20
80 CHAPTER 4 INCREASE IN CRITICAL CLEARING TIME USING SVC AND STATCOM IN TNEB 4.1 INTRODUCTION The preliminary study conducted to evaluate the potential due to the application of SVC and STATCOM on the TNEB 400 kV transmission network, generators and their respective step-up transformers directly connected to 400 kV substations in Tamil Nadu and nearby 400 kV substations (Trivendrum, Chittoor etc.,) is presented in this chapter. The study compares the results and effectiveness of SVC and STATCOM for enhancing the transient stability of the system through the critical clearing time using MiPower simulation software. The fault clearing time is increased up to the critical clearing time to test the robustness of the system and the effectiveness of the SVC and STATCOM. 4.2 LITERATURE REVIEW An occurrence of three phase fault on the bus and clearance of the fault within a short period of time (up to 100 ms) does not represent a large risk to the power system in terms of transient stability. For this reason, it is necessary to ensure that generators operating in the electric power system have a critical clearing time higher than 100 ms. The electric power system instability can be interpreted using various methods depending on the system configuration and operational

CHAPTER 4 INCREASE IN CRITICAL CLEARING …shodhganga.inflibnet.ac.in/bitstream/10603/24335/9/09...82 230 kV, 110 kV and 66 kV. In order to evacuate bulk power from one region to another

  • Upload
    others

  • View
    14

  • Download
    0

Embed Size (px)

Citation preview

80

CHAPTER 4

INCREASE IN CRITICAL CLEARING TIME USING

SVC AND STATCOM IN TNEB

4.1 INTRODUCTION

The preliminary study conducted to evaluate the potential due to

the application of SVC and STATCOM on the TNEB 400 kV transmission

network, generators and their respective step-up transformers directly

connected to 400 kV substations in Tamil Nadu and nearby 400 kV

substations (Trivendrum, Chittoor etc.,) is presented in this chapter. The study

compares the results and effectiveness of SVC and STATCOM for enhancing

the transient stability of the system through the critical clearing time using

MiPower simulation software. The fault clearing time is increased up to the

critical clearing time to test the robustness of the system and the effectiveness

of the SVC and STATCOM.

4.2 LITERATURE REVIEW

An occurrence of three phase fault on the bus and clearance of the

fault within a short period of time (up to 100 ms) does not represent a large

risk to the power system in terms of transient stability. For this reason, it is

necessary to ensure that generators operating in the electric power system

have a critical clearing time higher than 100 ms.

The electric power system instability can be interpreted using

various methods depending on the system configuration and operational

81

status. Traditionally, the question of stability has been connected to maintain

synchronous operations. The production of electricity is secured primarily

using synchronous generators. For this reason, it is important to secure their

synchronism and therefore the question of stability has mainly hinged on the

transient stability of synchronous machinery and on the relationship between

the active power and the rotor angle of the generator. Electric power system

instability can also appear even if synchronous operation of the generators is

not interrupted (Eleschova et al 2010).

On 1st July 1957, TNEB came into being and has remained as the

energy provider and distributor all these years. During the period, the

Government has extended the electrical network to all villages and towns

throughout the state. After fifty three years of journey, on 1st November

2010, TNEB restructured itself into TNEB Limited, Tamil Nadu Generation

and Distribution Corporation (TANGEDCO) Limited and Tamil Nadu

Transmission Corporation (TANTRANSCO) Limited. Ministry of

Power, Government of India, has planned to supply “Power for all by 2012”.

To achieve this, TANGEDCO Limited is making progress in generation and

distribution sector. TNEB limited has completed the electrification of all

villages and towns. To satisfy the energy needs of the state, TANGEDCO

Limited has installed generating stations of capacity 10, 214 MW which

includes state, central share and independent power producers. Besides, the

state has installations in renewable energy sources like windmill up to 5400

MW. Due to the astronomical increase in the energy demand in future, the

state has proposed new generation projects for the next five years.

TANTRANSCO Limited has a total of 1309 substations with

HT(High Tension) and EHT(Extra High Tension) lines to a length of 1.69

lakh km. The voltage levels in use in TANTRANSCO Limited are 400 kV,

82

230 kV, 110 kV and 66 kV. In order to evacuate bulk power from one region

to another region, there is more scope for enhancing the transmission

capability to 765 kV level and setting up of 800 kV High Voltage DC system.

