Upload
zoe-martiniak
View
78
Download
0
Embed Size (px)
Citation preview
Water Distribution Network for the Municipality of Barrhead, Alberta
Proposal Submitted by Hydrofour
Zoe Martiniak (260446300) Reid Hadaway (260518382)
Diane Kim (260462152) Svetlana Zdanovich (260482402)
April 6th, 2016
CIVE 421 Municipal Systems McGill University
Presented to Dr. Ronald Gehr
i
Abstract The primary objective of this report is to design a water distribution system to service the Town
of Barrhead, Alberta for a 20-year period. A population of 6295 was forecasted for the year 2036
using the exponential method. The designed water distribution system will supply the demands
of residential, commercial, and industrial sectors and the water demand per sector was calculated
based on existing and future developments in the town. Paddle River, which runs across the
south end of the town, was chosen as the water source. The intake location was determined based
on a calculated intake depth of 1.18 m. The critical fire flow was predicted to occur at the
Barrhead Healthcare Centre, close to the school district, and would require a total fire flow of
6750 L/min for a duration of 2 hours. Two storage units, a ground reservoir and an elevated
reservoir, were designed. The elevated reservoir, located across the industrial sector north of the
town, will provide the equalizing, fire, and emergency storages. The ground reservoir, attached
to the water treatment plant and located south of the town, will supply the average and maximum
daily flows. The water distribution network was designed using AquaCAD. Five scenarios were
modeled including average day, minimum hours, maximum hour, maximum day, and maximum
day + fire. The network was designed with respect to pressure limitations and minimal head
losses. The selected pipe sizes are: 200 mm, 300 mm and 480 mm. The pumping system, which
includes two continuously operating pumps in parallel and a third backup diesel pump, was
designed based on the required pressures of the network.
ii
Acknowledgements
We at HydroFour would like to graciously thank Professor Ronald Gehr along with Sarah El
Outayek, Angela Huston, and Martine LavallΓ©e for their support and instruction throughout the
preparation and completion of this project and report.
iii
Table of Contents ABSTRACT I
ACKNOWLEDGEMENTS II
TABLE OF CONTENTS III
LIST OF FIGURES V
LIST OF TABLES VI
1.0 INTRODUCTION 11.1 PURPOSE 11.2 SCOPE 11.3 TOWN CHARACTERISTICS 1
2.0 POPULATION FORECASTING 4
3.0 INTAKE LOCATION 63.1 GROUNDWATER 63.2 PADDLE RIVER 6
4.0 WATER DEMAND 84.1 ZONING 84.2 WATER DEMAND PER CAPITA 94.3 CRITICAL FIRE FLOW 104.4 CAPACITIES OF COMPONENT STRUCTURES 11
5.0 RESERVOIRS 135.1 GROUND LEVEL RESERVOIR 135.2 ELEVATED RESERVOIR 135.2.1 CAPACITY OF EQUALIZING OF STORAGE 135.2.2 CAPACITY OF FIRE STORAGE 145.2.3 CAPACITY OF EMERGENCY STORAGE 145.2.4 DIMENSIONS OF ELEVATED STORAGE 155.3 RESERVOIR LOCATIONS 165.4 RESERVOIR BEHAVIOUR 17
6.0 DISTRIBUTION NETWORK 196.1 PIPE SELECTION 196.2 WATER DEMAND ESTIMATION 206.3 PRESSURE DISTRIBUTION 216.4 VELOCITY DISTRIBUTION 236.5 HEAD LOSS DISTRIBUTION 246.6 NETWORK ROBUSTNESS 256.6.1 MAIN PIPE BREAK 256.6.2 PUMP FAILURE 26
iv
6.6.3 STANDBY PUMP 27
7.0 PUMPS 287.1 OVERVIEW 287.2 CHOICE OF PRIMARY HIGH-LIFT PUMPS 297.3 CHOICE OF STANDBY PUMP 32
8.0 CONCLUSION 36
REFERENCES 38
APPENDIX A β CLIMATE DATA 41
APPENDIX B β POPULATION FORECASTING CALCULATIONS 42
APPENDIX C β BARRHEAD COUNTY INFORMATION MAP 43
APPENDIX D β WATER DEMAND CALCULATIONS 44
APPENDIX E β FIRE FLOW CALCULATIONS 46
APPENDIX F β CAPACITIES OF COMPONENT STRUCTURES CALCULATIONS 47
APPENDIX G β WATER LEVELS IN THE ELEVATED RESERVOIR 49
APPENDIX H β PIPE CHARACTERISTICS 50
v
List of Figures Figure 1 β Map of Barrhead, AB (Google Maps, 2016) ................................................................. 2Figure 2 β Topography of Barrhead, AB (Toporama, 2016) .......................................................... 2Figure 3 β Barrhead Projected Population ...................................................................................... 5Figure 4 - Intake Location in the Paddle River (Google Maps, 2016) ........................................... 7Figure 5 β Barrhead Zoning Map .................................................................................................... 8Figure 6 β Simplified Schematic of the Water Distribution System of Barrhead ........................ 11Figure 7 β Equalizing Storage Mass Diagram .............................................................................. 14Figure 8 β Elevation View of the Elevated Reservoir .................................................................. 15Figure 9 β Plan View of the Elevated Reservoir ........................................................................... 16Figure 10 β Locations of Ground and Elevated Reservoirs (Town of Barrhead, 2016) ............... 17Figure 11 β Proposed Water Distribution Network ...................................................................... 20Figure 12 β Pressure Distribution at Nodes for Average Day Simulation .................................... 22Figure 13 β Distribution Pressures ................................................................................................ 23Figure 14 β Main Pipe Break ........................................................................................................ 25Figure 15 β Pump Failure ............................................................................................................. 26Figure 16 - Distribution of Pressures During a Standby Pump Scenario ..................................... 27Figure 17 - Parallel Arrangement of Pumps (Integrated Publishing Inc., 2016) .......................... 28Figure 18 β Primary Pump Characteristic Curve and Operating Point ......................................... 30Figure 19 β Two Identical Parallel Pumps' Operating Point ........................................................ 32Figure 20 β Standby Pump Characteristic Curve and Operating Point ........................................ 33Figure 21 β Pressure Distribution Under Maximum Day + Fire Flows, Standby Pump Alone ... 35Figure 22 β Barrhead Climate Data (ACIS, 2016) ....................................................................... 41Figure 23 β Barrhead County Information Map (Town of Barrhead, 2016) ................................ 43
vi
List of Tables Table 1 β Design Populations for Barrhead .................................................................................... 4Table 2 β Forecasted Water Demand per Sector ............................................................................ 9Table 3 β Barrhead's Variation in Water Demand ........................................................................ 10Table 4 β Capacities of the Component Structures of Figure 5 .................................................... 12Table 5 β Elevated Storage Flows ................................................................................................ 18Table 6 β Total Water Demand in AquaCAD Simulations .......................................................... 21Table 7 β Distribution of Pressures ............................................................................................... 22Table 8 β Distribution of Water Velocities ................................................................................... 24Table 9 β Distribution of Headlosses ............................................................................................ 24Table 10 β Primary High-Lift Pump Specifications (American Marsh Pumps) ........................... 29Table 11 β Flows and % of Total Demand Provided per Pump for Different Scenarios ............. 31Table 12 β Head per Pump for Different Scenarios ...................................................................... 31Table 13 β Operating Efficiency and Power per Pump for Different Scenarios .......................... 31Table 14 β Standby High-Lift Pump Specifications (American Marsh Pumps) .......................... 33Table 15 β Operating Points for Different Scenarios, Standby Pump Operating Alone .............. 34Table 16 β Barrheadβs Water Demand .......................................................................................... 44Table 17 β Fire Flow Demands ..................................................................................................... 46Table 18 β Hourly Consumption Rates on Peak Day Demand ..................................................... 47Table 19 β Characteristic of Selected Pipes from Georg Fischer Harvel ..................................... 50
1
1.0 Introduction
1.1 Purpose
The purpose of this project is to design a water distribution system for the town of Barrhead,
Alberta that is capable of meeting the current and projected water demand for a 20-year period.
