Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
CHAPTER 6
LABOUR PRODUCTIVITY THROUGH APPLICATION OF STOP WATCH
TIME STUDY METHOD IN SAIPL: DATA ANALYSIS AND
INTERPRETATION
Sr.No Title Page
No.
6.1 Introduction 147
6.2 Awareness of Labour Respondents on Stop Watch Time Study
Method 149
6.2.1 Perception (Belief) of Labour respondents on Work
Measurement 149
6.2.2 Awareness of Labour Respondents on Methods of Time Study
Method 151
6.2.3 Awareness of Labour Respondents on Stop Watch Time Study
Method 154
6.3 Responses of Labour Respondents on awareness of training
and training received on Stop Watch Time Study Method 156
6.3.1 Extent of Stop Watch Time Study training awareness among
Labour Respondents 157
6.3.2 Extent of Stop Watch Time Study training received by Labour
Respondents 158
6.3.3 Type of training received by Labour respondents 160
6.4 Procedure of Stop Watch Time Study Method adopted in the
Present Study 163
6.4.1 Defining and Measuring Labour Productivity 163
6.4.2 Definition of Time Study 165
6.4.3 Basic Equipments used in Measuring Time Study 165
6.4.4 Selection of Sections and Activity/ elements covered in the
Study 168
6.4.5 Steps/ Procedure employed for measuring Stop Watch Time
Study method 171
6.5
Analysis of Labour Productivity in Unloading Section of
Logistic department based on application of Stop Watch Time
Study Method
173
6.5.1 Maximum and Minimum time taken by Labour Respondents to
perform activities in Unloading Section. 174
6.5.2 Standard Time taken by Labour Respondents to complete the
activities in Unloading Section. 177
6.6
Analysis of Labour Productivity in Trolley Filling Area (TFA)
Section of Logistic department based on application of Stop
Watch Time Study Method
183
6.6.1 Maximum and Minimum time taken by Labour Respondents to
perform activities in TFA Section. 184
6.6.2 Standard Time taken by Labour Respondents to complete the
activities in TFA Section. 187
6.7
Analysis of Labour Productivity in Catwalk (Supermarket)
Section of Logistic department based on application of Stop
Watch Time Study Method
189
6.7.1 Maximum and Minimum time taken by Labour Respondents to
complete Bin Filling Activity in Catwalk Section. 192
6.7.2 Standard Time taken by Labour Respondents to complete Bin
Filling Activity in Catwalk Section. 195
6.7.3 Maximum and Minimum time taken by Labour Respondents to
complete Box Picking Activity in Catwalk Section. 197
6.7.4 Standard Time taken by Labour Respondents to complete Box
Picking Activity in Catwalk Section. 199
6.8
Analysis of Social and Technical barriers associated with
Labour Respondents while application of Stop Watch Time
Study Method.
201
6.8.1 Responses of Labour Respondents towards Social Barriers
involved in application of Stop Watch Time Study Method 201
6.8.2 Responses of Labour Respondents towards Technical Barriers
involved in application of Stop Watch Time Study Method 204
147
CHAPTER 6
LABOUR PRODUCTIVITY THROUGH APPLICATION OF STOP WATCH
TIME STUDY METHOD IN SAIPL: DATA ANALYSIS AND
INTERPRETATION
6.1 Introduction:
An attempt is made in this chapter -
(i) To study and understand the procedure of stop watch time study method
application.
(ii) To measure and study the labour productivity by application of stop watch
time study method.
(iii) To study and understand the social and technical barriers associated with
application of stop watch time study method on labour productivity.
Skoda auto India Private Limited (SAIPL) is selected for the study purpose.
Logistic department of the SAIPL is the study area. Unloading section, Trolley Filling
Area (TFA) and Catwalk (Supermarket) Section of the stores are the samples and the
Labours who are working in these sections are respondents of the study. Out of 43
Labours that are working in these three sections 25 Labours contributing to 57 Percent
of sample size is selected as sample labour respondents for study purpose. Here
productivity is measured in terms of output to input ratio. In the present study only
labour productivity is measured and studied whereas material, capital and energy
productivity is not studied.
Work measurement refers to the estimation of standard time that is the time
allowed for completing one piece/activity of job using the given method. This is the
time taken by average experienced labour for the job with the provision for delays
beyond the Labours control. There are several techniques used for estimation of
standard time in the industry. These include time study, work sampling, standard data
and predetermined time systems etc. In the present study, time study is used as a
technique of labour productivity measurement. This technique is based on measuring
148
the work content of the task when performed by the prescribed method, with the
allowance for fatigue and for personal and unavoidable delays. This is a technique to
estimate the time to be allowed to a qualified and well trained labour working at a
normal pace to complete specified task. The stop watch and the electronic timer are
the most widely used timing devices to perform time study. However, digital stop
watch device is used to measure time for the present study.
The measurement of the work in terms of productivity of Material, Money,
Method, Labour and ultimately overall. The present study measures the productivity
of the Labour working in selected three sections of Logistic Department and the time
study is the technique of work measurement to establish the time for qualified labour
to carry out specified task under specified conditions and at defined levels of
performance. Therefore, an attempt is made in the present study to measure and
analyse the productivity of the Labour respondents (i.e. performance of the Labour)
for maximum productivity improvement. In this scenario following questions needs to
be addressed:
1. How to measure the performance of productivity on the basis of stop watch time
study method?
2. What is the procedure of stop watch time study method?
3. How to measure Labour productivity in SAIPL.
4. Whether Labour respondents are aware about stop watch time study method?
5. Whether labour respondents have undergone any training of stop watch time
study method?
6. What time does the labour actually takes to complete the assigned task and
standard time to perform same task for 3 sections of logistic department.
7. What are the activity elements performed by 3 selected sections of SAIPL when
Stop Watch time study method was applied for measuring labour productivity?
8. What are the socio-technical barriers associated with application of stop watch
time study method?
149
6.2 Awareness of Labour Respondents on Stop Watch Time Study Method:
The manufacturing management and engineers only design and prepared the
skills but the production labours are the one who will implement it in the operation.
So the objective of time study can only be achieved if the production labours are
knowledgeable about the time study concept. There are 3 time study methods. It
consists of stop watch method, time recording machine and Motion picture camera.
Stop watch method is used by the researcher for recording time taken by a labour
respondent in completing assigned work. Before the application of stop watch time
study method, researcher felt the need to know the extent of belief of labor
respondents related to work measurement, awareness of labour respondents on stop
watch time study method and types of stop watch time study method. The sample
labour respondents were questioned and interviewed regarding above mentioned
aspects. Their responses are grouped into Yes or No and presented in various tables.
Perception of labour respondents on work measurement and their awareness on stop
watch time study method is analysed as under.
6.2.1 Perception (Belief) of Labour Respondents on work Measurement:
Before measuring the work performed by the labour it is necessary to believe
that there is need to measure the work to achieve higher productivity. In this section
whether sample labour respondents selected believed in work measurement or not is
assessed. In other words, perception of labour towards work measurement is studied
here. It is of utmost important to believe in measurement of work so as to support and
apply work measurement technique. Higher the belief towards work measurement,
higher the productivity or output or positive attitude. The response of labour
respondents towards belief (or perception of labour) is presented in Table 6.1 and
corresponding graphical representation is shown in Figure 6.1
150
Table 6.1
Believeness (Perception) of Labour Respondents on Work Measurement
Sr.No Responses Number Percent
1 Yes 22 88
2 No 3 12
Total 25 100
Figure 6.1
Believeness (Perception) of Labour Respondents on Work Measurement
X-Axis
Believeness (Perception) of Labour
Respondents on Work Measurement
Y-Axis Responses of Labour Respondents
Alternatives
A Yes
B No
Observations:
Table 6.1 and Figure 6.1 shows whether sample labour respondents of SAIPL
believe in work measurement or not. In other words to what extent labours believe in
work measurement principle is assessed. This is referred the perception of labour
towards work measurement. The survey shows that -
0
10
20
30 22 (88%)
3 (12%)
Believeness (Perception) of Labour Respondents
Res
pon
ses
of
Lab
ou
r R
esp
on
den
ts
A B
151
1. Out of 25 sample labour respondents, 22 (88 Percent) believe on work
measurement. It means majority agreed that work must be measured in a suitable
format to know the time of job completion and increase efficiency in performance
as well as for payment of wages. Since wages are interlinked with the output and
measuring output or productivity or time taken by labour to complete specific job
is a must. Hence, Table 6.1 and Figure 6.1 shows that 88 Percent of labours
believe in work measurement.
2. Table 6.1 and Figure 6.1 further highlights that 3 sample respondents (i.e. 12
percent) out of 25 do not believe in work measurement.
Findings:
Majority (88 Percent) labours respondents believe in work measurement. It
means that perception of 88 Percent of labour respondents towards work measurement
is positive and they believe it is essential to measure the work that is performed.
6.2.2 Awareness of Labour Respondents on Methods of Time Study Method:
Time study can be performed by following methods depending on the
accuracy:
1. Stop Watch Time Study Method
2. Time Recording Machine
3. Motion Picture Camera
Stop watch used to measure time during application of time study must be
accurate and preferably graduated in decimal so that it can measure time in 0.01
Minutes also. Basic equipments required for time study are (1) Time study board (2)
Time study form (3) Stop watch.
Time recording machine has a paper tape which rotates on two rollers at
uniform speed. The paper is graduated to give timing in fraction of minutes. Reading
can be seen and recorded through a slit provided in the casting of equipments.
152
Motion Picture camera is used in micro motion study. The camera is driven at
constant speed of several ranges. Due to constant speed, time taken by each film can
be calculated. Exact time can be calculated with the help of number of films taken.
This method is more accurate but expensive.
When it was asked to labour respondents regarding their awareness on stop
watch time study method, time recording machines and motion picture camera (i.e.
methods of time study) during the time of investigation, the summary of responses is
presented in table 6.2.and corresponding graphical representation is shown in Figure
6.2.
