PROJECT DESCRIPTIONCLA-SR 235-00.23
PID 94632
The Ohio Department of Transportation proposes to undertake safety improvements on StateRoute 235, from Dalton Drive to Dille Road, in Bethel Township, Clark County. State Route235 is an Urban Arterial carrying approximately 11,660 vehicles per day (2012).
Project History:
In 2011, the project corridor was identified as a Local Safety Hotspot for Clark County. TheState Route 235 intersections with Styer Drive and Hocker Avenue were ranked #2 and #6 on therural hot spot list, respectively.
In 2012, a Corridor Management Study (CMS) was completed for the corridor on behalf of theSpringfield-Clark County Transportation Coordinating Committee, the local MetropolitanPlanning Agency.
The CMS identified a total of 117 crashes (87 intersection related and 30 segment related) withinthe four-year study period (2007-2010). Of those, 65% were rear–end or angle-type crashes.Injuries were reported for 32% of the accidents. A total of six fatalities were reported, three ofwhich were pedestrians attempting to cross SR 235; a seventh pedestrian fatality occurred in2012. The corridor has a crash rate of 1.96 crashes per million vehicle miles travelled, higherthan the state average of 1.09 for two-lane urban collectors.
A total of 57 driveways were identified with the corridor studied in the CMS. These drives are,on average, 200 feet apart; this is less than the recommended minimum 360 foot spacing forcorridors posted at 45 mph.
[It should be noted that the CMS did not identify a level of service (LOS) issue within thecorridor. All intersections are operating at LOS C or better during peak hours, with mostoperating at LOS A or B. At LOS C, vehicles experience a delay of 16 to 25 seconds atunsignalized intersections and 21 to 35 seconds at signalized intersections.]
As part of the Corridor Management Study, various alternatives were presented to the public attwo public meetings. The final recommendations of the CMS reflected public input. Thefollowing improvements were recommended by the CMS:
Undertake access management improvements by consolidating drives on the west side ofSR 235.
Construct two mid-block pedestrian crossings, with raised medians within the center leftturn lane, to allow for a two-stage crossing.
Construct a sidewalk along the west side of SR 235, between Dille Road and DaltonDrive.
Construct a multi-use path on the east side of SR 235, between Dille Road and Dalton
Drive. Reconstruct traffic signal at Styer Drive intersection, with full pedestrian features,
including countdown pedestrian signal heads. Install corridor roadway lighting from Dille Road to Gerlaugh Road. Consolidate the McAdams Drive access point, by converting its intersections at Styer
Road (north and south) and Hocker Avenue (north) to cul-de-sacs. Replace the twodriveways on McAdams between Hocker Avenue and Styer Drive with a single accesspoint.
Remove the Hocker Avenue access to SR 235, by consolidating it with McAdams Drive.
In October 2012, a project was programmed to implement safety improvements based on therecommendations of the 2012 Corridor Management Study.
Purpose & Need:
The purpose of the project is to maintain the project corridor as a safe and effective componentof the transportation system for all users, by addressing conditions within the corridor that areresulting in a high number of crashes, including crashes involving pedestrians.
In order to meet the purpose of the project, it is necessary to address the following conditions:
Inadequate pedestrian facilities within the corridor, including a lack of pedestriancrossings.
Inadequate access management, particularly substandard drive spacing, resulting in ahigh number of conflict points within the corridor.
Goal of the Project:
A goal of the project is to avoid improvements that will unduly restrict access to area businessesand other properties.
Project Description:
The project will include the following improvements:
Provide a sidewalk on the west side of SR 235, from Dalton Drive to Dille Road. Provide a multi-use trail on the east side of SR 235, from Hocker Avenue to Dille Road. Provide pedestrian mid-block crossings with a raised median in the center left turn lane in
the vicinity of 2131 S. Dayton-Lakeview road and 1651 S. Dayton-Lakeview Road. Provide a new public road (“backage road”) west of SR 235, between North Business
Way and the public access drive located between 2133 & 2135 S. Dayton-LakeviewDrive.