The longevity of the designed system is based on the life expectancy of the PVC pipe, which is
typically 20 years.
1.2 Scope
This report documents the process of designing a water distribution system for the town of
Barrhead. The distribution network will provide water for residential, commercial, and industrial
uses, and will ensure that adequate flows can be provided during emergencies. The design
process is based on the following:
β’ Population forecasting
β’ Intake location
β’ Evaluation of component structure capacities
β’ Design of storage
β’ Design of distribution network
β’ Evaluation of pumps
1.3 Town Characteristics
Located 120 km Northwest of Edmonton, Barrhead has an overall area of 8.10 km2 with a
slightly varying elevation around 640m (Figure 1 and Figure 2) (CityData, 2016). The town has a
humid continental climate with typically warm summers and cold winters. Due to its high
altitude and close proximity to the Rocky Mountains, warm, dry chinook winds can greatly
increase the temperature during the winter months. The detailed climatic data is of Barrhead can
be found in Appendix A. Barrheadβs landscape consists of boreal forest and natural sand hill
while being close in proximity to the Athabasca, Pembina and Paddle river (Hydrogeological
consultants Ltd, 1998). The Paddle River, which runs across the town, will act as the water
source for the water distribution network.
2
Figure 1 β Map of Barrhead, AB (Google Maps, 2016)
Figure 2 β Topography of Barrhead, AB (Toporama, 2016)
Barrhead, Alberta is a town with a population of 4432 and is expected to have a current
population of 4542 (Statistics Canada, 2012). Despite its small population size, Barrhead is home
3
to a golf course, campground, several healthcare centers, multiple community facilities, and
commercial businesses. Schools in Barrhead include the Barrhead Elementary School, Barrhead
Composite High School, and the Vista Virtual school (Town of Barrhead, 2016).
The main sources of industry that support Barrheadβs economy are oil and gas, forestry and
agriculture. Regarding the regional industry, agriculture is of major importance to the Barrhead
economy. They pride themselves on their highly competitive hog operations and cattle feedlots.
The town of Barrhead serves as the regional trading and service center for the County of
Barrhead and the surrounding area, which services over 500 businesses in the region (Alberta
Community Profiles, 2016). Some of the manufactured products in the county of Barrhead
include animal feeds, chemicals and herbicides, concrete, fertilizers, and many more.
In terms of non-domestic development, the municipality of Barrhead has proposed for the
construction of the Barrhead Regional Aquatics Centre. This will greatly increase the amount of
water that the town will need and will have to be accounted for in the calculations for the water
distribution network.
4
2.0 Population Forecasting The population of Barrhead was 4,432 in 2011, according to the Canadian census of population
in Alberta (Statistics Canada, 2012). Assuming exponential growth, the current population in
2016 is 4,618 people and is projected to be 6,295 people in 2036 (Figure 3). Detailed
calculations can be found on Appendix B. In the recent months, Alberta has been experiencing a
sizeable amount of lay-offs in the oil and gas industry. However, with the current federal
government investing in renewable energy coupled with worker-led initiatives such as Iron &
Earth, who aims to retrain electricians from the oilsand sector to install solar panels, there is a
new niche market to be exploited (Lazzrino, 2016). This trend will retain current population and
potentially attract more skilled workers in smaller towns. Barrhead is planning two large housing
expansion projects that allow for accommodation for this future population growth, as well as
potentially welcome more population to settle in Barrhead. These housing expansion projects are
the Hillcrest Home and Beaver Brooke Estates, which are located at points 23 and 24 on the
Barrhead County information map in Appendix C.
Using the Exponential Method (with an acceptable R2 of 0.95244), we determine the current and
future population as indicated in Table 1.
Table 1 β Design Populations for Barrhead
Year 2001 2006 2011 2016* 2036*
Population 4213 4209 4432 4618 6295
*Projected using exponential method. (Source: Statistics Canada, 2012)
6
3.0 Intake Location
3.1 Groundwater
According to the Alberta Ministry of Environment and Sustainable Resource Development,
water level map, the static groundwater level in the wet well located near the proposed water
treatment plant is 5.5 m (Gov. of Alberta, 2016). Although the depth is not too problematic,
pumping from the aquifer would incur additional costs related to pipes, excavation work, and
pumps. For these reasons, groundwater was not considered as an intake source.
3.2 Paddle River
Barrhead is located North of Paddle River, which appears to be an appropriate source of water
for the community as it is easily available and abundant. The flow has been controlled by the
Paddle River Dam since 1986, and the design discharge is 272 m3/s (Gov. of Alberta, 2016),
which is more than sufficient for the proposed design. The region around this River used to be
prone to flooding, but the issue has been controlled ever since the dam was built (Groundspeak
Inc., 2016). For these reasons, Paddle River was selected to be the intake source.