Table 6.2
Awareness of Labour Respondents on Methods of Time Study
Sr.No Methods of time
study
Yes No Total
No. Percent No Percent No Percent
1 Stop Watch Method 23 92 2 8 25 100
2
Time Recording
Machine 19 76 6 24 25 100
3
Motion Picture
Camera 21 84 4 16 25 100
Total 21 84 4 16 25 100
153
Figure 6.2
Awareness of Labour Respondents on Methods of Time Study
X-Axis Methods of Time Study
Y-Axis Responses of Labour Respondents
Alternatives
A Stopwatch Method
B Time Recording Machine
C Motion Picture Camera
Observations:
It can be seen from Table 6.2 and Figure 6.2 that -
1. Out of 25 Labour respondents, 23 (92 Percent) are aware of stop watch method
and 3 (8 Percent) are not aware.
2. Regarding time recording machine, it was found that 19 (76 Percent) of Labour
respondents are aware of this method and 6 (24 Percent) are not aware.
3. Out of 25 Labour respondents, 21 (84 Percent) are aware of Motion Picture
camera method and 4 (16 Percent) are not aware respectively.
0
5
10
15
20
2523 (92%)
19 (76%)21 (84%)
2 (8%)
6 (24%)4 (16 %)
Yes
No
Methods of Time Study
Res
pon
ses
of
Lab
ou
r R
esp
on
den
ts
B CA
154
4. Majority of labour respondents are aware of Stop Watch Method (92 Percent),
time recording Machine (76 Percent) and Motion Picture Camera (84 Percent)
respectively.
5. Overall score of methods of time study awareness is 84 Percent .It means 84
Percent on an average labour respondent are aware of time study method.
Findings:
Majority of labour respondents are aware of time study method. The extent of
stop watch time study awareness is higher (92 Percent) than that of time recording
machine (76 Percent) and Motion Picture Camera (84 Percent).
6.2.3 Awareness of Labour Respondents on Stop Watch Time Study Method:
Time study is one of the most common and widely used work measurement
techniques. It is applied and practiced since long (i.e. from F.W.Taylor till today). It is
measured in number of way. In manufacturing or any company work measurement is
a part and parcel of quality control and efficiency. Labour exercise or experiment or
actually apply the time study and authorities measures their work. Therefore labour
must be aware of the method used for work measurement. Therefore researcher has
asked the sample labour respondents about their knowledge (awareness) of the stop
watch time study method. Their responses regarding extent of awareness are
presented in Table 6.3 and Figure 6.3.
Table 6.3
Awareness of Labour Respondents on Stop Watch Time Study Method
Sr.No Responses Number Percent
1 Yes 23 92
2 No 02 08
Total 25 100
155
Figure 6.3
Awareness of Labour Respondents on Stop Watch Time Study Method
X-Axis Awareness of Labour Respondents on
Stop Watch Time Study Method
Y-Axis Responses of Labour Respondents
Alternatives
A Yes
B No
Observations:
Table 6.3 and Figure 6.3 shows that out of 25 sample respondents, 23 (92
Percent) respondents are fully aware of stop watch time study method and 2 (8
Percent) labour respondents are not aware of the stop watch time study method. This
may be because the labours are newly appointed and time study was not yet
performed involving these respondents. On enquiry it was observed that two labours
respondents recently joined the logistic department of SAIPL.
Findings:
Majority of labour respondents (i.e. 92 percent) are aware and they know stop
watch time study method.
0
10
20
3023 (92%)
2 (8%)
Awareness of Labour Respondents on Stop Watch
Time Study Method
Res
pon
ses
of
Lab
ou
r R
esp
on
den
ts
A B
156
6.3 Responses of Labour Respondents on Awareness of Training and Training
Received on Stop Watch Time Study Method:
Acquisition of skills, concepts or attitudes that result in the improved
performance on job environment is referred as training. Training is a process that
bridges the gap between standard or desired performance of an individual and his/ her
actual performance. In other words, training induces a desired change in the working
method of an employee so as to improve his/ her performance. An important point to
be noted here is that training improves the ability to perform any work whether it is
purely physical work of lifting a heavy car body or purely mental work of drawing up
pricing strategy. Moreover, no matter how good an individual may be in doing his
work there is always some room for improvement. It can therefore be concluded that
training is essential for all types and levels of employees.
At the same time, studies in the past have shown that an individual requires to
be trained not only once but regularly throughout his/her working life. It has been
observed that an individual tends to develop and start using wrong methods of doing a
job over a number of years inspite of having undergone a through training a few years
ago. At the same time advancement of technology and changing conditions bring
about changes in the methods of job performance. Every Labour needs to be kept
abreast of these developments for constant improvement of efficiency. It is therefore,
always better that every individual goes through regular training sessions. A judicious
combination of on the job and off the job training for all levels , available today
enable organizations to use training to the best of their advantage.
From this point of view it was decided to find out details of type of training to
be given to SAIPL employees. To what extent training is received by labour
respondents will help company to save time of production and to that extent labour
productivity enhanced. In addition to the immediate gains mentioned, the training in
operation analysis and work simplification developed an analytical approach on the
part of operating personal so that in future they will be continually on the alert to find
a „better way‟. They developed an application of cost of manufacture and at the
completion of course, were more cognizant of the relationship between output and
157
selling price. Hence, it is essential to know whether employees are aware of the stop
watch training, to what extent they receive stop watch time study training. The
responses of selected sample labour respondents towards on the job training or off the
job training, awareness of training, extent of received training, types of training being
given to SAIPL company labour etc are studied in this section.
6.3.1 Extent of Stop Watch Time Study training awareness among Labour
Respondents:
Training awareness of labour respondents on stop watch time study method is
presented in Table 6.4 and Figure 6.4.
Table 6.4
Awareness of Labour Respondents on Training of Stop Watch Time
Study Method
Sr.No Responses Extent of Awareness
Number Percent
1 Yes 20 80
2 No 05 20
3 Total 25 100
Figure 6.4
Awareness of Labour Respondents on Training of Stop Watch Time Study
Method
0
5
10
15
20
20 (80%)
5 (20%)
Res
pon
ses
of
Lab
ou
r
Res
pon
den
ts
A B
Awareness of Labour Respondents on Training
158
X-Axis
Awareness of Labour Respondents on
Training of Stop Watch Time Study
Method
Y-Axis Responses of Labour Respondents
Alternatives
A Yes
B No
Observations:
Table 6.4 and Figure 6.4 shows that 80 (20 respondents) Percent of labour
respondents are aware of training related to stop watch time study method. They fully
know that there is special and rigorous training of stop watch method provided by
professional bodies. On the other hand, 20 Percent (5 respondents) are not aware of
stop watch time study method.
Findings:
Majority of labour respondents are aware that there is special training
provided for application of stop watch time study.
6.3.2 Extent of Stop Watch Time Study training received by Labour
Respondents:
The lack of success of some time and motion study program is in part due to
lack of understanding of the techniques by both management and the operating
personnel. One of the easiest ways to assure the success of any practical innovation is
to inform all affected parties as to how and why it operates. When the theories,
techniques and economic necessity of work measurement are understood by all the
parties, little difficulty will be encountered in its application. From this point of view
researcher would like to know what extent labour respondents have received stop
watch time study training. Table 6.5 summarises survey result in this regard and
equivalent graphical representation is shown in Figure 6.5.
159
Table 6.5
Extent of Training Received by Labour Respondents on Stop Watch Time Study
Method
Sr.No Responses Extent of Training received
Number Percent
1 Yes 25 100
2 No 0 0
Total 25 100
Figure 6.5
Extent of Training Received by Labour Respondents on Stop Watch Time Study
Method
X-Axis Extent of Training Received by Labour
Respondents on Stop Watch Time
Study Method
Y-Axis Responses of Labour Respondents
Alternatives
A Yes
B No
0
5
10
15
20
25
25 (100%)
0
Extent of Training Received by
Labour Respondents
Res
pon
ses
of
Lab
ou
r
Res
pon
den
ts
A B
160
Observations:
It can be seen from Table 6.5 and Figure 6.5 that 100 Percent (25 Labour
respondents) had received training. It may be by the way of job instruction,
demonstration and job rotation.
Findings:
All the labour respondents, those are working in unloading, Trolley Filing and
catwalk section of logistic department have received stop watch time study method
training.
The next question is then that which types of training is received by labour
respondents whether on the Job training or off the job training. This is assessed in the
next section.
6.3.3 Type of Training Received by Labour Respondents:
Training in the areas of performance rating, application of allowances,
standard data methods, stop watch method application and its operation method and
job evaluation are especially important. The companies that have provided training in
the elements of time study for union officials, job operators, as well as management
representatives had harmonious relationships in the field of productivity, quality
product and wage payment. Training can be provided on the basis of on the job
training method and off the job method. It was asked to labour respondents of all the
selected sections what type of training they have received for stop watch time study
method. 100 Percent of labour respondents in section A, B and C agreed that they
have received on the job training and out of 25 selected sample respondents 3 labours
have received off the job training. This is presented in Table 6.6 and Figure 6.6.
161
Table 6.6
Type of Training Received by Labour Respondents
Sr.No Responses
Training
Received
On the Job
Training
Off the Job
training
No. Percent No. Percent No. Percent
1 Yes 25 100 25 100 3 12
2 No 0 0 0 0 22 88
3 Total 25 100 25 100 25 100
Figure 6.6
Type of Training Received by Labour Respondents
X-Axis Type of Training Received by Labour
Respondents
Y-Axis Responses of Labour Respondents
Alternatives
A On the Job Training
B Off the Job Training
Observations:
On the basis of Table 6.6 and Figure 6.6 it can be seen that,
0
5
10
15
20
2525 (100%)
3 (12%)0
22 (88%)
Yes
No
Type of Training Received
Res
pon
ses
of
Lab
ou
r R
esp
on
den
ts
A B
162
Out of 25 labours, who are working in section A, B and C of logistic
department, 100 Percent (25 respondents) have received stop watch time study
method training. All the 25 respondents i.e. 100 Percent of labours have received on
the job training may be by the way of job instruction, lectures, demonstration or Job
rotation. Among 25 labour respondents, 3 have received off the job training. These 3
labours are senior and experienced. They are working in the company from last 10
years or so. Majority of the respondents have not received off the job training.