Undertake access management throughout the corridor, including:o Close the existing commercial drive at 2432 Dayton-Lakeview Road and create a
new drive connection to Dalton Avenue.o Extend Dalton Avenue west of SR 235 and provide drive connections to 2357 &
2350 S. Dayton-Lakeview Road. Remove the existing driveway connections to
SR 235 for those properties.o Consolidate the multiple driveway connections to SR 235 to single SR 235 access
points at the following properties: 1625, 1651, 1640, 1866, 1951, 2131, and 2353S. Dayton-Lakeview Road. driveways 2353 S. Dayton-Lakeview Road.
o Convert the SR 235 access points at the following properties to right in/right out:1525, 1625,and 2135 S. Dayton-Lakeview Road and the public access roadbetween 2133 & 2135 S. Dayton-Lakeview Road.
o Close Hocker Avenue at SR 235, while maintain the intersection of HockerAvenue and McAdams Drive.
o Close McAdams Drive at Styer Drive McAdams Drive access to SR 235 will beretained through the consolidated drive at 1640 S. Dayton-Lakeview Road (south)and its intersection with Dale Ridge Road (north).
The project is expected to require 0.4-acre of permanent right-of-way, most for construction ofthe “backage road”and 2.2 acres of temporary right-of-way.
The corridor generally developed in the 1960s as an auto-dependent commercial corridor.Within the corridor, there are no National Historic Landmarks, sites listed or known eligible forthe National Register of Historic Places, or sites for which Ohio Historic/Archaeological inventoryforms have been completed.
Vegetation within the corridor is generally limited to mown right-of-way. Two trees will need tobe removed for the extension of Dalton Drive. These trees do not offer roost habitat for theIndiana bat or northern long-eared bat. There are no waterways or wetlands within the corridor.
The project is being undertaken with federal and state Safety funds. Environmental clearance isscheduled for 12-15-2014. The anticipated award date is April 2016.
CLA-SR 235-0023PID 94632
New Carlisle, Ohio Quadrangle
0 1000 2000 3000 4000
Feet
0 250 500 750 1000
Feet
CLA-SR 235-0023PID 94632
N
6
3
CL
A-235-0.2
3P
LA
N - S
R
235
ST
A.
32
+50
TO
ST
A.
45
+0
0
c:\
pw
workin
g\
pitt\
d07
5834
8\
94
632
GP003.d
gn 2/7/2014 3:5
5:1
6
PM alitt
man
HO
RIZ
ON
TA
L
SC
AL
E IN F
EE
T
050
25
100
CA
LC
UL
AT
ED
CH
EC
KE
D
PE-R/W
MA
TC
H LIN
E S
TA. 32+50
MA
TC
H LIN
E S
TA. 45+00
MID-BLOCK PED
33 34 35 36 37 38 39 40 41 42 43 44 45
S3022
860.331 P
1= 0-24-
RC
P-
N
S3023
868.12
3P1= 0-15
X24-
CM
P-
N
HO
CK
ER
AV
E
DA
LT
ON
AV
E
McADAMS DR
12"
8"
2524 S DAYTON-LAKEVIEW RD
MULLINS CLEO
2478 DAYTON LAKEVIEW RD
GREENE ABRAHAM L & HELEN
2550 S DAYTON-LAKEVIEW RD
CHURCH METHODIST MEDWAY UNITED
2357 S DAYTON-LAKEVIEW RD
ECLIPTIX NETWORK SOLUTIONS INC
2131 S DAYTON-LAKEVIEW RD
CLOSEY DAVID M TRUSTEE
548 MC ADAMS DR
J O M I HOLDINGS LLC
570 MC ADAMS DR
NEW CARLISLE ASSOCIATES LLC
LAKEVIEW RD
2432 S DAYTON-
K O I INC
LAKEVIEW RD
2353 S DAYTON-
COMPANY LLC
KOZAP REALTY
LAKEVIEW RD
2350 S DAYTON-
OF NEW CARLISLE
MEL-O-DEE RESTAURANT 564 MC ADAMS DR
LAYNE LTD
ASSOCIATES PARK
NEW CARLISLE
LEGEND
ACCESS/PAVEMENT REMOVED
PROPOSED PAVEMENT
CONSTRUCTION LIMITS
PROPOSED STORM SEWER
BUFFER
SIDEWALK/MULTI-USE PATH
PROPOSED R/W
N
6
4C
CL
A-235-0.2
3P
LA
N - S
R
235
AL
TE
RN
ATIV
E
C
ST
A.
45
+00
TO
ST
A.
