25
Doornvallei Ext 5 Services Report 1 CIVIL ENGINEERING SERVICES REPORT (WATER AND SANITATION) DOORNVALLEI EXT 5 August 2015 Revision 0 PREPARED FOR: PREPARED BY: CITY OF TSHWANE: SERVICES INFRASTRUCTURE DEPARTMENT WATER & SANITATION DIVISION ROOM B615, CAPITOL TOWERS NORTH 225 MADIBA STREET, PRETORIA, 0001 CONTACT: MR STEVENS NOTOANE TEL: (012) 358 3773 FAX: (012) 358 3991 LV & PARTNERS OFFICE 10, 3 RD FLOOR 476 KINGS HIGHWAY LYNNWOOD, 0081 CONTACT: MR PIETER LINDEQUE TEL: (012) 664 6490 FAX: (012) 349 8256

CIVIL ENGINEERING SERVICES REPORT (WATER AND …nalisustainabilitysolutions.co.za/wp-content/uploads/2015/02/... · CIVIL ENGINEERING SERVICES REPORT (WATER AND SANITATION) DOORNVALLEI

  • Upload
    lamdieu

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

Doornvallei Ext 5

Services Report

1

CIVIL ENGINEERING SERVICES REPORT

(WATER AND SANITATION)

DOORNVALLEI EXT 5

August 2015

Revision 0

PREPARED FOR: PREPARED BY:

CITY OF TSHWANE: SERVICES

INFRASTRUCTURE DEPARTMENT

WATER & SANITATION DIVISION

ROOM B615, CAPITOL TOWERS NORTH

225 MADIBA STREET, PRETORIA, 0001

CONTACT: MR STEVENS NOTOANE

TEL: (012) 358 3773

FAX: (012) 358 3991

LV & PARTNERS

OFFICE 10, 3RD FLOOR

476 KINGS HIGHWAY

LYNNWOOD, 0081

CONTACT: MR PIETER LINDEQUE

TEL: (012) 664 6490

FAX: (012) 349 8256

Doornvallei Ext 5

Services Report

2

TABLE OF CONTENTS

CONTENTS PAGE

1. GENERAL INFORMATION 3

1.1 Introduction 3

1.2 Site description 4

1.3 Registered land owner 6

1.4 Township establishment conditions 6

1.5 Land use 6

2. WATER SUPPLY SCHEME 8

2.1 Existing infrastructure 8

2.2 Water design criteria 8

2.3 Water demand calculations 10

2.4 Proposed new infrastructure 11

2.5 Servitudes required 12

2.6 Construction cost estimate 12

2.7 Contributions for water 12

3. SEWER DRAINAGE SCHEME 13

3.1 Existing infrastructure 13

3.2 Sewer design criteria 13

3.3 Sewer outflow calculations 17

3.4 Proposed new infrastructure 18

3.5 Servitudes required 19

3.6 Construction cost estimate 19

3.7 Contributions for sewer 19

3.8 Solid waste management 19

APPENDICES

APPENDIX 1: LOCALITY PLAN

APPENDIX 2: TOWN PLANNER’S LAYOUT

APPENDIX 3: PROOF OF OWNERSHIP

APPENDIX 4: TOWNSHIP ESTABLISHMENT CONDITIONS

APPENDIX 5: GLS REPORT

APPENDIX 6: APPLICATION FOR RAND WATER CONNETION

APPENDIX 7: DRAWINGS

Doornvallei Ext 5

Services Report

3

1. GENERAL INFORMATION

1.1 INTRODUCTION

This development is envisaged on portion 107 of the farm Doornkloof 391 – JR.

LV & Partners Consulting Civil Engineers were appointed by M-T Development

(Pty) Ltd per letter dated 25 February 2008 to investigate bulk water and

sanitation infrastructure options and to compile a civil engineering services report

for the proposed development.

The purpose of this report is to verify and confirm the requirements and design

criteria of the Water and Sanitation Division of the Services Infrastructure

Department of the City of Tshwane. It also aims at facilitating the compilation of a

Services Agreement between the Developer and the Local Authority. The report

will enable the reader to determine the level and extent of municipal engineering

services to be provided, the preferred bulk infrastructure options, as well as the

associated estimated costs.

