CE-332 CONSTRUCTIONENGINEERING AND MANAGEMENT
CHP 4 - PROJECT CHRONOLOGY
LECTURER : ASSOC. PROF. DR.AHMET ZTA
UNIVERSITY OF GAZANTEPDEPARTMENT OF CIVIL ENGINEERING
Lecture 4
8/10/2019 CHP4-Project chronology.ppt
2/27
2 / 27
CHP4-PROJECT
CHRONOLOGY Introduction Project initiation Feasibility analysis Financing Design of project Procurement Construction Turnover and startup Operation of facility Disposal of facility Conclusion
8/10/2019 CHP4-Project chronology.ppt
3/27
3 / 27
Learning Objectives
In this chapter you will learn the following:
1. The principal tasks in life cycle of a project
2. What information must be gathered andinvestigated to successfully initiate aproject.
3. The principal phases in project design.
4. What must be done to move fromconstruction to operation.
8/10/2019 CHP4-Project chronology.ppt
4/27
4 / 27
Introduction-1
Life of a facility goes through many phases.
It starts with an idea.
Idea combined with money --- project is born.
Project is developed as drawings and specifications. Then, it is built.
When completed, turned over to owner, and occupied,maintained, repaired and eventually dies.
At some point in lifetime a facility is likely to be renovated,either to renew obsolete systems or change its use.
Figure 4.1 shows a design/build/use/dispose scenario for ashopping mall.
8/10/2019 CHP4-Project chronology.ppt
5/27
5 / 27
Life cycle of a shopping mall:
Feasibility analysis; investigate the economics ofthe mall
Design; produce biddable contract documents
Procurement; builder selection, material order
Construction; mall physically constructed
Turnover; transition from construction tooperation
Operation; business is conducted
Introduction-2
8/10/2019 CHP4-Project chronology.ppt
6/27
Sequence of a Project:
CONCEPT APPRAISAL
CONCEPT DEVELOPMENT
DESIGN AND DOCUMENTATION
CONSTRUCTION
COMMISSIONING
Feasibility study.
Concept estimate of cost andtiming
Progressive refinement of
cost and timing in relation to
the projects objectives.
Progressive and continuouscontrol of cost and timing
option to abandon
option to abandon
option to abandon
Who are the main Parties
to a project? . . .
8/10/2019 CHP4-Project chronology.ppt
7/277 / 27
Project initiation-1
All construction activity is the result of basiceconomic demand.
Individuals needs homes, roads, stores, shelter, etc.
Specific construction projects arise becausecorporations or government bodies recognize theneed --- serve this demand and act to createthem. Construction activity tends to fosterfurther construction activity.
Recognizing needs is first step, but there must be away to move from recognition to reality. Answerlies in economic structure of the country.
8/10/2019 CHP4-Project chronology.ppt
8/278 / 27
Project initiation-2
Demographic and market analysis are used toforecast future growth areas in the country.
Opportunities, once identified, are financed andthen projects initiated.
As businesses increase, population grow to workin them. Because these people must travel towork, roads and other transportation modesbecome necessary.
8/10/2019 CHP4-Project chronology.ppt
9/279 / 27
Feasibility analysis-1
Before deciding to invest in a specific area, an investor wantsto be sure on an adequate return. Therefore before anycommitment, an analysis is performed to examine theproposed investment from several standpoints.
These are shown on figure;
a) Market demand,
b) Cost of construction,
c) Cost of money,
d) Timing of project,
8/10/2019 CHP4-Project chronology.ppt
10/2710 / 27
Project initiation
Cost of money Schedule BudgetMarket
demand
Revise program
orcancel project Proceed?
Design
Feasibility analysis-2
8/10/2019 CHP4-Project chronology.ppt
11/2711 / 27
Feasibility analysis-3
During the early analysis stage, owner consults
Architects who provide early design advice, and
Construction professionals, who offer cost andconstructability advice.
Example:
8/10/2019 CHP4-Project chronology.ppt
12/2712 / 27
Financing
If project gets past the first hurdle of profitability for theinvestor, owner must arrange financial backing for someof the work. Some of it provide himself.
Commonly, initial investor acquires outside funds tosupplement his or her own.
Barrow from banks
Barrow from insurance company
Invite outside investors to share in future profits.
Example: A corporation wishing to build a factory couldbarrow from a bank or sell additional stocks or bonds.
Whatever the source of additional funds, other individuals orfirms decide to lend or invest funds based on their own
expectation of return on investment.
8/10/2019 CHP4-Project chronology.ppt
13/2713 / 27
Design of project
If owner decide to proceed, hires a designprofessional. If he elects to proceed using aconstruction management mode, he chooses a
construction professional, Who provides cost,schedule, and construction advice throughoutthe design process.
Design is divided into 4 stages.
