  • CHARLES VILLAGE STREETSCAPE

  • OVERALL PROJECT:  MARCH 2019 – DECEMBER 2019

    PHASE 1 – St. Paul Street West side:  Late‐March to Late‐May 

    PHASE 2A – St. Paul Street East Side/33rd Street North Side:  Late‐May to July

    PHASE 2B – St. Paul Street New Median /33rd Street North Side :  July to Mid‐August

    PHASE 3 – 33rd Street South Side: Mid‐August to Early October

    PHASE 4 – 33rd Street New Median: October to November

    PHASE 5 – 33rd Street final paving: Project Complete in December 2019

    ANTICIPATED PROJECT SCHEDULE

  • LATE‐MARCH 2019 to LATE‐MAY 2019

    Construction Duration: 2 Months

    PHASE 1: ST. PAUL STREET WEST  SIDE 3100 & 3200 BLOCKS

    Scope:

    ‐ Curb replacements, tree pit improvements, and electrical  installations along the west side of St. Paul Street.

    ‐ Temporary signal installations at 31st, 32nd, and 33rd Street  intersections.

    Impacts:

    ‐ All sidewalks will remain open for pedestrians.  All businesses  will be accessible.

    ‐ Parking lane closed on the west side of St. Paul Street,  between 31st and 33rd Streets

    ‐ Two thru travel lanes will remain on St. Paul Street for  southbound traffic.

    ‐ St. Paul Street northbound service lane, east side parking lane,  and median parking lane will remain in service.

    ‐ No impacts to 33rd Street during this phase.

  • LATE‐MAY 2019 to JULY 2019

    Construction Duration: 1.5 Months

    PHASE 2A: ST. PAUL STREET EAST  SIDE 3100 & 3200 BLOCKS/NORTH 

    SIDE OF 33RD STREET

    Scope:

    ‐ Curb replacements, tree pit improvements, and electrical  installations along the east side of St. Paul Street between 31st and 33rd Streets, on the west side of St. Paul street in front of  the bookstore, and on the north side of 33rd Street.

    ‐ Demolition of St. Paul Street median.

    Impacts:

    ‐ All sidewalks will remain open for pedestrians.  All businesses  will be accessible.

    ‐ St. Paul Street northbound service lane, east side parking lane,  and median parking lane will be out of service.

    ‐ Two thru travel lanes will remain on St. Paul Street for  southbound traffic.

    ‐ Parking lane on west side of St. Paul Street will be available.

    ‐ No parking along the north side of 33rd Street during this  phase.  All travel lanes on 33rd Street will remain open.

  • JULY 2019 to MID‐AUGUST 2019

    Construction Duration: 1.5 Months

    PHASE 2B: NEW ST. PAUL STREET MEDIAN  3100 & 3200 BLOCKS/NORTH SIDE OF 33RD

    STREET

    Scope:

    ‐ Curb replacements, tree pit improvements, and electrical  installations continue on the north side of 33rd Street, and on  the west side of St. Paul street in front of the bookstore.

    ‐ Installation of new St. Paul Street median.

    Impacts:

    ‐ All sidewalks will remain open for pedestrians.  All businesses  will be accessible.

    ‐ No parking lane on the west side or along the median of St.  Paul Street.

    ‐ Two thru travel lanes will remain on St. Paul Street for  southbound traffic.

    ‐ St. Paul Street northbound service lane and east side parking  lane will be available.

    ‐ No parking along the north side of 33rd Street during this  phase. All travel lanes on 33rd Street will remain open.

  • MID‐AUGUST 2019 to OCTOBER 2019

    Construction Duration: 2 Months

    PHASE 3: 33RD STREET SOUTH  SIDE/NE CORNER

    Scope:

    ‐ Curb replacements, tree pit improvements, and electrical  installations on the south side of 33rd Street, as well as the NE  corner of the 33rd Street/St. Paul Street intersection.

    ‐ Installation of new crosswalk across Charles Street at 33rd Street.

    ‐ Final paving of St. Paul Street to occur at the end of this phase

    Impacts:

    ‐ All sidewalks will remain open for pedestrians.  All businesses  will be accessible.

    ‐ No parking on the north or south sides of 33rd Street. All travel  lanes on 33rd Street will remain open.

    ‐ All St. Paul Street travel lanes are available.

    ‐ No parking along the NE corner of the 33rd Street/St. Paul  Street intersection.

  • OCTOBER 2019 to NOVEMBER 2019

    Construction Duration: 2 Months

    PHASE 4: 33RD STREET MEDIAN

    Scope:

    ‐ New median installation on 33rd Street.

    ‐ Completion of final traffic signal installations and  programming

    Impacts:

    ‐ All sidewalks will remain open for pedestrians.  All  businesses will be accessible.

    ‐ No parking on the north or south sides of 33rd Street.

    ‐ All travel lanes on 33rd Street will remain open.

  • DECEMBER 2019

    Construction Duration: 1/2 Month

    PROJECT COMPLETE

    PHASE 5: 33RD STREET FINAL  PAVING

    Scope:

    ‐ Final paving of 33rd Street.

    Impacts:

    ‐ All sidewalks will be open for pedestrians.

    ‐ All travel and parking lanes on St. Paul Street and 33rd Street are available.