The locality plan and town planner’s layout are appended to this report as

Appendixes 1 and 2 respectively.

Doornvallei Ext 5

Services Report

4

1.2 SITE DESCRIPTION

1.2.1 SITE LOCATION

The development falls inside the jurisdiction of the City of Tshwane. The site is

situated west of the R21 highway and south of the Hennops River (directly south

of the Irene Glen Estate). The site is 6.6479 hectares in size.

1.2.2 TOPOGRAPHY AND DRAINAGE

The site is located between 1517 masl and 1495 masl. The site slopes down in

an eastern direction initially and eventually northwards towards the Hennops

River. A watershed line is present on the western side. Drainage is in the form of

sheetflow or overland flow initially and becomes concentrated on the eastern

side.

1.2.3 FLORA

At present the site is undeveloped and covered by natural grass with some

indigenous trees present. Red data species are present on the western boundary

of the site.

1.2.4 CLIMATE AND WEATHER CONDITIONS

The site lies within the Highveld climatic region, the climate being described as

warm temperature with summer rainfall. The average daily maximum temperature

is in the order of 28ºC in January and 18ºC in July. The rainy season is from

October to March, with an average rainfall of about 750 mm per annum.

1.2.5 GEOLOGY

The site is underlain mainly by the chert rich dolomite of the eccles Formation of

the Malmani Subgroup of the Chuniespoort Group. The upper materials consist

mainly of chert gravel and in some places shallow dolomite rock is present.

Doornvallei Ext 5

Services Report

5

1.2.6 HYDROLOGY

No development is allowed below the 1:100 year flood line. The flood line study

(done by others) will confirm the position of the 1:100 year flood line.

1.2.7 ACCESS

Access to the site is via the existing road P112-1 (M57), running adjacent to the

site. The proposed access road will be off the existing access road to Irene

Glen Estate as indicated on the drawings attached as Appendix 7.

1.3 REGISTERED LAND OWNER

Refer to appendix 3 for details of the registered land owner.

1.4 TOWNSHIP ESTABLISHMENT CONDITIONS

The approved township establishment conditions are attached to this report as

Appendix 4.

1.5 LAND USE

The land use table for Doornvallei Extension 5 is indicated below:

Land Use – Zoning Erven Units

Residential 2 ( 27 dwelling units / ha) 1 150

Special – For access 1 N/A

Street N/A N/A

Total 2 150

Doornvallei Ext 5

Services Report

6

2. WATER SUPPLY SCHEME

2.1 EXISTING INFRASTRUCTURE

The property to be developed is currently vacant land as can be seen on the

picture on the front page of this report. The only existing water related

infrastructure is the existing Randwater pipeline running past the proposed

development along the existing provincial road P112-1 (M57).

2.2 WATER DESIGN CRITERIA

The following standards will be used in the design of the water reticulation:

• Average annual daily demand (AADD)

− Residential 2 (27 dwelling units/ha) : 0.8 kl/unit

− Gate house for access control : 0.6 kl/unit

− Street : N/A

• Peak hour demand

− Peak hour factor (PHF) : 4.6

− Peak hour demand : PHF x AADD

• System heads

− Maximum static head (no demand) : 90 m

− Minimum residual head under conditions

of peak hour demand at erf boundary

: 24 m

• Fire - fighting

− Fire risk category : Category C (residential)

− Total fire flow : 15 ℓ/s (< 30 units / ha)

− Flow at any one hydrant : 15 ℓ/s (< 30 units / ha)

− Minimum pressure at fire : 8 m (< 30 units / ha)

− Minimum pressure rest of system : 5 m (< 30 units / ha)

− Spacing of fire hydrants : 240 m max (< 30 units / ha)

• Linear pipeline velocity

− Maximum under conditions of peak hour : 1.8 m/s

− Maximum under conditions of fire-fighting : 2.2 m/s

• Dolomite risk category : Medium

Doornvallei Ext 5

Services Report

7

• Pipe material (dolomitic area) for pipes and

fittings > 75 mm Ø

: HDPE PE 100 to SANS ISO

4427

− Minimum pipe class : PN 12 (or higher pressure

class if required)