When using surface water as intake source, the intake depth must be carefully calculated due to
the development of the ice layer. The average ice thickness was calculated using the Lliboutry
formula (Briere, 1999):
d = 3.6A π
where d = average thickness of ice layer (cm)
A = snow cover and turbulence coefficient
g = freezing index in Β°C-days
Weather Canada data for the year 2015 shows that Barrhead was covered in snow for about 4
months, from late November to mid-March (Appendix A). Thus, the A coefficient would be the
one for a river covered with snow, which is 0.5 for a more conservative design. As for the
freezing index, it was found to be 1,441 degrees-days Β°C (DOW, 2008). Using the above formula,
the freezing depth equals to 68 cm. To account for worst-case conditions, the intake should be
placed 0.5 m under the ice layer. Therefore, the intake depth shall be 1.18 m. In addition, the
7
intake should have a clearance of 1 m from the river bed to avoid debris being sucked in.
Consequently, the intake location needs to be at a point where the depth of the river is more than
2.18 m. Figure 4 gives an approximation of the intake location.
Figure 4 - Intake Location in the Paddle River (Google Maps, 2016)
8
4.0 Water Demand
4.1 Zoning
The water use was distributed between residential, commercial, and industrial sectors, illustrated
by Figure 5. The main residential area is located in the southwest part of the town. The southwest
portion is also comprised of the town office, hotels, several parks, campgrounds, and a golf
course. The southeast portion of the town is primarily made up of businesses and housing such as
hotels and senior homes. Educational buildings including an elementary school, high school,
library, and school district office are located in the northwest portion of the town. The northwest
portion also includes a large park as well as a long-term health care center. The northeast of the
town is largely made of recreational buildings such as a bowling alley, museum, curling rink,
swimming pool, baseball diamonds, and rodeo grounds. There are also hotels and institutional
buildings such as the RCMP detachment and fire and ambulance. Above this area lies the
industrial park, the only industrial sector in the town, as well as a provincial building and a
learning center.
Figure 5 β Barrhead Zoning Map
9
4.2 Water Demand per Capita
The average daily water demand was calculated from the sum of water demand per building type
in the town of Barrhead, accounting for future developments such as the Hillcrest Home and
Beaver Brooke Estates projects as well as the Barrhead Regional Aquatic Centre project. The
EPA recommended design flows were used in calculating the average daily water demand
(Shammas and Wang, 2011). Appendix D summarizes the applied design flows for every
building in Barrhead. Table 2 summarizes the water demand per sector. The final water use per
capita is 0.8681 m3/day.
Table 2 β Forecasted Water Demand per Sector
Consumption
(%)
Water Use
(m3/day/capita)
Total residential consumption 67.13 0.5827
Total commercial consumption 7.90 0.2253
Total Industrial Park 6.93 0.0601
Total - 0.8681
Peak factors (Shammas and Wang, 2011) were used to account for the variations in water
demand in modeling four demand scenarios for the town of Barrhead. The results are
summarized in Table 3.
10
Table 3 β Barrhead's Variation in Water Demand
Average Daily
Flow (m3/day)
Max Daily Flow
(m3/day)
Max Hourly
Flow (m3/day)
Min hourly Flow
(m3/day)
Peak Factor 1 2 3 0.5
Adjusted Total
Water Use per
Capita
0.8681 1.736 2.604 0.4341
Total
Residential
3668 7337 11010 1834
Total
Commercial
432 863 1295 216
Total Industrial 379 379 379 379
Total 5465 8579 12680 2428
The Barrhead water distribution system must be designed to accommodate for the maximum
hourly flow of 12,680 m3/day.
4.3 Critical Fire Flow
The fire flow is designed for critical locations which are home to valuable assets or value. In this
case, the Barrhead Healthcare Centre was chosen due to its close proximity to the school and
commercial districts. Additionally, the healthcare centre is one of the most important buildings in
the community in terms of medical treatment as there are few clinics in the town. Alternative
critical and highly dense locations such as the school district and the Agrena & Swimming Pool
were also considered. Although the Agrena & Swimming Pool is the largest community services
facility, capable of accommodating a large number of people, it was considered less critical when
compared to the healthcare centre which sits facing the school district.
The Barrhead Healthcare Centre is an ordinary one story building mainly constructed from brick
and masonry walls with a total area of 4800 m2 according to the Healthcare Centre. Also, the
11
Healthcare Centre is 25 m away from a small supply building. Detailed calculations can be found
in Appendix E.
The critical fire flow was found to be:
πΉ = 6750πΏ/πππ
4.4 Capacities of Component Structures
As mentioned previously, the population of Barrhead was predicted to reach 6,295 people by
2036. Per our design calculations, the future water distribution system must be able to supply a
peak hourly flow of 16,390 m3/day and an average daily flow of 5,465 m3/day. Figure 6
represents a simplified schematic of the system as it was modeled.
Figure 6 β Simplified Schematic of the Water Distribution System of Barrhead
Table 4 outlines the capacities of the different component structures. Details of the calculations
can be found in Appendix F.
12
Table 4 β Capacities of the Component Structures of Figure 5
Component Required Capacity Capacity of system (m3/day)
Source Maximum day 8,579
Conduit I Maximum day 8,579
Low-lift pumps Maximum day + reserve 12,870
Water treatment plant Maximum day + reserve 12,870
High-lift pumps Maximum hour + reserve 19,020
Conduit II Maximum day 8,579
Distribution system
high-value district
Maximum hour 12,680
Conduit III Maximum hour 12,680
Total storage volume Maximum hour + fire + emergency 2,763 m3
These capacities were taken as basis for the sizing of the reservoirs, the pipes in the distribution
network and the high-lift pumps in the following sections.
13
5.0 Reservoirs
5.1 Ground Level Reservoir
The ground level reservoir will be located at the water treatment plant. Water pumped from the
river will undergo purification and treatment before being stored in the ground level storage
which is to be located at the water treatment plant. The ground level reservoir will supply the
average and maximum daily flows to the distribution network. This reservoir is designed to store
10,930 m3 of water, the double the average daily flow anticipated by the network.
ππππ’πππππΊπππ’ππππ‘πππππ = 2 π΄π£ππ·ππππ¦πΆπππ π’πππ‘πππ = 2 β 5,465πI = 10,930πI
5.2 Elevated Reservoir
The elevated reservoirs will provide for equalizing, fire, and emergency conditions. The
equalizing storage ensures the water supply during the peak hours of the day while fire and
emergency storage will ensure supply in case of emergencies such as fires or failures in the water
mains. From summing the equalizing, fire, and emergency storages, the elevated reservoir for the
town of Barrhead must have a minimum volume of 2,763 m3. Taking into account 0.8 meters for
overfill and for additional emergency capacity, our design volume is 2,808 m3. The calculations
and detailed descriptions of the equalizing, fire, and emergency storages are found in Appendix F
and the following sections 5.2.1, 5.2.2, and 5.2.3, respectively.
