Upload
others
View
9
Download
0
Embed Size (px)
Citation preview
Chapter - 4
Surveys and Investigations
4.0 General
Surveys and Investigations provide field data required for planning and
designing of various components of a Water Resources Development Project. A
project can be designed optimally and economically, only when the necessary
field data of specified standards are available. As such, NWDA has taken up
extensive field surveys and investigations in the project area for collection of the
data required for the preparation of Detailed Project Report (DPR) of Wainganga
(Gosikhurd) – Nalganga (Purna Tapi) Intra State link project of Maharashtra,
during the period from 2013 to 2017, as per the “Guidelines for preparation of
DPRs of Irrigation and Multipurpose Projects, Ministry of Water Resources-
2010.”
Detailed surveys and investigations such as Topographical surveys,
Geological & Geotechnical investigations including foundation investigations i.e.
drilling bore holes at identified major CD/CM structures & at lift points /PHs for
obtaining rock cores; Construction materials investigations; Geotechnical
investigations (soil) including borrow area surveys; Archaeological surveys,
Mineral surveys and Canal-top solar power studies etc., have been undertaken
Departmentally as well as through various specialized Organisations in order to
examine the feasibility of the project.
The Pre-feasibility Report (PFR) of Wainganga (Gosikhurd) – Nalganga
(Purna Tapi) link project was prepared by NWDA during the year 2009.As per
the PFR, the project proposal comprises the following elements:
1. Head-works at Gosikhurd with FRL +244.00 m.
2. A Link Canal of 478.200 km taking off from the existing Gosikhurd
reservoir to divert 2721 Mm3 of water annually, with FSL of + 243.00 m
upto Nalganga Project on Nalganga River, a tributary of Purna Tapi river.
The canal traverses between 280 and 300 m contours to irrigate 413750 ha
of area in Western Vidarbha region.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
89
3. Lifting arrangements at RDs 26.00 km, 47.00 km and 293.50 km with static
head of 40 m, 20 m and 20 m respectively i.e. a total lift of 80 m is involved
in three stages.
4. Total pump capacity required is about 224 MW (751 MU).
At PFR stage, no surveys & investigations were taken up.
In light of various surveys and investigation works and other technical studies
that could be carried out as part of DPR, additional component in the form of
canal top solar (PV) power plant is planned. The link project envisages
construction of the following components:
i) Head works at existing Gosikhurd reservoir (FRL 245.5 m) across
Wainganga river for a peak discharge of 347.2 cumec.
ii) Link canal of length 426.54 km from Gosikhurd reservoir to
Nalganga reservoir, comprising of open canal, pipe lines & tunnels
iii) Lifting arrangements through 6 stages of lifting 23.25 m (RD 2.4 to
2.9 km), 23.5 m (RD 20 to 20.9 km), 29.25 m (RD 39.9 to 42.7 km),
28 m ( RD 169.6 to 170.4 km), 30 m ( RD 176.9 to 178.1 km) and
21.25 m ( RD 292.85 to 293.7 km) totaling to 155 m of static lift
iv) Canal falls at two locations at RDs 302.93 km (7 m) and 426.43 km
(6 m) to dissipate the available excess head and reduce quantum of
filling
v) Pipelines for 25.98 km length in 11reaches viz., RD 27.40 km (1210
m ), RD 44 km (553 m), RD 49.65 km (1937 m), RD 60.05 km (9783
m), RD 83.6 km (3485 m), RD 87.7 km (1819 m), RD 93.4 km
(3551 m), RD 112.45 (1111 m), RD 257.1 km (500 m), RD 363.88
km (1698 m) and RD 370.48 km (331 m)
vi) Seven tunnels for a cumulative length of 13.826 km located at RD
73.50 km (3317 m), RD 141.45 km (776 m), RD 150.25 km (6489
m), RD 298.98 km (667 m), RD 371.53 km (781 m), RD 406.08
km (948 m) and RD 411.78 km (848 m)
vii) Out fall structures and Head regulators for integration of existing
reservoirs of Lower Wardha and Katepurna
viii) Raising of six existing storages to accommodate link waters
ix) Construction of 31 new storages along the link alignment to receive
diverted waters
Chapter – 4 Surveys and Investigations
90
x) 22 nos. of Feeder canals/Direct sluices for integration of 38 existing/
proposed intermittent storages along the alignment
xi) Subsidiary lift arrangements from main link canal to feeder canals at
RD 115.45 km (7 m), RD 147.55 km (5 m), RD 150.00 km (10 m),
RD 246.30 km (10 m) and RD 377.13 km (8 m)
xii) Cross drainage/cross masonry and regulating works across the link
canal (582 Nos.)
xiii) Command area development of about 371277 ha in Nagpur,
Wardha, Yeotmal, Amravati, Akola and Buldhana districts
xiv) Canal top solar power generation arrangement at appropriate reaches
along the link canal alignment.
xv) Outfall structure at existing Nalganga reservoir on Nalganga river, a
tributary of Purna Tapi with FRL 294.44 m
The surveys & investigations in respect of the link canal, canal structures,
lift points etc., have been undertaken departmentally and through various
specialized organizations at DPR stage. Relevant details in respect of existing
Gosikhurd, Lower Wardha, Katepurna and Nalganga projects and the proposed
enroute storages/tanks are collected from Water Resources Department, Govt. of
Maharashtra and incorporated in the report.
The various surveys & investigation works carried out at DPR stage are
described in the following paragraphs.
4.1 Topographical Surveys
Topographical surveys have been carried out as per the “Guidelines for
Preparation of Detailed Project Reports of Irrigation and Multipurpose Projects”
of Ministry of Water Resources, Govt. of India, 2010, to the extent applicable.
The Great Trigonometrical Survey (GTS) Bench Marks (BMs) of Survey
of India (SOI) located in the vicinity of link canal have been transferred and
connected at various locations along the canal alignment by conducting Double
Tertiary (DT) Leveling of about 179 km. Adequate number of
Permanent/Temporary Bench Marks (PBMs/TBMs) at different locations along
the alignment were established with reference to the above GTS Bench Marks.
The details of various GTS Bench Marks connected to the link alignment are
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
91
furnished in Table-4.1. The details of the TBMs established along the link project
are furnished in Annexure-4.1.1 to 4.1.3.
Table-4.1
GTS Bench Marks connected to the link alignment
Sl.No Description of the GTS Bench
Mark
RD of the
connected
TBM (km)
Surveyed
length (km)
1 GTS BM on cement platform 'N'
end of bridge over Kanhan River
about 800 m ‘N’ of rest house
(PWD), Mauda, (Mathani)
25.15 20.90+20.90
(To & fro)
2 BoM at NE end of NW parapet of
bridge over a nala about 160 m NE
of Borkhedi Railway station, on
Nagpur-Wardha section of
Central railway.
86.12 11.87
3 Type B BM embedded 60 cm
below ground level, on S. Side of
Circuit House, Wardha.
126.20 18.85
4 Type B BM On pillar in the
compound of rest house at
Talegaon*
177.25 18.00
5 On North pilaster cap of E
abutment of bridge, about 3
furlongs east of mile- post No. 426
from Bombay.
195.38 2.38
6 Type B BM at Asra Gram
Panchayat Rest House about 1.4
m E of east wall of rest house.
243.61 29.57
7 Type B BM in the back compound
of Gram Panchayat Office, Palso
271.61 21.63
8 BM (Type P) situated in NE.
corner of compound of Circuit
House, Akola
312.93 27.34
9 Type B BM in the front of S.
compound of PWD Rest House,
Khamgaon
381.21 7.01
(To & fro)
* Connected to the original alignment as per PFR
Chapter – 4 Surveys and Investigations
92
Topographical Surveys –Visit to GTS Bench mark near Borkhedi Railway
station on 23.09.2013
The line diagram of GTS BMs connected with the link alignment is shown
at Plate - 4.1.
4.1.1 Rivers
Wainganga (Gosikhurd) – Nalganga (Purna Tapi) link project takes - off
from the existing Gosikhurd reservoir and out-falls into the existing Nalganga
reservoir. Besides, the existing Lower Wardha and Katepurna reservoirs are
planned as balancing reservoirs. No river surveys were carried out at the DPR
stage, since no new dams/storages are proposed across the intermediate rivers that
the link canal crosses. However, 38 intermittent medium storages/tanks (besides
Lower Wardha and Katepurna) are proposed enroute in the command area for
which detailed surveys will be carried by the State at pre-construction stage.
Further, it is planned to drop the canal water at RD 167.90 km into Savangi stream
joining the Lower Wardha reservoir. The river surveys of the stream to assess its
discharge carrying capacity or remodeling/modernisation of the river channel will
be taken up at pre-construction stage.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
93
4.1.2 Reservoirs
At the DPR stage, no reservoir surveys have been conducted, since no new
dam is proposed across any of the intermediate rivers that the link canal crosses.