Findings:
From Table 6.4 to Table 6.6 and observations made by the researchers, it can
be concluded that:
1. Majority (i.e. 80 Percent) of respondents are aware of stop watch time study
method training.
2. 100 Percent of respondents have received training on Stop Watch Time Study
Method.
3. 100 Percent of sample respondent have received on the job training of stop watch
time study method.
4. Majority (i.e. 88 Percent) of the respondent have not received off the job training
for stop watch time study method.
5. Some of the respondents found that the trainers lack in depth knowledge of Stop
Watch time study method application procedure.
6. All the respondents wanted to be more demonstrative and practical oriented on the
job training programme.
7. All the respondents wanted off the job training programme to be provided as early
as possible.
8. Majority of the respondents (i.e. 65 Percent) felt that training sessions are a good
break from the daily routine giving them the opportunity to meet, discuss and
exchange or share views with their counterparts at other places.
163
9. Overall, training is found useful and necessary by the trainees. The company
should pay more attention on the contents of the time study training courses,
making labours more practical oriented.
10. No monetary or non monetary incentives are directly linked with the training.
6.4 Procedure of Stop Watch Time Study Method adopted in the Present Study:
This section discuss about measuring Labour productivity, General definition
of Time Study and Procedure adopted by the researcher to apply stop watch time
study method in all the selected three sections of Logistic Department.
6.4.1 Defining and Measuring Labour Productivity:
A crucial determinant of competitiveness is the productivity of key inputs.
Increasing labour productivity is not only key to improve a firm‟s competitiveness,
but widely acknowledged as the key to improve national economic well-being.
Increase in labour productivity allows payments to the labours (i.e. wage increase).
Manufacturing costs can be lowered by increasing the productivity of the company
and its workforce. This puts the burden on management to improve practices rather
than on labour to accept deep concessions. It also positions labour and management as
allies because strategies to improve productivity translate into higher skills and
ultimately higher wages for labour1.
Hence, MOST technique is used.
Simply, productivity is the ratio of output and inputs. Within SAIPL,
production managers and engineers measure the number of products produced by a
line of catwalk store labour in a specific time frame. Time study, also called work
study analysis measures the number of minutes required to produce or complete a
particular activity and compare that time to standard time.
Another productivity measure is labour efficiency, which is a comparison of
time spend working productivity to the total times spend at work.
164
Thus, the labour productivity can be measured in terms of hours or money as
under:
(a) In terms of input and output unit:
LP = O / I -------------------- (1)
Where,
LP = Labour Productivity
O = Total Output
I = Labour Input
(b) In terms of Hours:
LP = TQP/ AMHR --------------------- (2)
Where,
LP = Labour Productivity
TQP = Total quality produced
AMHR = Actual man Hours required to produce that quantity
(c) In terms of Money:
LP = TC / ASOW ---------------------- (3)
Where,
LP = Labour Productivity
TC = Total cost of output produced
ASOW = Amount spend on Labours
(d) Average Observed Time (OT):
∑ X / N ------------------------- (4)
165
Where,
∑ X = Sum total of Observed time
N = Number of Observations
(e) Normal Time (NT):
NT = OT * R ------------------------- (5)
Where,
NT = Normal Time
OT = Observed Time
R = Performance Rating
(f) Standard Time (ST):
ST = NT * A -------------------------- (6)
Where,
ST = Standard Time
NT = Normal Time
A = Allowance
6.4.2 Definition of Time Study:
Time study is a technique to estimate the time that is allowed to a qualified
and well trained Labour working at normal pace to complete a specified task.
6.4.3 Basic Equipments used in Measuring Time Study:
Time study is the most common and the widely used in the industry for work
measurement. Therefore, researcher is interested to know the result of application of
time study in SAIPL. For measuring the work using time study, the researcher has
used following equipment:
166
(A) Timing Device: Digital Stop Watch
(B) A Study Board: Time study Observation board
(C) Observation format: Time study observation sheet
(D) Other necessary equipments
(A) Timing Device (Digital Stop Watch):
Digital stop watch is used by the researcher to measure the time of activity
elements performed by labour respondents. Digital stop watch is used as it is
easily available, portable and can measure time to the second or third decimal of
a second accurately. It can keep a large volume of data in memory and is user
friendly. Figure7.7 shows digital stop watch used by the researcher for study
purpose.
Figure 6.7
Digital Stop Watch
(B) A Study Board (Time Study Observation Board):
Time study observation board was used by the researcher to hold observation
sheet and digital stop watch. It is light weight board made of wood. It is used to
hold the time study observation sheet and digital stopwatch. The watch is mounted
on the top left hand side corner for easy operation. The board had a clamp to hold
the observation sheet. During the time study, the board was held against the body
167
and the upper left arm by the researcher so as to operate the watch easily by using
either thumb or index finger of left hand. Figure 6.8 shows observation board used
for time study purpose by the researcher.
Figure 6.8
Time Study Observation Board
(C) Observation Format (Time study Observation Sheet):
Observation sheet used for the time study purpose was prepared by the researcher
using MS-Excel and hard copy of observation sheet was used to record the time
of activity elements of labour. Observation sheet consist of necessary information
about the operation being studied. It includes- Labour name, operation name,
department, section, time study person name, study number, sheet number, space
to record the time of activity elements, date and place of the study etc. Figure 6.9
shows the observation sheet used by the researcher for study purpose.
168
Figure: 6.9
Time Study Observation Sheet
Time Study Observation Sheet Name of
Labour
Study
Number
Department
Sheet
Number
Section Studied By
Activity Name
Sr.No
Activity
elements 1 2 3 4 5 6 7 8 9 10
1
2
3
4
5
6
7
8
9
10
Total Time
Average
Time
Date
Place
Checked by
(D) Other Necessary Equipments:
Other necessary equipments used to perform study were Pen, Pencil, Eraser and
Scientific Calculator.
6.4.4 Selection of Sections and Activity/ elements covered in the Study:
For experiment purpose, three sections namely Unloading, Trolley filling Area
and Catwalk section of logistic department are selected. In the unloading section total
21 labours are employed to perform different activities. For study purpose, 15 sample
labour are selected performing 9 different activities as respondents contributing to 71
169
Percent of sample size. Time study is performed on 15 labour respondents performing
the activity in unloading section of logistic department. Chart 6.1 shows the activities
covered in the present research study. Time taken by the labour to complete the job
allotted is calculated by using stop watch time study method.
Chart 6.1
Activities Covered in the Unloading Section for Research
Sr.No Activity name Labour
Respondents
1 Opening & Closing of Container Gate at
Dock Area 1
2 Unloading car body pallet from container
using forklift 1
3 Unloading of car body parts from the
pallet 7
4 Alignment of Trolley to Unloading Area 1
5 Cleaning of Car Body Shell 1
6 Verification of Packaging List 1
7 System operator to enter Container
Information in System 1
8 Carry Car body shell SUZ Pallet to
Assembly Line 1
9 To stick Packing list on Car Body shell
& Pantograph Alignment 1
Total 15
While 9 activities are undertaken by the labour respondents in unloading
section whereas only 2 activities are performed in Trolley Filling Area of stores ,
called here as Section B. These activities are: Filling the trolley and carrying trolley to
Trolley Filling Area. Time taken to complete these two activities is calculated on the
basis of stop watch time study method. There are total of 17 labour working in TFA,
170
but for study purpose 5 labours contributing to 29 % are selected as sample labour
respondents. Chart 6.2 represents the activity carried out and covered in TFA section
with selected sample labour respondents for study purpose.
Chart 6.2
Activities Covered in the Trolley Filling Area for Research
Sr.No Activities Labour
Respondents
1 Filling the Trolley 5
Total 5
In the catwalk section total of 5 labours are working. All the 5 labours
contributing to 100 Percent are selected as sample respondents for study purpose.
Following activities are performed in catwalk sections and are included in study as
shown in Chart 6.3.
Chart 6.3
Activities Covered in the Catwalk Section for Research
Sr.No Activities Labour
Respondents
1 Bin Filling Activity 3
2 Box Picking Activity 2
Total 5
Time taken by each of the 5 labour in catwalk section is calculated on the
basis of stop watch method. Workflow presented in the Figure. 6.10 undertaken by
catwalk labour respondents helps to understand the time direction.
171
Figure 6.10
Work flow in one direction: Catwalk Section
Labour Labour Labour Labour
Labour
6.4.5 Steps/ Procedure employed for Measuring Stop Watch Time Study method:
Time study technique is based on measuring the work content of the task when
performed by the prescribed method, with addition of allowances. The basic
procedure for Stop Watch Time Study Method is shown in Figure 6.11 step- wise
which is quite simple and easy to understand.
Figure: 6.11
Basic Procedure of Stop Watch Time Study Method
.
Work In
Activity
Flow
1 Activity Activit
y
Activity Activity Activity
2 3 4 5
Standardize the Method of Working
Select the operator for study Record details of task and conditions of Work
Break the task into element Measure the duration of each element and
access performance rating
Establish representative time of elements Extend observed time into basic time
Calculate allowances
Selection of task to be timed
Determine the Standard time
172
The above procedure is normally adopted to conduct time study. Since our
objective is to measure and analyse the labour productivity in terms of time taken by
the labour to perform activity for specified assigned job. Researcher has used above
steps for study purpose. Chart 6.4 explains the steps followed and the corresponding
procedure performed to conduct time study for research purpose.