58
+00
c:\
pw
workin
g\
pitt\
d07
5834
8\
94
632
GP004.d
gn 2/7/2014 3:5
5:1
9
PM alitt
man
HO
RIZ
ON
TA
L
SC
AL
E IN F
EE
T
050
25
100
CA
LC
UL
AT
ED
CH
EC
KE
D
PE-R/W
MA
TC
H LIN
E S
TA. 45+00
MA
TC
H LIN
E S
TA. 58+00
45 46 47 48 49 50 51 52 53 54 55 56 57 58
S3069
913.249P1= 0-15-
RC
P-
N
914.875
ST
YE
R
DR
N. B
USIN
ESS
WA
Y
McADAMS DR
ADAMS DR
730 MC-
ENID B
JERRY M &
FERGUSON
2135 S DAYTON-LAKEVIEW RD
MARTIN CORNELIUS A
PROPOSED FAMILY DOLLAR
640 S DAYTON-LAKEVIEW RD
NEW CARLISLE ASSOCIATES LLC
2133 S DAYTON-LAKEVIEW RD
MC DONALDS CORPORATION
2035 DAYTON LAKEVIEW RD
AND TRUST COMPANY
SECURITY NATIONAL BANK
680 MC ADAMS DR
GILLIAM DONALD L
1951 S DAYTON-LAKEVIEW RD
BANE SAUNDRA S
1824 STYER DR
LINDA S
CRAINE DANIEL E &
1810 STYER DR
MARJORIE J
DWAYNE &
GEORGE ANTHONY
ADAMS DR
738 MC-
PATRICIA A
CHARLES D &
BORDEN
ADAMS DR
804 MC-
JOSEPH
MC DOWELL
ADAMS DR
810 MC-
CAROLYN D
NELSON
ADAMS DR
818 MC-
PARK
GOOD SHEPHERD
METHODIST
CHURCH
ADAMS DR
824 MC-
KIMBERLY G
SAMMY L &
SUMNER
RIDGE RD
1815 DALE
SHARON T
NEAL L &
ZIMMERMAN
LAKEVIEW RD
1775 S DAYTON-
PROPERTIES INC
ROBINSON CARR
ADAMS DR
834 MC-
SR & DAWN
RANDY A
SINCLAIR
DR
BELLOWS
835
KEVIN
SEALS
LAKEVIEW RD
2015 DAYTON-
LLC
YOGI NARAYAN
BUSINESS WY
STRUEWING JAMES L
1900 BUSINESS WAY
STANKIEWICZ ENTERPRISESBUSINESS WAY
STRUEWING JAMES L
LAKEVIEW RD
1866 S DAYTON-
CHURCH
HUBER MENNONITE
LEGEND
ACCESS/PAVEMENT REMOVED
PROPOSED PAVEMENT
CONSTRUCTION LIMITS
PROPOSED STORM SEWER
BUFFER
SIDEWALK/MULTI-USE PATH
PROPOSED R/W
1897 BUSINESS WAY
FERRALLGAS LP
N
6
5
CL
A-235-0.2
3P
LA
N - S
R
235
ST
A.
58
+00
TO
ST
A.
71+00
c:\
pw
workin
g\
pitt\
d07
5834
8\
94
632
GP005.d
gn 2/7/2014 3:5
5:2
2
PM alitt
man
HO
RIZ
ON
TA
L
SC
AL
E IN F
EE
T
050
25
100
CA
LC
UL
AT
ED
CH
EC
KE
D
PE-R/W
MA
TC
H LIN
E S
TA. 58+00
MA
TC
H LIN
E S
TA. 71+
00
MID-BLOCK PED
58 59 60 61 62 63 64 65 66 67 68 69 70 71
S3024
931.
