Upload
trinhtruc
View
218
Download
5
Embed Size (px)
Citation preview
127
CHAPTER 6
A STUDY OF THE TRENDS IN PRICES OF MATERIALS
AND COST INDICES IN BUILDING CONSTRUCTION
CONTRACTS IN INDIA
6.1 INTRODUCTION
Medium to large construction projects take over a year for
completion and the cost of materials often increase which leads to major
problems in administration of the contract. Increase in price of materials
during the execution of the contract is the root cause for dispute between the
owner and contract and delay in completion of projects. In this chapter, study
carried out to identify the cost components of major materials contributing to
overall cost of the project through case studies of six building construction
projects. A study on trend in price of major materials (Steel, Cement, Brick,
Sand and Coarse Aggregate) over the period of six years, and cost indices in
India are also presented.
6.2 IDENTIFICATION OF MAJOR COST COMPONENTS OF
BUILDING CONSTRUCTION PROJECT
The major material components contributing to overall cost of the
projects were analysed through case studies of six building construction
projects i.e. Construction of educational building at Chennai, Construction of
office building at Delhi and Construction of hostel building at Chennai. The
128
case study analysis of construction of office building is presented in
Figure 6.1.
14.30%
18.50%
2.60%4.10%
0.60%2.50%
4.70% 6%
2.20%1.80%1.80%0.60%0.07%0.27%
20.50%
13.50%
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%Cem
ent Steel
Sand
bricks
Stone agg
regate
Timber
Aluminium works
Flooring
paintin
g work
sanita
ry, pipe
s and f
itting
s
MS grill
& struct
ural w
orks
Hardware
sAc s
heet
Expans
ion joint
Labour
cost
General
expen
ses an
d cost
per c
enta
ge %ge of overall project cost
Figure 6.1 Construction of Office Building at Chennai
From the Figure, it can be inferred that cost components of cement
and steel contributing to about 33% of overall cost of the project. Labour
components was about 20.50% and component of brick, sand, coarse
aggregates and timber contributing about 10% of overall cost of the project.
The case study analysis of construction of educational building-I is
presented in Figure 6.2.
129
17%
22%
4%2% 3%
1%
23%
2%
6% 5%
13%
0%
5%
10%
15%
20%
25%
Cement Stee
lBric
ksan
d
coarse
aggreg
ate
Timber
Labour
cost
Paintin
g
Aluminium
Plumbing an
d san
itary
works
Other exp
enses
Cost in %ge ofoverall cost
t
Figure 6.2 Construction of Educational Building – I at Chennai
From the Figure 6.2, it can be inferred that cost components of
cement is about 17% and steel is about 22% of overall cost of the project. The
Labour components contribute about 20% overall cost of the project.
16%
20.50%
4%2.50% 3% 2%
7%
4%
8%
22%
11%
0%
5%
10%
15%
20%
25%
Cement Stee
l
Brick
sand
Stone
aggreg
ate
Timbe
rA lum
inium
Plumbin
g and s
anita
ry work
s Tiles
Labour
co st Oth er
expens
es
%ge of overall project cost
Figure 6.3 Construction of Educational Building – II at Chennai
130
From the Figure 6.3, it is seen that cost components steel and
cement alone contribute to about 36.5% of overall cost of the project. Labour
components was about 22% and component of brick, sand, coarse aggregates
and timber contribute about 11.5% of overall cost of the project. The cost
components of construction of building in New Delhi is presented in
Figure 6.4.
21.50% 22%
4.00%5.00%
4.00%2%
26.00%
16%
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
Cement Steel Brick sand Stoneaggregate
T imber Labourcost
Otherexpenses
perc
enta
ge
overall project cost
Figure 6.4 Construction of Building at New Delhi
From the Figure 6.1 to 6.4, it is seen that cost components of
cement, steel, brick, sand, coarse aggregate and timber alone were
contributing to about 50% of overall cost of the project. One of the main
objectives was to analyse the movement of price of major materials (cement,
steel, brick, sand, coarse aggregate and timber) and their impact on cost
escalation in the building construction projects.