Chart 6.4
Time Study Procedure adopted for Study Purpose
Sr.No Basic Time study
Steps Time study procedure used for study purpose
1 Selection of Job 3 sections in Logistic department of SAIPL- Unloading ,
Trolley Filling Area, Catwalk section
2 Standardize the Method
of Working
confirmed whether on the job or off the job training is
provided to labourers to perform the assigned activity
efficiently
3 Select the operator for
study
Total 25 Labours-
15 from Unloading section ,
5 from Trolley Filling Area,
5 from Catwalk section
4 Record of details
Recorded details in observation sheet such as -
Name of labour , operation performed, department, section of
work activity, general information about activity performed,
awareness about time study, training provided, variations in
work activity, social and technical barrier faced.
5 Break the task into
element
Activities selected from each section are divided into small
elements to get accurate results
6 Determine number of
cycles to be measured
It was determined to measure 10 number of cycles for each
activity of all the selected 3 sections. (As per ILO Standard2)
7
Measure the time of
each element using stop
watch Time taken by each Labour to perform activity was recorded
using stop watch for all the selected 3 sections
8 Determine standard
rating for each Labour
Synthetic rating3 method is used to determine standard rating
for each Labour as it gives consistent results
9 Calculate Normal time
for activity
For each element of activity Normal time was calculated by
using:
Normal Time = Observed time * Rating
10 Determine allowances Since no one can work continuously , 20 Percent allowance
was added to the normal time as per SAIPL policy book
11 Determine Standard
time
Standard time was determined for each activity of all the
selected sections using:
Standard Time = Normal Time + Allowances
173
6.5 Analysis of Labour Productivity in Unloading Section of Logistic
department based on application of Stop Watch Time Study Method:
The Unloading section represents the first step of the logistics chain of
supply of the material to the warehouse and subsequently to the assembly line.
Containers which come from the Mumbai port dock at the unloading station. There
are two unloading dock, one is for unloading the body and other one for unloading the
material in box. Generally 20-22 containers are been unloaded in a shift. The
containers are been unloaded with the help of fork-lift. At Present 21 labours are
working in this section. Out of 21 labours, 15 labours (i.e. 71 Percent) are selected by
the researcher as sample respondents for study purpose. There are various activities
that are carried out in this section. Chart 6.5 shows the list of activities that were
studied by the researcher for application of time study.
Chart 6.5
Activity performed by Labour Respondents to complete Unloading Activities
Sr.No Activity name Labour No.
1 Opening & Closing of Container Gate at Dock Area 1
2 Unloading car body pallet from container using forklift 2
3 Unloading of car body parts from the pallet 3,4,5,7,9,12,15
4 Alignment of Trolley to Unloading Area 6
5 Cleaning of Car Body Shell 11
6 Verification of Packaging List 13
7 System operator to enter Container Information in System 14
8 Carry Car body shell SUZ Pallet to Assembly Line 10
9 To stick Packing list on Car Body shell & Pantograph
Alignment 8
Total 15
On the basis of activity elements or movements mentioned in chart 6.5,
collected data is interpreted and analysed as under:
1. Maximum and Minimum time taken by Labour to perform Activities in
Unloading section.
2. Standard time required for Labour to Complete Activities in Unloading section.
174
6.5.1 Maximum and Minimum time taken by Labour Respondents to perform
activities in Unloading Section:
The survey result of time taken by labour in Unloading section is analysed in
this section. The Maximum time and Minimum time taken by selected 15 labours to
complete the assigned job is analysed and interpreted by the researcher. The
maximum time is the highest time taken by individual labour to complete the job
among all the 10 cycles of observation reading. Minimum time is the lowest time
taken by labour in completion of job from all the 10 cycles of observation reading.
Table 6.7 shows the maximum time and minimum time taken by selected 15 labour
respondents to complete the activities in unloading section. Figure 6.12 shows the
graphical representation of Maximum and Minimum time taken by Labour
respondents to complete the unloading activities.
Table 6.7
Maximum and Minimum time taken by labour to
perform Activities in Unloading Section
Labour
No.
Maximum time
(Min)
Minimum time
(Min)
1 4.57 3.47
2 10.53 6.52
3 1.38 0.98
4 3.9 2.55
5 7.4 4.8
6 3.55 2.37
7 4.65 3.33
8 4.2 3.13
9 5.27 3.92
10 4.73 3.37
11 5.27 3.85
12 3.48 2.73
13 5.7 4.22
14 3.47 3.30
15 4.27 3.10
Average 4.82 3.44
175
Figure 6.12
Maximum and Minimum time taken by Labour to perform Activities in Unloading
Section
X-Axis Labour Respondents in Unloading Section
Y-Axis Time taken by Labour Respondents in
Minutes
Alternatives
A-O Labour 1 to Labour 15
Observations:
It can seen from Table 6.7 and Figure 6.12 that
1. Maximum time taken by Labour 1 to complete the activity of receiving, opening
and closing of container gate for unloading at dock area is 4.57 Minutes and
Minimum taken is 3.47 Minutes.
2. Labour 2 took maximum time of 10.53 Minutes to complete the activity of
unloading car body shell pallet from a container and minimum time of 6.52
Minutes to perform the activity of unloading.
0
2
4
6
8
10
12
4.57
10.53
1.38
3.9
7.4
3.55
4.654.2
5.274.73
5.27
3.48
5.7
3.474.27
3.47
6.52
0.98
2.55
4.8
2.373.33 3.13
3.923.37
3.85
2.73
4.22
3.3 3.1
Maximum time (in Minutes)
Minimum time (in Minutes)
Labour Respondents in Unloading
Section
A B C D E F G H I J K L M N O
Tim
e t
ak
en b
yL
ab
ou
r
Res
pon
den
ts i
n M
inu
tes
176
3. Maximum time taken by labour 3 to unload car body parts- Transaxle and Cockpit
from pallet is 1.38 Minutes and minimum time taken is 0.98 Minutes to perform
unloading activity.
4. Labour 4 took maximum time of 3.9 Minutes and minimum of 2.55 Minutes to
unload car body parts – Power steering, Gearshift, Wooden Strip, Fuel tank and
Pantograph alignment from the car body shell pallet.
5. Maximum time taken by Labour 5 to unload car body parts- Material box and
tyres from pallet is 7.4 Minutes and minimum time taken is 4.8 Minutes to
perform unloading activity.
6. Time taken by Labour 6 to perform the activity, alignment of trolley in Unloading
area is 3.55 Minutes and Minimum time taken is 2.37 Minutes.
7. Labour 7 took maximum time of 4.65 Minutes and minimum time of 3.33 Minutes
to unload car body parts - Axle, Gear Box and JIT Parts from the pallet.
8. Maximum time taken by labour 8 to stick the packing List on unloaded car body
shell pallet and alignment of pantograph to place car body shell on SUZ pallet is
4.2 Minutes and Minimum time taken is 3.13 Minutes.
9. Maximum and minimum time taken by labour 9 was to the extent of 5.27 Minutes
and 3.92 Minutes to unload car body parts - Material boxes and alignment of
trolley to unloading area.
10. Labour 10 took maximum time of 4.73 Minutes to carry car body shell SUZ Pallet
to assembly line and minimum time of 3.37 Minutes to perform the activity.
11. Maximum time taken by labour 11 to perform the activity of cleaning the car body
shell unloaded is 5.27 Minutes and minimum time is 3.85 Minutes to perform the
activity.
12. Maximum and minimum time taken by labour 12 was to the extent of 3.48
Minutes and 2.73 minutes to perform the activity of unloading of car body parts-
Bumper unloading.
177
13. Labour 13 took maximum time of 5.7 Minutes to verify the packaging received in
car body shell according to list received. Minimum time taken by labour 13 is 4.22
Minutes to perform the activity of verification.
14. Maximum and minimum time taken by labour 14 was to the extent of 3.47
Minutes and 3.30 Minutes to perform activity of entering information related the
container. Labour 14 is also called as system operator here.
15. Maximum time taken by labour 15 to unload car body part –Bumper and material
unloading is 4.2 Minutes and Minimum time taken is 3.13 Minutes.
Findings:
Thus, it can be inferred from Table 6.7 and Figure 6.12 that all the selected 15
labour respondents in unloading section are performing different activities to unload
the car body pallet.
6.5.2 Standard Time taken by Labour Respondents to complete the activities in
Unloading Section:
Standard time is the time allowed to an operator to carry out a specified task
under specified condition and at defined level of performance. Average observed time
is the average of time calculated for 10 number of cycle readings for each labour
respondent as observed by the researcher while application of stop watch time study.
As discussed in introduction section, synthetic rating method is used to calculate the
rating for each labour respondent. Normal time is the time which is derived by taking
the product of average observed time and rating factor. Since no Labour can work
continuously, 20 Percent allowances are added to the average observed time so as to
derive standard time. Standard time is the summation of normal time and 20 percent
allowance derived for each labour. Table 6.8 and Figure 6.13 gives measured values
of observed average time, normal time and standard time as well as allowances for all
the selected 15 labours respondents in unloading section.
178
Table 6.8
Standard Time Taken by Labour Respondents to
Complete the Activities in Unloading Section
Labour
No.