5.2.1 Capacity of Equalizing of Storage
Equalizing storage accounts for the daily fluctuations between water demand and pumping rates,
especially during hours of peak demand. The required equalizing storage is read from a mass
diagram, as shown in Figure 7 which plots Barrheadβs cumulative water consumption throughout
the day. The equalizing storage is the sum of the maximum ordinates between the demand and
supply lines. Barrheadβs required equalizing storage is 1,400 m3. Detailed calculations can be
found in Appendix F.
14
Figure 7 β Equalizing Storage Mass Diagram
5.2.2 Capacity of Fire Storage
According to the Fire Underwriters Survey performed by CGI Risk Management Services for the
Canadian Insurance industry, the minimal required duration of fire flow is 2 hours for a
population of 6, 295 (CGI Group Inc, 1999). The critical fire demand was calculated to be 6750
L/min in section 4.3. Based on this information, the required fire storage was calculated to be
810 m3. Detailed calculations can be found in Appendix F.
5.2.3 Capacity of Emergency Storage
The emergency storage accounts for 25% of the sum of the fire and equalizing storage. The
required emergency storage was found to be 552.5 m3. Detailed calculations can be found in
Appendix F.
15
5.2.4 Dimensions of Elevated Storage
The water tower will be situated beyond the townβs load center since the area provides high
elevations and since this setup will decrease the required head by the pumps. The AquaCAD
simulation has shown that the water in the tower will reach a maximum height of 22 m. An
additional 0.8 m will be added to the actual height of the tower to accommodate overfilling. The
water tower will be comprised of a cylindrical reservoir atop of a cylindrical column. The
minimum required elevated reservoir volume of 2,763 m3 will be split among the two cylindrical
structures. The suggested design dimensions are illustrated in Figures 8 and 9 below. The
cylindrical column will hold a volume of 295 m3 while the cylindrical reservoir will hold a
volume of 2513 m3, for a total volume of 2808 m3.
Figure 8 β Elevation View of the Elevated Reservoir
16
Figure 9 β Plan View of the Elevated Reservoir
5.3 Reservoir Locations
The location of the ground level and elevated reservoirs in Barrhead were chosen based on the
water intake location and the land topography. The ground water reservoir, alongside the water
treatment plant, will be situated at the cross section between the Paddle River and Highway 33,
where the ground elevation is 635 m. This was deemed to be the best location due to its close
proximity to both the intake location, the Paddle River, and the water main, which will be placed
along Highway 33. The elevated reservoir will be located at the north of the town, near the
industrial park, where the topography reaches the townβs highest elevation of 667 m. In placing
the elevated storage on an elevated topography, we are able to reduce pumping and energy
requirements. The locations of the ground and elevated reservoirs are illustrated in Figure 10.
17
Figure 10 β Locations of Ground and Elevated Reservoirs (Town of Barrhead, 2016)
5.4 Reservoir Behaviour
The flows of the elevated storage under various scenarios are outlined in Table 5 below, as
determined by AquaCAD. It should be noted that negatives flows represent the emptying of the
elevated reservoir.
18
Table 5 β Elevated Storage Flows
Scenario Flow (L/min)
Minimum Hour 5539
Average Day 3690
Maximum Day Balanced
Maximum Hour -3690
Fire + Maximum Day -6750
The height of the water in the elevated reservoir on an average day and during a maximum daily
water use is 22.2 m and 7.68 m, respectively. Detailed calculations can be found in Appendix G.
19
6.0 Distribution Network
6.1 Pipe Selection
The pipe network distribution is designed to lay underneath the road base of Barrhead to increase
ease of access to the pipes for maintenance or repair. However, some pipes were added that do
not lie directly under the road in order to avoid dead-ends and loops. A closed-loop system is
ideal for reducing head losses and allow for adequate distribution of water to meet the city's
water demands.
PVC was chosen as the pipe material, since PVC is generally preferred over metal pipes for
water distribution. Using metal pipes for water distribution can introduce dissolved metals into
the drinking water supply as a result of corrosion. PVC also has a higher Hazen-Williams
coefficient, which relates to a lower friction factor and therefore reduced head losses. The
Hazen-Williams coefficient for PVC pipes are usually around 150, however for design purposes
we have selected a Hazen-Williams coefficient of 140 for our hydraulic simulations. PVC pipes
are commercially available as schedule 40 or schedule 80. The main differences between these
schedules are the pipe thickness and the pressure rating. Schedule 80 pipes have thicker walls but
are more resistant ion, replacement to internal and external pressures. In order to prolong the
lifetime of the piping network and avoid pipe leaks, schedule 80 pumps are the optimal choice.
The layout of the primary, secondary and distribution mains are indicated in Figure 11. It was
decided that decided to maintain consistent sizing for each of the three types of water distribution
pipes to avoid construction and replacement issues, as well as reduce overall costs. The pipe
sizing was optimized for efficient distribution for average day, as well as all other simulations.
This was done by considering pressures and head losses throughout the distribution. The selected
pipe sizes are summarized in Appendix H. The nominal pipe diameters of 200 mm, 300 mm and
480 mm were selected for the water distribution, secondary and primary water main pipes,
respectively.
20
Figure 11 β Proposed Water Distribution Network
6.2 Water Demand Estimation
The water demand for each node was approximated by assuming a uniform distribution of water
demand across the industrial, commercial and residential sectors. Each pipe was labeled as
belonging to one of the three zones, and then the total sum of the length of pipes for each sector
was calculated. The total daily demand for each sector was divided by the total length of pipes
for that sector to obtain a consumption factor per length of pipe. The pipe demands were then
calculated by multiplying the consumption factor for the sector it belongs by the length of pipe.
It was assumed that the flow in each pipe distributes half of its flow to each of its two nodes.
Therefore, the flow at each node was calculated as the sum of flows for all pipes connected to the
21
node, divided by two. This method of consumption approximation is appropriate for Barrhead,
since the population density is relatively uniform throughout the residential sector, and the
commercial sector is centrally located along the water main. The total demand for each
simulation is summarized in Table 6.
Table 6 β Total Water Demand in AquaCAD Simulations
Average day
(L/min)
Max day
(L/min)
Max day +
fire (L/min)
Peak hour
(L/min)
Min Hour
(L/min)
Residential 2402 4803 4803 7205 1201
Commercial 966.2 1932 1932 2899 483.1
Industrial 345.9 345.9 345.9 345.9 345.9
Fire 0.00 0.00 6750 0.00 0.00
Total 3714 7081 13830 10450 2030
6.3 Pressure Distribution
Water pressures in the distribution systems should remain within the range of 140-450 kPa. The
minimum value is critical for providing adequate distribution and to meet the demands at every
location in the water distribution network and to prevent leaking. The maximum pressure value
is to prevent the pipes from breaking or bursting. The network is optimized for the lower
pressures in order to provide adequate distribution during the minimum hour and average day
demands. Schedule 80 PVC pipes were specifically selected to be able to resist the higher
internal water pressures in order to accommodate for optimizing for the lower pressure regions.