202P1= 0-18-
CP
P-S
W
S3025
933.264P1= 0-12-
CP
P-
NW
S3070
914.875P1= 0-15-
RC
P-S
S3071
919.648P1= 0-15-
RC
P-
N
HA
RT
LE
Y
AV
E
DA
LE RID
GE R
D
McADAMS DRMcADAMS DR
HA
RT
LE
Y
AV
E
LAKEVIEW RD
1775 S DAYTON-
PROPERTIES INC
ROBINSON CARR
ADAMS DR
834 MC-
SR & DAWN
RANDY A
SINCLAIR
DR
BELLOWS
835
KEVIN
SEALS
RIDGE RD
1815 DALE
SHARON T
NEAL L &
ZIMMERMAN
1701 DAYTON LAKEVIEW RD
GILLIAM ROSA L 1651 S DAYTON-LAKEVIEW RD
GILLIAM ROSA L
1625 DAYTON LAKEVIEW RD
SPEEDWAY SUPERAMERICA LLC 1525 S DAYTON-LAKEVIEW RD
SURE FIRE INVESTMENTS LTD
850 MC ADAMS DR
POFFENBERGER BLAINE R
1814 DALE RIDGE RD
& ELETA
WILLIAMS CHALMER S
ADAMS DR
860 MC-
CASEY L
LESLIE
ADAMS DR
868 MC-
SUSAN K
CASTLE
ADAMS DR
874 MC-
RANDALL A
WARD
ADAMS DR
904 MC-
PATRICIA G
DANIEL K &
HATMAKER
ADAMS DR
910 MC-
KEITH J
STORMS
922 MC ADAMS DR
KIMBERLY A
POTTER JAMES E &
1815 HARTLEY AVE
LINDLEY SHIRLEY A
1808 HARTLEY AVE
MATTINGLY MELODY A
1822 HARTLEY AVE
ALICE M
PRICE ROY L &
1950-1954 HARTLEY AV
HOUSING
SPRINGFIELD METROPOLITAN
1958-1960 HARTLEY AV
HOUSING
SPRINGFIELD METROPOLITAN
LAKEVIEW RD
1321-1323 S DAYTON-
GREASE MAGIC LTD
12355 DILLEY RD
BOARD OF EDUCATION OF TECUMSEH LOCAL
LEGEND
ACCESS/PAVEMENT REMOVED
PROPOSED PAVEMENT
CONSTRUCTION LIMITS
PROPOSED STORM SEWER
BUFFER
SIDEWALK/MULTI-USE PATH
PROPOSED R/W
N
6
6
CL
A-235-0.2
3P
LA
N - S
R
235
ST
A.
71+00
TO
ST
A.
85
+00
c:\
pw
workin
g\
pitt\
d07
5834
8\
94
632
GP006.d
gn 2/7/2014 3:5
5:2
5
PM alitt
man
HO
RIZ
ON
TA
L
SC
AL
E IN F
EE
T
050
25
100
CA
LC
UL
AT
ED
CH
EC
KE
D
PE-R/W
MA
TC
H LIN
E S
TA. 71+
00
71 72 73 74 75 76 77 78 7980
81
82
83
84
85
S3028
938.359P1= 0-12-
RC
P-
N
S3029
938.391 P
1= 0-12-
RC
P-S
S3030
937.649P1= 0-12-
RC
P-
N
S3031
937.118
P1= 0-12-
RC
P-S
S3032
935.344P1= 0-15-
RC
P-E
S3033
935.739P1= 0-12-
RC
P-
N
S3037
934.383P1= 0-15-
RC
P-
W
S3035
931.
864P1= 0-18
X30-
RC
P-S
S3036
932.986P1= 0-18
X30-
RC
P-
N
DIL
LE R
D
BELLEFO
NTAIN
E RD
V5-V6
LAKEVIEW RD
1321-1323 S DAYTON-
GREASE MAGIC LTD
12355 DILLEY RD
BOARD OF EDUCATION OF TECUMSEH LOCAL
1159 S DAYTON-LAKEVIEW RD
LONGSHORE H RICHARD & BRENDA A TRUSTEES
971 BELLEFONTAINE RD
GRAY WAYNE A & DEBORAH J
LAKEVIEW RD
1033 DAYTON-
& BRENDA A TRUSTEES
LONGSHORE H RICHARD
1033 S DAYTON-LAKEVIEW RD
BRENDA A TRUSTEES
LONGSHORE H RICHARD &
957 S DAYTON-LAKEVIEW RD
TURNER JAMES G
AVAILABLE
NO OWNER INFORMATION
LEGEND
ACCESS/PAVEMENT REMOVED
PROPOSED PAVEMENT
CONSTRUCTION LIMITS
PROPOSED STORM SEWER
BUFFER
SIDEWALK/MULTI-USE PATH
PROPOSED R/W