Out of the 38 medium enroute storages/tanks proposed in the command area,
detailed surveys will be carried out for 37 storages/tanks (leaving existing Bembla
project) by the State Govt. at pre-construction stage. Based on the topographical
surveys of the Gosikhurd dam carried out by the erstwhile Irrigation Department
(now WRD), Govt. of Maharashtra, the reservoir contour plan is collected and
incorporated at Plate -4.2.
4.1.3 Head Works
Gosikhurd Reservoir
The link canal takes off from the foreshore of the existing Gosikhurd
reservoir from its right flank. A head regulator is proposed to divert the regulated
water from the Gosikhurd reservoir to the link canal. The topographical survey
of the area covering 250 m upstream and 500 m downstream of the dam axis upto
the elevation of MWL + 5 m on both the banks at 10 m x 10 m grid basis was
carried out by the Govt. of Maharashtra.
The total length of Gosikhurd dam is 11.36 km. The length of the central
gated ogee shaped spillway is 903.90 m comprising of 773.90 m of overflow
portion and 130 m of non-overflow portion for passing a flood discharge of 67373
cumec at MWL. Crest of spillway of Gosikhurd dam is at 229 m. The spillway
has 33 gates of size 18.30 m x 16.50 m.
The proposed head regulator is located on the foreshore of reservoir near
village Rajoli. The FRL and MDDL of Gosikhurd reservoir s 245.5 m and 241.29
respectively. The off-take FSL of canal is assumed to be 241.0 m so as to draw
water just above MDDL. The Head regulator with 6 bays, 5.5 m wide each is
proposed. Identical vertical lift type fixed wheel service gate in each bay for
opening size of 5.5 m wide x 9.0 m high, are proposed to control the discharge
into canal. Sill level / Crest level is EL 236.5 m. The gate has been designed for
water head corresponding FRL of 245.50 m. The detailed layout plan of the
Gosikhurd dam axis showing the location of spillway, non-over flow concrete
portion, left and right bank outlets is shown at Plate 4.3.
Chapter – 4 Surveys and Investigations
94
D/S view of the Gosikhurd project on Wainganga river
Lower Wardha Reservoir
The W-N link canal outfalls into the Lower Wardha reservoir at RD 167.90
km through Savangi stream joining the reservoir from the left flank. The link
canal takes off from the Lower Wardha reservoir from the right flank with the
same RD i.e., 167.90 km. The length of the ogee shaped spillway of Lower
Wardha project is 580 m comprising of 462.5 m of overflow portion and 117.5
m of non-overflow portion with maximum discharging capacity of 20788 cumec
at MWL. Crest level of spillway of the dam is at 275.8 m. The spillway has
31radial gates of size 12 m x 8 m.
The proposed head regulator is located on the foreshore of reservoir near
village Pimpalkhuta. The FRL and MDDL of Lower Wardha reservoir is 283.80
m and 227.20 m respectively. The canal FSL is considered in such a way that
even it can draw water at 281.50 m of reservoir. The Head regulator with 4 bays,
5.0 m wide each is proposed. Identical vertical lift type fixed wheel service gate
in each bay for opening size of 5 m wide x 5.3 m high, are proposed to control
the discharge in canals. Sill level / Crest level is EL 278.5 m. The gate has been
designed for water head corresponding FRL of 283.80 m.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
95
Katepurna Reservoir
The link canal out falls into the existing Katepurna project across
Katepurna river at RD 298.63 km from the right side and takes off from the left
flank of the Katepurna reservoir with the same RD. The length of the ogee shaped
spillway of Katepurna project is 145 m. The spillway has a maximum discharging
capacity of 2784 cumec at MWL. The crest level of the spillway is 342.900 m.
The spillway has 10 gates of size 12 m x 5.2 m.
The proposed head regulator is located on the foreshore of reservoir close
to left end of dam axis. The FRL and MDDL of Katepurna reservoir are 347.77
m and 337.41 m respectively. The canal FSL is considered in such a way that
even it can draw water at 343.30 m of reservoir. The Head regulator with 2 bays,
4.25 m wide each is proposed. Identical vertical lift type fixed wheel service gate
in each bay for opening size of 4.25 m wide x 7.8 m high, are proposed to control
the discharge in canals. Sill level / Crest level is EL 340.00 m. The gate has been
designed for water head corresponding FRL of 347.77 m.
4.1.4 Plant and Colony Layout
The Plant and Colony layout survey for the link canal are proposed to be
carried out at pre-construction stage of the project. There are suitable locations
available for installation of various plants and colonies in the vicinity of the link
canal. Suitable provision towards Plant and Colony layout has been made in the
cost estimate.
4.1.5 Canal & Water Conductor System and Canal Structures
i) Link Canal & Water Conductor System
The total length of Wainganga (Gosikhurd) - Nalganga (Purna Tapi) link
canal is about 426.54 km. It is designed to carry 1772 Mm3 from Wainganga river
during monsoon months from July to September to cater to the needy areas in six
districts of Vidarbha region to meet irrigation, domestic & industrial demands.
The topographical surveys have been carried out departmentally as well as
through consultancy services on outsourcing during the period from February,
2013 to May, 2017.
Chapter – 4 Surveys and Investigations
96
The topographical survey work in respect of the link canal from its off take
point at Gosikhurd upto its outfall into Lower Wardha project (RD 0 to 167.9 km)
has been carried out departmentally by NWDA. The work for carrying out
topographical surveys from Lower Wardha reservoir upto its outfall into
Nalganga reservoir on Purna Tapi (RD 167.9 to 426.54 km) was outsourced to
private agency. Due to delay in the progress of outsourced surveys by the Agency
and in the interest of timely completion of DPR, the fixing of the link alignment
from Katepurna to Nalganga (RD 298.63 to 426.54 km) has been carried out
departmentally and the ground profile 150 m on either side of the alignment at 50
m interval has been generated from Digital Elevation Model data of NRSA using
Global Mapper software. The details of reach wise surveys carried out are given
in Table-4.2.
Table-4.2
Reach wise Topographical Surveys by NWDA/Outsourcing
S.No. Reach RD Survey done by
1 Gosikhurd reservoir to
Lower Wardha reservoir
0 km to 167.9 km NWDA
2 Lower Wardha reservoir
to Katepurna reservoir
167.9 km to
298.63 km
Outsourcing
(M/s Geo Environs
Private Ltd., Dehradun)
3 Katepurna reservoir to
Nalganga reservoir
298.63 km to
426.54 km
NWDA
(Fixing of link
alignment and
generation of ground
profile with DEM data
using Global Mapper
software)
Alignment of the link canal was fixed on the ground by taking into account
the actual site conditions such that forest patches, developed areas and valuable
lands were avoided as far as possible. R.C.C Temporary Bench Mark (TBM)
pillars of size 0.40 m x 0.40 m x 1.10 m were erected at about 2.0 km interval and
at the turning points along the alignment. The centre line pillars of size 0.15 m x
0.15 m x 0.75 m were embedded at about 200 m interval along the alignment. All
the above pillars were painted white and chainage along with name of the project
were written with red paint. The bearing statement of the canal alignment is given
in Annexure - 4.2.1 to 4.2.3.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
97
Longitudinal profile surveys of the link canal from Gosikhurd upto
Katepurna have been carried out by Double Tertiary (DT) leveling using auto
levels by taking levels at every 50 m interval and on top of all TBM pillars and
centre line pillars established along the alignment.
Cross sectional profile surveys of the link canal were carried out at every
50 m interval along the alignment by Single Tertiary (ST) leveling using auto
levels/Total station by taking levels at every 50 m (or less as per the requirement)
upto 150 m on either side of the link canal.
Topographical survey of the link alignment near Rengatur at RD. 3.30 km
on 01.03.2013
The maps showing link alignment on toposheets of 1:50000 scale are given
at Plates 4.4.1 to 4.4.21. The strip contour plan and L-section of the link canal
alignment has been prepared with 0.5 m contour interval and appended at Plates
- 4.5.1 to 4.5.173. The condensed L-section of the link canal is appended at Plates
- 4.6.1 to 4.6.3.
ii) Canal structures
The link canal on its way crosses a number of rivers/streams/tributaries/
nallas besides National/State/District highways and village roads/Railway lines.
Chapter – 4 Surveys and Investigations
98
In total there are 591 canal structures, consisting of 3 head regulators, 32
aqueducts, 13 super passages, 7 syphon aqueducts, 17 canal syphons, 2 canal
falls, 180 under tunnels, 150 over passes, 10 cross regulators, 18 feeder canal
regulators, 6 canal escapes, 4 under sluices, 3 four lane road bridges (FLRB), 23
double lane road bridges (DLRB), 112 single lane road bridges (SLRB), 5
Railway bridges and 6 lift points. Details of the CD/CM structures across the link
canal are furnished in Annexures-4.3.1 to 4.3.3. Grid Surveys at 50 m x 50 m
interval were carried out at each proposed major canal structure sites to cover an
area upto 300 m on either side of the centre line of the canal, upto 100 m d/s of
the point of exit of water and 100 m u/s of the point of water inlet.