The Government of India has approved nondiscriminatory open access for the

transmission system. The Government of Tamil Nadu has also permitted third

party sale of power produced by independent power producer (IPPs), captive

power plants (CPPs) and other private power producers through short term

intra-state open access to HT consumers within Tamil Nadu. TANGEDCO

has a consumer base of about 212.76 lakh consumers. 100% rural

electrification has been achieved. Per Capita consumption of Tamil Nadu is

1080 Units. To achieve reliable and quality power supply, and to minimize

the loss of energy, Ministry of Power, Government of India, has launched the

restructured APDRP (Accelerated Power Development and Reform Program)

scheme under the eleventh five year plan (www.cea.nic.in\reports\planning\

power_scenario.pdf.).

4.3 PROBLEM STATEMENT

Load growth, equipment outage, unplanned maintenance, aging of

substation equipment and increasing stress on grid leads poor voltage profile,

network overloading, increase in losses and thermal damage of the equipment.

A better method to improve the utilization ratio of the existing electric

network is expected. As the awareness of environmental protection is

increasing, it becomes critical that the existing transmission and distribution

resources can be fully utilized. As the system network grows in complexity

and load consumption continues to increase, interface loading conditions are

expected to worsen, resulting in more acute transient problem and may lead to

disasters and blackouts, which have not only huge commercial loss, but also

needs high restoring time. Here, Tamil Nadu 400 kV transmission network

83

and nearby interconnected 400 kV substations (Trivendrum, Chittoor etc.) are

considered for the study. This has prompted the need to consider broad

utilization of FACTS technology, including SVC and STATCOM. SVC and

STATCOM can be inserted independently in the TNEB system to achieve

control function including enhancement of the transient stability using

MiPower simulation software.

4.4 GENERAL REPRESENTATION OF SVC AND STATCOM

The representation of both SVC and STATCOM are discussed in

sections 2.5 and 3.4 respectively. The SVC and STATCOM model used here

is shown in Figures 4.1 and 3.2 respectively.

4.5 TNEB 400 kV TRANSMISSION NETWORK

Tamil Nadu 400 kV transmission network and nearby

interconnected substations (Trivendrum, Chittoor etc.) are considered for the

purpose of identifying the critical clearing time at all 400 kV buses to ensure

rapid fault clearance and thereby maintaining the transient stability. The

system model includes the representation of thirty four 400 kV buses, eleven

generators, eleven transformers etc. Transmission network (only 400 kV) of

TNEB is modeled using MiPower. Transmission line parameters of various

conductors (Moose and Zeebra) are used as per manufacturer’s standard. Line

length and type of conductor are considered as per information available in

the Power Grid and Ministry of Power website. The generators directly

connected to TNEB 400 kV transmission network are modeled along with the

generator step-up transformers. The generator, AVR, TG and transformer data

are given in the Tables 4.1 to 4.4 respectively. The block diagrams of type1

AVR and TG are depicted in Figures 4.2 and 4.3 respectively.

84

Figure 4.1 Modeling of SVC

N[9]

N[8]N[6]N[5]N[12]

N[4]N[13]N[2]

N[3]

+

N[7]

N[10]

T=0.003

K = 1

K=2.23 K = 1.04

T=0.2 T=0.003Max=0.529

Min=-0.278

Max=1

Min=-1

Vref[1]

SVC

Q Supply

85

Table 4.1 Generator data in TNEB 400 kV transmission network

Generator NameRated

MVA

AVR

TypeTG No.