Observed
Time Rating
Normal
Time Allowances Standard Time
1 3.95 0.43 2.17 0.79 2.96
2 8.45 0.64 4.64 1.69 6.33
3 1.17 0.59 0.64 0.23 0.88
4 3.20 0.88 1.75 0.64 2.39
5 6.12 0.74 3.36 1.22 4.58
6 2.90 0.37 1.59 0.58 2.17
7 4.00 0.52 2.20 0.80 3.00
8 3.64 0.35 2.00 0.73 2.73
9 4.61 0.71 2.53 0.92 3.45
10 3.95 0.49 2.16 0.79 2.95
11 4.51 0.46 2.47 0.90 3.37
12 3.15 0.37 1.73 0.63 2.36
13 4.88 0.45 2.68 0.98 3.66
14 3.95 0.53 2.17 0.79 2.96
15 3.66 0.69 2.01 0.73 2.74
(Average) -
0.55
179
Figure 6.13
Standard Time Taken by Labour Respondents to
Complete the Activities in Unloading Section
X-Axis Labour Respondents in Unloading Section
Y-Axis
Time taken by Labour Respondents in
Minutes
Alternatives
A-O Labour 1 to Labour 15
Observations:
It can be stated from Table 6.8 and Figure 6.13 that,
i) For labour 1 average observed time is 3.95 Minutes to complete his assigned job
of receiving, opening and closing of container gate for unloading. With the
calculated rating of 55 Percent, Normal time achieved for labour 1 is 2.17
Minutes. With the addition of 20 Percent allowances, the standard time for
labour 1 to complete the activity is 2.96 Minutes. Thus it can be inferred that
standard time required to complete the assigned activity for labour 1 is 2.96
0
1
2
3
4
5
6
7
8
9
3.95
8.45
1.17
3.2
6.12
2.9
43.64
4.61
3.954.51
3.15
4.88
3.953.66
2.96
6.33
0.88
2.39
4.58
2.17
32.73
3.452.95
3.37
2.36
3.66
2.96 2.74
Observed Time
Standard Time
B C D E F G H I J K L M N O
Labour Respondents in Unloading
Section
Tim
e t
ak
en b
yL
ab
ou
r
Res
pon
den
ts i
n M
inu
tes
180
Minutes which is less as compared to the average observed time labour1 took to
complete his activity.
ii) Average observed time taken by labour 2 is 8.45 Minutes to the complete
activity of unloading the car body pallets from the container. At 55 Percent of
performance rating, Normal time taken by labour 2 is 4.64 minutes. With the
addition of 20 Percent allowances, the Standard time for labour 2 achieved is
6.33 Minutes which is less as compared to the observed average time.
iii) Labour 3 performs the activity of unloading of car body parts from the pallet
specifically-transaxle and cockpit. Average observed time taken by labour 3 to
perform the activity is 1.17 Minutes. With rating of 55 Percent, Normal Time
achieved is 0.64 Minutes. 20 Percent allowances resulted in Standard time of
0.88 Minutes to perform the activity by Labour 3. Thus it can be said that
standard time to perform the activity is less as compared to the observed average
time taken by labour 3 to perform the unloading activity.
iv) Average observed time taken by labour 4 is 3.20 Minutes to complete the
activity of unloading the car body pallets from the container specifically- Power
Steering, Gearshift, Wooden Strip, Fuel Tank and Pantograph Alignment. At 55
Percent of performance rating, Normal time taken by labour 2 is 1.75 minutes.
With the addition of 20 Percent allowances, the Standard time for labour 4
achieved is 2.39 Minutes which is less as compared to the observed average
time taken by labour 4 to complete the activity.
v) Average observed time taken by Labour 5 is 6.12 Minutes to perform the
activity of unloading the car body pallets from the container specifically-
Material Boxes and Tyres. Normal time calculated for labour 5 is 3.36 Minutes
with 55 Percent of rating. With the addition of 20 Percent allowances, the
standard time achieved for Labour 5 is 4.58 Minutes respectively. This means
that standard time to perform the activity of Labour 5 is less as compared to the
average time taken by Labour 5 to complete the activity.
vi) Labour 6 takes average observed time of 2.90 Minutes to complete the activity
of alignment of trolley to unloading area. With 55 Percent of rating, Normal
181
time achieved was 1.59 Minutes. With additional 20 percent allowances,
standard time required to perform the activity is 2.17 Minutes. This shows that
labour 6 takes more time to perform the activity as compared to the standard
time achieved.
vii) Average observed time taken by Labour 7 to perform the unloading of car body
parts from pallet specifically - Axle, Gear Box and JIT Parts is 4 Minutes. With
55 Percent rating, Normal time achieved is 2.20 Minutes. Standard time
achieved with addition of 20 Percent of allowances is 3 Minutes respectively.
This means that average observed time is more as compared to the standard time
required to perform the activity.
viii) Labour 8 takes average observed time of 3.64 Minutes to complete the activity
of sticking the packaging list to the unloaded car body shell and alignment of
pantograph to place car body shell on the SUZ pallet. With 55 Percent rating,
Normal time achieved is 2 Minutes. Standard time achieved with addition of 20
Percent of allowances is 2.73 Minutes respectively. This means that average
observed time is more as compared to the standard time required to perform the
activity. Labour 8 took more time as required to perform the activity.
ix) Average time taken by Labour 9 to perform the activity of unloading of car body
parts from the pallet specifically - Material box and trolley alignment is 4.61
Minutes. With 55 Percent rating, Normal time achieved is 2.53 Minutes.
Standard time achieved with addition of 20 Percent of allowances is 3.45
Minutes respectively. This means that average observed time is more as
compared to the standard time required to perform the activity and labour 8 took
more time as required to perform the activity.
x) Labour 10 takes the average observed time of 3.95 Minutes to complete the
activity to carry the car body shell SUZ Pallet to Assembly Line. Normal time
achieved with 55 percent of rating is 2.16 Minutes. With addition of 20 Percent
allowances, standard time required to perform the activity for Labour 10 is 2.95
Minutes respectively. This means that labour 10 takes more amount of time to
perform the activity as compared to the standard time.
182
xi) Average time taken by labour 11 to perform the activity of cleaning the car body
shell is 4.51 Minutes. Normal time achieved is 2.47 Minutes with rating of 55
Percent. With addition of 20 Percent allowances, Standard time required to
perform the activity for Labour 11 is 2.95 Minutes respectively. This means that
standard time required to perform the activity for Labour 11 is less as compared
to the actual observed time taken by the labour.
xii) Average observed time taken by labour 12 to complete the activity of unloading
bumper from the car body shell is 3.15 Minutes. For of 55 Percent rating,
Normal time achieved is 1.73 Minutes. With 20 Percent allowances, standard
time required to perform the activity is 2.36 Minutes respectively. Thus, it can
be said that, labour 12 takes more time as compared to the standard time
required to perform the activity.
xiii) Average observed time taken by labour 13 to complete the verification of
packaging list is 4.88 Minutes. For of 55 Percent rating, Normal time achieved
is 2.68 Minutes. With 20 Percent allowances, standard time required to perform
the activity is 3.66 Minutes respectively. Thus, it can be said that, labour 13
takes more time as compared to the standard time required to perform the
activity.
xiv) Labour 14 takes average observed time of 3.95 Minutes to complete the activity
as system operator i.e to enter the required information related to the container
unloaded. For of 55 Percent rating, Normal time achieved is 2.17 Minutes. With
20 Percent allowances, standard time required to perform the activity is 2.96
Minutes respectively. Thus, it can be said that, labour 13 takes more time as
compared to the standard time required to perform the activity.
xv) Average observed time taken by labour 15 to complete the activity of unloading
the car body pallet specifically - Bumper, Material unloading and scrap disposal
activity is 3.66 Minutes. For of 55 Percent rating, Normal time achieved is 2.01
Minutes. With 20 Percent allowances, standard time required to perform the
activity is 2.74 Minutes respectively. Thus, it can be said that, labour 15 takes
more time as compared to the standard time required to perform the activity.
183
6.6 Analysis of Labour Productivity in Trolley Filling Area (TFA) Section of
Logistic department based on application of Stop Watch Time Study
Method:
Trolley Filling Area is also called as Supermarket in Logistic section of
SAIPL. Supermarket concept is very useful and sophisticated method for storing and
issuing the material to assembly line. According to the production plan of next day,
material required for the production is stored in the super market area. Generally most
frequent and high value parts are stored in super market area. Filled trolley from
trolley filling area in supermarket is moved to trolley storing area. Trolley picking
person collects filled trolley from trolley filled area to assembly line as per the
requirement of tact. Empty trolley from assembly line is brought by trolley picking
person and kept in trolley filling area to fill the trolley. At present 17 Labours are
working in Trolley Filling Area. Out of 17 Labours, 5 labours (i.e.29 Percent) are
selected as sample based on random method. All the labour performs same activity of
filling the trolley with required material. Each labour respondent performs 11 activity
elements or movements to complete the assigned job of trolley filling. In other words,
trolley filling activity is divided into 11 sub-movements. Therefore, labour
productivity or time taken by all the 5 labours are measured separately as their activity
is divided into similar elements. Since each labour performs activity in different
nature, the work is measured and analysed accordingly. Observations, questionnaire,
personal interviews, discussions were used to collect primary data. To get accurate
results of time study, each labour respondent was observed and 10 cycle readings
were taken by the researcher for study purpose. Chart 6.6 shows 11 activity elements
observed by the researcher to complete trolley filling activity. Activity elements or a
movement shown in Chart 6.6 are considered for the study purpose. Time taken by
each of the 5 labour was observed and average of 10 number of cycles was considered
to arrive at accurate time study results. Time taken by each of 5 labour respondents is
referred to as labour productivity here. Thus, it can be said that there is work
measurement of labour in terms of time.
On the basis of activity elements or movements mentioned in chart 6.6,
collected data is interpreted and analysed as under:
184
1. Maximum and Minimum time taken by Labour respondents to perform
Trolley Filling Activity
2. Standard time required by Labour respondents to complete Trolley Filling
Activity
Chart 6.6
Activity Elements performed by Labour Respondents
to complete Trolley Filling Activity
Sr.No Activity Elements
1 Walks towards trolley area
2 Carries empty trolley to supermarket
3 Opens material box
4 Picks material
5 Places material in trolley
6 Repeats step 4 & 5 till one side of trolley is filled
7 Turns the trolley to fill second side
8 Picks material
9 Places material in trolley
10 Repeats step 8 & 9 till II side of trolley is filled
11 Carries filled trolley to TFA
6.6.1 Maximum and Minimum time taken by Labour Respondents to perform
activities in TFA Section:
The survey result of time taken by labour respondents in TFA is analysed in this
section. The maximum time and Minimum time taken by all the 5 labour respondents
in TFA section to complete the assigned job is analysed and interpreted by the
researcher. The maximum time is the highest time taken by each labour respondents
to complete the job among all the 10 cycles of observation reading. Minimum time is
the lowest time taken by labour respondents in completion of job from all the 10
185
cycles of observation reading. Table 6.9 and Figure 6.14 shows the maximum time
and minimum time taken by all the 5 labour respondents to complete the trolley filling
activity.