Contour plans were prepared in 1:2000 scale with 0.5 m contour interval
to facilitate the designs of cross drainage structures, as well as refining the final
alignment precisely. Cross sections of the rivers have also been taken along the
centre line of the canal and the same have been plotted to the scale of 1: 2000 H
and 1:100 V. The contour plans, longitudinal section and cross sections of 5
Nos. of major canal structures along the link canal are appended at Plates - 4.7.1
to 4.7.5.
4.1.6 Lift Points
Lifting arrangements comprising pump-house, sump-well and delivery
cistern are proposed at 6 locations along the link canal. Topographical surveys
have been carried out for these arrangements by taking cross sections at 50 m
interval to an extent of 150 m to 250 m on either side of the alignment. The details
of the six lift points are furnished in the Table-4.3.
Table-4.3
Details of lift points
S.No. Location (RD in km) Static head (m)
1 2.4 to 2.9 23.25
2 20 to 20.9 23.50
3 39.9 to 42.7 29.25
4 169.6 to 170.4 28.00
5 176.9 to 178.1 30.00
6 292.85 to 293.7 21.25
Total lift 155.25
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
99
4.1.7 Command Area
Wainganga (Gosikhurd) – Nalganga (Purna Tapi) link project envisages
diversion of 1772 Mm3 of surplus waters of Wainganga river from Gosikhurd
project during monsoon to serve water deficit areas in Vidarbha districts for
irrigation, domestic & industrial purposes. It is planned to provide irrigation to
an extent of 371277 ha in six districts of western Vidarbha in Maharashtra State
viz. Nagpur, Wardha, Amravati, Yeotmal, Akola and Buldhana in Wainganga &
Wardha sub-basins of Godavari basin and Tapi basin utilising 1286 Mm3 of
water. The command area is mainly proposed under 40 enroute storages/tanks to
be integrated with the link canal. Besides, the link will also provide 32 Mm3 of
drinking water to 11.33 lakh population in the command area. It is also
contemplated to provide 397 Mm3 of water towards industrial requirement in the
vicinity of the project. The estimate for on-farm development works is considered
in the report based on the command area surveys carried out for nearby projects
(Par-Tapi-Narmada). However, the detailed survey in likely command area is
proposed to be carried out at pre-construction stage.
4.2 Other Surveys
4.2.1 Archaeological Survey in the Canal Area
The Archaeological Survey of the project area has been carried out by
Archaeological Survey of India (ASI), Nagpur in 2014. An area of 5 km on either
side of the canal alignment was surveyed in order to explore the archaeological
remains/sites, ancient temples or their remains, Central/State protected
monuments falling in the area. The Superintending Archaeologist, Pre-history
branch, Nagpur vide letter No.1/1/Gosikhurd Pr/2013-14/642 dated 16-2-2015
have submitted the brief report based on the above archaeological survey. It was
informed that there is no adverse impact on Centrally protected monuments
located in the districts of Nagpur, Wardha, Amravati, Akola and Buldhana, since
all are more than 3 km away from the canal alignment. State protected
monuments are also unaffected since nearest protected site at Mandal is about 3
km away from the alignment of canal. All other sites bearing ancient remains are
safe from the construction of canal since all are far from the proposed alignment
and are situated between 500 m to 4 km range. A copy of the report on
archaeological survey by ASI is at Appendix- 4.1.1. However, as already
discussed in preceding chapters, the canal alignment beyond Wardha river
Chapter – 4 Surveys and Investigations
100
crossing has undergone major changes so as to facilitate storing of water in about
40 en route storages/tanks located at higher elevations for use in non-monsoon
period. In view of change in alignment, the ASI, Nagpur has been requested to
take up Archaeological surveys for the modified alignment. In response, ASI,
Nagpur has carried out the archaeological surveys for the modified alignment
beyond Lower Wardha upto Nalganga during January, April-May, 2017 and
submitted a brief report vide letter no. 1/2/2016/WNCP/Tech-71 dated 7th June,
2017. It was reported by ASI that no major archaeological site has been noticed
directly on the proposed canal alignment and a buffered area of 200 m on both
flanks of the canal is also safe for digging. It was concluded by ASI that the area
marked for the proposed canal is devoid of archaeological sites and monuments
and therefore, Phase II (Excavation) and Phase III (Mitigation) of archaeological
impact assessment are not needed. A copy of the report on archaeological survey
by ASI for the modified alignment is at Appendix- 4.1.2.
4.2.2 Mineral Survey in the Canal Area
GSI, Central region, Nagpur has carried out the mineral survey of the
project area. GSI, Nagpur vide Letter No. 232/8/PSS/GSI/CR/2014 dated 12th
March, 2014 (Annexure-4.4) informed that Rengatur Gold prospect in Bhiwapur
tehsil, Kolari Gold prospect located about 2 km NW of Pular village on Pular-
Dhamna forest road and Ranbori tungsten prospect all in Nagpur district are
found to lie in the vicinity of the link alignment in its initial reach of about 32 km,
but do not fall in the proposed route of the alignment. In the further reaches of
the link canal, only basalt is exposed and no significant mineral deposit/prospect
is reported. Subsequently, GSI, Nagpur has also been requested to take up mineral
surveys for the modified alignment beyond Lower Wardha upto Nalganga. In
response, GSI, Nagpur has carried out the surveys for the modified alignment and
informed vide letter no. 730/NWDA/PSS/GSI/CR/2013 dated 28th July, 2016
(Annexure - 4.5) that the revised alignment proposed by NWDA is mostly on
Deccan Trap terrain and small stretch is proposed over the alluviums and no
significant economic mineral deposit prospect is reported in these areas.
4.2.3 Right of Way Surveys for the Reservoirs
No right of way survey has been carried out since only the existing
reservoirs are planned to be used as head works/balancing reservoirs/outfall
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
101
points of the proposed link canal. However, in respect of proposed enroute
storages/tanks, this kind of surveys, as required will be carried out at pre-
construction stage.
4.2.4 Communication Surveys
Wainganga (Gosikhurd) – Nalganga (Purna Tapi) link Project is proposed
to pass through Nagpur, Wardha, Amravati, Washim, Akola & Buldhana districts
of Maharashtra State. The existing Gosikhurd reservoir functions as the head
works of the link canal. The dam is located at about 10 km from Pauni town in
Bhandara district and is approachable from Nagpur through bituminous roads via
Umred, Bhiwapur & Pauni towns. The off-take point from Gosikhurd reservoir
near entrance of Rajoli village which is situated on the upstream of Gosikhurd
project in Kuhi taluk of Nagpur district is approachable from Nagpur through
Nagpur-Ambhora road. In the initial reach of the link canal, lifting arrangements
in 3 stages are proposed at RD 2.40 km near Rengatur village, at 20.00 km near
Musalgaon village and at RD 39.90 km near Dongargaon village and these are
approachable from Kuhi. The nearest airport in the vicinity of the off take point
of the link canal is located at Nagpur at about 85 km. Also, the link canal crosses
Nagpur-Nagbhid narrow gauge railway line at RD 26.73 km, Nagpur–Hyderabad
road (NH-7) at RD 59.72 km and Nagpur-Wardha South Central Railway line at
RD 60.46 km (20 km from Nagpur railway station), Wardha–Arvi (Anji–
Karangna) road at RD 138.37 km (25 km from Wardha), Rohna-Arvi Road which
is about 6 km from Arvi town in Wardha district.
The link canal is proposed to outfall into the Lower Wardha reservoir at
RD 167.90 km through Savangi stream near Savangi village in Wardha district.
The nearest airport in the vicinity of the existing Lower Wardha reservoir is
located at Nagpur at a distance of about 130 km. Off-taking from Lower Wardha,
the canal crosses Nagpur-Mumbai Central Railway line at RD 197.71 km (25 km
from Amravati), Amravati-Yeotmal road at RD 219.13 km (10 km from
Amravati), Nagpur-Aurangabad (NH-6) road at RD 248.64 km (25 km from
Amravati), Murtizapur-Yeotmal road at RD 260.15 km (10 km from Murtizapur
town) and Akola–Mangrulpir (Mahan – Hatola) road at RD 298.08 km. Lifting
arrangement are proposed in further 3 stages at RD 169.60 km near Anjansingi
village, at RD 176.90 km near Amduri village, both in Amravati district and at
RD 292.85 km near Mahan town in Akola district.
Chapter – 4 Surveys and Investigations
102
Thereafter, the link canal joins the existing Katepurna reservoir at RD
298.63 km which is at a distance of 2 km from Mahan town in Akola district.
Off-taking from Katepurna, the link canal crosses Akola-Washim road at RD
319.46 km (30 km from Akola), Patur–Balapur road at RD 327.01 km,
Khamgaon-Buldhana road at RD 391.82 km (3 km from Khamgaon town),
Motala–Nandura road at RD 419.55 km and Buldhana-Malkapur road at RD
425.13 km (5 km from Motala town). Finally, the link outfalls in the existing
Nalganga reservoir at RD 426.54 km about 4 km from Motala town.
