Upload
shawn-knox
View
219
Download
0
Embed Size (px)
Citation preview
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
1/14
EXECUTIVE REPORT
C O O P R E F I N E R Y C O M P L E X I N C I D E N T
D E C E M B E R 2 4 , 2 0 1 3
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
2/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page1
TechnicalSafetyAuthorityofSaskatchewanEXECUT IVE REPORT
CO OP REF INERY COMPLEX INC IDENT DECEMBER 24 , 2013
INCIDENTSUMMARYOnDecember24,2013atapproximately3:25pmlocaltime,anexplosionoccurredinthePolymerization
Unit27(PMU)attheCoopRefineryComplex(CRC)inRegina,Saskatchewan. Theensuingfirewas
extinguishedatapproximately9:00pmlocaltimeonDecember24,2013. Theblastandfiredestroyedthe
equipmentandstructurearoundreactors1,2and3inthePMU. TheremainingfivereactorsinthePMU
sufferedblastandpostincidentfreezingdamage,andwererenderedunusable. Blastdamagealso
occurredtoCRCbuildingsandequipmentoutsideofthePMU. Blasteffectswerealsofeltatlocations
outsidetherefinerycomplex. Nopersonnelwereinjuredintheincidentorinthesubsequentemergency
response. Figure1showsapartialviewoftheexplosionfromaCRCsurveillancecamera. InFigure1,the
PMUisnotwithintheviewofthesurveillancecamera,butislocatedoutsidetheupperleftoftheimage.
Figure1: Explosionat3:25PMDecember24,2013
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
3/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page2
REFINERYDESCRIPTION
LocatedinRegina,Saskatchewan,theCoopRefineryComplex(CRC)isawhollyownedsubsidiaryof
FederatedCooperavesLimited(FCL)whichownsandoperatestheCoopRefineryComplex(CRC)
facilies.
TheCRCwasincorporatedonApril1,1934,andonMay27,1935produconof500barrelsofcrudeoilper
daybegan.TheCRCcelebratedits79thyearofoperaonin2014.
CRCFactsandHighlights:
Occupies575acresoflandinNorthRegina;
Employsover800peopleonapermanentbasis;
Employsandcontractsover1,000addionalpeopleduringpeakmaintenanceperiodsand
turnarounds;
A$2.7billionprojecttoexpandandrevamptheCoopRefineryComplexwascompletedin2013;
TheexpandedCRCcurrentlyhasabalancedproductcapacityof130,000BPDandpotenalfor145,000BPD;
Approximately36.5millionbarrelsofcrudewereprocessedin2013,a20percentincreaseover
2012andthelargestvolumeprocessedinthehistoryoftheCRC.
INVESTIGATIVEPROCESS
TheinvesgaonbeganwithemergencyresponsebyReginaFireandProtecveServices(RFPS)ontheday
ofDecember24,2013.RFPSsecuredthesceneandbeganinialassessmentsandevidencecolleconon
December25,2013. TheTechnicalSafetyAuthorityofSaskatchewan(TSASK)iniateditsinialdata
colleconandassessmentonDecember24,2013.OnJanuary7,2014TSASKandRFPSformedajointinvesgaonteamcomprisedofmembersfrombothorganizaons.
PMUDESCRIPTION
ThepurposeofthePMUistotakelightolefinsresulngfromtheFluidCatalycCrackingUnit(FCCU)
processandpassthemoveraphosphoricacidcatalystinsidepolymerizaonreactorstoproduceahigher
molecularweightproductcalledpolygasoline. ThePMUreactorsoperateatapproximately1060psig
internalpressureat390F. ThePMUhadatotalofeightpolymerizaonreactorsandadisllaonsecon
forpropane,butane,andgasolineseparaon. The"frontend"oftheunitincludesanaminetreatment
seconandcauscandwaterwashestoremovecontaminantsfromthefeedstock. Figure2illustratesthe
PMUpriortotheincident. Theunitisdesignedto:
1. Collect"polyfeed",propane,butane,andolefinsforchargetothereactors;
2. Treat"polyfeed"forhydrogensulfide,mercaptan,andnitrogencompoundremoval;
3. Processolefinsoveracatalystbedtocreatepolygasoline;
4.
Distillandseparateoutpropane,butane,andpolygasolineproducts.
