permitting activities be complete or nearly complete at the time of CCN application.
Table 3: Second BA - Clines Corners 345 kV Line Construction Schedule
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
10
3) Due to length of the CCN review, the transmission line design will occur concurrently with the later months of the CCN approval process. . This will allow exercising of land options, site developments, and materials orders to start immediately upon issuance of the CCN.
4) Based on current lead times, some key equipment and materials’ orders will need to be placed one to three months before an issuance of the CCN to allow sufficient time for delivery and construction.
5) The transmission line cut-ins and energizations of the station improvements will need to be staged to avoid concurrent facility outages.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
11
Appendix A: Cost Estimate Detail Table 4: Detailed total Cost Estimate of Second BA - Clines Corners 345 kV Line and Network Upgrade
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
12
Table 5: New 345 kV Line from Diamond Tail to Clines Corners Detail Cost Estimate
Notes and Assumptions:
1) Routing is based on using the existing utility corridor established by the Clines Corner-BA 345kV line. A new 150 foot wide transmission easement adjacent to the existing Clines Corner-BA 345kV line will be required for the length of the new line with the transmission structures placed on the centerline.
2) For estimating purposes, a 345kV H-frame steel pole design was selected for tangent structures.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
13
3) Three-pole guyed structures are used for angles and dead-ends. 4) The conductor is twin-bundle ACSR 795 MCM 26/7 “Drake”. 5) There are two shield wires on the new line which are OPGW. The two OPGW cables coming
from Clines Corners are the two sources of communication to Diamond Tail. 6) Pricing for this project is based on a traditional design build approach. 7) The cited costs include looping the existing Clines Corner-BA 345 kV line into the new
Diamond Tail station and retirement of a short section of this line. 8) The approximate location of the transmission line is shown in Figure 1.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
14
Notes and Assumptions:
1) The routing of the new line is generally parallel to PNM’s existing Clines Corner-BA 345kV line. 2) A new adjacent 150 foot wide transmission easement will be required for the length of this
double circuit line with the transmission structures placed on the centerline. 3) For estimating purposes, a 345kV double circuit single steel pole design was selected for tangent
structures and multi-pole guyed structures were used for angles and dead-ends. 4) The conductor is twin-bundle ACSR 795 MCM 26/7 “Drake”. 5) The shield wire is OPGW. 6) This loop effectively splits the Norton-BA 345kV line into two circuits; a) Norton to Diamond Tail,
and b) Diamond Tail to BA.
Table 6: Norton - BA 345 kV Line Loop in into Diamond Tail Detail Cost Estimate
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
15
7) Pricing for this project is based on a traditional design build approach. Table 7: Diamond Tail Switching Station including RAS Detail Cost Estimate
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
16
Notes and Assumptions:
1) Approximately 40 acres of land will need to be purchased and access rights acquired. 2) An estimated site location was chosen for purposes of the Cost Estimate. The final selected
location may vary. 3) The station will be built to similar design standards as the existing Clines Corners station. 4) Major equipment includes eight (8) 345 kV circuit breakers, twenty-two (22) 345 kV
disconnect switches, control house and sixteen (16) control panels, and numerous instrument transformers.
5) Communications pricing is based on using by fiber optic ground wires (OPGW) installed on the new transmission line from the Clines Corners station.
6) Station service is provided from two (2) 345 kV Station Service Voltage Transformers (SSVT) with a generator back-up.
7) The estimate also includes costs for the expansion of eastern New Mexico RAS. 8) Pricing for this project is based on an Engineering, Procure, and Construct (EPC) approach
with certain larger equipment purchased directly by PNM. 9) The one-line for this station is shown in Figure 5. The layout used for estimating purposes is
presented in Figure 6.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
17
Notes and Assumptions:
1) The existing yard and control house are sized to accommodate this expansion. 2) Major equipment includes the addition of four (4) 345 kV circuit breakers, six (6) 345kV
disconnect switches, seven (7) control panels and six (6) 345kV Capacitive Voltage Transformers.
Table 8: Clines Corners 345 kV Station Expansion Detail Cost Estimate
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
18
3) Pricing for this project is based on an Engineering, Procure, and Construct (EPC) approach with certain larger equipment purchased directly by PNM.
4) The draft one-line for this station is shown as Figure 7. The layout used for estimating purposes is presented in Figure 8.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
19
Table 9: Relay Upgrades at BA Switching Station Detail Cost Estimate
Notes and Assumptions:
1) Presented costs are based on outside service contract for construction.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
20
Table 10: Relay upgrade at Norton Switching Station Detail Cost Estimate
Notes and Assumptions:
1) Presented costs are based on outside service contract for construction.
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
21
Appendix B: Detailed Switching Station layout and one line diagrams
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
22
Figure 5 - One Line Diagram of Diamond Tail Switching Station
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
23
Figure 6 - Electrical Plan Layout of Diamond Tail 345 kV Switching Station
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
24
Figure 7 - One Line Diagram of Clines Corners 345 kV Switching Station
Transmission Service Facilities Study for the Second BA – Clines Corners 345 kV Line
25
Figure 8 - Electrical Plan Layout of Clines Corners 345 kV Switching Station