Figure 12 below illustrates the pressure distribution at nodes for the average day simulation. The
lower pressures exhibited at the top right corner of the system are due to the elevation difference
between those points and the ground reservoir of around 30 meters.
22
Figure 12 β Pressure Distribution at Nodes for Average Day Simulation
As shown in Table 7 and Figure 13, the pressure in the pipes fall within the allowable range of
140 to 450 kPa except for a few nodes which are very close to the range limits (for example, 148
kPa or 454 kPa).
Table 7 β Distribution of Pressures
Pressure
(kPa)
Average day Maximum
Day
Peak Hour Minimum
Hour
Maximum
Day + Fire
<150 0.2% 0.2% 0.5% 0.2% 0.7%
150-250 24.7% 24.5% 24.2% 24.7% 26.1%
250-350 34.7% 35.2% 39.9% 40.6% 47.6%
350-450 39.6% 39.4% 35.0% 39.4% 25.6%
>450 0.7% 0.7% 0.0% 0.9% 0.0%
23
Figure 13 β Distribution Pressures
6.4 Velocity Distribution
The range for velocities in most water distribution systems in North America is generally 0.6-1.5
m/s. This range ensures that water does not remain stagnant in the piping system, as well as
avoid erosion and abrasion of the pipes. However, in order to maintain adequate pressures within
the system and minimize pumping, the velocities calculated in AquaCAD were below this range.
Therefore, the proposed network operates with lower velocities in order to reduce head losses
and reduce operational costs. As shown in Table 8, the velocities in the pipe network were
usually within the range of 0-0.3 m/s. For the maximum day, 4% of the network operated within
the suggested velocity range.
24
Table 8 β Distribution of Water Velocities
Velocity
(m/s)
Average Day Maximum
Day
Peak Hour Maximum
Daily + Fire
Minimum
Hour
0.00-0.1 94% 72% 60% 63% 100%
0.1 - 0.3 6% 24% 32% 25% 0%
0.3-0.6 0% 3% 5% 7% 0%
0.6-1.5 0% 1% 3% 4% 0%
Low velocities in the system will increase the pipe's lifetime by reducing erosion and internal
forces on the pipe. Velocities significantly increased during the peak hour and maximum day +
fire scenarios, which illustrates that the emergency demand will be met quickly. In order to
mitigate especially low velocities in critical locations, a flushing mechanism installed at various
locations throughout the network is suggested.
6.5 Head Loss Distribution
The network was optimized to maintain adequate pressure throughout the entire network,
therefore minimizing head losses in the pipes is a crucial. The head losses were fairly minimal,
as shown in Table 9.
Table 9 β Distribution of Headlosses
Headlosses
(cm)
Average
Day
Maximum
Day
Peak Hour Minimum
hour
Peak Hour +
Fire
0-3 100.0% 95.4% 88.6% 100.0% 81.9%
3-6 0.0% 4.1% 6.6% 0.0% 8.1%
6-10 0.0% 0.6% 3.9% 0.0% 5.4%
10-20 0.0% 0.0% 1.0% 0.0% 4.1%
>20 0.0% 0.0% 0.0% 0.0% 0.6%
25
6.6 Network Robustness
In order to evaluate the system robustness, three emergency scenarios were considered.
6.6.1 Main Pipe Break
The first emergency scenario considered is failure in one of the primary pipe mains. The system
is tested for a pipe failure between node 129 & 130 broke, which is one of the first pipes that
introduce the flow into the network as illustrated in Figure 14. Therefore, the flow is forced to
travel through smaller distribution pipes. This results in a pressure drop in the rest of the network,
however the distribution of water throughout the majority of the network is still within
acceptable ranges of 138 β359 kPa.
Figure 14 β Main Pipe Break
26
6.6.2 Pump Failure
The network was designed with two parallel pumps that will provide water to the network, as
well as a stand-by diesel pump in case of an electrical shut down or failure of the parallel pumps.
The design of our pump system is detailed in the next section.
The second emergency scenario is failure of one of the parallel pumps, therefore the system is
operating with only one pump before the standby pump is activated. This simulation was done
under peak hourly conditions. Figure 15 illustrates that the pressures remained fairly similar to
the normal operating pressure ranges. Therefore, this system could still provide adequate
pressures in case of a pump failure.
Figure 15 β Pump Failure
27
6.6.3 Standby Pump
In the case of failure in one or both of the parallel pumps, we have included a diesel standby
pump in our design. The third emergency situation will simulate failure of both of the parallel
pumps. Figure 16 shows the distribution of pressures for the stand-by pump supplying the total
demand for Barrhead. The pressures are generally within the accepted range of 150-450 kPa,
therefore the standby pump can adequately supply demand for these scenarios.
Figure 16 - Distribution of Pressures During a Standby Pump Scenario
28
7.0 Pumps
7.1 Overview
In order to adequately deliver water from the treatment plant to the town of Barrhead and then to
the elevated reservoir, three high-lift pumps were selected according to the calculated required
capacity and the total pressure of the distribution system. Two identical pumps placed in parallel
at the ground reservoir will operate continuously, each being responsible for supplying half of
the water demand. In addition, a diesel-operated pump will be in standby to cope with
emergencies such as power failures. This third pump will be able to provide the full flow.
This is a more efficient design, because pumps in parallel can supply a greater flow than a single
pump (Figure 17), and it is also a more appropriate design compared to pumps in series, which
are usually used to overcome a larger system head loss.
Figure 17 - Parallel Arrangement of Pumps (Integrated Publishing Inc., 2016)
Since the modeling performed minimized the system head loss, placing the pumps in parallel is
more relevant and more advantageous in terms of lifecycle costing. There are three main
advantages for this arrangement. First, parallel arrangement eliminates the need of oversized,
thus costly, pumps and motors. As said previously, each pump will supply half of the total flow,
since in this arrangement the flow through each pipe is additive, such that the pumps can be
smaller. Second, parallel pumps help minimize current surge at motor start-up, which can cause
29
problems to the electrical circuit. The use of costly equipment to prevent such damage is
consequently avoided. Last but not least, the water distribution system will be more reliable;
parallel arrangement adds redundancy to the design. If one of the pumps is turned off or fails, the
second one will continue to operate (ITT Industries Inc, 2005).
It is worth noting that pumps usually have a lifespan of 5 years. Since the proposed water
distribution system was designed for a 20-year period, the selected pumps may need replacement
before the end of this design life. Modeling was performed as if pumps were put in place once
the system has achieved its ultimate capacity.