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
4/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page3
OPERATIONSIMMEDIATELYPRECEDINGTHEEXPLOSION
Prior
to
the
incident
on
December
24,
2013,
the
PMU
was
opera
ng
within
normal
parameters
forfl
ows,
pressuresandtemperatures. Operatorsdidnotobserveanythingoutoftheordinaryduringprocess
operaonsthatday. ThefirstindicaonofaprobleminthePMU,asreportedbywitnesses,wasawhistling
noiseanumberofsecondspriortotheexplosion. Instrumentaonforpolyfeedflowtoreactors#1and#3
inthePMUrecordedbaddataqualitysignals16secondspriortotheappearanceoftheexplosionona
surveillancecamera. Thebaddataqualitysignalswerecausedbytheescapeofpolyfeedfromarupturein
thepipinginthePMU.
Figure2: PolymerizaonUnit27(PMU)Before
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
5/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page4
INCIDENTANALYSIS
Preceding MaintenanceOutages
IntheweeksbeforetheDecember24,2013incident,thereweretwoPMUmaintenanceoutages,as
follows:
Outage1: ThePMUwasshutdownbetweenNovember26,2013andDecember4,2013duetoa
maintenanceoutageontheupstreamfluidcatalyccrackingunit(FCCU). Sincethisresultedin
shutdownofthepolyfeedfromtheFCCUtothePMU,opportunitywastakentoperform
maintenanceinthePMU. AnumberofmaintenanceitemsinthePMUwereidenfiedand
completed.
Outage2: ThePMUwasshutdownbetweenDecember12,2013andDecember18,2013dueto
anothermaintenanceoutageontheupstreamFCCU. Thisoutageagainresultedinshutdownof
feedfromtheFCCUtothePMU,althoughtherewasnomaintenanceperformedinthePMUduring
thisoutage.
Outage1: November 26, 2013 December 4, 2013
InordertopreparetheFCCUforthemaintenanceacviesduringoutage1,awaterfloangprocedure
wasusedtopurgehydrocarbonsfromtheFCCUpipingandvessels. Waterfloanghadhistoricallybeen
usedforthepurposeofpurginghydrocarbons. Waterfloangisaprocessthatulizeswatertoflush
hydrocarbonresiduefromthesystemandrenderthepipingandvesselsfreeofexplosivehydrocarbonsand
safeforwork. Theintentwasforthewaterfloangproceduretointroducewateruptothewaterbooton
thecombinedfeeddrum,whichislocatedupstreamofthePMUreactors. Itwasintendedthat
instrumentaonandasightglassonthewaterbootofthecombinedfeeddrumwouldbeusedtodetect
thewaterleveltoenabletheintroduconofwatertobeproperlystoppedatthatpoint. ThecombinedfeeddrumwaslocatedupstreamofthePMUreactors,andlimingthewateratthecombinedfeeddrum
waterbootwouldprecludeanywaterfromreachingthePMUreactors.
Duringoutage1,thewaterfloangprocedurewasiniatedduringthenightshi ofNovember26,2013,as
planned,buttheprocessfailedtostopthewateratthecombinedfeeddrumwaterboot. The
instrumentaonatthewaterbootwasdefecveandthesightglasswasdifficulttoread. Waterwas
pumpedpastthecombinedfeeddrumandintothePMUpipingandreactors. Thepumpingofwaterinto
thePMUpipingandreactorswasnotintended. Theshutdownguidelinesforbothoutagesspecifiedthat
thepolymerizaonreactorsweretobepurgedwithnitrogengasastheyweretakenoffline. Figure3
illustrates
the
planned
and
es
mated
actual
extent
of
waterfl
oa
ng,
as
well
as
a
schema
c
representa
on
ofapolyfeedbypassline.
MaintenancepersonnelbegandrainingwaterfromthePMUonNovember27,2013,however,issueswith
freezingwaterwereencounteredasthisprocesswasundertaken,especiallyastemperaturesdroppedat
night. Waterdrainingandicethawingacviesconnuedthroughtheremainderofoutage1. Thawing
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
6/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page5
methodsincludedthewrappingofsteamtracelinesaroundprocesslines,aswellastheinseronofsteam
lancesintopipinginsulaonjackets.
Duringoutage1,outdoortemperaturesdroppedconsiderablytowardtheendoftheoutage,ascanbeseen
inthemelineandtemperaturedatashowninFigure4.
Figure3: WaterFloangExtent
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
7/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page6
Nov. 26, 2013
Outage 1 begins.