Table 6.9
Maximum and Minimum Time taken by Labour Respondents to
Complete Trolley Filling Activity
Labour
No.
Maximum time
(Minutes)
Minimum time
(Minutes)
1 12.55 5.9
2 17.8 5.2
3 19.85 5.17
4 17.48 6.42
5 15.47 7.07
Average 16.6 5.95
Figure 6.14
Maximum and Minimum Time taken by Labour Respondents to
Complete Trolley Filling Activity
0
5
10
15
20
12.55
17.819.85
17.4815.47
5.9 5.25.17
6.427.07
Maximum
time
(Minutes)
Minimum
time
(Minutes)
Labour Respondents in TFA Section
Tim
e t
ak
en b
yL
ab
ou
r
Res
pon
den
ts i
n M
inu
tes
B C D E
186
X-Axis Labour Respondents in TFA Section
Y-Axis Time taken by Labour Respondents in
Minutes
Alternatives
A-E Labour 1 to Labour 5
Observations:
It can be revealed from Table 6.9 and Figure 6.14 that
1. Labour 1 took maximum time of 12.55 minutes and minimum of 5.9 Minutes
to complete the trolley filling activity.
2. Labour 2 took maximum time of 17.8 Minutes and minimum time of 5.2
Minutes to complete the activity.
3. Maximum time taken by labour 3 to complete the activity is 19.85 Minutes and
minimum time taken to perform the activity is 5.17 Minutes.
4. Maximum time taken by labour 4 was to the extent of 17.48 Minutes and
minimum time taken to complete the activity was to the extent of 6.42 Minutes
5. Labour 5 took 15.47 Minutes of maximum time and 7.07 Minutes of minimum
time to complete the trolley filling activity.
6. It can be said that maximum time required to perform trolley filling activity is
16.6 Minutes and minimum time required to complete the activity is 5.95
Minutes.
7. Labour 1 took maximum less time i.e. 12.55 Minutes to complete the activity
as compared to other maximum time of labours performing the same activity.
8. Labour 2 took minimum less time i.e.5.2 Minutes to complete the activity as
compared to other labours performing same activity.
187
Findings:
Maximum time taken by labour 1,2,3,4, and 5 is 12.55, 17.8, 19.85, 17.48 and
15.47 Minutes respectively, whereas, minimum time taken by labour to perform same
activity was to the extent of 5.9, 5.2, 5.17, 6.42 and 7.07 Minutes respectively.
Labour 1 took maximum 12.55 Minutes and minimum of 5.9 Minutes to complete the
activity as compared to other labours which shows that labour 1 performs with higher
productivity than other labours.
6.6.2 Standard Time taken by Labour Respondents to complete the activities in
TFA Section:
Table 6.10 gives measured values of observed average time, normal time and
standard time as well as allowances for all the selected 5 labours in TFA section.
Table 6.10
Standard Time Taken by Labour Respondents to Complete Trolley Filling
Activity
Labour
No.
Average Observed
Time (Min)
Normal Time
(Min)
Allowances
(Min)
Standard Time
(Min)
1 9.47 8.36 1.89 10.26
2 9.89 8.73 1.98 10.71
3 9.84 8.69 1.97 10.66
4 11.36 10.03 2.27 12.30
5 10.63 9.38 2.13 11.50
188
Figure 6.15
Standard Time Taken by Labour Respondents to Complete Trolley Filling
Activity
X-Axis Labour Respondents in TFA Section
Y-Axis
Time taken by Labour Respondents in
Minutes
Alternatives
A-E Labour 1 to Labour 5
Observations:
It can be seen from table 6.10 and Figure 6.15 that
i. For labour 1 average observed time is 9.47 Minutes to complete his assigned
job. With the rating of 88 Percent, Normal time achieved for labour 1 is 8.36
Minutes. With the addition of 20 Percent allowances, the standard time for
labour 1 to complete trolley filling activity is 10.26 Minutes. Thus it can be
inferred that standard time required to complete assigned activity for labour 1
is 10.26 Minutes which is more as compared to the average time labour1 took
to complete his activity.
0
2
4
6
8
10
12
14
9.47 9.89 9.84
11.36 10.6310.26 10.71 10.6612.3 11.5
Average
Observed
Time (in
Minutes)
Standard
Time (in
Minutes)
Labour Respondents in TFA Section
Tim
e t
ak
en b
yL
ab
ou
r
Res
pon
den
ts i
n M
inu
tes
B C D EA
189
ii. Average observed time taken by Labour 2 to complete his activity is 9.89
Minutes. At the rating of 88 percent, Normal time for labour 2 is 8.73 Minutes.
With addition of 20 Percent allowances standard time derived for labour 2 is
10.71 Minutes.
iii. Labour 3 takes average of 9.84 Minutes to complete the trolley filling activity.
With 88 percent of rating, normal time for Labour 3 is 9.84 Minutes. 20
Percent allowance addition results in 10.66 Minutes of standard time required
for labour 3 to complete his activity.
iv. Average time taken by labour 4 to complete the activity is to the extent of
11.36 Minutes. With 88 percent of rating, Normal time for Labour 4 is 10.03
Minutes. When 20 Percent allowance is added, standard time for labour 4 to
complete the trolley filling activity is 12.30 Minutes.
v. Labour 5 takes average of 10.63 Minutes to complete the trolley filling
activity. With 88 percent of rating, normal time for Labour 5 is 9.38 Minutes.
20 Percent allowance addition results in 11.50 Minutes of standard time
required for labour 5 to complete his activity.
Findings:
It can be stated that standard time for Labour 4 is highest (i.e.12.30 Min) and for
Labour 1 is lowest (i.e. 10.26 Minutes) as compared to other Labours performing
same activity of trolley filling. Thus, it can be said that the productivity for Labour 1
is high and productivity for labour 4 is lowest as compared to other labours.
6.7 Analysis of Labour Productivity in Catwalk Section of Logistic department
based on application of Stop Watch Time Study Method:
Catwalk section is one of the important sections of logistic department. It is
part of stores area where material received is stored in boxes on shelf. It means that
the basic function of this section is to store the material boxes received from mother
plant in systematic and scientific way. At present 5 labours are working in this
190
section. All the 5 Labours (i.e.100 Percent) are selected as sample size for study
purpose. Out of 5, 3 labours respondents perform activity of filling the bin, whereas, 2
labour respondents perform box picking activity. Labour respondents 1, 2 and 3 does
18 activities or movements (motion), while completing their assigned job (i.e filling
the bin). On other hand, labour No.4 and 5 does 12 activities or movements (i.e
Motion) during their completion of box picking activity. In other words, filling the bin
activity is divided into 18 sub movement and picking box activity is divided into 12
sub movements. Therefore, labour productivity or time taken by first 3 labour
respondents are measured separately as their activity is one and divided into equal and
same movements. The nature of movement of first labour respondents is same. Other
2 labour respondents work nature is different. Hence, their work is separately
measured and analyzed accordingly. Observations, questionnaire, personal interviews,
discussions were used to collect the primary data. To understand and measure how
much time a labour takes to fill bin with material, systematical movement wise 10
readings were taken on 18 elements or movements. These 18 elements are shown in
chart 6.7. Activity elements or movements given in above chart are considered in this
study and time taken by labour on each element or movement is measured 10 times on
the basis of stop watch time study method in minutes. The time taken by each labour
to perform 18 activity elements or movements is referred as labour productivity. On
other sense, this is a work measurement of labour in terms of time.
Similar exercise is undertaken on labour 4 and 5 performing box picking
activity.
Time taken by labour 4 and 5 on box picking activity is measured on the basis
of stop watch time study method after classifying this activity into 12 elements or
movements.
191
Chart 6.7
Activity Elements Performed by Labour Respondents to complete
Bin Filling Activity of Catwalk Section
Sr.No Activity Elements
1 Collect empty bin from stores
2 Walk towards work table
3 Place empty bin on Work table
4 Pick material box
5 Place material box on the table
6 Remove tag from material box
7 Stick tag on empty bin
8 Pick up the cutter
9 Cut the packaging of material box
10 Cut the covering of materials
11 Pick up material from box
12 Place material in bin
13 Repeat steps 14 & 15 till the bin is full
14 Pick the filled bin
15 Walk towards trolley
16 place the filled bin on trolley
17 Reach to work station
18 remove the empty empty box from work table
Chart 6.8 presents what activity elements or movements are considered in this
study by the researcher.
192
Chart 6.8
Activity Elements Performed by Labour Respondents
to Complete Box Picking Activity of Catwalk Section
Sr.No Activity Elements
1 Pick the card from table
2 Pick the material box
3 carry material box to Work Table
4 Place material box on Work table
5 Move towards rack
6 Pick up material box from rack
7 Reach towards Work table
8 Place the material box on Work table
9 Pick the filled material box
10 Walks towards trolley
11 Place the material box on trolley
12 Repeat steps 10 and 11 till the trolley is full
On the basis of activity elements or movements mentioned in chart 6.7 and
chart 6.8, collected data is interpreted and analysed as under:
6.7.1 Maximum and Minimum time taken by Labour Respondents to Complete
Bin Filling Activity in Catwalk Section:
The survey result of time taken by labour respondents 1, 2 and 3 in performing
Bin Filling Activity is presented in Table 6.11 and Figure 6.16.
