3
Project Name : WORTEL FIELD DEVELOPMENT PROJECT Customer : SANTOS (Sampang) Pty. Ltd. Drawing Reff. / Rev : System / Sub No. : Single Line No. / Rev : System Desc. : Location / Area : E/I Building Area Sub System Desc. : Notes : Print Name Date Company Signature ELECTRICAL MECHANICAL COMPLETION CHECK SHEETS ELECTRICAL SUPPORT Description Performed by Witnessed / Approved by Witnessed / Approved by No. Inspection Check List Tag No.       9       8       2       0          N       L       D       B          0       0       2       9       8       2       0          N       L       D       B          0       0       1       9       8       2       0          N       L       D       B          1       0       1       9       8       2       0    -       E       L       D       B          0       0       1       9       8       2       0          E       L       D       B          1       0       1 2 Check support design accordance with design drawing 1 Check support support material have correct specifiction and size 4 Check that support have completed fabrication work 3 Check support have correct dimension accordance to design drawing 6 Check support installation are level, correct elevation and adequate for electrical installation 5 Check that support location refer to layout 8 Check that support are tight installed 7 Check welding visualy inspected where applicable 9 Check that support have completed finishing work 11 12 10 E24MC SANTOS (SAMPANG ) PTY LTD

Check List Electrical_new

Embed Size (px)

Citation preview

Page 1: Check List Electrical_new

8/13/2019 Check List Electrical_new

http://slidepdf.com/reader/full/check-list-electricalnew 1/3

Project Name : WORTEL FIELD DEVELOPMENT PROJECT

Customer : SANTOS (Sampang) Pty. Ltd.

Drawing Reff. / Rev : System / Sub No. :

Single Line No. / Rev : System Desc. :

Location / Area : E/I Building Area Sub System Desc. :

Notes :

Print Name

Date

Company

Signature

ELECTRICAL

MECHANICAL COMPLETION CHECK SHEETS

ELECTRICAL SUPPORT

Description Performed by Witnessed / Approved by Witnessed / Approved by

No. Inspection Check List

Tag No.

      9      8      2      0   -      N      L      D      B   -      0      0      2

      9      8      2      0   -      N      L      D      B   -      0      0      1

      9      8      2      0   -      N      L      D      B   -      1      0      1

      9      8      2      0   -      E      L      D      B   -      0      0      1

      9      8      2      0   -      E      L      D      B   -      1      0      1

2 Check support design accordance with design drawing

1 Check support support material have correct specifiction and size

4 Check that support have completed fabrication work

3 Check support have correct dimension accordance to design drawing

6Check support installation are level, correct elevation and adequate for

electrical installation

5 Check that support location refer to layout

8 Check that support are tight installed

7 Check welding visualy inspected where applicable

9 Check that support have completed finishing work

11

12

10

E24MC

SANTOS (SAMPANG ) PTY LTD

Page 2: Check List Electrical_new

8/13/2019 Check List Electrical_new

http://slidepdf.com/reader/full/check-list-electricalnew 2/3

Project Name : WORTEL FIELD DEVELOPMENT PROJECT

Customer : SANTOS (Sampang) Pty. Ltd.

Drawing Reff. / Rev : System / Sub No. :

Single Line No. / Rev : System Desc. :

Location / Area : E/I Building Area Sub System Desc. :

Notes :

E24MC

12

10

11

9 Check that support have completed finishing work

8 Check that support are tight installed

7 Check welding visualy inspected where applicable

6Check support installation are level, correct elevation and adequate for

electrical installation

5 Check that support location refer to layout

4 Check that support have completed fabrication work

3 Check support have correct dimension accordance to design drawing

2 Check support design accordance with design drawing

1 Check support support material have correct specifiction and size

Inspection Check List

Tag No.

      9      8      2      0   -      I      S   -      2      5      0      /      2      6      0

Description Performed by Witnessed / Approved by Witnessed / Approved by

ELECTRICAL

MECHANICAL COMPLETION CHECK SHEETS

ELECTRICAL SUPPORT

No.

Signature

Company

Date

Print Name

SANTOS (SAMPANG ) PTY LTD

Page 3: Check List Electrical_new

8/13/2019 Check List Electrical_new

http://slidepdf.com/reader/full/check-list-electricalnew 3/3

Project Name : WORTEL FIELD DEVELOPMENT PROJECT

Customer : SANTOS (Sampang) Pty. Ltd.

Drawing Reff. / Rev : System / Sub No. :

Single Line No. / Rev : System Desc. :

Location / Area : E/I Building Area Sub System Desc. :

Notes :

Print Name

Date

Company

Signature

ELECTRICAL

MECHANICAL COMPLETION CHECK SHEETS

ELECTRICAL SUPPORT

Description Performed by Witnessed / Approved by Witnessed / Approved by

No. Inspection Check List

Tag No.

      9      8      2      0   -      U      P      S      D      B   -      0      0      1

      9      8      2      0   -      U      P      S      D      B   -      0      0      2

2 Check support design accordance with design drawing

1 Check support support material have correct specifiction and size

4 Check that support have completed fabrication work

3 Check support have correct dimension accordance to design drawing

6Check support installation are level, correct elevation and adequate for

electrical installation

5 Check that support location refer to layout

8 Check that support are tight installed

7 Check welding visualy inspected where applicable

9 Check that support have completed finishing work

11

12

10

E24MC

SANTOS (SAMPANG ) PTY LTD