131
6.3 STUDY OF PRICE OF MAJOR BUILDING MATERIALS IN INDIA
The six years price data (2003 - 2009) of major materials (cement,
steel, brick, sand and stone aggregate) were collected from Larson and
Toubro Limited and Builders Association of India. The collected data were
analysed in detail, analysis includes month-wise trend in increase in price of
materials and monthly percentage change in price of material over the period
of time.
6.3.1 Trend in Price of Materials over the Period of Time (2003 –
2009)
Cement: Trend in month-wise price of cement (2003-2009) was
analysed. The price of cement had gone up to 127.5% in Chennai region,
107.5% in Delhi region, 98.01% in Kolkatta region, 92% in Mumbai region.
The movement of cement price in India over the period of six years is
presented in Figure 6.5.
0.00
50.00
100.00
150.00
200.00
250.00
300.00
Jan'03
May'03
Sep'03
Jan'04
May
'04Sep
'04Jan
'05May
'05Sep
'05Jan
' 06
May ' 0
6Sep
' 06
Jan ' 0
7May ' 0
7Sep
' 07
Jan '08
May '0
8Sep
'08
Jan '09
Month
Pric
e pe
r 50
kg b
ag
Chennai regionDelhi regionKolkatta regionMumbai region
Figure 6.5 Trend in price of cement (2003-2009) in India
132
Steel: Month-wise movement of price of steel was analysed for six
years (2003-20009). From the analysis, it is found that increase in price of
steel was 281% in Chennai region, 250% in Delhi region, 251% in Bangalore
region, 254% in Kolkatta region, 252% in Mumbai region. The Month-wise
movement of steel price over the period of six years is presented in Figure
6.6.
0
10000
20000
30000
40000
50000
60000
70000
Jan'
03
May
'03
Sep'
03
Jan'
04
May
'04
Sep'
04
Jan'
05
May
'05
Sep'
05
Jan
' 06
May
' 06
Sep'
06
Jan
' 07
May
' 07
Sep
' 07
Jan
'08
May
'08
Sep
'08
Jan
'09
May
'09
Month
Pric
e pe
r MT
Chennai regionDelhi regionBangalore regionKolkatta regionMumbai region
Figure 6.6 Trend in price of steel (2003-2009) in India
Brick, sand and stone aggregate: The month-wise price of brick,
sand and stone aggregate in Chennai region from 2003 to 2008 were analysed.
The average price of brick had gone up to 242%, sand 286% and stone
aggregate 250% within the period of 6 years. The movement of price of brick,
sand and stone aggregate is presented in Figures 6.7, 6.8 and 6.9.
133
0.00
2000.00
4000.00
6000.00
8000.00
10000.00
12000.00
14000.00
16000.00
Jan'03
Jun'03
Nov'03
Apr'04
Sep'04
Feb'05
Jul'05Dec
'05
May ' 0
6
Oct ' 0
6
Mar ' 0
7
Aug ' 07
Jan '08
Jun '08
Nov '0
8
April ' 0
9
Month
Pric
e pe
r 30
00 N
os
Brick price
Figure 6.7 Trend in price of brick (2003-2009) in Chennai region
0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
Jan'03
Jul'03Jan
'04Jul'04
Jan'05
Jul'05
Jan ' 0
6
July ' 06
Jan ' 0
7
July '07Jan
'08
Jul '08
Jan '09
Month
Pric
e pe
r C
ft
Sand price
Figure 6.8 Trend in price of sand (2003-2009) in Chennai region
134
0.00
5.00
10.00
15.00
20.00
25.00
30.00
Jan'03
Jun'0
3
Nov'03Apr'0
4Se
p'04Feb
'05Ju
l'05Dec
'05
May ' 0
6
Oct ' 06
Mar
' 07
Aug ' 07
Jan '0
8Ju
n '08
Nov '08
April ' 0
9
Month
Pric
e pe
r Cft
Aggregate price
Figure 6.9 Trend in price of coarse aggregates
6.3.2 Trend in Monthly Percentage Change in Price of Materials
over the Period of Time (2003 – 2009)
Cement: Trend in monthly percentage change in price of cement
and steel (2003-2009) were studied. The monthly average percentage
fluctuation in price of cement in Chennai region was in the maximum range
of between -11% and 18%. In the Delhi region it was between -5% and
+18%, in Kolkatta region it was between -12% and +15% and in the Mumbai
region it was between -12% and +17%. The fluctuation in monthly price of
cement over the period (2003-2009) is presented in Figure 6.10.