− Supply lengths : 12 m minimum

− Joints : Butt–welded to SANS 10268

– Part 1 or electro-fusion

welding as per SANS 10268

– Part 2 where butt –

welding is impossible

• Boundary roughness (k-value) : 0.1 mm

• Flow formula : D’Arcy Weissbach

• Depth of cover below final ground level

− On sidewalks : 1.0 m(min) – 1.5 m(max)

− Across streets : 1.0 m(min) – 1.5 m(max)

• Placement of pipes inside 13 m to 25 m road

reserves

: 2.2 m from erf boundary on

high side of road (16 m road

reserves)

: 1.8 m from erf boundary on

high side of road (13 m road

reserves)

• Placement of isolating valves : Opposite splay corner pegs

in networks

: So that not more than 4

valves have to be shut off to

isolate any part of the

network.

• Placement of hydrants : Fire Department to specify

type and placement

: Opposite the communal erf

pegs and between 0.3 m and

0.5 m away from them

: Not closer than one erf

length to any intersection.

Doornvallei Ext 5

Services Report

8

2.3 WATER DEMAND CALCULATIONS

Land Use No of No of Erf size Total Area Total Area % of Density Measuring Unit Water AADD Peak hourly Peak Domestic

Erven Units (m2) (ha) m

2Township (units/ha) unit/day Consumption (kl) (kl/day) factor Consumption (l/s)

Residential 2 1 150 n/a 5.5565 55565 83.58 27 kl per unit 0.8 120.00 4.6 6.39

Special for Access 1 1 n/a 0.457 4570 6.87 n/a kl per unit 0.6 0.60 4.6 0.03

Streets n/a n/a n/a 0.6344 6344 9.54 n/a n/a n/a n/a n/a n/a

Total 2 151 6.6479 66479 100 120.60 6.42

AADD : Average annual daily demand

FIRE FLOW UNDER PEAK DOMESTIC DEMAND CONDITIONS

Min./Max.

Pressure(m)

Peak hour demand - minimum 20 to 24

Static (no demand) - maximum 90Fire flow (@ peak hour demand)

Total Flow at Min. pesssure

Area where fire occurs fire flow hydrant at fire(l/s) (l/s) (m)

Residential 3 15 15 8

16 to 20

Absolute Min./Max.

Flow Condition Pressure(m)

5

120See below

Min. pressure rest

of system(m)

Doornvallei Ext 5

Services Report

9

2.4 PROPOSED NEW INFRASTRUCTURE

Refer to the draft GLS report enclosed in Appendix 5 regarding bulk water supply

options in the area.

The proposed township known as Doornvallei Extension 5 on portion 107 of the Farm

Doornkloof 391-JR will be supplied with potable water from a permanent connection

on the nearby Randwater Pipeline. The future Van Riebeeck High Level Reservoir will

be supplied with potable water from this very same connection.

A pressure boosting pump station and a pressure reducing valve (PRV) station will be

installed at the connection point comprising the following pressures:

• Maximum upstream static head of 135 m

• Minimum upstream dynamic head of 48 m

• Constant downstream PRV pressure setting of 30 m.

The original application for the Rand Water connection is enclosed in Appendix 6. It is

proposed that items VRH.15, VRH.16, VRH.17, VRH.18, BVR.1a and BVR.9 (shown

in red below) be installed under Doornvallei Extension 6 and items 1, 2, 3, BVR.1,

BVR.10, BVR11 and BVR.12 be installed under Doornvallei Extension 5.

2.5 SERVITUDES REQUIRED

A servitude for the installation of a Booster Pump Station and a Pressure Reducing

Valve Station will have to be secured and registered at the Rand Water connection

point. The existing Rand Water and Eskom servitudes will be crossed at the proposed

connection point. A 3m water pipeline servitude will also be required to accommodate

pipe items VRH.15, VRH.16, VRH.17 and VRH.18 as shown in the GLS report.