Model

type

Rated

Voltage(kV)P Schedule Q min Q max

Droop

Constant

Neyveli-1 247 1 1 2 11 163 0 130.03 4

Neyveli-Ext 295 1 1 2 11 225 0 156.60 4

Kudamkulam 1111.11 1 1 2 21 850 0 484.32 4

Tuticorin-ST4 555.56 1 1 2 21 450 0 242.17 4

Tuticorin 555.56 1 1 2 21 450 0 242.17 4

Ind-Bharath 666.67 1 1 2 21 600 0 290.60 4

Coastal Ene 666.67 1 1 2 21 510 0 290.60 4

Mettur 555.56 1 1 2 21 450 0 242.17 4

Chennai JV 733.33 1 1 2 21 637.5 0 319.64 4

North Chennai 666.67 1 1 2 21 510 0 290.60 4

North Chennai

ABAN 666.67 1 1 2 21 510 0 290.60 4

86

Figure 4.2 Block diagram of type1 AVR

-

-

+

+

-

87

Table 4.2 Type1 AVR data in TNEB 400 kV transmission network

Variable Description Data

Trec Input rectifier time constant in s 0.05

Ka Amplifier gain 200

Ta Amplifier time constant in s 0.1

Ke Exciter gain -0.05

Te Exciter time constant in s 0.5

Kf Regulator stabilizing circuit gain 0.05

Tf Regulator stabilizing circuit time constant 0.5

Vse1 Saturation function at 0.75 times maximum

field voltage

0.06

Vse2 Saturation function at maximum field voltage 0.3

Vrmax Maximum amplifier voltage 1

Vrmin Minimum amplifier voltage -1

Efdmax Maximum field voltage 4.3

Efdmin Minimum field voltage 0

88

Figure 4.3 Block diagram of TG

++

++ +

+

+

-

+

+

-

89

Table 4.3 TG data in TNEB 400 kV transmission network

Variable Description Data

Droop 0.04

Pmax Maximum power limit 1.1

Pmin Minimum power limit 0

Cmax Rate of valve opening 0.1

Cmin Rate of valve closing - 1

K1 + K2 Power extraction at HP turbine 0.276

K 3 + K 4 Power extraction at IP turbine 0.324

K 5 + K 6 Power extraction at LP turbine 0.4

T1 Phase compensation 1 0.1

T2 Phase compensation 2 0.03

T3 Servo time Constant 0.4

Thp HP section Time constant in s 0.26

Trh Reheat section Time constant in s 10

Tlp LP section Time constant in s 999

Tip

IP section Time constant (including re-

heater) in s0.5

90

Table 4.4 Transformer data in TNEB 400 kV transmission network

Sl.

No.Bus Name

MVA

Rating

Primary

Voltage

(kV)

Secondary

Voltage

(kV)

Zp.u.Taps(Min

and Max)

OCTC

(Taps)

1 Neyveli-1 250 400 11 0.14 1 and 9 OCTC(5)

2 Neyveli-Ext 300 400 11 0.14 1 and 9 OCTC(5)

3 Kudamkulam 1200 400 21 0.14 1 and 9 OCTC(5)

4Tuticorin-

ST4560 400 21 0.14 1 and 9 OCTC(5)

5 Tuticorin 560 400 21 0.14 1 and 9 OCTC(5)

6 Ind-Bharath 670 400 21 0.14 1 and 9 OCTC(5)

7 Coastal Ene 670 400 21 0.14 1 and 9 OCTC(5)

8 Mettur 560 400 21 0.14 1 and 9 OCTC(5)

9 Chennai JV 740 400 21 0.14 1 and 9 OCTC(5)

10North

Chennai670 400 21 0.14 1 and 9 OCTC(5)

11

North

Chennai

ABAN

670 400 21 0.14 1 and 9 OCTC(5)

Single line diagram of the TNEB 400 kV transmission network

system is shown in Figure A 1.2.

91

4.6 RESULTS WITH DISCUSSIONS

Critical clearing time is the principal criterion for the assessment of

transient stability. Fault should be cleared well within the critical clearing

time to maintain the transient stability of the power system, even while

critical clearing time is not the sufficient criterion to evaluate the transient

stability when considering various scenarios of severe fault occurrence in the

power system. The oscillation of generators is basically measured with

respect to infinite bus / grid which are represented as slack bus. The

oscillation level of the generator depends on the disturbance severity and its

time duration. If the generator oscillation goes beyond 180 degrees, the

generator loses its synchronism and will not be able to regain the steady state.

That is, the generator will not be synchronous with rest of the system. Hence,

180 degrees is standardized as the transient stability limit. Since a severe

fault (three phase fault) is assumed, the ability of the generator to remain in

synchronism depends on the fault clearing time. The time to clear the fault is

slowly increased up to the critical clearing time with the help of SVC and

STATCOM.

The effect of SVC and STATCOM on the transient stability of the

power system is analyzed by creating three phase to ground fault at various

buses using MiPower through the critical clearing time. By placing the SVC

and STATCOM independently at Sholinganallur, Neyveli, Karaikudi and

Salem 400 kV substations, the fault clearing time is increased up to the

critical clearing time. Critical clearing time for the various buses with SVC at

the 400 kV substations, are tabulated in Table 4.5 and compared with critical

clearing time without SVC.