135
-15.00
-10.00
-5.00
0.00
5.00
10.00
15.00
20.00
25.00
Jan'03
May'03
Sep'03
Jan'04
May'04Sep
'04Jan
'05May'05Sep
'05Jan
' 06
May ' 06
Sep' 0
6Jan
' 07
May ' 07
Sep ' 0
7Jan
'08May
'08Sep
'08
Jan '09
Month-wise
Mon
thly
%ge
cha
nge
Chennai regionDelhi regionKolkatta regionMumbai region
Figure 6.10 Monthly % ge change in price of cement (2003 – 2009) in
India
Steel: The monthly fluctuation in price of steel in Chennai region
was in the range of between -11% and +19%, in the Delhi region it was
between -12% and +16%, in the Bangalore region it was between -19% and
+24%, in the Kolkatta region it was between -12% and +17%, and in the
Mumbai region it was between -13% and +19%. The movement of monthly
fluctuation over the period (2003-2009) is presented in Figure 6.11.
136
-30.00
-20.00
-10.00
0.00
10.00
20.00
30.00
40.00
50.00
Jan'03
May'03
Sep'03
Jan'04
May'04
Sep'04
Jan'05
May'05
Sep'05
Jan ' 0
6
May ' 06
Sep' 06
Jan ' 0
7
May ' 07
Sep ' 07
Jan '08
May '08
Sep '08
Jan '09
May'09
Chennai regionDelhi regionBangalore regionKolkatta regionMumbai region
Figure 6.11 Monthly %ge change in price of steel (2003 – 2009) in India
Brick, Sand and Coarse aggregate: Trend in monthly percentage
change in price of brick, sand and coarse aggregate from 2003-2009 data were
analysed to study the price fluctuation. The study, reveals that there was a
fluctuation in prices of brick, sand and stone aggregate throughout the year, it
was also observed that fluctuation in prices are seasonal. The maximum
monthly percentage change in price of brick was between - 23% and +33%.
The movement of price of brick over the period (2003-2009) is presented in
Figure 6.12.
137
-30.00
-20.00
-10.00
0.00
10.00
20.00
30.00
40.00
Jan'
03
Jun'
03
Nov
'03
Apr
'04
Sep'
04
Feb'
05
Jul'0
5
Dec
'05
May
' 06
Oct
' 06
Mar
' 07
Aug
' 07
Jan
'08
Jun
'08
Nov
'08
Apr
il '
Month
Mon
thly
%ge
cha
nge
Brick Price
Figure 6.12 Monthly %ge change in price of brick (2003 – 2009)
The average monthly percentage change in price of sand over the
period of six years (2003-2009) was between -36% and +122% and stone
aggregate between -39% to +46%. The movement of price of sand over the
period (2003-2009) is presented in Figure 6.13.
-60.00
-40.00
-20.00
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
Jan'
03
May
'03
Sep'
03
Jan'
04
May
'04
Sep'
04
Jan'
05
May
'05
Sep'
05
Jan
' 06
May
' 06
Sep'
06
Jan
' 07
May
' 07
Sep
' 07
Jan
'08
May
'08
Sep
'08
Jan
'09
May
'09
Month
Mon
thly
%ge
Cha
nge
Sand price - chennai region
Figure 6.13 Average Monthly %ge change in price of sand (2003 – 2009)
138
The average monthly percentage change in price of coarse
aggregate over the period of six years (2003-2009) was between -39% and
+46%. The movement of price of coarse aggregate over the period (2003-
2009) is presented in Figure 6.14.
-5.00
-4.00
-3.00
-2.00
-1.00
0.00
1.00
2.00
3.00
4.00
Jan'03
May'03
Sep'03
Jan'04
May'04
Sep'04
Jan'05
May'05
Sep'0
5
Jan ' 0
6
May ' 0
6
Sep' 0
6
Jan ' 0
7
May ' 0
7
Sep ' 0
7
Jan '0
8
May '08
Sep '0
8
Jan '09
May'09
Month-wise
Pric
e in
Rs.