Doornvallei Ext 5

Services Report

10

2.6 CONSTRUCTION COST ESTIMATE

Description Unit Quantity Rate (R) Amount (R) Totals (R)

Item 1 - Isolating Valve 550mm diameter no 1 R 244,000.00 R 244,000.00

Item 2 - Isolating Valve 550mm diameter no 1 R 244,000.00 R 244,000.00

Item 3 - Isolating Valve 450mm diameter no 1 R 127,000.00 R 127,000.00

Item BVR.1a - RW Connection 5m x 600mm diam m 5 R 285,600.00 R 1,428,000.00

Item BVR.1 - Main Feed Pipe 285m x 600mm diam m 285 R 7,463.72 R 2,127,160.20

Item BVR.9 - PRV 355mm diam no 1 R 387,800.00 R 387,800.00

Item BVR.10 - Main Feed Pipe 15m x 600mm diam m 15 R 47,786.67 R 716,800.05

Item BVR.11 - Head Pump 55m x 245 l/s no 1 R 3,152,100.00 R 3,152,100.00

Item BVR.12 - 450 mm diam Check Valve no 1 R 700,000.00 R 700,000.00

Item VRH.15 - Main Pipe 1065m x 400mm diam m 1,065 R 3,219.87 R 3,429,161.55

Item VRH.16 - Main Pipe 360m x 400mm diam m 360 R 2,853.78 R 1,027,360.80

Item VRH.17 - Main Pipe 305m x 250mm diam m 305 R 1,632.26 R 497,839.30

Item VRH.18 - Main Pipe 495m x 250mm diam no 495 R 1,169.78 R 579,041.10

Total (Excl. P&G, Contingencies, Fees & VAT) R 14,660,263.00 R 14,660,263.00

Plus:

Preliminaries & General @ 15% R 2,199,039.45

Contingencies @ 5% R 733,013.15

Total (Excl. Fees & VAT) R 17,592,315.60

2.7 CONTRIBUTIONS FOR WATER

The unofficial bulk cash contribution for water is R2,931.00/kl/day x 120.60 kl/day =

R353,478.60.

It is proposed that funds invested in external infrastructure be subtracted from bulk

contributions payable.

Doornvallei Ext 5

Services Report

11

3. SEWER DRAINAGE SCHEME

3.1 EXISTING INFRASTRUCTURE

The existing sewer reticulation inside Irene Glen Estate is regarded as sub-

standard. The existing City of Tshwane main outfall sewer runs north of and along

the Hennops river north of the development. An existing weir across the Hennops

river facilitates the connection between the Irene Glen Estate sewer reticulation and

the main outfall sewer pipeline, which drains toward the Sunderland Ridge Waste

Water Treatment Works.

3.2 SEWER DESIGN CRITERIA

The following standards will be used in the design of the sewer reticulation:

• Sewage outflow per day

− Residential 3 (20-40 units/ha) : 0.6 kl/unit

− Gate house for access control : 0.6 kl/unit

− Street : N/A

• Peak factor : 2.5

• Sewer capacity : Pipes shall be designed to run at

70% full, measured in terms of

flow depth

• Provision for stormwater infiltration : The remaining 30%

• Flow formula : Manning with n = 0.013

• Minimum velocities in sewers : 0.75 m/s at full flow with

absolute minimum 0.6 m/s

• Fall through manholes : 80 mm (for sewers ≤ 315 mm Ø)

• Minimum pipe size for reticulation

pipes

: 145 mm Internal diameter

• Sewer erf connections : 110 mm diameter at the lowest

point of each erf in the case of

Res 1 erven and to a distance of

500 mm inside the erf boundary

and not less than 1m from the

side boundary

Doornvallei Ext 5

Services Report

12

• Minimum gradients

Nominal Ø (mm) Minimum grade with

depth of flow = 1/5 D and

V = 0.6 m/s

Minimum grade with

depth of flow = ½ D

and V = 0.82 m/s

160 1/80

(for fewer than 24

dwelling units connected)

1/100

200 1/120 1/200

250 1/160 1/240

315 1/200 1/300

• Depth of sewer

− In mid-blocks : 1.2 m depth to invert

− In street reserves : 1.5 m depth to invert

• Sewer system in mid-blocks or street

reserves

: Mid-block system acceptable if

sewers are not installed deeper

than 2 m and the main sewer not

deeper than 3 m, otherwise a

double system may be

considered depending on costs.

