Chapter (Estimating)

Embed Size (px)

Citation preview

  • 7/23/2019 Chapter (Estimating)

    1/14

    KJC326

    hapter Six

    ESTIMATING

    6.1 ESTIMATING

    An estimating is trial to judge the value size, cost etc or to forecast of what a job or

    service is expected to cost. Normally it is generally based on similar works or projects

    taken up in the past, making necessary amendments especially for the cost materials

    and wages. The total cost of a work is made up of the cost of various individual

    elements. The estimating of the total cost consists of

    !i" #stimating the cost of the $ndividual #lements of the %ost.

    !ii" &uilding up the total cost, taking into consideration each individual

    element of the cost concerned.

    The cost of various individual elements may be under the work section of

    !i" 'reliminaries ( which shall include insurance, progress photographs

    report, warning sign, lamps, signboard, watchman, and etc.

    !ii" )ain work ( which shall include building, roads, water tanks, bridge, tower,

    and etc.

    !iii" $nternal services ( which shall include air conditioning, fire extinguisher,

    electrical installation, sprinkler

    !iv" #xternal works ( which shall include electrical mains comprise of

    capital*service charge, sewerage, water supply, special foundations, site

    work, surface drainage, road and paths, fencing and gates.

    !v" Advertisement

    !vi" +upervision

    !vii" )iscellaneous!viii" 'rofessional fees ( which shall include surveyor, designer.

    !ix" %ontingencies ( it is a sum entered to allow for possible additional work or

    dayworks assume it was -/ of the total cost estimated.

    0 * 1

  • 7/23/2019 Chapter (Estimating)

    2/14

    KJC326

    6.2 OBJECTIVES OF ESTIMATING

    The main objectives of estimating are as follows

    gives prior indication of the economic viability of a particular project

    to make a decision whether to proceed the project or not due to its cost

    an estimate helps establish data for the purpose of comparing

    estimating may help a new design to reduce the cost of the project, when the original

    design is found uneconomical.

    6.3 STAGES OF ESTIMATING

    Traditional civil engineering projects can be divided into six stages

    i" $dentification,

    ii" Appraisal,

    iii" 2efinition,

    iv" Approval,

    v" $mplementation and

    vi" 3peration.

    Figure 6.3 : Variati! I! T"pe O# E$ti%ate &ith Cha!ge$ I! 'r(e)t Stage$

    0 * 4

    Preliminaryestimate

    Appraisal

    estimates

    Proposal

    estimate

    Approvedestimate

    Post-contract

    estimate

    Achieved

    estimate

    Pre-tender

    estimate

    Time

    Operation

    Implementation

    Approval

    Definition

    Appraisal

    Identification

    ProjectStage

  • 7/23/2019 Chapter (Estimating)

    3/14

    KJC326

    5igure 0.- shows the se6uence of these project stages and indicates the types of

    estimate used in each stage.

    Preliminary estimate ( an initial estimate at the earliest possible stages.&ased on crude indication of the project size or

    capacity, to be used in planning stage.

    Appraisal estimate ( should include all costs which be charged against the

    project in order to provide best estimate off anticipated

    total cost.

    Proposal estimate ( based on a conceptual design and design study

    specifications.

    Approved estimates ( proposal estimate was modified due to client7s view

    Pre-tender estimate ( a refinement of the approved estimate based on the

    definitive design work using the information provided in

    the tender documents. At this stage the estimate

    should reflect the total capital cost of the project and all

    the charges and fees and allowances or contingency

    for the client7s risk.

    Post-contract estimate ( a further refinement of the pre(tender estimate

    Achieved cost ( actual costs of the job in order to review performance

    and provide data for future projects.

    0 * -

  • 7/23/2019 Chapter (Estimating)

    4/14

    KJC326

    6.* T+'ES OF ESTIMATING TEC,NI-E

    The five common estimating techni6ues are summarised as follows (

    G/0a/ ( a simple estimating techni6ue which based on existence of data

    from similar projects.

    Fa)tria/ ( a techni6ue used widely on process plants where the key

    components can be easily identified and priced and all other works

    are calculated as factors of these components.

    Ma!hur ( works is estimated in total man(hours and cost in conjunction with

    plant and material costs.

    !it rate ( based on bill of 6uantities, where the 6uantities if work are defined

    and measured in accordance with standard method of

    measurement.