Stone aggregate price
Figure 6.14 Average Monthly %ge change in price of coarse aggregate
(2003 – 2009)
6.4 STUDY OF BUILDING COST INDEX IN INDIA
6.4.1 Construction Cost Index
In the USA, Engineering News Record (ENR)’s cost indices are
commonly used to measure the cost trends in the construction industry
(Touran and Lopez, 2006). Building Cost Information Services (BCIS,
subsidiary of the Royal Institute of Chartered Surveyors), are used to measure
cost trends in construction industry in the United Kingdom (Dawood and
Bates, 2002). In India, The Central Public Works Department (CPWD) is
publishing the building cost index from 1958 onwards and also Construction
139
Industry Development Council (CIDC) has developed and has been
publishing the construction cost indices since 1998 to measure the cost trends
in the construction Industry.
6.4.2 Trend in Building Cost Index (CPWD) in India
The CPWD cost indices for 50 years were analysed in detail to
study the movement of construction cost in India. The trend in building cost
index from 1958- 2008 is presented in Figure 6.15.
0
200
400
600
800
1000
1200
1400
1958
1962
1968
1972
1976
1980
1984
1988
1992
1996
2000
2004
2008
Year
Inde
x va
lue
CPWD Cost Index
Figure 6.15 Movement of CPWD Cost Indices (1958-2008) in India
Based on analysis of CPWD’s Building Cost Indices, from 1958 to
2008, it is found that early in the 1960 – 61 and 1971, 1974 – 1975 was a
period of high inflation for the construction industry in India. During 1979 –
1984, cumulative percent of change for the India was 236% with an average
of 39.3% per year. During 1988 – 1991, cumulative percent of change of cost
140
index was 201% with an average of 50.25% per year. The yearly percentage
change in CPWD cost index (1958-2008) is presented in Figure 6.16.
-20.00
0.00
20.00
40.00
60.00
80.00
100.00
1958
1961
1964
1969
1972
1975
1978
1981
1984
1987
1990
1993
1996
1999
2002
2005
Year
perc
enta
ge c
hang
e
CPWD Cost Index
Figure 6.16 Yearly % ge change in CPWD cost index (1958 - 2008)
The average building construction cost escalation in India from
1958 to 2008 is about 4.22% per year.
6.4.3 Modelling Escalation Factor in Building Construction Project
in India
The CPWD cost indices for 50 year datas were used for modelling
escalation factor for building construction projects in India to measure the
average cost construction escalation in India. The escalation factor is the rate
of change of the Building Cost Index (BCI) from year to year can be
calculated from the following Equation (Touran et al 2006).
%10011
i
ii I
I (6.1)
141
where I = percent of change of period i; Ii = index of period i; and 1iI = index
of the previous period (i-1). A positive value of i is an indication of increase
in cost. In contrast, if the value of i is negative, that is because period i has
experienced a deflation. i is then the escalation factor that we are trying to
model.
The average value of escalation factor for the period of 1958–2008
was computed using the following equation:
%1001/1
n
b
e
IIr (6.2)
where r =average rate of change; Ie and Ib=index values in the ending period;
and the beginning period, respectively; and n=number of periods between e
and b.
From the above formula, the average value of escalation factor for
the period of 1958–2008 was computed as 4.22 % per year.
6.4.4 Forecasting Building Construction Cost Escalation
Forecasting building construction cost escalation using statistical
time series methods, 50 years CPWD building cost indices and 6 years
month-wise price data were considered for the study. Forecasted building
construction cost escalation for five years using the software Forecast X. The
forecasted details are presented in Figure 6.17 and Table 6.1.