193
Table 6.11
Maximum and Minimum time taken by Labour Respondents to
Complete Bin Filling Activity in Catwalk Section
Labour
No.
Maximum time
(in Minutes)
Minimum Time
(in Minutes)
1 8.7 6.92
2 8.5 6.53
3 6.55 4.73
Average 7.9 6.06
Figure 6.16
Maximum and Minimum time taken by Labour Respondents to
Complete Bin Filling Activity in Catwalk Section
X-Axis Labour Respondents in Catwalk Section
Y-Axis
Time taken by Labour Respondents in
Minutes
Alternatives
A-C Labour 1 to Labour 3
0
5
10 8.7 8.5
6.556.92 6.53
4.73
Maximum
Time (in
Minutes)
Minimum
Time
(in
Minutes)
Labour Respondents in Catwalk Section
Tim
e t
ak
en b
yL
ab
ou
r
Res
pon
den
ts i
n M
inu
tes
Labour Respondents in Catwalk SectionLabour Respondents in Catwalk Section
B C
194
Observations:
Table 6.11 and Figure 6.16 shows that
1. Labour 1 took maximum 8.70 minutes and minimum 6.92 minutes to complete
bin filling activity. On the other hand, for the same activity labour 2 took
maximum and minimum 8.50 minutes and 6.53 minutes respectively.
Moreover, time taken by labour 3 to perform similar activity was maximum
and minimum to the extent of 6.55 minutes and 4.73 minutes respectively. This
indicates that on an average, maximum and minimum time required to perform
the bin filling activity is 7.91 minutes and 6.06 minutes using stop watch
method without adding rating factor and allowances.
2. Labour 3 took less time as compared to labour 1 and 2 with respect to
maximum as well as minimum time. Among the 3 labours average time taken
by labour is also less as compared to labour 1 and 2 respectively. This means
that the productivity of labour 3 is higher than that of labour 1 and 2.
Findings:
Similar exercise is undertaken on labour 4 and 5 performing box picking
activity.
Time taken by labour 4 and 5 on box picking activity is measured on the basis
of stop watch time study method after classifying this activity into 12 elements or
movements.
Average maximum time taken by labour 1,2 and 3 to complete Bin filling
activity was 8.70, 8.50 and 6.55 minutes respectively, whereas, average minimum
time taken by labour 1, 2 and 3 to complete same activity where to the extent of 6.92,
6.53 and 4.73 minutes respectively. Labour 3 takes less time as compared to labour 1
and 2 and productivity of labour 3 is higher than that of labour 1 and 2 respectively.
195
6.7.2 Standard Time taken by Labour Respondents to complete the Bin Filling
Activity in Catwalk Section:
Standard time is the time allowed to an operator to carry out a specified task
under specified condition and at defined level of performance. Average observed time
is the average of time calculated for 10 number of cycle readings for each labour as
observed by the researcher while application of stop watch time study. As discussed
in introduction section, synthetic rating method is used to calculate the rating for each
labour. Normal time is the time which is derived by taking the product of average
observed time and rating factor. Since no Labour can work continuously, 20 Percent
allowances are added to the average observed time so as to derive standard time.
Standard time is the summation of normal time and 20 percent allowance derived for
each labour. Table 6.12 and Figure 6.17 gives measured values of observed average
time, normal time and standard time as well as allowances for labour 1, 2 and 3 in
catwalk section performing bin filling activity.
Table 6.12
Standard Time Taken by Labour Respondents to
Complete Bin Filling Activity in Catwalk Section
Labour
No.
Average
Observed Time
(Min)
Normal
Time (Min)
Allowances
(Min)
Standard
Time
(Min)
1 7.86 4.90 1.57 6.48
2 7.46 4.65 1.49 6.15
3 5.65 3.52 1.13 4.65
196
Figure 6.17
Standard Time Taken by Labour Respondents to
Complete Bin Filling Activity in Catwalk Section
X-Axis Labour Respondents in Catwalk Section
Y-Axis
Time taken by Labour Respondents in
Minutes
Alternatives
A-C Labour 1 to Labour 3
Observations:
It can be seen from Table 6.12 and Figure 6.17 that
i. For labour 1 average observed time is 7.86 Minutes to complete his assigned job
of bin filling. With the rating of 62 Percent, Normal time achieved for labour 1 is
4.90 Minutes. With the addition of 20 Percent allowances, the standard time for
labour 1 to complete bin filling activity is 6.48 Minutes. Thus it can be inferred
that standard time required to complete assigned activity for labour 1 is 6.48
Minutes which is less as compared to the average time labour1 took to complete
his activity.
ii. Average observed time taken by Labour 2 to complete his activity is 7.46
Minutes. At the rating of 62 percent, Normal time for labour 2 is 4.65 Minutes.
0
2
4
6
8
7.867.46
5.656.48 6.15
4.65
Average
Observed
Time (in
Minutes)
Standard
Time (in
Minutes)
Labour Respondents in Catwalk Section
Tim
e t
ak
en b
yL
ab
ou
r
Res
pon
den
ts i
n M
inu
tes
Tim
e t
ak
en b
yL
ab
ou
r
Res
pon
den
ts i
n M
inu
tes
Tim
e t
ak
en b
yL
ab
ou
r
Res
pon
den
ts i
n M
inu
tes
B CA
197
With addition of 20 Percent allowances standard time derived for labour 2 is 6.15
Minutes.
iii. Labour 3 takes average of 5.65 Minutes to complete bin filling activity. With 62
percent of rating, normal time for Labour 3 is 3.52 Minutes. 20 Percent allowance
addition results in 4.65 Minutes of standard time required for labour 3 to complete
his activity which is less as compared to Labour 1 and 2.
Findings:
Standard time for Labour 3 is less (i.e.4.65 Min) as compared to Labour 1 and
2. Labour 3 takes less time to complete the same activity that is performed by labour 1
and 2.
6.7.3 Maximum and Minimum time taken by Labour Respondents to Complete
Box Picking Activity in Catwalk Section:
The survey result of time taken by labour respondents 4 and 5 in performing
box picking activity is presented in Table 6.13 and Figure 6.18.
Table 6.13
Maximum and Minimum Time Taken by Labour to
Complete Box Picking Activity
Labour No. Maximum time
(in Minutes)
Minimum time
(in Minutes)
4 8.65 6.68
5 7.63 5.03
Average 8.14 5.86
198
Figure 6.18
Maximum and Minimum Time Taken by Labour Respondents to
Complete Box Picking Activity in Catwalk Section
X-Axis Labour Respondents in Catwalk Section
Y-Axis
Time taken by Labour Respondents in
Minutes
Alternatives
A Labour 4
B Labour 5
Observations:
Table 6.13 and Figure 6.18 shows that -
1. Labour 4 took maximum 8.65 minutes and minimum 6.68 minutes to complete box
picking activity. On the other hand, for the same activity labour 5 took maximum
and minimum 7.63 Minutes and 5.03 Minutes respectively. This indicates that on
an average, maximum and minimum time required to complete the box picking
activity is 8.14 Minutes and 5.86 Minutes using stop watch method without adding
rating factor and allowances.
0
2
4
6
8
108.65
7.636.68
5.03
Maximum
time (in
Minutes)
Minimum
time (in
Minutes)
Labour Respondents in Catwalk Section
Tim
e t
ak
en b
yL
ab
ou
r
Res
po
nd
ents
in
Min
ute
s
BA
199
2. Labour 5 took less time as compared to labour 4 with respect to maximum as well
as minimum time. Among the 2 labours average time taken by labour 5 is also less
as compared to labour 4. This means that the productivity of labour 4 is higher than
that of labour 4.
Findings:
It can be stated from Table 6.13 and Figure 6.18 that average maximum time
taken by labour 4 and 5 to complete box picking activity was 8.14 Minutes
respectively, whereas, average minimum time taken by labour 4 and 5 to complete
same activity was to the extent of 5.86 minutes respectively. Labour 5 takes less time
as compared to labour 4 and productivity of labour 5 is higher than that of labour 4
respectively.
6.7.4 Standard Time Taken by Labour Respondents to Complete Box Picking
Activity in Catwalk Section:
Table 6.14 and Figure 6.19 gives measured values of observed average time,
normal time and standard time as well as allowances for labour 4 and 5 in catwalk
section performing Box Picking Activity.
Table 6.14
Standard Time Taken by Labour Respondents to
Complete Box Picking Activity in Catwalk Section
Labour
No.
Average
Observed
Time (Min)
Normal
Time
(Min)
Allowances
(Min)
Standard
Time (Min)
4 7.64 4.76 1.53 6.29
5 6.43 4.01 1.29 5.30
200
Figure 6.19
Standard Time Taken by Labour Respondents
to Complete Box Picking Activity in Catwalk Section
X-Axis Labour Respondents in Catwalk Section
Y-Axis
Time taken by Labour Respondents in
Minutes
Alternatives
A Labour 4
B Labour 5
Observations:
It can be seen from table 6.14 and Figure 6.19 that -
i. For labour 4 average observed time is 7.64 Minutes to complete his activity of box
Picking. With the rating of 62 Percent, Normal time achieved for labour 4 is 4.76
Minutes. With the addition of 20 Percent allowances, the standard time for labour 4
to complete activity is 6.29 Minutes.
ii. Labour 5 takes average of 6.43 Minutes to complete box picking activity. With 62
percent of rating, normal time for Labour 5 is 4.01 Minutes. 20 Percent allowance
0
2
4
6
87.64
6.436.29
5.3
Average
Observed
Time (in
Minutes)
Standard
Time (in
Minutes)Labour Respondents in Catwalk Section
Tim
e t
ak
en b
yL
ab
ou
r
Res
pon
den
ts i
n M
inu
tes
BA
201
addition results in 5.30 Minutes of standard time required for labour 5 to complete
his activity which is less as compared to Labour 4.