• Maximum manhole spacing : 110 m

• Placement of sewers inside 13 m to

25 m road reserves

: 2.85 m from erf boundary on high

side of road (16 m road reserves)

: 2.45 m from erf boundary on high

side of road (13 m road reserves)

• Placement of sewers inside mid-

blocks

: 1.2 m from erf boundary

• Dolomite risk category : Medium

• Pipe material (dolomitic area) for

sewers < 280 mm internal diameter

: HDPE PE 80 to SANS ISO 4427

− Minimum pipe class : PN 6 SDR 21

− Supply lengths : 12 m minimum

− Joints : Butt-welded to SANS 10268 –

Part 1 or electro – fusion welding

Doornvallei Ext 5

Services Report

13

as per SANS 10268 – Part 2

where butt-welding is not

possible

• Sewer manholes : Precast concrete rings with “Pro-

Struct 687” sealant at joints

The following standards will be used in

the design of outfall sewers:

• Pipe material (dolomitic area) for

sewers < 280 mm

: As for reticulations

• Pipe material (dolomitic area) for

sewers ≥ 280 mm internal diameter

: HDPE structured wall sewer

pipes to ISO 9969 SANS 503

2000 X SN8 Spigot and Socket

joints without rubber seal to be

extrusion welded to SANS

18268-4, 12 m lengths

• Sewer Manholes : Precast concrete rings with “Pro-

Struct 687” sealant at joints

Doornvallei Ext 5

Services Report

14

3.3 SEWER OUTFLOW CALCULATIONS

Land Use No of No of Erf size Total Area Total Area % of Density Measuring Unit Water AADD Peak hourly Peak Domestic

Erven Units (m2) (ha) m

2Township (units/ha) unit/day Consumption (kl) (kl/day) factor Consumption (l/s)

Residential 2 1 150 n/a 5.5565 55565 83.58 27 kl per unit 0.6 90.00 2.5 2.60

Special for Access 1 1 n/a 0.457 4570 6.87 n/a kl per unit 0.6 0.60 2.5 0.02

Streets n/a n/a n/a 0.6344 6344 9.54 n/a n/a n/a n/a n/a n/a

Total 2 151 6.6479 66479 100 90.60 2.62

Doornvallei Ext 5

Services Report

15

3.4 PROPOSED NEW INFRASTRUCTURE

The eastern half of Doornvallei (Ext 5) drains to the north-eastern corner of the

development where it will connect to a 160 mm ND outfall sewer. The anticipated

peak dry weather flow rate for the western portion is 2.62 ℓ/s.

In line with the GLS report (refer to Appendix 5) a new 160 and 200 mm diameter

gravity sewer pipeline is proposed from the north-eastern connection of the

development down along the eastern boundary of Irene Glen Estate towards and

across the river by means of a new weir.

It is proposed that items OF_F011.01, OF_F011.02 and OF_F011.03 (shown in

red below) be installed under Doornvallei Extension 6 and items OF_F013.02 and

OF_F013.01 be installed under Doornvallei Extension 5.

3.5 SERVITUDES REQUIRED

The topography of the site, together with the township layout, dictate to a large

extent the positioning of the sewer pipelines. Servitudes will be necessary to

accommodate mid-block sewers, as well as servitudes on the low side of some

erven.

A servitude will be required along the western boundary of Irene Glen Estate

down towards the river and along the existing weir across the river up to the

existing main outfall sewer of the City of Tshwane.

A servitude will also be required along the eastern boundary of Irene Glen Estate

down towards the river and across the Hennops river for a new weir across the

river up to the existing main outfall sewer of the City of Tshwane.