142
CPWDCI1955
0
200
400
600
800
10001200
1400
1600
1800
200019
6119
6319
6519
6719
6919
7119
7319
7519
7719
7919
8119
8319
8519
8719
8919
9119
9319
9519
9719
9920
0120
0320
0520
0720
0920
1120
1320
15
CPWDCI1955 Forecast of CPWDCI1955 Fitted Values Upper Low er
Figure 6.17 Forecasting CPWD cost index for 5 years from 2010 to 2015
Table 6.1 Forecasted Building Cost Index (CPWD) from 2010 to 2015
Year Forecast(Holt-Winters) 2010 1,246.73 2011 1,338.60 2012 1,443.76 2013 1,536.78 2014 1,642.18 2015 1,731.99 AIC 443.17 BIC 448.84 Mean Absolute Percentage Error (MAPE) 3.30% R-Square 99.53% Durbin Watson 1.95 Mean 555.69 Median 576.00 Standard Deviation 308.10
143
The R-squared statistic indicates that 99.53% of the variation of the
index is explained by the model. This shows that the model fits the historical
data very well. The mean absolute percentage error is 3.30%.
Based on six years building materials price data, the building
material prices for twelve months has been forecasted using the software
Forecast X. The forecasted details of cement, steel, brick, sand and coarse
aggregates are presented in Figures 6.18 to 6.22.
0
50
100
150
200
250
300
350
Cement
Cement Forecast of Cement Fitted Values Upper Lower
Figure 6.18 Forecasted cement price for 12 months (June’2009 to
May-2010)
144
Steel
0
10000
20000
30000
40000
50000
60000
70000Ja
n-03
Apr-
03
Jul-0
3
Oct
-03
Jan-
04
Apr-
04
Jul-0
4
Oct
-04
Jan-
05
Apr-
05
Jul-0
5
Oct
-05
Jan-
06
Apr-
06
Jul-0
6
Oct
-06
Jan-
07
Apr-
07
Jul-0
7
Oct
-07
Jan-
08
Apr-
08
Jul-0
8
Oct
-08
Jan-
09
Apr-
09
Jul-0
9
Oct
-09
Jan-
10
Apr-
10
Steel Forecast of Steel Fitted Values Upper Low er
Figure 6.19 Forecasted steel price for 12 months (June’2009 to May-2010)
Brick
0
2000
4000
6000
8000
10000
12000
14000
16000
Jan-
03
Apr-
03
Jul-0
3
Oct
-03
Jan-
04
Apr-
04
Jul-0
4
Oct
-04
Jan-
05
Apr-
05
Jul-0
5
Oct
-05
Jan-
06
Apr-
06
Jul-0
6
Oct
-06
Jan-
07
Apr-
07
Jul-0
7
Oct
-07
Jan-
08
Apr-
08
Jul-0
8
Oct
-08
Jan-
09
Apr-
09
Jul-0
9
Oct
-09
Jan-
10
Apr-
10
Brick Forecast of Brick Fitted Values Upper Low er
Figure 6.20 Forecasted brick price for 12 months (June’2009 to May-2010)
145
Sand
0
5
10
15
20
25
30
35
Jan-
03
Apr-
03
Jul-0
3
Oct
-03
Jan-
04
Apr-
04
Jul-0
4
Oct
-04
Jan-
05
Apr-
05
Jul-0
5
Oct
-05
Jan-
06
Apr-
06
Jul-0
6
Oct
-06
Jan-
07
Apr-
07
Jul-0
7
Oct
-07
Jan-
08
Apr-
08
Jul-0
8
Oct
-08
Jan-
09
Apr-
09
Jul-0
9
Oct
-09
Jan-
10
Apr-
10
Sand Forecast of Sand Fitted Values Upper Low er
Figure 6.21 Forecasted sand price for 12 months (June’2009 to May-2010)
Coarse Aggregates
0
5
10
15
20
25
30
35
40
45
Jan-
03
Apr-
03
Jul-0
3
Oct
-03
Jan-
04
Apr-
04
Jul-0
4
Oct
-04
Jan-
05
Apr-
05
Jul-0
5
Oct
-05
Jan-
06
Apr-
06
Jul-0
6
Oct
-06
Jan-
07
Apr-
07
Jul-0
7
Oct
-07
Jan-
08
Apr-
08
Jul-0
8
Oct
-08
Jan-
09
Apr-
09
Jul-0
9
Oct
-09
Jan-
10
Apr-
10
Stone Forecast of Stone Fitted Values Upper Low er
Figure 6.22 Forecasted coarse aggregate price for 12 months (June’2009
to May-2010)
146
The forecasted price of cement, steel, brick, sand and coarse
aggregates for twelve months ((June’2009 to May-2010) is presented in
Table 6.2.
