1 September 1, 2015 Finance and Economic Development Committee Q2 2015 Operating Status and Year-End Forecast

City of Ottawa - Q2 2015 Status Report

Embed Size (px)

DESCRIPTION

City of Ottawa - Q2 2015 Status Report - Budget

Citation preview

Page 1: City of Ottawa - Q2 2015 Status Report

1

September 1, 2015Finance and Economic Development Committee

Q2 2015 Operating Status andYear-End Forecast

Page 2: City of Ottawa - Q2 2015 Status Report

2

2015 Year-End Forecast

§ $34 M forecasted deficit in tax supported services, excluding Transit, Police, Library and Public Health, from:§ Winter Maintenance activities § Arbitrated settlements§ Additional WSIB work related illnesses

§ $7 M forecasted deficit in rate supported services from:§ Cold weather and frozen pipes§ Lower water consumption

Page 3: City of Ottawa - Q2 2015 Status Report

3

Strategies to Cover the Deficit

§ Hiring and discretionary spending freeze

§ Capital project closure or reduction to return funds to the City Wide and Rate Reserves

§ 2015 Disposition Report in March 2016 will recommend use of reserve funds to cover deficit

Page 4: City of Ottawa - Q2 2015 Status Report

4

2016 Budget Implications

§ Additional costs from settlements and WSIB need to be covered

§ Winter maintenance accounts need to be adjusted

§ Water consumption estimates need to be reduced

Page 5: City of Ottawa - Q2 2015 Status Report

5

Questions?