33
EMS User’s Group 2008 Presented By Curtis Crews of ERCOT and Margaret Goodrich of Project Consultants, LLC Presented to EMS User’s Group Atlanta, GA September 8, 2006 CIM and Utility Integration

CIM and Utility Integration

  • Upload
    gaura

  • View
    29

  • Download
    1

Embed Size (px)

DESCRIPTION

CIM and Utility Integration. Presented By Curtis Crews of ERCOT and Margaret Goodrich of Project Consultants, LLC Presented to EMS User’s Group Atlanta, GA September 8, 2006. Topics. ERCOT Nodal Project Introduction Who is ERCOT What is Nodal The ERCOT Challenge The CIM Requirement - PowerPoint PPT Presentation

Citation preview

Page 1: CIM and Utility Integration

EMS User’s Group 2008

Presented ByCurtis Crews of ERCOT and Margaret Goodrich of Project

Consultants, LLC

Presented to

EMS User’s GroupAtlanta, GA September 8, 2006

CIM and Utility Integration

Page 2: CIM and Utility Integration

2© 2008 Project Consultants, LLC All rights reserved.

Topics

• ERCOT Nodal Project Introduction– Who is ERCOT– What is Nodal– The ERCOT Challenge– The CIM Requirement– Project Schedule

• Nodal Implementation Plan• Data Exchange Plan• CIM Implementation Plan• Operational to Planning Model Conversion• Lessons Learned

Page 3: CIM and Utility Integration

3© 2008 Project Consultants, LLC All rights reserved.

ERCOT Nodal Project Introduction – Who is ERCOT

• Grid covers 75% of Texas’ land and serves 85% of Texas’ load

• 38,000 miles of +60kV transmission lines

• 750 miles of 345kV lines added since 1999

• ~4000 miles of transmission lines over the next 5 years (wind)

• 70,000 MW of total resources

• 26,000MW of generation added since 1998

• ~4000 MW/yr of new generation over the next 5 years (wind)

• 63,056 MW peak load (8/17/2006)

• 5400 Bus Model

• ERCOT is a single control area with no seams issues

• ERCOT has 3 pairs of DC ties

• ERCOT has roughly 2000 model changes per year

ERCOT

Page 4: CIM and Utility Integration

4© 2008 Project Consultants, LLC All rights reserved.

ERCOT Nodal Project Introduction – What is Nodal

Zonal Market• Insufficient price transparency

• Resources grouped by portfolio

• Indirect assignment of local congestion

• Minimum number of Congestion Management

Zones

Nodal Market• Improved price signals

• Improved dispatch efficiencies

• Direct assignment of local congestion

• 4000 Nodes

Page 5: CIM and Utility Integration

5© 2008 Project Consultants, LLC All rights reserved.

ERCOT Challenge is unique in North American Interconnected Grids

Unique ERCOT Characteristics

Intra-state electric interconnection

Single regulatory body – Public Utility Commission of Texas (PUCT)

Registration is unique in Texas Unique provisions for Non Opt-In

Entities (Munis and Coops) in Texas Requirement to model equipment at

lower voltages (down to 60kV)

High pace of economic growth in Texas

Wholesale and Retail scope impact

Metering and data aggregation is unique at ERCOT

Texas consumers and market participants expect benefits similar to that of other ISOs in the Nodal market, but ERCOT differs significantly in technical protocols, governance, organizational structure and economic landscape.

Page 6: CIM and Utility Integration

6© 2008 Project Consultants, LLC All rights reserved.

The CIM Requirement

• The principal binding document (the ERCOT Nodal Protocols signed into Order, Docket #31540) established the requirements for the Nodal Program

• Document was approved by the PUCT & the Market Participants

• Section 3.10 (7) states: ERCOT shall use an automated process to manage the CIM-compliant packages loaded into the Network Operations Model as each construction phase is completed.

• Section 3.10 (8) states: each change must be posted using the CIM data exchange format showing incremental changes to the last posted ERCOT Network Operations Model

• Section 3.10.4 (8) states: ERCOT shall provide model information through the use of the Electric Power Research Institute (EPRI) and NERC-sponsored Common Information Model (CIM) and Web-based XML communications.

Page 7: CIM and Utility Integration

7© 2008 Project Consultants, LLC All rights reserved.

Initial Project Schedule

• The PUCT, the Texas Legislature, and the Market Participants defined the Schedule as follows:

– CIM Model and all CIM Data Exchange functions to Go Live on March 31, 2008

– Real-Time Operations to Go Live on December 1, 2008

– Day Ahead and CRR Market to Go Live on December 08, 2008

• This schedule gave ERCOT less than 3 years to select the vendors and implement the Nodal Market.

