Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 1 of 63
Chapter 3 Structure Plans and Appendix 2 Decisions
Structure Plans – General
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Wilson David Jolly
1244.001 3 Structure Plans
Support in part
Undertake a Structure Planning exercise for the area surrounding Temple View village. Amend Volume 1 – Section 3 – Structure Plans as follows: Add a new section 3.8 – Temple View with chapter headings of a similar nature to those that apply to Peacocke, Rototuna, Rotokauri and Ruakura as follows: Introduction Vision Objectives and Policies Structure Plan components
Reject The undertaking a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.
WJ & MR Laverty (Feathers Planning Limited)
FS8.003
Support Reject
Further submissions 8.003, 9.002 and 180.009 are rejected as 1244.001 have been rejected.
WR & JM FALCONER (Feathers Planning Limited)
FS9.002
Support Reject
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.009
Support Reject
Simon Dyke Farms Ltd
1245.001 Support in part
Undertake a Structure Planning process for the area surrounding Temple View village. Amend Volume 1 – Section 3 – Structure Plans as follows: Add a new section 3.8 – Temple View with chapter headings of a similar nature to those that apply to Peacocke, Rototuna, Rotokauri and Ruakura as follows: Introduction Vision Objectives and Policies Structure Plan components
Reject The undertaking a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.
WJ & MR Laverty (Feathers Planning Limited)
FS8.002
Support Reject
Further submissions 8.002, 9.003 and 180.01 are rejected as 1245.001 have been rejected. WR & JM FALCONER (Feathers Planning Limited)
FS9.003
Support Reject
The Church of FS180.01 Support Reject
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 2 of 63
Jesus Christ of Latter Day Saints Trust Board
Jon Francis & Elizabeth Howie Jarvis
1254.001 Support in part
Undertake a Structure Plan exercise for the area surrounding Temple View village. Amend Volume 1 – Section 3 – Structure Plans as follows: Add a new section 3.8 – Temple View with chapter headings of a similar nature to those that apply to Peacocke, Rototuna, Rotokauri and Ruakura as follows: Introduction Vision Objectives and Policies Structure Plan components
Reject The undertaking a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.
WJ & MR Laverty (Feathers Planning Limited)
FS8.001
Support Reject
Further submissions 8.001, 9.004 and 180.011 are rejected as 1254.001 have been rejected.
WR & JM FALCONER (Feathers Planning Limited)
FS9.004
Support Reject
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.011
Support Reject
W.J. & M.R. Laverty
313.001 Support in part
Include a Structure Plan for Temple View in Section 3- Structure Plans as set out in the submission.
Reject The undertaking a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.007
Support Reject Further submission 180.007 is rejected as 313.001 has been rejected.
W.R & J.M Falconer
360.001 Support in part
A Structure Plan for Temple View is developed for inclusion in Section 3 - Structure Plans.
Reject The idea of undertaking a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.008
Support Reject Further submission 180.008 is rejected as 360.001 has been rejected.
The Church of Jesus Christ of Latter Day Saints Trust Board
1201.001 Support in part
Amend Chapter 3 Structure Plans to include Temple View via a formal structure planning exercise as set out in the submission.
Reject The undertaking a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.
WJ & MR Laverty (Feathers Planning Limited)
FS8.004
Support Reject
Further submission 8.004 and 9.001 are rejected as submission 1201.001 has been rejected. WR & JM FALCONER (Feathers Planning Limited)
FS9.001
Support Reject
Meiana Jenelle Nin
FS27.002
Oppose Accept Further submission 27.002 is accepted as submission 1201.001 has been rejected.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 3 of 63
Rakaipaka Puriri FS275.001
Oppose Reject This submission is not related to the matters contained in 1201.001.
Jodhi Ponga FS279.001
Support Reject
Further submission 279.001 and 284.001 are rejected as submission 1201.001 has been rejected. Temple View Heritage Society
FS284.001
Support Reject
Robert W. Belbin 291.003 Support in part
Include a section for Temple View within Rule 3.0 Structure Plans. Reject The undertaking a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.005
Support Reject
Further submission 180.005 and 180.006 are rejected as submission 291.003 has been rejected. The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.006
Support Reject
The Church of Jesus Christ of Latter Day Saints Trust Board
1201.002 Support in part
Amend Appendix 2 Structure Plans to include Temple View as a structure plan area.
Reject
The undertaking of a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.This would involve a separate variation or plan change to the district plan.