Maintenance work
in FCCU and PMU
is performed
during this outage.
Water floatingprocedure done on
night of Nov. 26
accidentally
introduces water
into the PMU
including bypass
line 123BPL.
Dec. 5, 2013
Operations resume.Numerous frozen
lines in the PMU
require thawing.
Bypass line 123BPL
was found frozen
and was thought to
have been thawed.
Dec. 24, 2013
Operations are
within normal
parameters with
no indication of a
problem.
Rapidly rising
temperatures
cause the ice plug
in bypass line
123BPL to thaw
and allow high
pressure poly
feed to escape
from the rupture in
the bypass line.
The hydrocarbons
ignite causing an
explosion in the
PMU.
Dec. 19, 2013
Operations resume and are within normal
parameters during Dec. 19 23 with no
indication of a problem.
At some point, ice formation in bypass line
123BPL causes the bypass line to rupture.
An ice plug remains inside bypass line
123BPL, preventing the escape of poly
feedDec. 12, 2013
Outage 2 begins.
Maintenance done
to pressure relief
valve in FCCUresulting in feed
outage to the PMU.
Water floating not
done in this outage.
Dec. 23, 2013
The coldesttemperatures
during the period
Nov. 26 Dec. 24
are reached
during the early
morning hours of
Dec. 23.
Figure4: TimelineofEvents NovembertoDecember,2013
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
8/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page7
Unit OperationDecember 5, 2013 December 11, 2013
AstheFCCUandPMUweregraduallybroughtbacktooperaonaeroutage1,manyfrozenprocesslines
connuedtobefoundandrequiredthawinginordertomakeprogress. ThePMUreactorinletsandoutlets
werefoundfrozen. Thereactorfeedbypassline123BPLwasalsofoundfrozen. Gradually,processlines
werethawedandunitoperaonwasachievedbyDecember6,2013.
Reactorfeedbypassline123BPL,locatedadjacenttoPMUreactor2,isapartofthePMUandservesto
divertfeedstockflowaroundPMUreactors1,2and3whenflowthroughthereactorsisnotneeded. Flow
throughreactorfeedbypassline123BPLwasnotnecessaryduringthestartupandoperaonofthePMU,
andthislineisnormallyclosedduringPMUoperaon. Bypassline123BPL,showninFigure5,formsa
naturaldeadlegwhentheblockvalveslocatedattheboomofthelineareclosed. Deadlegsare
componentsofapipingsystemthatnormallyhavenosignificantflow. Deadlegscanaccumulatewaterand
freezemorereadilythanpipingthatisopentoflow. Deadlegsfrequentlyrequiregreateraenonwhen
thawinganddraininginordertoachievecompleteclearing. Operatorswereunderthebeliefthattheyhad
thawedanddrainedbypassline123BPLduringtheireffortstoachieveunitoperaon. Thethawingand
drainingofthefrozenlineswasnotsystemacanddocumented,butreliedonoperatorexperseand
memory. Theinvesgaondeterminedthatbypassline123BPL,infact,wasnotproperlydrainedofwater.
DuringtheperiodofoperaonfromDecember5,2013toDecember11,2013temperatureswerecold
throughoutascanbeseeninthemelineandtemperaturedatashowninFigure4.
Outage2:December12 December18,2013
Thepurposeofoutage2wastorepairafailedpressurereliefvalveintheFCCU,againresulnginshutdown
ofthePMUduetoaninterruponoffeedfromtheFCCU. Duringthisoutage,procedureswererevisedin
ordertomigatethefreezingissuesexperiencedduringoutage1,andwaterfloangdidnotimpactthe
PMUreactorsandpiping. Addionally,nomaintenanceacvieswereperformedinthePMU. Theshutdownandsubsequentstartupaeroutage2wentrelavelysmoothly,withnoaddionalfreezing
issues.
Theinvesgaondeterminedthatthebypassline123BPLlikelyremainedfilledwithwaterthroughoutage
2.
Duringoutage2,temperatureswarmedupconsiderably,peakingat0ConDecember16,2013,andthen
droppeddramacallytoastaclowof24Cwithawindchilllowof34Cattheendofoutage2on
December18,2013,asshowninFigure1.
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
9/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page8
Figure5: RupturedBypassLine123BPL
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
10/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page9
UnitOperaonDecember19,2013December24,2013
TherewerenofreezingissuesthataffectedunitstartupandoperaonduringDecember19to24,2013.