• All RFPs were written, distributed and all Vendors were selected by June 2006 – AND THE PROJECT BEGAN….

Page 8: CIM and Utility Integration

8© 2008 Project Consultants, LLC All rights reserved.

Nodal Market Scheduled to Go Live December 2008

EMS

Trials & Implementation

MMS

CRR

MIS

NMMS

Commercial Systems

ERCOT & MP Readiness

Q2 2008 Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006 Q4 2007 Q1 2008Q3 2006 Q1 2009

Integration

EDW

Q2 2009

EDS 3

MMS FAT ITEST

CRR Design, Build, Pre-FAT CRR FAT ITEST

Final MP Interface Specs

3/31

12/01/08Real Time Operations

GO LIVE

MIS (EMS/MMS/CRR) Design, Build, Pre-FAT

EDW FAT ITEST

StatementsLayout

Script test

ITESTEMS EMS FATEMS Requirements, Conceptual Design

ITESTMIS (SCED) Design, Build, Pre-FAT MIS FAT

MMS Design, Build, Pre-FATMMS Requirements, Conceptual Design

ITEST

OS Build

FAT

OS Requirements, Conceptual Design

CRR Requirements, Conceptual Design

Commercial Systems Design, Build, Pre-FAT CS FAT ITEST

EDW Requirements, Conceptual Design

ITESTSCED Build SCED FATSCED Requirements, Conceptual Design

Registration ready

Business Requirements

complete 10/30

Preliminary MP Interface

Specs 12/31

CS Requirements, Conceptual Design

EDW Design, Build, Pre-FAT

MIS FAT ITEST

EDS 4 Go-live Trans.

OTS ITEST

OTS FAT

EDS 3 Mote & ERCOT UAT

Planning UI

FAT ITEST

Naming Convention DB

Common model update processNMMS Conceptual Design

Naming Convention information collection

Model Data Certification Model Data Remediation Reconciliation

NMMS Build

Outage Scheduler

EDS 1/2

Build FAT ITESTRequirements, Conceptual Design

ITESTOS FAT

6/30/08LMP Market

Readiness Criteria

MET

Q3 2007

Operations UI

Qualification Freeze

Registration complete

168 hour market trials

End of Trials

MP Nodal Registration MP Financial & Operational Qualification

MPSCED Offers

Begin MP trial participation

3/31/08Single Entry Model

GO LIVE12/08/08

Day Ahead Market/CRR

GO LIVEZonal Shutdown

GO/NO GO

Page 9: CIM and Utility Integration

9© 2008 Project Consultants, LLC All rights reserved.

Project Schedule

• The schedule was too aggressive

• The schedule did not include sufficient time for integration of the systems

• The initial schedule will not be met.

• An assessment is underway and a new schedule will be completed soon.

Page 10: CIM and Utility Integration

EMS User’s Group 2008

10

Nodal Implementation Plan

Page 11: CIM and Utility Integration

11© 2008 Project Consultants, LLC All rights reserved.

ERCOT’s Zonal Implementation

KeyERCOTSiebelAreva

ManualLODESTAR

Other

MP Registration

Market Operations

OSGenesys

EDWTML EMS

CM&M

Load F MOS

Business and Engineering Model

SettlementMid Term Day Ahead Real Time

User Interface Power Operations

QSE Systems

S&B

Integration

IMM

Current Application Vendors

B&S Billing & Settlements CRR Congestion Revenue Rights CM&M Credit Monitoring & Management DAM Day-Ahead Market EDW Enterprise Data Warehouse FT Financial Transfer IMM Independent Market Monitor LF Load Forecast MIS Market Information System MP Reg Market Participant Registration NMMS Network Model Management System OS Outage Scheduler RUC Reliability Unit Commitment SCED Security Constrained Economic Dispatch

Page 12: CIM and Utility Integration

12© 2008 Project Consultants, LLC All rights reserved.

ERCOT Nodal Implementation

KeyERCOTSiebel

SiemensABB

ArevaROME

AWS TruewindNexant

LODESTARUISol

EnterpulseOther

MP Registration

Market Operations

OS CRRNMMS

EDWMIS EMS

DAM

CM&M

Load F SCEDRUC

Business and Engineering Model

SettlementMid Term Day Ahead Real Time

User Interface Power Operations

QSE Systems

S&B

Tibco Integration Bus

IMM

RPPF

Nodal Application Vendors

B&S Billing & Settlements CRR Congestion Revenue Rights CM&M Credit Monitoring & Management DAM Day-Ahead Market EDW Enterprise Data Warehouse FT Financial Transfer IMM Independent Market Monitor LF Load Forecast MIS Market Information System MP Reg Market Participant Registration NMMS Network Model Management System OS Outage Scheduler RUC Reliability Unit Commitment SCED Security Constrained Economic Dispatch

Page 13: CIM and Utility Integration

13© 2008 Project Consultants, LLC All rights reserved.