Meiana Jenelle Nin
FS27.001
Oppose Accept Further submission 27.001 is accepted as submission 1201.002 has been rejected
Rakaipaka Puriri FS275.001
Oppose Reject This submission is not related to the matters contained in 1201.002.
Jodhi Ponga FS279.001
Support Reject
Further submission 279.001 and 284.002 are rejected as submission 1201.002 has been rejected Temple View Heritage Society
FS284.002
Support Reject
Wilson David Jolly
1244.002 Support in part
Amend Volume 2, Appendix 2 – Structure Plans Locality Guide by adding an additional legend to depict the Temple View Structure Plan. Further amendments are required by adding additional Figures 2-20, 2-21 and 2-22 as required. Any other consequential and related amendments to other rules as required.
Reject The undertaking of a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.This would involve a separate variation or plan change to the district plan.
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.09
Support Reject Further submission 180.09 is rejected as submission 1244.002 has been rejected
Simon Dyke Farms Ltd
1245.002 Support in part
Amend Volume 2, Appendix 2 – Structure Plans Locality Guide by adding an additional legend to depict the Temple View Structure Plan. Further amendments are required by adding additional Figures 2-20, 2-21 and 2-22 as required. Any other consequential and related amendments to other rules as required.
Reject The undertaking of a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.This would involve a separate variation or plan change to the district plan.
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.091
Support Reject Further submission 180.091 is rejected as submission 1244.002 has been rejected
Jon Francis & Elizabeth Howie Jarvis
1254.002 Support in part
Amend Volume 2, Appendix 2 – Structure Plans Locality Guide by adding an additional legend to depict the Temple View Structure Plan. Further amendments are required by adding additional Figures 2-20, 2-21 and 2-22 as required.
Reject The undertaking of a structure planning exercise for the Temple View area is supported. However, such a process must be undertaken in an integrated and collaborative manner that is best achieved through a separate First Schedule process.This would involve a separate variation or plan change to the district plan.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 4 of 63
Any other consequential and related amendments to other rules as required.
Hounsell Holdings Ltd
1104.003 Oppose Figures relating to the Rotokauri Structure Plan (Figure 3.6.2a, b, c, d, e, f, and g) should be included in the Appendix 2.
Reject Figures 3.6.2a to 3.6.2g are directly related to the structure plan text and their placement within chapter 3 will assist in the clarity and understanding and usability of the Plan. It is not considered appropriate to relocate the figures to Appendix 2 as part of the Rotokauri Structure Plan.
Porter Properties Ltd
1164.003 Oppose Figures relating to the Rotokauri Structure Plan (Figure 3.6.2a, b, c, d, e, f, and g) should be included in the Appendix 2.
Reject Figures 3.6.2a to 3.6.2g are directly related to the structure plan text and their placement within chapter 3 will assist in the clarity and understanding and usability of the Plan. It is not considered appropriate to relocate the figures to Appendix 2 as part of the Rotokauri Structure Plan.
Hamilton JV Investment Company Ltd
1170.003 Oppose Figures relating to the Rotokauri Structure Plan (Figure 3.6.2a, b, c, d, e, f, and g) should be included in the Appendix 2.
Reject Figures 3.6.2a to 3.6.2g are directly related to the structure plan text and their placement within chapter 3 will assist in the clarity and understanding and usability of the Plan. It is not considered appropriate to relocate the figures to Appendix 2 as part of the Rotokauri Structure Plan.
Hounsell Holdings Ltd
1104.004 Appendix 2 Structure Plans
Oppose (Figures 3.6.2a, 3.6.2b, 3.6.2c, 3.6.2d, 3.6.2e, 3.6.2f, and 3.6.2g relating to the Rotokauri Structure Plan should be included in the Appendix 2.
Reject Figures 3.6.2a to 3.6.2g are directly related to the structure plan text and their placement within chapter 3 will assist in the clarity and understanding and usability of the Plan. It is not considered appropriate to relocate the figures to Appendix 2 as part of the Rotokauri Structure Plan.
Porter Properties Ltd
1164.004 Oppose Figures 3.6.2a, 3.6.2b, 3.6.2c, 3.6.2d, 3.6.2e, 3.6.2f, and 3.6.2g relating to the Rotokauri Structure Plan should be included in the Appendix 2.
Reject Figures 3.6.2a to 3.6.2g are directly related to the structure plan text and their placement within chapter 3 will assist in the clarity and understanding and usability of the Plan. It is not considered appropriate to relocate the figures to Appendix 2 as part of the Rotokauri Structure Plan.