ThePMUfunconedwithinnormalparametersforpressures,temperaturesandflowsduringthisperiod.
Operatorswerenotawareofanyprocessproblemsthatcouldleadtoacomponentfailureduringthis
period.
OutdoortemperatureswereverycoldfromDecember19,2013toDecember21,2013. Beginningon
December22andconnuingintoDecember23outdoortemperaturesdroppeddramacallytoastaclow
of35Cat2:00AMonDecember23andawindchilllowof47Cat6:00AMonDecember23. These
were,infact,thecoldesttemperaturessincethewaterfloangprocedureofNovember26,2013.
Thebypassline123BPLdeadlegcontainedwaterthroughoutthecoldweatherthatoccurredbetween
November26,2013andDecember24,2013. Waterinthelinefrozeandrupturedthelinedueto
hydrostacoverstressatsomepointduringthisperiod. Aniceplugexistedwithinthelineandcreateda
sealwhichpreventedtheescapeofhighlyvolalepolyfeedthroughthepiperupture.
Beginningat6:00AMonDecember23,2013thetemperaturebegantorisedramacally,peakingat2Cat
2:00PMonDecember24,2013.
OnDecember24,2013unitoperaonswerewithinnormalparameters. DuetotheChristmasholiday,a
numberofoperaonsstaff hadle earlythatday,resulnginmuchfewerthannormalpersonnelaround
thePMUasthedayprogressed.
Asoutdoortemperatureswarmed,combinedwithheatfromunitoperaons,theicepluginbypassline
123BPLthawedandeventuallygavewaytothehighpressurepolyfeed. At3:25PMthiscausedasudden
releaseofhydrocarbonsintothePMU,followedbyalargeexplosionandensuingfire. Theexplosionand
firewerecentredonPMUreactors2and3,resulnginextensivedamagetothePMUstructurearound
reactors1,2,3. TheexplosioncausedblastdamagetootherareasofthePMUaswellastosurrounding
buildingsinotherunits. TheblastwasfeltinareasofReginawelloutsidetherefinerycomplex.
Figure5showstherupturedbypassline123BPLaertheincident. Figure6showstheextentofdamageto
thePMU.
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
11/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page10
Figure6: DamagetothePMU
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
12/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page11
FINDINGSANDRECOMMENDATIONS
1. Proceduresforcoldweathershutdownshouldberevisedtoimprovedecisionmakingandthe
idenficaonofcondionswhencoldweathershutdownispermissibleandcondionswhenitis
not.
Proceduresforcoldweathershutdownwereinadequate,astheydidnotconsiderthehighrisksposedbyextremecold.
2. Proceduresforincidentinvesgaonshouldberevisedtoensurethatcorrecveaconsare
implementedsothatincidentsdonotrepeat.
AsimilarpiperuptureduetofreezingoccurredinDecember,2008,wheretheresulngvapour
clouddidnotignite. Effecvecorrecveaconswerenotimplemented.
3. CRCshouldestablishawrienfreezeproteconprogramthatincludestheidenficaon,
migaon,managementofchangeandauditrequirementsforequipmentatriskduetofreezing.
4. Proceduresforwaterfloangshouldberevisedtoensurethatinstrumentaonandprocess
controlsareeffecveandmaintained. Addionalredundancyininstrumentaon,controlsand
verificaonmethodsshouldbedeveloped.
Theprimaryelectronicinstrumentforwaterlevelmeasurementatthecombinedfeeddrum
waterbootwasaFisher2500pneumacleveltransmier. Thisinstrumentwasfoundtobe
defecvewhentestedduringtheinvesgaon. Historicaldatafromtheinstrumentwas
reviewedandconfirmedthattheinstrumentwasdefecveonNovember26,2013.
Asightglassservedasasecondaryinstrumentforthewaterlevelmeasurementinthe
combinedfeeddrumwaterboot. Thissightglasswasoperaonal,butwasdifficulttoread
becausetheappearanceofwaterandpolyfeedarenearlyidencal.
5. Thawingproceduresshouldberevisedtoensureallareasareaddressedsystemacally,especially
deadlegs.
Thawingprocedureswereinadequateinthattheydidnotsystemacallythawallvulnerable
locaons. Thawingrelieduponoperatorknowledgeandmemoryofvulnerablelocaonsas
opposedtoadocumentedandsystemacapproach.
6.