92

Table 4.5 Critical clearing time of various 400 kV buses with and

without SVC

Bus

No.Bus Name

Bus

Description

Critical clearing time in ms

Without

SVC

SVC at

Sholinganallur

SVC at

Neyveli

SVC at

Karaikudi

SVC at

Salem

402 ALAM_4 Alamanthi 120 148 145 149 149

404 SVC_4 SVC 200 208 209 208 208

405 MLKTYR Malekuttaiyur 200 225 220 225 225

406 SHLGNR Sholinganallur 260 268 268 268 268

407 PONDI_4 Pondicherry 550 565 560 585 565

410 TRCHY_4 Trichy 250 290 295 290 290

411 KARKDI Karaikudi 180 190 190 188 188

412 MDRAI_4 Madurai 140 149 149 148 148

415 KYTHR_4 Kaythar 180 185 200 188 185

416 TM_WND TM_Wind 170 172 180 172 170

417 TRNVL_4 Tirunelveli 120 125 128 145 125

419 TRNDRM Trivandrum 190 700 800 800 800

420 TRVLM_4 Tiruvelam 170 250 260 250 260

421 SNGRPT Singarpet 220 220 225 228 228

422 PGLR_4 Pugalur 180 188 187 188 188

423 SALEM_4 Salem 170 172 175 170 170

424 UDMLPT Udumalpet 180 188 189 188 188

426 ARSR_4 Arasur 290 290 310 310 310

427 KRMDI_4 Karmadai 480 488 488 488 488

428 MVTPHA Muvattupuzha 310 315 320 310 310

429 N_TRCHR N_Trichur 310 310 310 325 310

431 HOSUR_4 Hosur 410 410 430 430 410

Total 5280 6056 6238 6253 6056

Critical clearing time for the various buses with STATCOM at the

400 kV substations, are tabulated in Table 4.6 and compared with critical

clearing time without STATCOM.

93

Table 4.6 Critical clearing time of various 400 kV buses with and

without STATCOM

Bus

No.Bus Name Bus Description

Critical clearing time in ms

Without

STATCOM

STATCOM

at

Sholinganallur

STATCOM

at

Neyveli

STATCOM

at

Karaikudi

STATCOM

at

Salem

402 ALAM_4 Alamanthi 120 149 149 150 152

404 SVC_4 SVC 200 215 208 210 209

405 MLKTYR Malekuttaiyur 200 225 225 230 228

406 SHLGNR Sholinganallur 260 275 273 270 272

407 PONDI_4 Pondicherry 550 565 565 580 572

410 TRCHY_4 Trichy 250 290 300 295 300

411 KARKDI Karaikudi 180 190 195 185 189

412 MDRAI_4 Madurai 140 145 146 149 145

415 KYTHR_4 Kaythar 180 185 188 210 185

416 TM_WND TM_Wind 170 175 175 180 175

417 TRNVL_4 Tirunelveli 120 120 130 150 125

419 TRNDRM Trivandrum 190 750 900 850 850

420 TRVLM_4 Tiruvelam 170 240 250 260 250

421 SNGRPT Singarpet 220 225 230 230 230

422 PGLR_4 Pugalur 180 190 190 195 190

423 SALEM_4 Salem 170 175 170 172 170

424 UDMLPT Udumalpet 180 185 190 185 185

426 ARSR_4 Arasur 290 300 290 290 310

427 KRMDI_4 Karmadai 480 490 490 495 490

428 MVTPHA Muvattupuzha 310 315 315 310 310

429 N_TRCHR N_Trichur 310 310 310 310 310

431 HOSUR_4 Hosur 410 420 425 425 430

Total 5280 6134 6314 6331 6134

Impact of FACTS device on the transient stability enhancement is

analyzed with the help of critical clearing time. Critical clearing time at

Alamanthi 400 kV substation without FACTS is 120 ms. Considering the

relay delay time (40 ms) and circuit breaker opening time (30 ms) in the

Alamanthi substation, the relay and circuit breaker fails to isolate the fault

during N-1 contingency ( i.e during struck breaker operation - after struck

breaker, all other breaker should open to isolate the fault) within the critical

clearing time. However, with FACTS installation at various buses, the critical

94

clearing time is increased from 120 ms to around 150 ms. This increased

cushion of 30 ms (1.5 cycle) will maintain the stability for three phase fault at

Alamanthi even for N-1 contingency.