    Operati!a/ ( based on all the constituents operations necessary to construct

    the works and estimating the labour, plant and materials costs

    together with the overheads.

    Table 0.8 shows the five estimating techni6ues in terms of their project data

    re6uirements and estimating data re6uirements.

    0 * 8

  • 7/23/2019 Chapter (Estimating)

    5/14

    KJC326

    Ta0/e 6.* : Mai! E$ti%ati!g Te)h!iue$ A! Their 4ata 5euire%e!t$

    4ATA5E-I5EMENTS

    ESTIMATING TEC,NI-E

    G/0a/ Fa)tria/ Ma!hur$ !it rate Operati!a/

    'roject data %ompletiondate

    9ocation

    +ize*capacity

    %ompletiondate

    9ocation

    9ist of maininstalledplant items

    %ompletiondate

    9ocation

    :uantities

    +implemethod

    statement

    ;ey dates

    %ompletiondate

    9ocation

    &: !at leastmain items"

    %ompletiondate

    )aterials

    :uantities

    )ethodstatement

    'rogram

    &asic #stimating

    2ata

    'otential

    'roblems,

    eneralinflationforecasts

    )arkettrends

    $nflationindices

    Achievedoverallcosts ofsimilarprojects!ade6uatelydefined"

    >eneralinflationforecasts

    )arkettrends

    $nflationindices !forhistoricalprices"

    #stablishedfactorialestimatingsystem

    eneralinflationforecasts

    )arkettrends

    $nflationindices

    ?istoricalunit rates forsimilar workitems

    'reliminaries

    )aterialscosts

    9abour ratesandproductivity7s

    'lant costsandproductivities

    3verheadcosts

    )aterialscostsforecasts

    9abour rateforecasts

    'lant capitalandoperatingcostsforecasts

    0 * @

  • 7/23/2019 Chapter (Estimating)

    6/14

    KJC326

    6. CONSTITENTS OF ESTIMATE

    The price of an item of work is made up of the following components (

    %ost of materials ( calculate the materials re6uired for the item of work and

    allow for waste and delivery to site.

    %ost of labour ( this is very uncertain factor, the output of labour varies

    considerably accordingly to place of works, weather

    condition, heights etc.

    %ost of tools and plants ( the cost should include

    initial cost of machine

    interest on capital cost

    the economic life span of machine

    maintenance

    cost of transporting machine to site

    number of hours machine is operated in one year

    consumption of machines fuel cost

    driver*foreman unskilled workers ( wages

    output of machine

    0 * 0

  • 7/23/2019 Chapter (Estimating)

    7/14

    KJC326

    0 *

  • 7/23/2019 Chapter (Estimating)

    8/14

    KJC326

    0 * B

  • 7/23/2019 Chapter (Estimating)

    9/14

    KJC326

    0 * C

  • 7/23/2019 Chapter (Estimating)

    10/14

    KJC326

    0 * 1

  • 7/23/2019 Chapter (Estimating)

    11/14

    KJC326

    6.6 &O57E4 E8AM'9ES

    Exa%p/e 6.6.1 E$ti%ati!g O# Ex)aati! &r;$ 3 hr

    The labour time costs 3 hr

    9abour cost of excavating 1 m-of rock including 1@/ profit

    F

  • 7/23/2019 Chapter (Estimating)

    12/14

    KJC326

    Exa%p/e 6.6.1.a E$ti%ati!g O# Ex)aati! &r;$

  • 7/23/2019 Chapter (Estimating)

    13/14

    KJC326

    Exa%p/e 6.6.2 E$ti%ati!g O# Fr%r;

    =sing 9a0ur a! Materia/ C!$ta!t$, prepare estimation cost for fixing one !1" piece

    -mm x -mm heavy duty car porch tile with 4mm thick of cement and total cost ofthe proposed car porch tiles project abiding on data below. The project duration is

    expected to be two !4" days and re6uires two !4" skilled workers and two !4" unskilled

    workers.

    2ata

    1. Dhite horse heavy duty tile !-mmx-mm" F

  • 7/23/2019 Chapter (Estimating)

    14/14

    KJC326

    4. Ce%e!t

    a" vol. of cement F .- x .- x .4

    F .1Bm-

    Total vol. of cement F @ x .1BF 1.-C@m-

    %ost of cement F !1.-C@ x 4Bbag" x rm1@.

    F