7.2 Choice of Primary High-Lift Pumps
The two high-lift pumps need to provide a flow of 3,795 L/min together, thus each should supply
1,898 L/min. The total system head loss was 46 m during the average daily flow simulation. The
selection of the pumps was maximized based on highest efficiency for the average daily flow
since this is the most frequent scenario. Using the PUMP-FLO centrifugal pump selection
software (Engineered Software Inc, 2016), two identical βAmerican-Marsh Pumpsβ units were
chosen. Selecting different sizes for the parallel pumps can cause problems, as one pump can
override the second, force closing its check valve, thus potentially leading to a risky situation
(ITT Industries Inc, 2005). For this reason, a safer and simpler route was taken by having
identical pumps. Table 10 states relevant information about the selected model, and the
characteristic curve is shown in Figure 18 with the operating point indicated by the red arrow.
Table 10 β Primary High-Lift Pump Specifications (American Marsh Pumps)
Type Model Diameter Speed Flow Head Efficiency NPSHr Power Motor
480_VRT-
TURBINE/
ENCL
11LC
(6 stage)
224 mm 1170
rpm
1898
L/min
46.8 m 86.8 % 1.4 m 16.7 kW 18.5 kW
30
Figure 18 β Primary Pump Characteristic Curve and Operating Point
Tables 11, 12, and 13 compile the pump operating points under varying conditions and demand
scenarios. All the values are given for one pump. As mentioned previously, each parallel pump
provides 50% of the average daily flow and is operated 24 hours/day. The head per pump ranges
from 45.2 to 47.4 m, and the efficiency from 86.2 to 87% across the different configurations and
scenarios.
31
Table 11 β Flows and % of Total Demand Provided per Pump for Different Scenarios
Minimum
Hour (L/min)
Average Day
(L/min)
Maximum
Day (L/min)
Maximum
Hour (L/min)
Maximum Day
+ Fire (L/min)
2 Primary
Pumps ON
1868 1872 1882 1907 1942
1 Primary
Pump ON
1880 1882 1900 1933 1977
Table 12 β Head per Pump for Different Scenarios
Minimum
Hour (m)
Average Day
(m)
Maximum
Day (m)
Maximum
Hour (m)
Maximum
Day + Fire (m)
2 Primary
Pumps ON
47.4 47.3 47.1 46.6 45.9
1 Primary
Pump ON
47.2 47.1 46.8 46.1 45.2
Table 13 β Operating Efficiency and Power per Pump for Different Scenarios
Minimum
Hour
Average Day
(m)
Maximum
Day (m)
Maximum
Hour (m)
Maximum
Day + Fire
(m)
Eff.
(%)
Power
(kW)
Eff.
(%)
Power
(kW)
Eff.
(%)
Power
(kW)
Eff.
(%)
Power
(kW)
Eff.
(%)
Power
(kW)
2 Primary
Pumps
ON
86.3 17 86.3 17 86.2 17 86.9 16.7 87 16.8
1 Primary
Pump ON
86.2 17 86.2 17 86.2 17 87 16.8 86.8 16.8
Figure 19 illustrates the operating point of the system when both pumps are operating to supply
the average daily demand.
32
Figure 19 β Two Identical Parallel Pumps' Operating Point
7.3 Choice of Standby Pump
The diesel-operated standby pump needs to supply the full flow in case of a power failure or
emergency, thus the selection was based on an average daily flow of 3,795 L/min and the total
system head loss of 46 m. Using the pump selection software, a βAmerican-Marsh Pumpsβ unit
was chosen based on highest efficiency for the average daily flow scenario. Table 14 states
relevant information about the selected model, and the characteristic curve is shown in Figure 20
with the operating point indicated by the red arrow.
= Operating point
33
Table 14 β Standby High-Lift Pump Specifications (American Marsh Pumps)
Figure 20 β Standby Pump Characteristic Curve and Operating Point
Table 15 compiles the pump operating points under varying conditions and demand scenarios.
The head ranges from 45.2 to 47.2 m, and the efficiency from 84.7 to 85.3% across the scenarios.
Type Model Diameter Speed Flow Head Efficiency NPSHr Power Motor
480_VRT-
TURBINE/
OPEN
14LS
(4 stage)
280 mm 1160
rpm
3,795
L/min
46 m 85 % 2.53 m 34.2
kW
37 kW
34
Table 15 β Operating Points for Different Scenarios, Standby Pump Operating Alone
Figure 21 depicts the pressure distribution across the network during a simulation using
maximum daily flow coupled with a fire flow. As shown, the pressures are above the minimum
allowable value of 140 kPa. Thus, if the backup pump can sustain adequate pressures during an
emergency scenario, it can surely supply enough flow for other less critical conditions.
Minimum hour Average day Maximum
day
Maximum
hour
Maximum day +
fire
Flow
(L/min) 3734 3744 3767 3828 3914
Head (m) 47.2 47.1 46.8 46.1 45.2
Efficiency
(%) 84.7 84.8 84.9 85.1 85.3
Power (kW) 33.9 34 34.1 34.2 34.5
36
8.0 Conclusion In conclusion, the hydraulic simulations of our proposed water distribution network confirm that
our design provides an economical and robust distribution solution for the town of Barrhead.
This project is designed for a lifetime of 20 years since the pipes are anticipated to experience
some form of failure after 20 years, and therefore we recommend the town to allocate a cost for a
system inspection after 20 years of installation.
Barrhead is located in Alberta, which is predicted to experience a transition from an oil and gas
economy to renewable energy, which will most likely increase the townβs population. Barrhead
is the biggest town for the county of Barrhead, therefore we have accommodated for an
exponential increase in population. The projected consumption was calculated based on the
estimated consumption in 20 years for the given population, which includes future housing
development projects. The maximum daily, peak hourly, minimum hourly flows, and a critical
fire situation were calculated based on this projected average consumption. The system is
designed to operate under all of these scenarios, including an emergency fire situation. The
proposed water distribution network is optimized for the average daily flow, since this is the
scenario that will occur most commonly.
The hydraulic simulations indicated the need to tradeoff between providing adequate water
pressures or allowing for adequate velocities. Making sure that the water pressure is within the
accepted ranges is prioritized in order to ensure that all locations in the water distribution
network will receive adequate water. Optimizing for water pressure to reduce head losses will
result in reduced operating cost and reduce risk of failure, which provides a more economic and
robust design option. In order to mitigate especially low velocities in critical locations, we
suggest installing a flushing mechanism. This will prevent water from remaining stagnant, and
will ensure that every location along the water distribution network will receive adequate flows
to meet their demand.