The swing curves of generators in Neyveli-1, Neyveli-Ext,

Kudamkulam, Tuticorin-ST4 for a three phase fault at Alamanthi 400 kV

substation with and without SVC are presented here.

Figure 4.4 Swing curves of generators without SVC

The swing curves of generators in Neyveli-1, Neyveli-Ext,

Kudamkulam, Tuticorin-ST4 for 120 ms duration of a three phase fault at

Alamanthi 400 kV substation without SVC are shown in Figure 4.4. If the

95

fault clearing time exceeds 120 ms, the oscillations of generators exceed

180 degrees.

Figure 4.5 Swing curves of generators with SVC at Sholinganallur

SVC at Sholinganallur, increases the critical clearing time from

120 ms to 148 ms for a three phase fault at Alamanthi 400 kV substation. The

swing curves of generators in Neyveli-1, Neyveli-Ext, Kudamkulam,

Tuticorin-ST4 for 148 ms duration of a three phase fault at Alamanthi 400 kV

substation with SVC at Sholinganallur are shown in Figure 4.5. If the fault

clearing time exceeds 148 ms, the oscillations of generators exceed

180 degrees.

96

Figure 4.6 Swing curves of generators with SVC at Neyveli

SVC at Neyveli, increases the critical clearing time from 120 ms to

145 ms for a three phase fault at Alamanthi 400 kV substation. The swing

curves of generators in Neyveli-1, Neyveli-Ext, Kudamkulam, Tuticorin-ST4

for 145 ms duration of a three phase fault at Alamanthi 400 kV substation

with SVC at Neyveli are shown in Figure 4.6. If the fault clearing time

exceeds 145 ms, the oscillations of generators exceed 180 degrees.

97

Figure 4.7 Swing curves of generators with SVC at Karaikudi

SVC at Karaikudi, increases the critical clearing time from 120 ms

to 149 ms for a three phase fault at Alamanthi 400 kV substation. The swing

curves of generators in Neyveli-1, Neyveli-Ext, Kudamkulam, Tuticorin-ST4

for 149 ms duration of a three phase fault at Alamanthi 400 kV substation

with SVC at Karaikudi are shown in Figure 4.7. If the fault clearing time

exceeds 149 ms, the oscillations of generators exceed 180 degrees.

98

Figure 4.8 Swing curves of generators with SVC at Salem

SVC at Salem, increases the critical clearing time from 120 ms to

149 ms for a three phase fault at Alamanthi 400 kV substation. The swing

curves of generators in Neyveli-1, Neyveli-Ext, Kudamkulam, Tuticorin-ST4

for 149 ms duration of a three phase fault at Alamanthi 400 kV substation

with SVC at Salem are shown in Figure 4.8. If the fault clearing time exceeds

149 ms, the oscillations of generators exceed 180 degrees.

Without FACTS, the critical clearing time at Trichy 400 kV

substation is 250 ms. With FACTS, this is improved to around 300 ms. This

99

will be certainly helpful to maintain the stability, when the backup protection

isolates the fault due to primary relay failure.

Similarly at all other buses, with FACTS devices the critical

clearing time has increased or maintained for three phase to ground faults.

The total critical clearing time of the system has significantly improved with

the help of FACTS devices.

4.7 CONCLUSION

The TNEB 400 kV transmission network is modeled using

MiPower. The critical clearing time is found at various 400 kV buses of

TNEB system and is tabulated. The proposed SVC and STATCOM model is

placed independently at Sholinganallur, Neyveli, Karaikudi and Salem

400 kV substations to identify the critical clearing time of various 400 kV

buses to ensure the rapid fault clearance and thereby maintaining the transient

stability. The critical clearing time increases appreciably after placing the

SVC and STATCOM independently in the TNEB 400 kV transmission

network. This is shown in Tables 4.5 and 4.6. It is evidenced that the transient

stability of the system has improved.

The result obtained in the TNEB system is valid only for the

present scenario. The study should be repeated as and when the considerable

capacity of new generation (> 500 MW) is added.