CRC
should
adopt
the
deadleg
defi
ni
on
set
out
in
the
American
Petroleum
Ins
tute
standard
570
andensurethisdefinionisunderstoodacrosstheorganizaon.
Inthecourseoftheinvesgaondifferinginterpretaonsofwhatconstutesadeadlegwere
apparentatCRC.
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
13/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page12
7. Deadlegsinpipingshouldbesystemacallyidenfied,documentedandeliminatedorotherwise
migatedwhereverpossible. Deadlegsthatmustremainshouldbehighlightedandgivenspecial
aenonthroughoutoperaonsandmaintenanceacvies.
Thedeadlegonbypassline123BPLallowedwatertobecometrapped. Thiswatersubsequently
frozeandrupturedtheline,causingthehydrocarbonleakandexplosionofDecember24,2013.
8. Maintenanceproceduresshouldberevisedtoensurethatcricalsensingandmonitoring
equipmentremainsfunconal.
TheFischer2500pneumacleveltransmieratthecombinedfeeddrumwaterbootwas
foundtobedefecve.
9. CRCshouldsystemacallyidenfywhereinstalledpipingdiffersfromthedesignspecificaons. The
differencesshouldbeanalyzedandsuitablyaddressedasnecessary.CRCshouldinvesgate
whethercorrosionsurveydatacouldbeusedtoidenfywherepipingdoesnotconformtodesign
specificaons.
Althoughnotacauseofthisincident,inthecourseoftheinvesgaonbypassline123BPLwas
foundtobe2Schedule80,whiledesigndocumentsspecifiedthislinetobe2Schedule160.
2Schedule80hasawallthicknesswhennewof0.218,whereas2Schedule160hasawall
thicknesswhennewof0.344.
Thicknessmonitoringlocaons(TML)onbypassline123BPLwerelocatedatthetopelbowand
theboomelbow,bothlocaonsbeingwellawayfromtherupturedarea. CRCthickness
monitoringdataofOctober29,2013showsawallthicknessof0.220atthetopelbowanda
wallthicknessof0.200attheboomelbow.
10.CRCshouldreviseitscorrosionsurveyprocedurestoassesscorrosionunderinsulaon(CUI)on
jacketedandinsulatedcomponents. Thecorrosionsurveyproceduresshouldulizemethodsto
idenfyandassessareaswherecorrosionisthegreatest.
Althoughnotacauseofthisincident,significantexteriorcorrosionwasfoundonbypassline
123BPL. Bypassline123BPLwasjacketedandinsulated.
Datafromthicknessmonitoringlocaons(TML)onbypassline123BPLdidnotdetectthe
exteriorcorrosionthatwasfound. TheTMLswerenotlocatedattheareawheretheCUIwas
found.
CUIonbypassline123BPLresultedinawallthicknesslossofupto27%.
Theplacementofsteamlancesinsideinsulaonjacketsforthepurposeofthawingfrozenlines
isacommonpracceatCRC,andthismayplayaroleinCUI.
8/10/2019 Christmas Eve refinery explosion cause by frozen, ruptured pipe
14/14
TechnicalSafetyAuthorityofSaskatchewanExecuveReport
October2014
Page13
GLOSSARYOFTERMSANDABBREVIATIONS
BPDbarrelsperday
BypassLine123BPLThe2polyfeedbypasslinelocatednearthenorthsideofpolymerizaonreactor#2. Thisbypasslinedivertspolyfeedflowaroundpolymerizaonreactors#1,2and3.Thisbypassline
isdesignatedonCRCdrawingsas27P1070FA5A2IH.
CRC CoopRefineryComplex
CUICorrosionUnderInsulaon
DeadlegsComponentsofapipingsystemthatnormallyhavenosignificantflow.Someexamples
includeblankedbranches,lineswithnormallyclosedblockvalves,lineswithoneendblanked,
pressurizeddummysupportlegs,stagnantcontrolvalvebypasspiping,sparepumppiping,levelbridles,
reliefvalveinletandoutletheaderpiping,pumptrimbypasslines,highpointvents,samplepoints,
drains,bleeders,andinstrumentconnecons.
FCCUFluidCatalycCrackingUnit
PMUPolymerizaonUnit27
PSIGPoundspersquareinch,gage. Ameasureofpressure.
RFPSReginaFireandProtecveServices
TMLThicknessMonitoringLocaon
TSASKTechnicalSafetyAuthorityofSaskatchewan