Charles County Government – Energy Supply Program 1 CHARLES COUNTY GOVERNMENT ENERGY SUPPLY PROGRAM October 22, 2019

Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program1

CHARLES COUNTY GOVERNMENTENERGY SUPPLY PROGRAM

October 22, 2019

Page 2: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program2

TABLE OF CONTENTS

THE MAN I. THE JOINT VENTURE

II. THE SOLAR POWER PURCHASE PROGRAM

III. THE SOLAR POWER PROJECTS

IV. THE PROPOSED ENERGY PURCHASE PROGRAM

V. NEXT STEPS

Page 3: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program3

THE JOINT VENTURE

Page 4: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program4

THE JOINT VENTUREENERGY VENTURES IPP, LLC

INDEPENDENT POWER PRODUCER

• Formation: August 2014 (Delaware)

• Core Competency: Renewable energy power generation facility acquisition, development, ownership and management

• Market Area: United States

• Target Customers: Federal, state and local government agencies, commercial, industrial and institutional entities, and utility companies

• Gov’t Certifications: Federal: SDB, VOSB, SDVOSBState & Local: DBE, MBE

• Gov’t Contracts: U.S. Army ID/IQ MATOC (Solar)

• Pipeline: 5 Projects / 100 MW[dc]

• Employees: 1 – 10

Page 5: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program5

THE JOINT VENTUREX-ELIO ENERGY USA, INC.

• X-Elio is a leading vertically-integratedcompany with a long-standing trackrecord in development, construction,operations and management of solarPV assets

• It was founded in 2005, and hasrapidly grown into a globally-recognized player in the Solar PVspace, having developed, built andgrid-connected more than 1.1 GW

• The Company relies on a team of 200highly skilled professionals. Withpresence in 14 countries, X-ELIO hasoffices in Spain, Italy, South Africa,Japan, USA, Mexico, Chile and Australia

• The Company’s shareholders areBrookfield Renewable Partners L.P.(50%) and KKR & Co. Inc. (50%)

Page 6: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program6

THE SOLAR POWER PURCHASE PROGRAM

Page 7: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program7

THE SOLAR POWER PURCHASE PROGRAMPROGRAM GOALS

• Priority I: Financial Considerations

o Reduce County energy expense

o Reduce volatility and increase predictability ofCounty energy expense

• Priority II: Environmental Responsibility

o Increase use of green energy

o Reduce carbon footprint

o Sensitive use of County natural resources

• Priority III: Socio-Economic Development

o Minority Business Enterprise participation

o Small Local Business Enterprise participation

Page 8: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program8

THE SOLAR POWER PURCHASE PROGRAMPROGRAM INCENTIVES

• Energy Consumption

o Purchase commitment of 100% of project(s)output up to maximum County demand

• Real Estate

o 44 County-owned potential development sitesoffered for lease

o Below-market site lease payment rate

o Expedited planning & zoning approval

• Tax Authority

o Payment-in-lieu of taxes agreement (PILOT)

Page 9: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program9

THE SOLAR POWER PROJECTS

Page 10: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program10

THE SOLAR POWER PROJECTSPISGAH LANDFILL

• Location: 6645 Masons Springs RoadLa Plata, MD 20646

• Site Size: 101 acres

• Vegetation Cover: Grassland over a capped solid-waste landfill

• Site Owner: Charles County Government

• System Type: PV Solar, ground-mounted

• Capacity: 29.5 MW(dc) / 22.5 MW(ac)

• Peak Output: 20.18 MW

• Annual Production: 39,851 MWh

Page 11: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program11

DAVIS ROAD

• Location: 2500 Davis Road, Waldorf, MD 20603

• Site Size: 96 acres

• Vegetation Cover: Shrubland

• Site Owner: Charles County Government

• System Type: PV Solar, ground-mounted

• Capacity: 12.6 MW(dc) / 10.0 MW(ac)

• Peak Output: 9.83 MW

• Annual Production: 17,179 MWh

THE SOLAR POWER PROJECTS

Page 12: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program12

Chares

t

TOTAL

• Location: La Plata, White Plains & Waldorf

• Aggregate Size: 301 acres

• Site Owner: Charles County Government

• System Type: PV Solar, ground-mounted

• Capacity: 72.3 MW(dc) / 54.8 MW(ac)

• Peak Output: 51.97 MW

• Annual Production: 97,408 MWh

THE SOLAR POWER PROJECTSDEVELOPMENT/OPERATIONS APPROACH

• Financial Considerations

o Minimize cost & risk of development to the County

o Minimize cost & risk of operations to the County

o Potential revenue sharing with the County

• Environmental Considerations

o Minimize negative impact to the environment

o Maximize positive impact to the environment

• Socio-Economic Development Considerations

o Maximize use of MBEs

o Maximize use of SLBEs

Page 13: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program13

THE PROPOSED ENERGY PURCHASE PROGRAM

Page 14: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program14

THE PROPOSED ENERGY PROGRAMOVERVIEW OF ELECTRICITY MARKET

Power Market Wholesale Retail

Generation Transmission Distribution

FERC & PJM

Supplier (LSE)(1) SMECO

Maryland

(1) LSE: Load servicing entity, e.g. EnVen/X-Elio

Page 15: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program15

JV DevCo JV RESCo

Pisgah Landfill(Project

Company)