Table 6.2 Forecasting of building material cost – for 12 months (1 year)
Dates
Cement – Forecast
(Box Jenkins)
Steel – Forecast
(Box Jenkins)
Brick – Forecast
(Box Jenkins)
Sand – Forecast
(Box Jenkins)
Stone – Forecast
(Holt-Winters)
Jun-09 262.57 39,267.69 11,500.00 20.67 22.88
Jul-09 262.73 39,038.23 11,500.00 21.54 23.53
Aug-09 262.78 38,623.55 11,500.00 21.51 23.70
Sep-09 262.79 38,238.23 11,500.00 21.26 23.64
Oct-09 262.79 38,163.12 11,500.00 21.07 23.46
Nov-09 262.80 38,199.84 11,500.00 21.11 24.13
Dec-09 262.80 38,266.83 11,500.00 21.21 24.29
Jan-10 262.80 38,329.84 11,500.00 21.20 24.23
Feb-10 262.80 38,342.21 11,500.00 21.17 24.04
Mar-10 262.80 38,336.16 11,500.00 21.16 24.72
Apr-10 262.80 38,325.14 11,500.00 21.18 24.89
May-10 262.80 38,314.79 11,500.00 21.19 24.82
AIC 515.45 1,436.02 1,197.89 386.44 270.14
BIC 517.79 1,438.36 1,200.23 395.82 277.17
Mean Absolute Percentage Error
(MAPE) 2.33% 4.57% 3.36% 9.63% 6.12%
R-Square 98.79% 92.35% 96.54% 79.60% 95.66%
Durbin Watson 2.00 1.90 2.08 2.06 1.95
Mean 172.16 31,214.29 8,387.01 16.44 18.94
Median 140.00 30,000.00 7,500.00 14.50 20.00
Standard Deviation
62.05 9,748.68 3,085.32 6.29 6.50
147
6.5 SUMMARY
The major material components contributing to overall cost of the
projects were analysed through case studies of six building construction
projects. From the study, it is found that cost components of key materials i.e.
cement, steel, brick, sand, coarse aggregates and timber were contributing
about 50% of overall cost of the project. In addition it was also identified that
these materials have more impact on cost escalation in building construction
projects.
Based on the analysis of escalation in prices of key materials
(cement, steel, brick, sand and aggregates), the study reveals that major
building material prices have increased drastically. Cement price has gone up
around 108%, steel 250%, brick 240%, sand 286% and stone aggregate 250%.
The trend in monthly percentage change in price of major materials were also
analysed. The study proves that maximum percentage change reported for
cement was between -15% and 18%, steel between -17% and 19%, brick
between -23% and 33%, sand between -36% and 48%, stone aggregate
between -39% and46%.
From the study, it is found that there was a drastic fluctuation in the
prices of key construction materials of cement, steel, brick, sand and coarse
aggregates. Contractors working under these circumstances, find that
estimating, bidding and executing the construction projects are challenges.
Many contractors face significant losses due to fixed price construction
contracts. Hence, it is recommended that escalation may be paid for key
construction materials like cement, steel, brick, sand and coarse aggregates
based on actual procurement prices.
Based on analysis of CPWD’s Building Cost Indices, from 1958 to
2008, it is found that during the period of 1960 – 61 and 1971, 1974 – 1975
148
high inflation was witnessed for the construction industry in India. During
1979 – 1984, cumulative percent of change of building construction cost for
the India was 236% with an average of 39.3% per year. During 1988 – 1991,
cumulative percent of change of cost index was 201% with an average of
50.25% per year. The average building construction cost escalation for the
last 50 years (1958 to 2008) in India was computed as 4.22 % per year. The
building construction cost indices and also the building material prices have
been forecasted for five years and twelve months respectively using the
software “Forecast X”. The lessons from this analysis would be of substantial
use for planning engineer and construction manager working in the
construction industry. They can make use of these findings to minimize the
cost escalation.