Thus, the entire link canal traverses in the vicinity of many villages and
towns. The head works, balancing reservoirs, enroute storages/tanks and canal
alignment are well approachable by means of National Highways, State High
ways, major district roads and village roads of bituminous top. The existing road
network can be used during the period of construction activities of the link
project. However, necessary provision is kept in the cost estimate for widening
of some village roads in addition to new approach roads, if any required at the
time of execution of the project.
All the villages/towns in the vicinity of the head works, balancing
reservoirs, enroute storages/tanks, link canal alignment and outfall point are fully
electrified and connected by telephone lines. Further, suitable provision is made
in the project estimate towards electrification and laying telephone lines in the
colony area during the execution of the project.
The map showing the communication network in the vicinity of the link
canal project is appended at Plate - 4.8.
4.2.5 Drainage Surveys
The link project is envisaging transfer of water through lined canal to
extend irrigation benefits in the water short areas of Vidarbha region of
Maharashtra. As such, no water logging/drainage problem is anticipated in the
command area. Suitable provision is, however, made in the cost estimate towards
providing good drainage network.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
103
4.2.6 Soil Surveys
The Wainganga (Gosikhurd) – Nalganga (Purna Tapi) link project is
mainly an irrigation project. The proposed command area mostly falls in the
Lower Maharashtra region of Deccan Plateau in Buldhana, Akola, Amravati,
Wardha, Yeotmal and Nagpur districts of western Vidarbha region. Based on the
map of ‘Soils of Maharashtra’ published by the National Bureau of Soil Survey
and Land Use Planning (NBSS&LUP), Nagpur, it could be seen that basalt and
alluvium are predominant along the Tapi, Godavari, Purna rivers and their
tributaries. Majority of the area has deep, clayey, cracking soils which have high
water retentive capacity and length of growing period. The area has high
productivity potential due to inherent fertility of soils. Watershed based crop
planning can be adopted to exploit the high potential of the area for agricultural
production. Also, proper water management practices need to be adopted to
prevent the development of salinity and alkalinity. Soil map of the command area
prepared based on the ‘Soil map of Maharashtra’ of NBSS & LUP, Nagpur is
given at Plate - 4.9.
4.2.7 Cadastral Surveys
Wainganga (Gosikhurd) – Nalganga (Purna Tapi) link canal is aligned to
pass through Nagpur, Wardha, Amravati, Washim, Akola & Buldhana districts
of Maharashtra State. The taluk wise cadastral maps of seven taluks, four in
Nagpur district (Kuhi, Umred, Nagpur and Hingna) and three in Wardha district
(Arvi, Selu and Dhamangaon Railway) covering the link alignment upto Lower
Wardha and four taluks, two each in Akola district (Barshi Takli, Patur) and
Buldhana district (Khamgaon, Motala) covering the link alignment from
Katepurna upto Nalganga have been collected from the Department of Land
records, Pune for assessing the extent of different types of land acquisition
involved under the link canal. The field surveys along with furnishing cadastral
information for the reach of the link project beyond Wardha river upto its outfall
point at Katepurna river have been carried out by outside agency. In addition, the
land use/land cover maps of the project area along the entire link alignment have
been procured from by WRD, Govt. of Maharashtra from Maharashtra Remote
Sensing Application Centre (MRSAC), Nagpur and supplied to NWDA. Based
on these maps, the land acquisition under the link canal is 7342 ha including
Chapter – 4 Surveys and Investigations
104
agricultural land of 6399 ha, barren land of 548 ha, water body of 39 ha, habitat
land of 202 ha and forest land of 154 ha.
4.2.8 Canal-top Solar Power Potential Studies
Solar Energy generation is a clean technology. In accordance with the
policy initiative taken by the Ministry of New and Renewable Energy (MNRE)
Govt. of India, NWDA sought to explore the possibility of implementing the
scheme on canals proposed in Interlinking of Rivers projects and incorporate the
same in the Detailed Project Reports. Accordingly, the study for setting up of grid
connected solar (PV) power plant on canal top/canal banks and to assess possible
solar power potential along the link canal has been assigned to Gujarat Energy,
Research and Management Institute (GERMI), Gandhinagar on consultancy
basis. The firm has identified the stretch of the canal which can hold 1MW canal-
top solar PV plant and carried out techno-commercial feasibility of the project
(solar power component) including Capex and Opex which has been then
extrapolated for the full length of canal. The study also suggested various
probable arrangements viz. ‘E-W portal, N-S truss & Canal bank configurations’
for the proposed canal-top solar PV project. The study assessed the solar potential
of the link project as 1884 MW.
Based on the tentative arrangement for the typical canal section and
dimensions so considered, GERMI prepared nine types of designs. As per the
financial analysis of GERMI, the capital cost of the 1 MW plant is estimated at
Rs. 9.73 crore and the operation and maintenance cost is calculated at Rs. 9.73
lakh for the first year, which is approximately 1.0% of the capital cost. Thereafter,
the O&M cost is considered to escalate @ 5.72% annually. The debt-equity ratio
is taken at 70:30 based on common practice, while the interest on loan is taken at
12.50% per annum. The Capacity Utilization Factor (CUF) of the plant is
calculated at 17.9% for the first year, thereafter degrading by 1% per year relative
and compared to the previous year. Without Accelerated Depreciation (A.D.),
financial analysis yields project Internal Rate of Return (IRR) and equity Internal
Rate of Return (Equity IRR) at 6.95% and 1.95% respectively and Debt Service
Coverage Ratio (DSCR) of 0.87. Whereas in case of A.D., equity IRR increases
slightly to 2.10% and DSCR increases upto 0.90.
The study report on the canal top/bank solar power (PV) plant prepared by
GERMI, Gandhinagar is furnished as Appendix- 4.2.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
105
4.3 Geology and Seismic Investigations
4.3.1 Regional Geology
The entire area of the Maharashtra State (which comprises the project
area), forms a part of the “Peninsular Shield” which is composed of rocks
commencing from the most ancient rocks of diverse origin which have undergone
considerable metamorphism. Over these ancient rocks of Precambrian era lie a
few basins of Proterozoic era and of permo carboniferous periods which are
covered by extensive sheets of horizontally bedded lava flows comprising the
Deccan trap. More than 80% area of the State is covered by the Deccan trap which
has concealed geologically older formations. The Wainganga (Gosikhurd) –
Nalganga (Purna Tapi) link Project area is mostly covered by Deccan trap.
The area around the link canal alignment from Gosikhurd to Lower Wardha
is predominantly occupied with the rock formations ranging in age from
Archaean to Upper Cretaceous-Paleocene age. Granite gneiss and migmatites
belonging to the Tirodi Gneissic Complex, Amgaon Gneissic Complex and
Bengpal Group occupy the major eastern and northern part of the area. They
form the basement for the overlying rocks of Sakoli Group, Sausar Group,
Gondwana Supergroup, Lameta Group and Deccan Trap Supergroup. The project
area beyond Lower Wardha is represented by Quaternary alluvium and Deccan
Trap Basalts.
The broad and tentative succession of the area, as worked out in 1:50000
Geological Map Series (GMS) by Geological Survey of India is given below:
Age Supergroup Group Formation Rock type
Recent Alluvium
Upper
Cretaceous to
Palaeocene
Deccan Trap Satpura Unclassified Basalt Flow 24
Basalt Flow 23
Basalt Flow 22
-------------- Unconformity --------------- ---------------
Upper
Cretaceous
Lameta Cherty and
impure
limestone, cherty
conglomerate,
sandstone,
-------------- Unconformity --------------- ---------------
Chapter – 4 Surveys and Investigations
106
Gondwana
Lower
Gondwana
Kamthi Sandstone
Talchir
Fine grained
sandstone
Neoproterozoi
c
Penganga sandstone, minor
slate and
conglomerate
-------------- -------------- Unconformity --------------- ---------------
Palaeo
proterozoic
Sausar
Chorbaoli Quartzite
Lohangi
calc-silicate rock,
calc-gneiss,
impure marble
Sakoli Pauni Slate , phyllite
meta-arkose ,
quartzite, matrix
supported
conglomerate,
Biwapur Mainly
metapelites with
interbands of
metamorphosed
acid volcanics
/tuffs of rhyolite
Dhabetekri Mainly
metabasalt with
subordinate
meta-pelites,
---------------- --------------- Tectonised contact ----------- ---------------------
Archaean
Tirodi
Gneissic
Complex/Am
gaon Gneissic
Complex/Ben
gpal Gneiss
Granite gneiss,
Gneiss and
migmatites,
meta-ultramafics
and pre-
Sakolisupracrusta
l assemblages of
high grade schist
including
quartzite kyanite
and
sillimaniteschist,
calc-silicate
rock,etc.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
107
Economic Minerals
Occurrences of strata bound copper sulphide ores are known in Ranmangli
area. Tungsten mineralization is also noticed in the area. Coal is being mined near
Umred(55P/5). Occurrences of strata bound copper sulphide ores are known from
several places viz., Pular-Parsori, Kosari, Khapri, Thutanbori, Pahungaonetc.,
Presence of gold mineralization with or without copper ores have been noticed in
metarhyollite/tuff of Pular-Parsodi and Kosari areas. Abandoned old-workings
for chromite in ultramafic rocks are noticed in Pauni area (55P/9). From economic
point of view, epigenetic tungsten mineralization i.e. scheelite and wolframite
have been reported and explored from granitoid/ pegmatite greisen zones from
Kuhi-Khobna and Agargaon area (55O/8). Investigation for tungsten lies between
northern end of the Pular ridge in north, Mokabardi in south, Khapri in the east
and Ranbori in the west (55 P/5 and P/9). No minerals of economic importance
have been recorded along canal alignment during geological mapping by GSI.