Davis Road(Project

Company)

OwnershipSolar PPA

Solar PPA

Charles County Govt

PJM Wholesale(Merchant)

Other Structured Supply

Delivered Fuel Mix via Retail Electricity Supply Agreement

THE PROPOSED ENERGY PROGRAMPROCUREMENT STRUCTURE

Brown PPAs

Charles County PS

Other Entities

Page 16: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program16

• Volume based on annual load data provided by the County• Shape based on historic profile from SMECO with estimated profile tranches• Peak Load Demand: 9.932 to 11.257 MW• Annual Consumption: 43,079 MWh

0

1

2

3

4

5

6

7

8

9

10

1/1/2011 2/1/2011 3/1/2011 4/1/2011 5/1/2011 6/1/2011 7/1/2011 8/1/2011 9/1/2011 10/1/2011 11/1/2011 12/1/2011

MW

Estimated Hourly Demand Profile

THE PROPOSED ENERGY PROGRAMCOUNTY DEMAND PROFILE

Page 17: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program17

• Brown power (grey) is sold to Charles County during the 24-hour day• No Solar power is sold by SMECO to Charles County Government

$0

$10

$20

$30

$40

$50

$60

0

1

2

3

4

5

6

7

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

$/M

Wh

MW

Hour Ending

Daily Average Demand/Production - Average June Day

Average Load Hourly LMP

THE PROPOSED ENERGY PROGRAMCOUNTY FUEL MIX PROFILE (CURRENT)

Page 18: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program18

• Solar power via the Solar PPA (yellow) will be sold to Charles County during the day to meet its demand during production hours

• Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

• Excess Solar Power via the Solar PPA (green w/diagonal lines) will be sold to other entities (e.g. Charles County PS) during production hours

THE PROPOSED ENERGY PROGRAMFUEL MIX PROFILE

$0

$10

$20

$30

$40

$50

$60

-

5

10

15

20

25

30

35

40

45

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

$/M

Wh

MW

Hour Ending

Daily Average Demand/Production - Average June Day

PV Production Grid Producion Excess Solar Average Load Hourly LMP

Page 19: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program19

THE PROPOSED ENERGY PROGRAMBENEFITS TO THE COUNTY

N0. ITEM COUNTY GOAL

1. Reduction in annual energy expense

2. Reduction of volatility and increase in predictability of annual energy expense

3. Monetization of unused or undervalued County real estate

4. Potential for revenue sharing from sale of excess solar power

5. Increased use of green energy

6. Reduction in carbon footprint

7. Sensitive use of County natural resources

8. Potential for participation by County-based MBEs

9. Potential for participation by County-based SLBEs

Page 20: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program20

NEXT STEPS

Page 21: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program21

NEXT STEPSSCHEDULE OF MILESTONES

EVENT AGENCY PROJECTDAVIS PISGAH

1. Notice of Intent to Award Charles Co. Jan 2017 Jan 20172. Ground Lease Execution Charles Co. Sep 2018 Sep 20183. Power Purchase Agreement Approval (Initial) Charles Co. Nov 2018 Nov 20184. Interconnection Application Submission PJM Mar 2019 Mar 20195. Interconnection Feasibility Study Begins PJM Oct 2019 Oct 20196. Transaction Progress Report to County Commission Charles Co. Oct 2019 Oct 20197. Interconnection Feasibility Results Published PJM Jan 2020 Jan 20208. Special Exception Application Submission Charles Co. Feb 2020 Mar 20209. CPCN Request Submission Maryland PSC Mar 2020 Apr 202010. Special Exception Application Approval Charles Co. Jul 2020 Aug 202011. Site Development Plan Submission Charles Co. Aug 2020 Sep 202012. Site Development Plan Approval Charles Co. Apr 2021 May 202113. Interconnection Application Approval PJM/SMECO Apr 2021 May 202114. CPCN Request Approval Maryland PSC Apr 2021 May 202115. Construction Start EnVen/X-Elio Jun 2021 Jul 202116. Construction Completion EnVen/X-Elio Jan 2022 Feb 202217. COD EnVen/X-Elio Feb 2022 Mar 2022

Page 22: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program22

NEXT STEPSCRITICAL ISSUES

• Transaction Documentation

o Ground Lease Amendments

o Power Purchase Agreement Re-Structuring Amendments

o PILOT Agreements

Page 23: Charles County Supply Development · 10/22/2019  · • Brown power via the Brown PPA (grey) will be sold to Charles County during off-peak hours, the balance of the 24-hour day

Charles County Government – Energy Supply Program23