Findings:
Thus, it can be stated that the standard time for Labour 5 is less (i.e. 5.30
Minutes) as compared to Labour 4. Labour 5 takes less time to complete the same
activity that is performed by labour 4.
6.8 Analysis of Social and Technical barriers associated with Labour
Respondents while application of Stop Watch Time Study Method:
The process of determining a standard time for completing an assigned job is
complex. Labour setting is far from easy. Each custom, high skill or no skill labour
environment has inherent barriers that often prevent the stop watch (traditional) time
study from quickly obtaining accurate data. These barriers can be divided into two
categories: Social and Technical.
6.8.1 Responses of Labour Respondents towards Social Barriers involved in
application of Stop Watch Time Study Method:
Social barriers consist of (i) Hierearchy or organization culture (ii) Lack of full
support (iii) Reluctance to measure and (iv) fear of job loss. Of these 4, only 3 social
barriers are considered for study purpose. Organization culture barrier is not studied
by the researcher. The question were asked to sample labour respondents on
reluctance to measure work, fear of job loss and support provided for application of
stop watch time study method. The social barriers associated with Stop Watch Time
Study method implementation is presented in Figure 6.20.
202
Figure 6.20
Social Barriers associated with application of Stop Watch Time Study Method
It was asked to sample labour respondents to state their positive or negative
responses on social barriers experienced by them while application of stop watch time
study method. A response of labour towards social barrier involved in application of
Stop Watch Time Study Method is presented in Table 6.15 and Figure 6.21.
Table 6.15
Responses of Labour Respondents towards Social Barriers involved
in application of Stop Watch Time Study Method (N= 25)
Sr.No Social Barriers
Responses of labours
Yes No To some extent
Nos. Percent Nos. Percent Nos. Percent
1
Reluctance to
Measure 2 8 19 76 4 16
2 Fear of Job loss 3 12 17 68 5 20
3 Lack of Support 3 12 18 72 4 16
Average 3 12 18 72 4 16
Reluctance
to Measure
Lack of full
Support
Fear of Job
Loss
Social Barriers
203
Figure 6.21
Responses of Labour Respondents towards Social Barriers involved
in application of Stop Watch Time Study Method (N= 25)
X-Axis Social Barriers involved
in application of Stop Watch Time Study
Method
Y-Axis Responses of Labour Respondents
Alternatives
A Reluctance to Measure
B Fear of Job loss
C Lack of Support
Observations:
It can be seen from Table 6.15 and Figure 6.21 that -
1. Out of 25 respondents, 2 (8 Percent) are reluctant to measure, 19 (76 Percent) are
not reluctant to measure and 4 (16 respondents) are to some extent reluctant to
measure their work respectively. It means that labour of all the selected sections do
not create any kind of hurdles and do not feel any pressure on them as majority of
labours (i.e. 76 Percent) are not reluctant when their work is measured using stop
watch time study method.
0
5
10
15
20
2 (8%) 3(12%) 3(12%)
19(76%)17 (68%) 18(72%)
4 (16%) 5(20%) 4(16%)
Yes
No
To some
extentSocial barriers
Res
po
nse
s o
f L
ab
ou
r
Res
pon
den
ts
A B C
204
2. Out of 25 respondents, 03 (12 Percent) agreed that they fear job loss when their
work is measured using stop watch time study method, 17 (68 Percent) do not
agree and 5 (20 Percent) said they agree to some extent to the fear of job loss due
to application of time study. It means that majority of the respondents (i.e. 68
Percent) do not fear job loss when their work is measured. On the other hand, they
fully supported to implement stop watch time study method to measure work.
3. When it was asked to the respondents whether they show lack of support attitude
when their work is measured using Stop Watch time study method, majority of the
respondents i.e.18 (72 Percent) stated that they do not show lack of support instead
they agree to provide full support to measure their work by application of stop
watch time study method. This means that majority of the labour feel that the work
should be measured and process should be improved using proper work
measurement method.
4. Overall result on social barriers shows that only 03 (12 Percent) agreed that they
face the above discussed social barrier in implementation of stop watch time study
method. On the other hand, 18 (72 Percent) respondents have not faced or
overcome the social barriers and 4 (16 Percent) respondents have faced social
barriers to some extent. It means that majority of the respondents (72 percent) have
overcome the social barriers and do not create any hurdles in work measurement
when stop watch time study method is applied in SAIPL.
6.8.2 Responses of Labour Respondents towards Technical Barriers involved in
application of Stop Watch Time Study Method:
The variation of work method, shortage of needed samples and ambiguity of
process elements is referred to as technical barriers here. Whether labour respondents
in all the selected sections faced any type of technical barriers to measure their work
using stop watch time study method. Because higher the technical barrier, lower the
productivity and longer time to complete assigned job. Figure 6.22 shows technical
barriers considered for the study purpose.
205
Figure 6.22
Technical Barriers associated with application of Stop Watch Time Study
Method
Variation of Work Method
Ambiguity of Process elements Shortage of needed Samples
In practice, high skill industry is not only tedious but it also lacks accuracy.
Variations in base time may be observed due to method being used to complete
assigned job. Such variations are prevalent in an auto industry, because each high skill
job often employee individuals who complete difficult task in a variety of styles or
ways.
Secondly, more the number of observed readings, more likely it is that average
of those times will be an accurate estimate of how long the task will take. Generally
10 number of observation readings per variable per operator is recommended
according to ILO. In today‟s setting, a traditional work measurement process is often
conducted by a person in the organization, as part of a larger improvement plan.
Hence, there can be shortage of sample number of readings that can lead to inaccurate
results. He may report less or more or inaccurate reading to higher authority and to
labour also. So when there is difference in reading and reporting it is called shortage
of sample which constitutes to technical barrier in work measurement using stop
watch application method.
Thirdly, unless the person timing a labour is familiar with the work or job
carried out by labour, operator cannot determine independent elements of the activity.
Independence in this sense means that the variability of one element is unrelated to
the variability of the other elements. Without determining independent tasks and
timing them separately the variability of time estimates cannot be explained. For
Technical
Barrier
BaBarrier
s
206
example, if a complete job is timed at once, and the observed times range from very
long to very short, the operator/ observer cannot determine which portion of the job
caused this wide range. One or two independent task likely caused the problem, but
the observer or operator has no way of knowing because he or she cannot separate the
task originally. Whether labours of all the selected section in SAIPL have faced such
technical situation is studied by the researcher.
Researcher would like to know the opinions of labour on technical barriers
which are considered for study purpose. It was asked to the labours that do you
experienced any:
(i) Variation in application of stop watch time study method.
(ii) Shortage of needed sample in application of Stop Watch Time Study method,
and
(iii) Ambiguity in activity elements when stop watch time study method is applied.
Table 6.16 and Figure 6.23 shows the summary of survey conducted related to
technical barriers observed / experienced by labour in implementation of stop watch
time study method.
Table 6.16
Responses of Labour Respondents towards Technical Barriers
involved in application of Stop Watch Time Study Method
Sr.No Technical Barriers
Responses of labour
Yes No
To some
extent
Nos. Percent Nos. Percent Nos. Percent
1
Variation in application
of Stop watch time
study method and time
measurement 6 24 10 40 9 36
2
Variation in shortage of
needed samples 4 16 16 64 5 20
3
Ambiguity in activity
elements 3 12 18 72 4 16
Average 3 12 16 64 6 24
207
Figure 6.23
Responses of Labour Respondents towards Technical Barriers
involved in application of Stop Watch Time Study Method
X-Axis Technical Barriers involved
in application of Stop Watch Time Study
Method
Y-Axis Responses of Labour Respondents
Alternatives
A Variation in application of Stop watch time
study method and time measurement
B Variation in shortage of needed samples
C Ambiguity in activity elements
Observations:
Table 6.16 and Figure 6.23 shows that,
1. Out of 25 sample respondents, 6 (24 Percent), 10 (40 Percent), and 9 (36
Percent) agreed, discussed and to some extent agreed on variation in
application of stop watch time study method and time measurement. This
means that majority of labour sample respondents (i.e. 40 Percent) stated that
0
5
10
15
20
6 (24%)4(16%) 3(12%)
10 (40%)
16(64%)
18(72%)
9 (36%)
5(20%)4(16%)
Yes
No
To some
extentTechnical barriers
Res
pon
ses
of
Lab
ou
r
Res
pon
den
ts
A B C
208
there is no variation in time measurement and application of stop watch time
study method.
2. Regarding shortage of needed samples, it was observed that out of 25 sample
labour respondents, 04 (16 Percent) agreed, 16 (64 Percent) did not agreed and
5 (20 Percent) agreed to some extent that there is shortage of needed sample to
measure work using stop watch time study method.
3. For ambiguity in activity elements, it was seen that the out of 25 labour
respondents, 63 (12 Percent) agreed, 18 (72 Percent) are not agreed and 4 (16
Percent) agreed to some extent that there is ambiguity in activity elements
carried out to measure the work using stop watch time study method. It means
that majority of respondents (i.e 72 Percent) state that there was no ambiguity
observed in the activity elements to measure work.
4. Overall regarding technical barriers it was observed that, majority of the
respondents (64 percent) stated that they have not created any kind of technical
hurdles in application of stop watch time study method. On other hand, they are
fully supporting to measure their work performance.
209
References:
1. United States Agency for International Development, „Measuring
Competitiveness and Labour Productivity in Cambodia‟s garment industry‟.
Nathan Associates Inc. and its Parther Organisations, 2005, P.17.
2. International Labour Organisation, „Introduction to Work Study‟, Universal
Book Corporation, 3rd
Edition, 1986, PP.248.
3. Nor Diana Hashim, „Time Study Method Implementation in Manufacturing
Industry‟, A B.E Report, Universiti Technikal Malaysia, Melaka, 2008.