4.3.2 Local Geology
Wainganga (Gosikhurd) – Nalganga (Purna Tapi) link canal traverses for
its entire length of 426.54 km through Nagpur, Wardha, Amravati, Washim,
Akola and Buldhana districts of Maharashtra. The lithotypes broadly belong to
Amgaon gneissic complex/Tirodi gneissic complex/ Bengpal gneiss and partly
by Sakoli Group (Bhiwapur Formation), Deccan trap Supergroup (Basalt flows)
and granite/pegmatite intrusive and considerable variations are observed in regard
to their mineral assemblage, structural set-up and field relationship along the
proposed link canal alignment.
In the initial reach of about 6 km of the link alignment, Sakoli Group of
rocks are represented by andulasite mica schist and Phyllite of Bhiwapur
Formations intruded by granite/granitised mylonite. Then, major part of the reach
upto about RD 32 km is predominantly covered under thick soil and alluvium, its
thickness varying from 5 to 7 m. For the next 5 km, the canal passes through flat
to undulatory basaltic terrain. Thereafter, from RD 37 km to RD 62 km, the canal
passes through broad open terrain surrounded by isolated dissected hillocks
(Ashokban and Kaldongri) in a vast pediplained area with a gentle slope towards
east. Thereafter, the canal alignment upto Lower Wardha passes through Deccan
Trap basaltic flows belonging to the Satpura Group.
Chapter – 4 Surveys and Investigations
108
Pegmatite/granite exposed Massive basalt exposed in a
on river bed of Amb Nadi quarry section (3rd lift at RD 39.90 km)
4.3.3 Geological and Geotechnical Investigations
The objective of the geological investigations is to find out type of rock,
major joints, shear zones, faults & fractured zones if any, in the project area. The
geological and geo-technical investigations for the link project (i) from take off
at Gosikhurd reservoir upto Wardha river crossing(phase-I) and (ii) from Lower
Wardha to outfall into Nalganga project (Phase-II) were carried out by
Engineering Geology Division, GSI, Nagpur.
The Geological mapping of the proposed canal alignment was carried out
on 1:10,000 scale covering a cumulative area of 133.36 sq. km from RD 0 to RD
426.54 km covering 150 m on either side of alignment. As per the GSI report, the
Granite gneiss of Amgaon Gneissic Complex (Pre-Sakoli Group), Bhiwapur
Formation of Sakoli Group, Basalt flows of Deccan trap Supergroup constitute
the geology at different reaches of the canal. The Sakoli Group of rocks intruded
by pegmatite/granite, show a tectonised contact with underlain granite gneiss,
which is exposed from off take point (0.00 km) to 19.60 km and unconformity is
marked at RD 33.626 km between granite gneiss overlain by basaltic rocks. It is
tentatively estimated that the thickness of overburden soil in granite gneissic
terrain is up to 5 m, whereas, it extends up to 5 to 7 m in Sakoli meta-sediments
and nil to 1.5 m in basaltic terrain.
Major portion of proposed canal alignment beyond Lower Wardha passes
through cultivation area with shallow soil (overburden) cover (~ up to 3m).
Scanty rock exposures comprising massive and at places vesicular basalt
constitutes the geology along proposed canal alignment. Based on surface
geological mapping, it has been interpreted that basalt lava flows of Deccan Trap
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
109
Supergroup shall be encountered as rock type at different reaches of the canal
alignment and as such no geological uncertainty had been observed.
Reconnaissance survey by Superintending Geologist, GSI at Off-take
point from Gosikhurd on 22.05.2014
In addition, Geotechnical investigations including drilling were carried out
at proposed major cross drainage (CD)/cross masonry (CM) works at the
river/stream, road and railway crossings to evaluate the depth and nature of bed
rock, overburden and bed characteristics. NWDA has carried out sub surface
exploration at 28 nos. of bore holes by double tube barrel diamond core drilling,
through outside drilling agency. Bore logging and assessment of the cores have
been made by GSI, Nagpur for a cumulative depth of 426 m. The rock types
encountered in the mapped reaches include granitic pegmatite, vesicular basalt,
vesicular amygdular basalt, massive basalt, Sericite schist, Quartz, etc.
Chapter – 4 Surveys and Investigations
110
Rock Cores recovered from the Drill hole at Venna river crossing at
RD 63.521 km
The report on the geological mapping & geotechnical investigations of the
link project received from GSI, Nagpur is at Appendix – 4.3.1 (for Phase – I)
and Appendix - 4.3.2 (for Phase-II).
4.3.4 Laboratory Investigations of Rock Samples
CSMRS, New Delhi has been assigned with laboratory investigations of
rock samples for the Wainganga (Gosikhurd) – Nalganga (Purna Tapi) Link
Project. The core samples collected from exploratory drill holes were got tested
at CSMRS Rock Mechanics Laboratory, New Delhi.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
111
Selected Rock Samples for Testing by CSMRS, New Delhi
The recommended design parameters based on the laboratory
investigations of representative samples of three rock types viz. I. Phyllite/Quartz
with Phyllite, II. Vesicular/Massive basalt and III. Vesicular Amygdular basalt as
suggested by CSMRS are presented in Table-4.4.
Table-4.4
Recommended Design Parameters for Rock
Parameter Recommended Parameters
I II III
Bulk Density (dry), Υdry, (kg/m3) 2710 2720 2590
Bulk Density (saturated), Υsat, (kg/m3) 2715 2760 2680
Grain Density (saturated), Υgrain, (kg/m3) 2780 2810 2800
Water Content (at saturation), w.c.(%) 0.3 2.0 5.0
Apparent Porosity, ŋ (%) 0.7 5.8 12
Slake Durability Index, I cycle (%) 99 98.5 98
Slake Durability Index, II cycle (%) 98.5 98 97
Uniaxial Compressive Strength, UCS
(MPa)
45 35 --
Tangent Modulus, E (GPa) 40 35 --
Poisson’s ratio, µ 0.25 0.25 --
Chapter – 4 Surveys and Investigations
112
Apparent Cohesion, c(MPa) 4.0 3.5 --
Angle of Internal Friction, Φ (Degree) 55 50 --
Indirect Tensile Strength (MPa) 6 10 5
Point Load Strength Index (diametral)
(MPa)
4.5 9 1.8
Point Load Strength Index (axial)
(MPa)
-- 11 1.9
The report on Laboratory Investigations of rock samples received from
CSMRS, New Delhi is at Appendix – 4.4.
4. 3.5 Geophysical Investigations
Since no new dams are proposed as head works/balancing
reservoirs/outfall structures of the link project, no Geophysical investigations
were required to be conducted. Such investigations for the proposed enroute
storages/tanks shall be carried out by the Govt. of Maharashtra on finalization
of their locations on the field after carrying out the detailed topographical
surveys. During the discussions with GSI, Nagpur, it was given to understand
that geophysical investigations may not be required for a canal and hence were
not taken up long the link alignment.
4.3.6 Seismic Investigations
The link canal takes off from Gosikhurd reservoir and out falls into
Nalganga project, utilising existing Lower Wardha and Katepurna reservoirs as
balancing reservoirs. Since all the four reservoirs are existing reservoirs and no
new dams/reservoirs are proposed for diversion of water through the link canal,
no site specific seismic studies are conducted at present. From the general
seismology of Vidarbha region, the eastern districts of Bhandara and Nagpur fall
in earthquake zone-I, which is considered the safest in India, while the other
districts fall in zone-II. Gosikhurd project is located in Bhandara district,
Nalganga in Buldhana district, Lower Wardha in Wardha district and Katepurna
in Akola district. The enroute storages/tanks are proposed in Nagpur, Wardha,
Amravati, Yeotmal, Akola and Buldhana districts. Therefore, the existing as well
as proposed storages, which will be part of the link project are in Seismic Zone –
I & II which are considered to be not earthquake prone.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
113
4.4 Geotechnical Investigations (Soils) and Borrow Area Survey
The works of Geotechnical investigations (Soils) and borrow area survey
for the Wainganga (Gosikhurd) – Nalganga (Purna Tapi) Link Project have been
carried out by CSMRS, New Delhi.
The scope of the work includes:
(i) Collection of representative disturbed soil samples from borrow areas
in filling reach and undisturbed soil samples from cutting reach from
trial pits along the proposed canal alignment.