Majority of ERCOT Systems to be replaced or upgraded…

MP Registration

Market Operations

OS CRRNMMS

EDWMIS EMS

DAM Commercial Applications

CM&M

LF SCEDRUC

Business and Engineering Model

SettlementMid Term Day Ahead Real Time

User Interface Power Operations

IMM

Integration (information bus)

B&S Billing & Settlements CRR Congestion Revenue Rights CM&M Credit Monitoring & Management DAM Day-Ahead Market EDW Enterprise Data Warehouse FT Financial Transfer IMM Independent Market Monitor LF Load Forecast MIS Market Information System MP Reg Market Participant Registration NMMS Network Model Management System OS Outage Scheduler RUC Reliability Unit Commitment SCED Security Constrained Economic Dispatch

Degree of change100% New/replacement

>50% Upgrade/enhancement

<10% Enhancement

QSE Systems

RPPF

Integration Architecture is being upgraded to improve flexibility and maintainability

Page 14: CIM and Utility Integration

EMS User’s Group 2008

14

Data Exchange Plan

(AKA NMMS using CIM/XML RDF Standards)

Page 15: CIM and Utility Integration

15© 2008 Project Consultants, LLC All rights reserved.

Data Exchange Plan

• Integration had to handle exchange of data between 13 different systems.

• There were 4,000 separate and distinct data exchanges that had to be completed – point to point integration was not possible

• The data also had to be available to all ERCOT stakeholders

• ERCOT had to have a single, well documented and well understood data format that was not proprietary that all vendors could embrace

• It was decided the only way to complete integration in time was to use the CIM as the foundation to maintain, distribute and exchange the data

• This data exchange would include all models, model files and messages.

Page 16: CIM and Utility Integration

16© 2008 Project Consultants, LLC All rights reserved.

Data Exchange Plan

• Create a central repository Database with a GUI and features to import, export and validate models and model changes

• Generate all models for all processes (and Vendors)

– Repository for all model information

– Both full and incremental CIM files

– Use CIM/XML RDF Standards for file exchange format

• Accept incremental modeling updates in CIM/XML RDF standard file exchange format

– Submitted by the Market Participants (TSP, RE)

Page 17: CIM and Utility Integration

17© 2008 Project Consultants, LLC All rights reserved.

The Big Picture – NMMS: the CIM Repository

Page 18: CIM and Utility Integration

18© 2008 Project Consultants, LLC All rights reserved.

NMMS Scope and Value Proposition

• NMMS High Level Scope Summary:• Consistency between Operations and Planning models• Streamlined method of entering modeling changes • Common Industry Standard Format for submitting and

posting model data, to eliminate a significant amount of manual work

• Faster, more efficient method of loading models and ability to provide multiple time-based models

• Improved tracking of model changes

Page 19: CIM and Utility Integration

19© 2008 Project Consultants, LLC All rights reserved.

ERCOT NMMS system provides Transmission Service Providers and ERCOT staff with the capability to submit changes to the network model electronically

Via a Graphical GUI interface

Via a CIM/XML RDF Incremental File or a CIM/XML RDF Full Model

NMMS performs initial validation on connectivity, equipment uniqueness, and basic constraints to reduce errors

NMMS exports the changes in a CIM/XML RDF Incremental file for each change that is submitted

NMMS generates CIM/XML RDF Incremental files or Full Models for all Downstream systems and the Transmission Service Providers.

Common Data Entry

Page 20: CIM and Utility Integration

20© 2008 Project Consultants, LLC All rights reserved.

Time Based Models

Capability to provide time based models on a consistent basis

Sending the same model to multiple destination applications for any future date

NMMS is a single model generating solution for all downstream applications at ERCOT.

NMMS can create both CIM/XML and PSSE file formats

Page 21: CIM and Utility Integration

EMS User’s Group 2008

21

CIM Implementation Plan

Page 22: CIM and Utility Integration

22© 2008 Project Consultants, LLC All rights reserved.

CIM Definition – Obligatory Slide

•CIM is…– An information model that describes real-world objects and their

interrelations within the electric power industry

– A format for exchanging information

•Why is it important?– Provides a standard way of depicting data

– Enables the integration of multiple applications and vendors

– Facilitates bulk and incremental model exchange

Common Information Model (CIM)

Page 23: CIM and Utility Integration

23© 2008 Project Consultants, LLC All rights reserved.