Programming, Schematic design,
Design development,
Construction documents.
8/10/2019 CHP4-Project chronology.ppt
14/27
14 / 27
Programming-1
A program is a written statement of the requirementsof the building. It is the basis of design.
Program describes
Spaces needed,
Services required in those spaces, and
Relationships of functions to be performed in the
building.Written by owner or user of building,
by architect, or
by a professional hired.
8/10/2019 CHP4-Project chronology.ppt
15/27
15 / 27
The nature of the programming process dependson two things:
The sophistication of the owner; Owners varyconsiderably in their degree of understandingabout building process and it affects program.
The complexity of the proposed facility;Thecomplexity of the project itself can determinehow the programming needs to be accomplished.
Using these information owner proceed or cancel
Programming-2
8/10/2019 CHP4-Project chronology.ppt
16/27
16 / 27
When programming is complete, the owner hasinformation about:
The needed size of the project in relation to therequirements of the users
The mechanical, electrical and plumbing systems
Vertical and horizontal circulation Public areas
Programming-3
8/10/2019 CHP4-Project chronology.ppt
17/27
17 / 27
Once the program is complete and the ownerhas decided to proceed, the designer beginsactual design of the project.
The process begins with the schematic design-the stage in which the designer defines thebuildings characteristics in a number of ways.
Before schematic design begins;
The owner selects a site for the building Site investigations done by the owner give
the designer information about soil conditionsand makeup that in large part determine the
type of foundation and structure possible forthe particular site
Schematic design-1
8/10/2019 CHP4-Project chronology.ppt
18/27
18 / 27
The architect develops preliminary floor plans thatreflect the relationships of the various functionalareas to one other
Sitting and location of the building are determined aswell as its visual form.
When the schematic design is complete, the owner isagain faced with the decision to proceed further or tocancel the project. At this time, all informationdeveloped to date-market information, financingcosts, construction costs and design-are factored intothe decision.
Schematic design-2
8/10/2019 CHP4-Project chronology.ppt
19/27
19 / 27
When project team enters design development, itpursues a single design concept.
The purpose of this stage is to refine the design andobtain detailed information from the users abouttheir requirements.
During this phase owner, designer and construction
professional finalize the design of major buildingsystems.
For examplestructural, plumbing, elevator,roofing, mechanical, exterior faade, electrical.
Design development
8/10/2019 CHP4-Project chronology.ppt
20/27
20 / 27
Architect creates final working constructiondocuments used to bid the job for
construction and to build the job in the field.Documents including specifications anddrawings, Should meet
program criteria, programming
Reflect the design .. schematic design, and
Refine all detailed work, designdevelopment
Constructiondocuments
8/10/2019 CHP4-Project chronology.ppt
21/27
8/10/2019 CHP4-Project chronology.ppt
22/27
22 / 27
Construction
Once procurement process completed, construction can begin
Main element: task of managing and coordinating the fieldoperations. This means;
Scheduling crews in proper sequence, Choosing most efficient and safe construction techniques
and methods
Directing the production process.
To accomplish this task, construction professional must order correct material,
ensure adequate supply of necessary tools & equipment,
monitor schedule, cost, and quality.
A parallel task is contract administration.
8/10/2019 CHP4-Project chronology.ppt
23/27
23 / 27
Turnover and start-up
After construction completed, project must be turned over toowner for use during the rest of its economic life.
Turn over involves complicated technical issues and problems
For example: testing of piping
Turnover is also a legal process, involves various legal certification,such as certification of occupancy, and certificate ofsubstantial completion. The process is long and tedious.
Document includes insurance certificates,
inspection reports,
completed change orders.
8/10/2019 CHP4-Project chronology.ppt
24/27
24 / 27
Operation of facility
This phase is the responsibility of owner or tenant of building.In this, building is put to the use for which it was intended.The period can last for many years before a major renovation
is necessary.
This phase is also the period of greatest expenditure on theproject total operating cost are higher.
More money will be invested up front, but the payback canbe realized in the operating costs of the facility
Facility owners and managers usually need advice aboutthe best model to use in making decisions during theplanning stages of the project
8/10/2019 CHP4-Project chronology.ppt
25/27
25 / 27
Disposal of facility
At the end of its useful life, a project or a facilitymay meet any one of a number of fates.
It may be closed down or simply abandoned.
It may be disassembled or removed.
It may also be renovated or overhauled
8/10/2019 CHP4-Project chronology.ppt
26/27
26 / 27
CONCLUSION
People are involved in the life cycle of abuilding.
Who analyze the need for the facility and decide Project enters the design/build phase
Architects are hired to design
Construction professionals are hired to carry outthe actual assembly
All parties need to work in harmony
8/10/2019 CHP4-Project chronology.ppt
27/27
Next Chapter
Chapter 5
Construction Services during design