(ii) Conducting in-situ permeability tests in the cutting portion of the canal,
and
(iii) Conducting various laboratory tests on the collected soil samples for
ascertaining their suitability as construction material in filling portion
and for assessing competency of foundation in cutting portion of the
canal.
4.4.1 Soil Investigations along the Canal Alignment
The soil investigation along the canal alignment involves collection of
undisturbed / disturbed soil samples from the trial pits of size 3 m x 3 m x 3 m
excavated at the regular intervals of four to five km along the canal alignment. A
total of 66 soil samples were collected along the canal alignment from Gosikhurd
upto Nalganga. Representative disturbed soil samples were collected from
borrow areas in the filling portion of canal alignment and undisturbed soil
samples were collected using core cutters from the cutting reaches of the canal
alignment. Out of 66 samples, 47 samples have been collected from filling
potions and 17 samples from cutting reaches and 2 samples from level (balanced)
reaches where much cutting and filling is not involved.
Chapter – 4 Surveys and Investigations
114
Soil Investigations by CSMRS and Logging of pits by GSI at RD 86.115 km
on 25.02.2015
4.4.2 Laboratory Investigations on Soil Samples from the Canal
Alignment including Borrow Area
To ascertain the suitability of the borrow area material as construction
material in filling reaches of canal alignment together with soil characteristics in
cutting reaches of the canal, representative soil samples have been collected and
laboratory investigations conducted by CSMRS, New Delhi.
The following laboratory investigations were carried out on the soil
samples collected from cutting and filling reaches as per the Bureau of Indian
Standards and other standard procedures:
- Mechanical Analysis
- Atterberg Limits
- Standard Proctor Compaction
- Insitu density and Natural Moisture Content
- Triaxial Shear (CU )
- Specific Gravity
- One Dimensional Consolidation
- Laboratory Permeability
- Free Swell Index
- Chemical Analysis
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
115
pH
CaCo3
TSS
Organic Matter
Water Soluble Sulphates
Water Soluble Chloride
- Dispersivity of Soil
Classification of these soil samples was done as per IS: 1498.
Based on the findings of the laboratory investigations carried out on soil
samples collected from the borrow areas along the canal alignment, following
conclusions have been arrived at.
The grain size analysis of soil samples indicate that soil samples in the
reach upto Lower Wardha in general possess predominantly silt sizes
followed by fine sand and clay. Whereas in the reach beyond Lower
Wardha, it is gravel followed by silt and clay.
The liquid limits of samples vary from 26.1 to 76.3 which indicate that the
tested soil samples possess low to high compressibility characteristics.
The plasticity index values of the tested soil samples vary from 4.7 to 41.4
indicating that the materials in general possess low to high plasticity
characteristics except eight soil samples which exhibit non-plastic
characteristics.
Based on the results of grain size distribution and Atterberg limits tests, out
of 66 soil samples , 17 soil samples fall under SM (silty sand) group , 9 soil
samples fall under SC (clayey sand) group, 8 soil samples fall under GC
(clayey gravel) group, 4 soil samples fall under MI (silt of intermediate
compressibility) group, 4 soil samples each fall under CH (clay of high
compressibility) group and 7 samples fall under MH (silt of high
compressibility) group and 2 soil samples each falls under CI (clay of
intermediate compressibility) group and 13 soil samples fall under GM
Chapter – 4 Surveys and Investigations
116
(silty gravel) group, one each under ML (silt of low compressibility) and
GP-GM (poorly graded silty gravel) as per BIS soil classification system.
The results of In-situ dry density tests carried out on soil samples from the
foundation pits show that material has low to good In-situ dry densities.
The results of Standard Proctor tests show that materials are capable of
achieving low to good compaction densities.
The values of specific gravity of samples from all borrow area vary from
2.56 to 2.94.
The total and effective cohesion (c & c’) and angle of shearing resistance
values(Ø& Ø’) of the tested soil samples from cutting reaches were found
to vary from (0.25 to 0.468 kg/cm2 & 0.12 to 0.385 kg/cm2) and (13.110 to
19.50 & 24.350 to 27.80) respectively. The same in respect of tested samples
from filling reaches were found to vary from (0.15 to 0.256 & 0.06 to
0.214) and (16.360 to 25.20& 25.070 to 31.60). The test results indicate that
soil in both cutting and filling reaches in general are likely to exhibit very
good shear strength characteristics.
The compressibility values of all tested soil samples indicate that soil
samples are likely to exhibit low to high compressibility characteristics
depending upon variability of soil in different stretches.
The results of Laboratory Permeability test indicate that the soil samples in
general are impervious to semi- pervious in nature.
The results of free swell index conducted on 3 soil samples indicate
moderate degree of expansion.
On the basis of chemical analysis done on 2 samples, the conductivity
values in terms of total dissolved salts (TDS) are below 1.0 milli mho/cm
indicating normal behavior of foundation soil.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
117
The consensus arrived at based on the Soil Dispersivity identification tests
indicates that the tested soil samples possess non-dispersive to intermediate
characteristics.
CSMRS recommended that based on geotechnical investigations carried
out, the link canal can be taken up along the proposed route. However, in reaches
where very weak soil such as soil of MH and CH group are present, it was
suggested to deviate route slightly based on the soil availability or else the
designers may design the canal based on investigated data.
The recommended design parameters by CSMRS in the phases I & II of
the link alignment are given in Tables 4.5 & 4.6 respectively.
Table-4.5
Recommended Design Parameters for Soil in the reach from Gosikhurd to
Lower Wardha (Phase-I)
S.No. Name of the tests Average
Average
minimum
I Filling reaches of canal
1.
Standard Proctor Compaction
i. Maximum Dry Density (Υd), g/cc 1.70 1.66
ii. Optimum Moisture Content,% 17.64 16.27
iii. Specific Gravity 2.76 2.73
2. Triaxial Shear Test
i. Total Cohesion (c), kg/cm2 0.18 0.17
ii. Effective Cohesion(c’), kg/cm2 0.08 0.07
iii. Total angle of shearing resistance, (ø) 21.3o 21.0o
iv. Effective angle of shearing
resistance, (ø)
30.6o 30.0o
3. Consolidation Test
i. Compression index 0.103 0.103
ii. Swelling index 0.019 0.019
4. Permeability Test
Coefficient of Permeability ‘K’ Impervious to
semi-pervious
5. Dispersivity Test
Consensus of four dispersivity tests Non Dispersive to
Intermediate
II Cutting reaches of canal
1. i. Insitu Dry Density (Υd) g/cc 1.55 1.52
Chapter – 4 Surveys and Investigations
118
ii. Insitu Permeability cm/sec Semi-
impervious
Impervious
2.
Triaxial Shear Test
i. Total Cohesion (c) kg/cm2 0.20 0.20
ii. Effective Cohesion(c’) kg/cm2 0.09 0.09
iii. Total angle of shearing resistance,
(ø)
19.5o 19.5o
iv. Effective angle of shearing
resistance, (ø)
27.8o 27.8o
3.
Consolidation Test
i. Compression index 0.336 0.336
ii. Swelling index 0.0387 0.0387
Table-4.6
Recommended Design Parameters for Soil in the reach from Lower
Wardha to Nalganga (Phase-II)
S.No. Name of the tests Average
Average
minimum
1.
Standard Proctor Compaction
i. Maximum Dry Density (Υd) g/cc 1.66 1.59
ii. Optimum Moisture Content,% 20.55 18.70
iii. Specific Gravity 2.82 2.79
2.
Triaxial Shear Test
Filling Section
i. Total Cohesion (c) kg/cm2 0.10 0.10
ii. Effective Cohesion (c’) kg/cm2 0.05 0.05
iii. Total angle of shearing resistance,
(ø)
16.4o 16.4o
iv. Effective angle of shearing
resistance, (ø)
25.4o 25.2o
Cutting Section of the Canal
i. Total Cohesion (c) kg/cm2 0.18 0.16
ii. Effective Cohesion(c’) kg/cm2 0.10 0.10
iii. Total angle of shearing resistance,
(ø)
18.0o 18.0o
iv. Effective angle of shearing
resistance, (ø)
26.7o 26.5o
3.
Consolidation Test
Filling Section of the Canal
i. Compression index 0.160 0.145
ii. Swelling index 0.028 0.026
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
119
Cutting Section of the Canal
i. Compression index 0.099 0.096
ii. Swelling index 0.015 0.013
4.
Permeability Test
Type of Permeability Drainage Characteristic
Field Permeability Test (cutting
section)
Good drainage
Coefficient of Laboratory
Permeability ‘k’ (filling section)
Impervious
5. Dispersivity Test
Consensus of four dispersivity tests Non Dispersive to Dispersive
The reports on laboratory investigations on soil samples from borrow area
along the canal alignment received from CSMRS, New Delhi for phases I & II
are at Appendix – 4.5.1 and 4.5.2. The map showing the location of soil samples
collected is at Plate-4.10.