The pumps will have to be replaced every 5 years in order to provide safe and adequate water
distribution. One item that is worth looking into is modulating the operations of the parallel
pumps. Having them continuously operated consumes a lot of energy and could decrease the
37
lifespan of the equipment. An easy solution would be to add variable frequency drives, which
will yield interesting energy savings without compromising the efficiency of the system.
Other aspects to consider would be the social acceptance of the project in the community of
Barrhead, and further research would be required to investigate the potential ecological damage
inflicted to Paddle River from the water pumping operations.
38
References ACIS. 2016. Current and Historical Alberta Weather Station Data Viewer. Alberta. Available
from: http://agriculture.alberta.ca/acis/alberta-weather-data-viewer.jsp
Alberta Community Profiles. 2016. County of Brarhead No. 11. Available from:
http://albertacommunityprofiles.com/Profile/Barrhead_No_11_County_of/255
Briere, F. C. 1999. Drinking water, distribution, sewage, and rainfall collection. Polytechnique
International Press.
CGI Group Inc. 1999. Fire Underwriters Survey: Water Supply for Public Fire Protection.
CityData. 2016. Barrhead β Town, Alberta, Canada. Available from: http://www.city-
data.com/canada/Barrhead-Town.html
DOW. 2008. Tech Solutions 605.0: Calculating Insulation Needs to Fight Frost Heave by
Comparing Freezing Index and Frost Depth. Available from:
http://msdssearch.dow.com/PublishedLiteratureDOWCOM/dh_01f6/0901b803801f6296.pdf?file
path=styrofoam/pdfs/noreg/178-00754.pdf&fromPage=GetDoc
Engineered Software Inc. 2016. Pump-Flo. Available at: https://eng-
software.com/products/pump-flo/
GCSAA. 2009. Golf Course Environmental Profile Volume II: Water Use and Conservation
Practices on US Golf Courses. Available from:
https://www.gcsaa.org/Uploadedfiles/Environment/Environmental-Profile/Water/Golf-Course-
Environmental-Profile--Water-Use-and-Conservation-Report.pdf
Georg Fischer Harvel LLC. 2016. Dimensions - Schedule 40 & 80 Pipe - PVC Industrial &
Industrial PLUS. Available from:
http://www.harvel.com/piping-systems/harvel-pvc-pipe/schedule-40-80/dimensions
39
Gov. of Alberta. 2016. Alberta Water Wells. Available from:
http://groundwater.alberta.ca/WaterWells/d/
Gov. of Alberta. 2016. Flood Hazard Identification Program. Barrhead β Paddle River β Flood
Hazard Study β Summary. Available from: http://aep.alberta.ca/water/programs-and-
services/flood-hazard-identification-program/flood-hazard-studies/documents/Barrhead-
Paddle.pdf
Groundspeak Inc. 2016. Paddle River Dam β Rochfort Bridge, Alberta. Available from:
http://www.waymarking.com/waymarks/WMH1N0_Paddle_River_Dam_Rochfort_Bridge_Albe
rta
Hydrogeological Consultants Ltd. 1998. County of Barrhead No. 11, Parts of the Pembina and
Athabasca River Basins, Groundwater Potential Evaluation. Agriculture and Agri-Food Canada.
Integrated Publishing Inc. 2016. Centrifugal Pumps. Available from:
http://nuclearpowertraining.tpub.com/h1012v3/css/h1012v3_76.htm
ITT Industries Inc. 2005. Parallel Pumps Can Provide Multiple Benefits. Available from:
http://wea-inc.com/pdf/parrallel.pdf
Lazzrino, D. 2016. Oilsands workers call on Alberta government to retrain electricians as solar
installation specialists. Edmonton Sun. Available from:
http://www.edmontonsun.com/2016/03/21/oilsands-workers-call-on-alberta-government-to-
retrain-electricians-as-solar-installation-specialists
Shammas, N. and L. Wang. 2011. Water and Wastewater Engineering: Wastewater Supply and
Wastewater Removal. 3rd Edition. Hoboken, NJ: Wiley.
40
Statistics Canada. 2012. Population and dwelling counts, for Canada, provinces and territories,
and census subdivisions (municipalities), 2011 and 2006 censuses (Alberta). Available from:
http://www12.statcan.gc.ca/census-recensement/2011/dp-pd/hlt-fst/pd-pl/Table-
Tableau.cfm?LANG=Eng&T=302&SR=1&S=51&O=A&RPP=9999&PR=48&CMA=0
The Atlas of Canada β Toporama. Available from:
http://atlas.nrcan.gc.ca/toporama/en/index.html
Town of Barrhead. 2016. Proposed New Regional Aquatic Centre. Available from:
http://www.barrhead.ca/proposed-aquatic-centre
Town of Barrhead. 2016. Town of Barrhead. Available from: http://www.barrhead.ca
42
Appendix B β Population Forecasting Calculations
Geometric Growth Method: growth rate and current/future population
πΎM = ππ(π2011/π2006)(2011 β 2006) =
ππ(4432/4209)5 = 0.010325
ππππ πππ π¦πππ
π2016 = π2011 β πR.RSRITUβ TRSVWTRSS = 4432 β π(R.RSRITUβU) = 4618ππππ πππ
π2036 = π2016 β πR.RSRITUβ(TRIVWTRSV) = 4618 + π(R.RSRITUβIR) = 6295ππππ πππ
43
Appendix C β Barrhead County Information Map
Figure 23 β Barrhead County Information Map (Town of Barrhead, 2016)
44
Appendix D β Water Demand Calculations
Note that this table was constructed with reference to Appendix C: Barrhead County Information
Map.