ERCOT CIM – Namespaces and Profiles

Name Space - CIM

Name Space – Siemens (SPC)

Name Space – ERCOT (ETX)

= +Vendor

AVendor

BVendor

CName Space

CIM

SPC

ETX

CIM

ETX

ETX

ETX

T TT

F TT

F TF

T FF

F TT

T TT

T FF

Attribute 1

Attribute 2

Attribute 3

Attribute 4

Attribute 5

Attribute 6

Attribute 7

Vendor CName Space - C

Vendor AName Space - A

Vendor BName Space - B

• Required non-CIM attributes must be added to a separate namespace

• There are 3 namespaces that make ERCOT CIM

•CIM

•SPC – Siemens

•ETX – ERCOT

Page 24: CIM and Utility Integration

24© 2008 Project Consultants, LLC All rights reserved.

CIM Extension Statistics (to date)

12 new packages defined: ETXContingency, ETX, ETXLoadModel, ETXMonitoring, ETXNetwork, ETXPlanning, ETXRating, ETXRegulation, ETXSCADA, etc

Roughly 140 new Classes

Roughly 850 new Attributes

Roughly 250 Associations

Roughly 70 Data Types defined

Roughly 150 Data Type enumeration defined

ERCOT is continuing to work with all vendors to ensure that the extensions will work in downstream applications (e.g. EMS, MMS, etc)

For each downstream system, a profile is created that contains each CIM Class, Attribute and Association required for that system.

Page 25: CIM and Utility Integration

25© 2008 Project Consultants, LLC All rights reserved.

ERCOT CIM Profiles

ERCOT NMMS CIM Repository provides profile data exchange files for each of the following applications:

Emergency Management System (EMS) – Real-Time Model

Outage Scheduling (OS) – Model Topology

Outage Evaluation (OE) – Time Based Models

Operation Training Simulator (OTS) – Real-Time Model

Market Management System (MMS) – Day Ahead Model

Planning (PSS/E) – PSS/E Bus Branch Model

Congestion Revenue Rights (CRR) – Augmented Bus Branch Model

Settlements and Billing (S&B) – Small Profile Settlement Data File

Page 26: CIM and Utility Integration

EMS User’s Group 2008

26

Operational to Planning Model Conversion

Page 27: CIM and Utility Integration

27© 2008 Project Consultants, LLC All rights reserved.

Operational to Planning Model Conversion

Requires ERCOT to transfer and convert Operations modeling (Breaker level) data to Planning (Bus-Branch level) data

Requires business process in adding new equipment into the network model and conversion of the new equipment to planning models

Requires fast performance

NMMS solved this by creating a back end API to convert Operations models to Planning models

Page 28: CIM and Utility Integration

28© 2008 Project Consultants, LLC All rights reserved.

Operational to Planning Model Conversion

• NMMS provides the tools and interfaces to create a Planning Model from the Operational Model.

• Planning Model is generated from the Operations Model• A Topology Processor is used to modify the Operations Model • The Topology Processor has options that may be selected

based on the planning or CRR needs:– Consolidate Transformers to Three Winding Transformers– Distribution System Reduction– Remove Parallel Zero Impedance Branches

• Defined CIM Extensions for Planning and submitted to the EPRI CIM for Planning project for review and possible submission to the IEC standards group.

Page 29: CIM and Utility Integration

29© 2008 Project Consultants, LLC All rights reserved.

NMMS High Level Architecture

• Network operation and Planning use a single platform with multiple applications and business processes to generate models

• Single set of user interfaces for submitting changes for Market Participants

• Single application architecture allows for “soft” coupling of application systems.

Network Operation Model Planning Model

Page 30: CIM and Utility Integration

30© 2008 Project Consultants, LLC All rights reserved.

Consistent Network & Planning Models

Traditional network modeling practices are for planning and operations organizations to use separate topological representations

ERCOT Nodal Protocols states that Planning models must be consistent with Operations models.

ERCOT will convert Operations models to Planning models on a time basis, including approved future based changes

Page 31: CIM and Utility Integration

EMS User’s Group 2008

31

Lessons Learned

Page 32: CIM and Utility Integration

32© 2008 Project Consultants, LLC All rights reserved.

Lessons Learned

• Know your Data and define the following prior to extending the CIM:

– Data Owner – this is the primary source of the Data

– Data Consumer – what applications need a specific data element. This needs to be as detailed as possible

– Make this the first part of the project and do not define the final integration plan until this effort is complete

• Do not try to implement every system across the enterprise at the same time.

• Set up Phases that bring value add to the organization as each phase is completed.

• Each phase should be small enough to complete in one year

• Get management complete buy-in and keep it with the phased successes

Page 33: CIM and Utility Integration

33© 2008 Project Consultants, LLC All rights reserved.

Contact for Additional Information

•Curtis Crews – ERCOT

– Email: [email protected]

•Margaret Goodrich – Project Consultants, LLC

– Email: [email protected]