4.4.3 Foundation Investigations of CD/CM Structures
Foundation investigations at Major CD/CM structures & lift points involve
drilling the drill holes at each side of CD/CM structures and conducting the
Standard Penetration tests (SPT) and In-situ permeability tests alternatively at
every 1.50 m interval, besides, collection of undisturbed soil samples in shelby
tubes and SPT samples from the drill holes. A total of 28 boreholes were drilled
at 15 different locations, viz. at two lift points at RD 3.30 km & RD 176.90 km
and 13 CD/CM structures sites along the canal alignment upto Nalganga .
Chapter – 4 Surveys and Investigations
120
Foundation Investigations at Left Bank of Venna river (Bore-Hole No.1) at
RD 63.439 km on 09.02.2016
Water Permeability Test at Left Bank of Venna river(Bore-Hole No.1)
at RD 63.439 km on 10.02.2016.
11 SPT samples and 7 UD samples collected from 12 bore holes in the link
canal reach up to Wardha crossing (Phase-I) were sent to CSMRS, New Delhi.
The foundation investigations of soil were not carried out for the phase-II (from
Lower Wardha to Nalganga) of the link alignment in consultation with CSMRS
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
121
as the soil depth in the drill holes was very shallow and no representative SPT
and UD soil samples could be collected from any of the bore holes. The following
laboratory tests were conducted by CSMRS for ascertaining the suitability of
foundation soil:
Mechanical Analysis
Atterberg limits
In-situ Density and Moisture Content
Specific Gravity
Triaxial Shear
Direct Shear
One Dimensional Consolidation
All the above tests were carried out in accordance with the
recommendations of the relevant Indian Standard codes and other standard
procedures. The recommended design parameters are given in Table-4.7.
Table-4.7
The Recommended Design Parameters on Foundation Investigations
Suggested by CSMRS
Parameter Average Average
minimum
In-situ Density
In-situ Dry Density (γd), g/cc 1.75 1.70
Tri-axial Shear
Total Cohesion ( c ), kg/cm2 0.31 0.26
Total angle of shearing resistance (ø) 16.8o 14.1o
Effective Cohesion (c), kg/cm2 0.17 0.14
Effective angle of shearing resistance (ø) 22.3o 19.7o
The report on Foundation investigations of cross drainage/cross masonry
structures and at deep cut/lift point (RD 3.3 km) received from CSMRS, New
Delhi is at Appendix – 4.6. The map showing the location of drill holes at
CD/CM structures and at lift point is at Plate-4.11.
Chapter – 4 Surveys and Investigations
122
4.5 Construction Materials Survey
The CSMRS, New Delhi has carried out the construction materials
survey of coarse and fine aggregates for the link alignment (Phases -I&II) in the
vicinity of the project area along with laboratory investigations for assessing their
suitability to use as coarse and fine aggregates in concrete during construction of
the project.
4.5.1 Rock and Aggregates
The CSMRS team inspected the rock quarry sites which are located in
the vicinity of the proposed project (upto Lower Wardha) during 18th - 20th March,
2015.
Following 6 probable rock quarry sites have been identified by CSMRS
team in Nagpur & Wardha districts for coarse aggregate.
1. Surgaon rock quarry adjacent to the canal alignment and 22 km from
Nagpur
2. Sawangi-Deoli rock quarry 5 km right of the canal alignment
3. Haladgaon rock quarry just right side of the Nagpur-Wardha road
and about 4 km left of the canal alignment
4. Keljhar rock quarry1 km away from the Nagpur-Wardha road and 5
km left of the canal alignment
5. Yelakeli rock quarry about 7 km from Wardha district and 20 km
left of the canal alignment
6. Sorta rock quarry left side of the Arvi-Pulgaon road and 25 km left
of the canal alignment
Further, CSMRS, New Delhi visited the project area from Lower Wardha
upto Nalganga (Phase-II) during 19-23, June, 2016 and finalised the following
rock quarries in Amravati, Akola and Buldhana districts.
1. Sonegaon rock quarry 1.5 km from Chandur railway and 4 km left
of the canal alignment
2. Palaskhed rock quarry 2 km from Chandur railway and 5 km left of
the link alignment
3. Masood rock quarry about 16 km right of the canal alignment
4. Borgaon Manju rock quarry about 20 km right of the canal
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
123
alignment
5. Mathni rock quarry about 2 km right of the canal alignment
6. Tembhurna rock quarry on Khamgaon–Akola road and adjacent to
the canal alignment
7. Yeota rock quarry on Akola-Malkapur to Kumbhari road about 16
km right of the canal alignment
All these quarries located in the proximity of the link alignment have
sufficient quantity of rock for use as coarse aggregate for the construction of the
link project.
Construction Materials Survey (C.A) by CSMRS at Surgaon Quarry Site
(Nagpur district) on 18.02.2015
The samples from the above thirteen rock quarries were collected and the
physical and chemical tests viz., water absorption, specific gravity, aggregate
impact value, aggregate abrasion loss, aggregate crushing value, soundness loss
(5 cycles of Na2 So4), alkali aggregate reactivity and Petrographic analysis were
conducted on the representative rock samples (as per IS: 2386-1963) for assessing
their suitability as per IS: 383-2002 for use in concrete.
Based on physical & chemical tests and ASR test conducted, it is found
that all the coarse aggregates samples (barring sample from Sorta quarry) are
conforming to the codal requirements for use as coarse aggregate in concrete for
Chapter – 4 Surveys and Investigations
124
both wearing as well as non- wearing surfaces as per IS: 383-2002/2016. The
sample from Sorta quarry is also suitable as per physical test results for use as
coarse aggregate in concrete for both wearing as well as non-wearing surfaces,
but it is found to be potentially deleterious in the alkali aggregate reactivity test.
Also, the sample from Mathni quarry shows higher expansion and reactive to
ASR test . Hence, CSMRS recommended that rock material from Sorta and
Mathni quarries may be used as coarse aggregate in concrete for both wearing as
well as non-wearing surfaces with suitable remedial measures like mineral
additives such as fly ash, slag, silica fume, rice husk, GGBS, triple blended
cement etc. to prevent the ASR in concrete.
4.5.2 Sand
The CSMRS, New Delhi after visiting the project area in the vicinity of
the proposed project (upto Lower Wardha) during 18th - 20th March, 2015 have
finalized the following sand quarries for fine aggregate in Nagpur and Wardha
districts
1. Binaghat sand quarry at confluence point of Kanhan and Pench
river about 57 km from the canal alignment
2. Wadhona sand quarry near Wadhona village on the left bank of the
Kanhan river about 17 km from the canal alignment
3. Saikheda sand quarry on left bank of Wardha river about 3.5 km d/s
of Lower Wardha dam and about 6 km from the canal alignment
Further, CSMRS, New Delhi visited the project area from Lower
Wardha upto Nalganga (Phase-II) during 19-23, June, 2016 and finalized the
following sand quarries in the Amravati, Akola and Buldhana districts.
1. Bhatkuli sand quarry near the Bhatkuli village on bank of Pedhi
river and 16 km right side of the canal alignment
2. Hivrakorde sand quarry near Hivra korde village on the bank of
Pedhi river and 12 km right side of the canal alignment
3. Bhastan sand quarry on the bank of Purna river and 30 km right
side of the canal alignment
4. Yerli sand quarry near Yerli village on the bank of Purna river and
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
125
30 km right of the canal alignment.
One natural sand sample from each sand quarry have been collected for
ascertaining the suitability for use as fine aggregate in concrete for the proposed
project.
Construction Materials Survey by CSMRS (FA) at Kanhan river near
Wadhona village (Nagpur district) on 18.02.2015
The physical and chemical tests viz., specific gravity, grading and fineness
modulus, organic impurities, silt and clay content, soundness loss (5 cycles of Na2
So4), Alkali aggregates reactivity and Petrographic analysis were conducted on
the representative sand samples as per BIS (IS: 2386-1963) for assessing their
suitability for use in concrete as fine aggregate.
Based on physical & chemical tests and ASR tests, it is found that the sand
samples from Binaghat & Wadhona are suitable for use in concrete works. The
sand sample from Saikheda which is slightly coarse with FM of 3.46 is also
conforming to grading zone-I and the same may be used in the construction work
with proportionately blending of fine sand to make the FM 2.5 to 3.0. As per the
ASR test results, this sample is found to be of deleterious behaviour and the same
may be used with suitable remedial measures like mineral additives such as fly
ash, slag, silica fume, rice husk etc. to prevent the ASR.
As regards to the samples from the four quarries located in the phase-II
reach of the link alignment, based on physical tests conducted, it is found by
CSMRS that the entire natural sand are very coarser in nature and FM is varying
Chapter – 4 Surveys and Investigations
126
between 3.45 to 3.88 and may require blending with fine sand to achieve FM in
the range of 2.6-2.8. As per petrographic report of these samples, it is found that
all sand samples are having mica content in free form which would result in
reduction of compressive strength of concrete. Therefore, CSMRS concluded that
trial mixes shall have to be conducted and ensured that it meets the required
technical specification requirements.