Table 16 β Barrheadβs Water Demand
Unit Type Flow Rate
Unit (gallons/day)
Quantity Units Total Consumption (gallons/day)
1 Campground 75 per campsites
21 Campsites 1575
2 Park 5 per capita 25 125 3 Golf Course * 110561 4 Healthcare Centre 175 per bed 34 beds 5950 5 Town Office 15 per employee 25 employee
s 375
6 Elementary School and Library
16 per student 732 students 11712
7 Bowling Alley 75 per lanes 8 lanes 600 8 Senior's Drop-in
Centre 25 per person 50 persons 1250
9 Museum 125 per capita 100 persons 12500 10 Tennis Courts 80 per court per
hour 3 courts 240
11 Curling Rink 25 per unit 1 rink 25 12 Agrena and
Swimming Pool 10 per swimmer 1650 swimmer 16500
13 Ball Diamonds 5 per capita 800 persons 4000 14 Rodeo Grounds 5 per capita 60 persons 300 15 School District
Office 15 per employee 658 employee
s 9870
16 RCMP Detachment 125 per person 11 members 1375 17 Long Term Care
Centre 175 per bed 100 beds 17500
18 Park 5 per capita 100 persons 500 19 Provincial Building
(aspen health services)
175 per bed 142 beds 24850
20 Learning Centre (virtual school)
16 per teacher 6 teachers 96
21 Hotels 120 per room 101 rooms 12120 22 Motels 150 per units 27 units 4050
45
23 Senior Home 125 per capita 131 persons 16375 24 Estates 400 per lot 114 lots 45600 25 Park 5 per capita 30 persons 150 26 Fire and Ambulance 125 per capita 26 persons 3250
Industrial Park 10000 per unit 10 units 100000 High School 16 per student 630 students 10080 Conventional
residential 370 per unit 114 units 42180
Larger sized residential
550 per unit 13 units 7150
High density apartment
400 per unit 1 units 400
Occupied residential 475 per unit 1805 units 857375 Churches (11) 750 per church 11 Churches 8250 Commercial
businesses 2000 per unit 43 units 86000
Gas stations 400 per unit 7 stations 2800 Restaurants (16) 35 per seats 800 seats 28000 Total for
distribution 1443684
5% Backwashing 72184.2 10% Losses 721.842 Total Water
Demand 1516590
*Calculations for golf course:
π΄ππππππππππππ’ππ π(πππππ΄πππππππ₯πΆ) = 157500πT = 40πππππ
Assuming 2.9 acre-feet/irrigated turgrass acre (GCSAA, 2009),
πΊππππππ’ππ ππ€ππ‘ππππππππ = 37800000πππππππ π¦π = 103561.64
πππππππ πππ¦
Accounting for the restaurant operating in the golf course (200 seats),
πΊππππππ’ππ ππ€ππ‘ππππππππ = 103561.64πππππππ πππ¦ + 35
πππππππ πππ¦ β π πππ‘ β 200π πππ‘π
= 110561πππππππ πππ¦
46
Appendix E β Fire Flow Calculations
Table 17 β Fire Flow Demands
Design Area for Fire Flow 4800 m2
Coefficient Related to the Type of
Construction
1.0
Fire Flow 15242 L/min
Adjusted Fire Flow 15000 L/min
Deduction due to Low Hazard Occupancies 25%
Deduction due to Automatic Sprinkler
System
50%
Increase Due to Adjacent Building 10%
Design Fire Flow 6750 L/min
πΉ = 220πΆ π΄ = 220 1.0 4800 = 15242πΏπππ β 15000
πΏπππ
Low Hazard Occupancies Deduction β 25%
πΉ = 15000 β 0.75 = 11250πΏπππ
Automatic Sprinkler System Deduction β 50%
πΉ = 11250 β 0.5 = 5625πΏπππ
Adjacent Building Increase β 10%
πΉ = 11250 β 0.1 = 1125πΏπππ
Design Fire Flow
πΉ = 5625 + 1125 = πππππ³
πππ
47
Appendix F β Capacities of Component Structures Calculations
πππ₯πππ’ππππππ¦ππππ€ = 8,579πI
πππ¦
πππ₯πππ’πβππ’πππ¦ππππ€ = 12,679πI
πππ¦
πΉπππππππ€ = 6,750πΏπππ 0.001
πI
πΏ 1,440ππππππ¦ = 9,720
πI
πππ¦
Storage Calculations
Equalizing Storage:
The simulations of hourly fluctuations were based on problem 3 in the CIVE 421 Assignment 3.
Thus, the hourly consumption rates for Barrhead were obtained by assuming the same
consumption patterns but summing it up to the maximum daily flow of 8,579 m3/day. The
obtained hourly consumption rates for the town of Barrhead is summarized in Table 18.
Table 18 β Hourly Consumption Rates on Peak Day Demand
Time Water
Consumption
(m3/h)
Time Water
Consumption
(m3/h)
12:00:00 AM 0 1:00:00 PM 463.89
1:00:00 AM 178.42 2:00:00 PM 374.68
2:00:00 AM 160.58 3:00:00 PM 374.68
3:00:00 AM 160.58 4:00:00 PM 356.84
4:00:00 AM 178.42 5:00:00 PM 392.52
5:00:00 AM 231.95 6:00:00 PM 428.21
6:00:00 AM 267.63 7:00:00 PM 517.42
7:00:00 AM 371.71 8:00:00 PM 463.89
8:00:00 AM 481.73 9:00:00 PM 446.049
9:00:00 AM 570.94 10:00:00 PM 321.15
48
10:00:00 AM 535.26 11:00:00 PM 267.63
11:00:00 AM 481.73 12:00:00 AM 178.42
12:00:00 PM 374.68
πΈππ’ππππ§ππππ π‘πππππ(πl) = 6,000 β 4,600 πI = 1,400πI
πΉπππππππ€π π‘πππππ(πm) = (6,750πΏπππ)(0.001
πI
πΏ )(120πππ) = 810πI
πΈππππππππ¦π π‘πππππ(πn) = 0.25(πl +πm) = 0.25(1,400 + 810) = 552.5πI
πππ‘πππ π‘πππππ = πl +πm +πn = 1,400 + 810 + 552.5 = 2,762.5πI
Pumps and Water Treatment Plant Calculations
In order to provide for breakdowns and repair of pumps and water purification units, a reserve
unit is installed, which is the diesel-operated standby pump, in addition to the two continuously
operating pumps. Thus, the total unit count is 2 + 1 = 3.
πΏππ€ β ππππ‘ππ’πππ =32 πππ₯πππ’ππππππ¦ππππ€ =
32 β 8,579 = 16,393.5
πI
πππ¦
π»ππβ β ππππ‘ππ’πππ =32 πππ₯πππ’πβππ’πππ¦ππππ€ =
32 β 12,679 = 19,018.5
πI
πππ¦
πππ‘πππ‘ππππ‘ππππ‘πππππ‘ =32 πππ₯πππ’ππππππ¦ππππ€ =
32 β 8,579 = 12,868.5
πI
πππ¦
49
Appendix G β Water Levels in the Elevated Reservoir
The height of the water in the elevated reservoir on an average day:
(23 β 0.8)π = 22.2π
The height of the water in the elevated reservoir during a maximum daily water use:
Taking maximum average daily flow sustained for 12 hours as the critical flow, the maximum
volume of water leaving the reservoir can be calculated.
3690.94πΏ
πππ β 60πππβ β
πI
1000πΏ = 221.43πI
β β 12β = 2657.13πI
Subtracting this value from the volume of the reservoir to calculate for the volume left over in
storage,
2808 β 2657.13 πI = 150.87πI
Calculating for the height,
π =ππTβ4
β =4πππT =
4 150.87ππ(5πT) = 7.68π