Doornvallei Ext 5

Services Report

16

3.6 CONSTRUCTION COST ESTIMATE

Description Unit Quantity Rate (R) Amount (R) Totals (R)

WESTERN SEWER:

Item no OF_F011.01 m 275 R 1,280.00 R 352,000.00

Item no OF_F011.02 m 650 R 1,280.00 R 832,000.00

Item no OF_F011.03 m 350 R 1,280.00 R 448,000.00

River Crossing m 25 R 10,000.00 R 250,000.00

EASTERN SEWER:

Item no OF_F013.01 m 897 R 1,280.27 R 1,148,402.19

Item no OF_F013.02 m 182 R 1,281.87 R 233,300.34

River Crossing m 25 R 10,000.00 R 250,000.00

Total (Excl. P&G, Contingencies, Fees & VAT) R 3,513,702.53 R 3,513,702.53

Plus:

Preliminaries & General @ 15% R 878,425.63

Contingencies @ 5% R 175,685.13

Total (Excl. Fees & VAT) R 4,567,813.29

3.7 CONTRIBUTIONS FOR SEWER

The development drains by means of gravity lines on site and via external gravity

sewers to eventually end up in the Sunderland Ridge Waste Water Treatment

Works. Bulk contributions will be payable. It is proposed that funds invested in

external infrastructure be subtracted from bulk contributions payable. The

unofficial bulk cash contribution for sewer is calculated as follows : R5300/kl/d x

90.6 kl/d = R480,180.00.

Doornvallei Ext 5

Services Report

17

3.8 SOLID WASTE MANAGEMENT

3.8.1 Guidelines

Local Government is responsible for solid waste management in South Africa.

The objective is to monitor a sustainable waste management plan encompassing

environmental, social, technological and economical criteria. To this end the

Local Government Act (Act No. 32 of 2003) with a Solid Waste Management Bill

applies.

Soild waste collection is overseen by Local Authorities through private

contractors. The collected solid waste is then transported to landfills via transfer

stations which is managed and maintained by the government through private

contractors. Solid waste are compacted, collected and transferred through to

landfill.

The following norms and statutory requirements are utilised where applicable:

o National Solid Waste Management Plan (NSWMP) – 1994

o Government Solid Waste Management Strategy – to minimize solid waste

by recycling and composting.

3.8.2 Waste storage and processing systems

A solid waste compacter is envisaged. The waste generated will be temporarily

stored in different operational waste containers or bins. Waste will be dumped

into the static compacter to be provided. The waste will be collected from the

waste generating sites and taken directly to the compacter. The compacted

waste slugs will be stacked in a container for proposed weekly removal or if

required removed daily per arrangement in similar quantities.

3.8.3 Design data and information

The following design parameters are applicable:

WASTE GENERATION GUIDELINES

Residential (Medium developments) 0.8 kg/cap/d

Residential (Upper developments) 1.2 kg/cap/d

Commercial (Financial) 0.01 kg/m2/d

Commercial (Mixed) 0.05 kg/m2/d

Doornvallei Ext 5

Services Report

18

3.8.4 Waste generated estimate

The daily waste generation figures for the various areas in this development are

indicated below.

WASTE GENERATION

No of erven Rate

(kg/cap/d) Occupants

Weight per day

(kg)

Res 2 (27 dwellings / ha) 0.8 300 240

Special – Gate House 0.8 2 1.6

Street N/A N/A 0

Total

241.6

Based on the assumed loose densities of waste of 100 – 150 kg/ m3, the

estimated waste generation volume is 2 m3 per day.

Doornvallei Ext 5

Services Report

19

APPENDIX 1: LOCALITY PLAN

20 Doornvallei Ext 6

Services Report

APPENDIX 2: TOWN PLANNER’S LAYOUT

21 Doornvallei Ext 6

Services Report

APPENDIX 3: PROOF OF OWNERSHIP

22 Doornvallei Ext 6

Services Report

APPENDIX 4: TOWNSHIP ESTABLISHMENT CONDITIONS

23 Doornvallei Ext 6

Services Report

APPENDIX 5: GLS REPORT

24 Doornvallei Ext 6

Services Report

APPENDIX 6: APPLICATION FOR RAND WATER CONNECTION

25 Doornvallei Ext 6

Services Report

APPENDIX 7: DRAWINGS