The Reports on the Construction Materials Survey and Laboratory
investigations of coarse and fine aggregate samples for assessing their suitability
for use as Coarse and Fine Aggregate in Concrete for Wainganga–Nalganga link
Canal Project received from the CSMRS, New Delhi for phases-I & II are given
at Appendix-4.7.1 and Appendix - 4.7.2 respectively. The map showing the
location of quarry sites visited by CSMRS in respect of coarse and fine aggregates
is at Plate-4.12.
4.5.3 Bricks and Tiles
Cement Bricks/hollow concrete bricks/Red Bricks and tiles are
available locally in the vicinity of the Project area.
4.5.4 Pozzolana
The pozzolana materials are not considered to be used in the
construction of the project.
4.5.5 Cement
A no. of Cement Industries are located in Vidarbha region at Nagpur,
Chandrapur, Amravati, Akola etc. To name a few, ‘Ambuja cement industries’,
‘Chanda ACC cement plant’ and ‘Ultra-tech cement limited’ are some of the
cement companies located in the vicinity of the project area. Thus, the required
cement for construction of the project is available in project area.
4.5.6 Steel
The steel required for the Project construction can be procured from the
plants located in Vidarbha region such as ‘Factor Steel’, ‘Vidarbha Iron & Steel
Corporation Ltd., Bajaj Steel Industries Ltd. etc.
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
127
4.5.7 Scarce Material
No scarce materials are anticipated to be used in the project which may
cause hindrance to the construction of the project.
4.5.8 Any other Material
Apart from the above, there will be many other items such as iron rods
/pillars, iron asbestos sheets, CGI sheets, coal tar, wood, paint, coir ropes etc.,
which are required for construction of temporary rooms/sheds etc. All such items
are available at Nagpur, Wardha, Amravati, Akola and Buldhana districts within
the vicinity of project area.
4.6 Hydrological and Meteorological Investigations
4.6.1 Rainfall and Run-off
4.6.1.1 Rainfall
There are 30 rain gauge stations in the catchment of Wainganga upto
Gosikhurd dam site. There is no snowfall occurrence in Wainganga/Pranhita sub-
basin. The precipitation is in the form of rainfall and the intensity of rainfall varies
fairly in time and space as observed from the data. The sub-basin receives more
than 80% of the annual rainfall during monsoon period from June to October. The
available rainfall data for the period from 1970-2014 has been considered in the
hydrological studies upto Gosikhurd dam site. The list of 30 rain gauge stations
in Wainganga catchment up to Gosikhurd dam site with corresponding average
annual rainfall (mm) for the period from 1970 to 2014 is given in Table-4.8.
Table-4.8
Rain-gauge Stations in Wainganga catchment up to Gosikhurd Dam Site
Sl.
No.
Name of the Rain
gauge Station
Average Annual
Rainfall (mm)
(1970-2014)
1. Amla 1039
2. Multai 925
3. Mokhed 980
4. Junnardeo 1109
5. Sausar 893
6. Katol 856
Chapter – 4 Surveys and Investigations
128
7. Saoner 844
8. Khindsi 1023
9. Umred 1084
10. Chhindwada 911
11. Seoni 1098
12. Tamiya 1563
13. Chaurai 1007
14. Amarwada 973
15. Parseoni 967
16. Ramtek 1089
17. Deolapar 1025
18. Harai 1078
19. Lakhnadaun 1047
20. Mandla 1214
21. Rumal 1188
22. Waraseoni 1162
23. Gondia 1212
24. Bhandara 1192
25. Balaghat 1437
26. Baihar 1243
27. Chuikhadan 840
28. AmbagarhChowki 1140
29. Sakoli 1444
30. Khairbanda 1004
4.6.1.2 Run-off
The catchment of Wainganga river upto Gosikhurd has been divided into
four sub-catchments namely Kanhan, Pench, Bagh & Wainganga for hydrological
studies. The Central Water Commission (CWC) is maintaining a no. of G&D sites
on Wainganga/Pranhita river and its major tributaries. The data of two sites
namely Ramakona on Kanhan river and Rajegaon on Bagh river have been used
in the present hydrological study. Also, the Gauge data being observed by
Hydrology Project, Govt. of Maharashtra at one site viz. Kardha across
Wainganga river and the tank gauge data at Pench pick up weir are used for the
yield assessment in the present study. The details of these G&D sites/Pick up weir
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
129
in the catchment of Wainganga upto Gosikhurd dam site along with some major
G&D sites on main Wainganga/Pranhita river are given in Table-4.9.
Table-4.9
Gauge & Discharge Sites in the Wainganga/Pranhita sub-basin
Sl.
No.
Name of Gauge
& discharge site
Maintained
by
River /
Tributary
Catchment
area (km2)
Year from
which
data is
available
1. Ramakona CWC Kanhan 2500 1986
2. Pench pickup weir WRD Pench 4662 1994
3. Rajegaon CWC Bagh 5380 1986
4. Kardha Hydrology
Project,
GOM
Wainganga 13706 1994
5. Pauni CWC -do- 35520 1965
6. Asthi CWC -do- 50990 1965
7. Tekra CWC Pranhita 108780 1965
4.6.2 Sunshine, Cloud Cover and Visibility
There are four IMD observatories located within the Wainganga/Pranhita
sub-basin at Seoni, Chhindwara, Gondia and Nagpur. Three more observatories
at Mandla, Chandrapur and Betul are located close to the sub-basin. As per the
climatological data of these IMD stations for the period from 1980-2010, the
normal maximum cloud cover is 7.1 oktas during the month of August, where as
the normal minimum cloud cover is 0.6 oktas during the month of April.
4.6.3 Wind Velocity
As per the climatological data of the above IMD stations for the period
from 1980-2010, the normal maximum and minimum wind velocities are 13.1
km/hr in June and 1.9 km/hr in December respectively.
Chapter – 4 Surveys and Investigations
130
4.6.4 Relative Humidity
As per the climatological data of the IMD stations for the period from
1980-2010, the normal maximum and minimum relative humidity are observed
to be 93% and 19% in the months of August and April respectively.
4.6.5 Temperature
As per the climatological data of the IMD stations for the period from
1980-2010, the normal daily maximum and minimum temperature are found to
be 42.9o C and 8oC in the months of May and December respectively.
4.6.6 Sedimentation
In the Pranhita sub-basin, sediment analysis is being carried out by Central
Water Commission (CWC) at Kumhari, Pauni & Asthi G&D sites on Wainganga
river, at Tekra on Pranhita river, at Bhatpalli on Peddavagu, at Satrapur on
Kanhan and at Rajegaon on Bagh. The Pauni G&D site (35520 km2) is located
just 10 km downstream of the Gosikhurd dam (34862 km2) for which the data on
sediment inflow is available for the period from 1969-70 to 2004-05. As per the
available sediment data, the rate of average annual sediment inflow at the site
works out to 13173764 M.T, out of which 13084669 M.T is during the monsoon
period.
4.6.7 Water Quality
Different chemical and physio-chemical parameters of water quality of
Wainganga river at Gosikhurd dam are observed on a regular basis. The Govt. of
Maharashtra under Hydrology Project collects the water samples from Gosikhurd
reservoir during all the months in a year. These samples are tested at Water
Quality Testing lab (a level-II Lab certified by ISO 9001-2008) under Hydrology
Project Division, Nagpur for ascertaining the water quality status. The water
samples are tested for General parameters (pH, Electron Conductivity, Total
Dissolved Solids, Total Suspended Solids, Turbidity etc.), Nutrients, Organic
matter (BoD, DoD), Alkalinity, Hardness, Major Ions, Coliforms etc. The latest
data pertaining to the years 2015 to 2018 on laboratory test results of the water
Detailed Project Report of Wainganga (Gosikhurd)-Nalganga (Purna Tapi) link project
131
samples of Gosikhurd reservoir have been collected and are presented in Table-
7.2 of Chapter-7 ‘Reservoirs & Enroute Storages’.
In the DPR of Gosikhurd project (1982), it was reported that the river water
in the Wainganga at the dam site is quite fit for use on masonry/concrete or any
other construction work without any special treatment. For drinking purpose, the
water can be used with normal treatment of chlorine and alum dose.
4.6.8 Evaporation
The designed utilisation of Gosikhurd project including supplementation
of Asolamendha tank is 1634 Mm3. Out of this, 265.97 Mm3 is provided towards
evaporation losses in the reservoir which accounts for 16.3% of the annual
utilisation and 23.2% of the gross storage of the reservoir. The monthly
evaporation depths at Gosikhurd are in the range of 0.075 m (Nov.) to 0.362 m
(May). The monthly pan evaporation depths considered for the Gosikhurd project
in the DPR are furnished in Table-4.10.
Table-4.10
Monthly Evaporation depths at Gosikhurd
S.No. Month Evaporation Depth (m)
1 June 0.236
2 July 0.133
3 August 0.109
4 September 0.103
5 October 0.113
6 November 0.100
7 December 0.075
8 January 0.085
9 February 0.135
10 March 0.200
11 April 0.248
12 May 0.362