Hamilton JV Investment Company Ltd
1170.004 Oppose Figures 3.6.2a, 3.6.2b, 3.6.2c, 3.6.2d, 3.6.2e, 3.6.2f, and 3.6.2g relating to the Rotokauri Structure Plan should be included in the Appendix 2.
Reject Figures 3.6.2a to 3.6.2g are directly related to the structure plan text and their placement within chapter 3 will assist in the clarity and understanding and usability of the Plan. It is not considered appropriate to relocate the figures to Appendix 2 as part of the Rotokauri Structure Plan.
Structure Plan 3.1 Purpose
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Deborah June Fisher
282.001 3.1 Purpose Oppose Prior to a Structure Plan being included in the District Plan require the following: 1. Structure Plans to publicly provide an Environmental Impact Report prior to their inclusion in the District Plan. 2. Details of proposed adverse environment effects and the level of those effects. 3. Evidence of Open Consultation with anyone potentially affected by a Structure Plan. 4. Removal of current structure plans from the Proposed District Plan that has not met these conditions. 5. Require Industrial Structure Plans to provide a "Noise Management Plan" similar to that of Appendix 1-5-21 prior to inclusion.
Reject The structure plans (apart from the Ruakura Structure Plan) included in the Plan have all passed through the 1st
Schedule RMA process and outline the future growth and development expectations of the city in line with the PRPS and HUGS. The structure plans included within the Plan have been transferred from the Operative District Plan (ODP). Prior to their adoption within the ODP, they were all processed under the first schedule of the RMA, 1991 (Variation 18 – Rotokauri, Variation 12 – Rototuna and Variation 14 – Peacockes). As such and in accordance with the Act, each variation was subject to extensive public consultation and input, including the preparation of a number of background analysis and specialist reports covering a wide range of topics such as ecological and landscape assessments, roading and infrastructure. As such, full consideration was been given to aspects such as the type and location of land uses with the aim of identifying the optimum spatial pattern taking into account the efficient use of land, environmental protection, amenity, the need to support and protect appropriate existing land use and opportunities for economic development. The structure plans have been retained in the plan as it would reduce the effectiveness of the Plan in terms of achieving its stated objectives and policies if they were removed
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.001
Oppose Accept FS180.001 is accepted as submission 282.001 has been rejected.
Future Proof Implementation Committee
608.005 Support Future Proof supports 3.1 Purpose and 3.2 Principles set out in the Structure Plan chapter and seeks the retention of those sections as notified.
Accept in Part
This submission is in support of 3.1 and 3.2. and is accepted in part as the provisions that the submission seeks to retain have been amended in response to other submissions See Tracked Changes for Chapter 3.
Lynette Joyce Williams
1050.001 Support Retain the flow chart in 3.1 Purpose of Structure Plans. Accept in Part
These submissions support the flow chart (3.1 a). They are accepted in part as the provision that the submissions seek to retain has been amended in response to other submissions See Tracked Changes for Chapter 3.
Niall Baker 1158.001 Support Retain the flow chart in section 3.1 (Structure Plan Purpose).
Accept in Part
Waikato Regional Council
714.004 Support in part
3.1 Purpose (Structure Plans). Amend the diagram in 3.1a) to include reference to Strategic Framework objectives and policies.
Accept This submission supports 3.1. The proposed amendments will improve the:
Internal consistency of the Plan
Clarity of the Plan for users See Tracked Changes for Chapter 3
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 5 of 63
Chedworth Properties Ltd
1171.006 Support in part
Supports intent of 3.1 d) (Structure Plans - Purpose) - seeks amendments, as set out in the submission in respect of the land use pattern, and recognising the need to provide for staging but in a way that recognises the uncertainties associated with long term growth.
Accept in Part
The submissions support 3.1 (Purpose). They are accepted in part as that part of the submission relating to:
3.1 d) ii and iii are accepted as this will improve the effectiveness of the Plan in achieving the objective of integrated planning.
3.1 d) v has been amendment in response to another submission
See Tracked Changes for Chapter 3.
Waikato-Tainui Te Kauhanganui Inc
771.010 Support in part
Amendments are sought, as set out in the submission, to the provisions in 3.1 (d) (Structure Plans Purpose) relating to the purpose of a Structure Plan in order to strengthen the policy in respect of the land use pattern and recognise the need to provide for staging but in a way that recognises the uncertainties associated with long term growth.
Tainui Group Holdings Ltd
913.007 Support in part
Retain the Purpose of the Structure Plan Chapter with amendments to include reference to future land use patterns, staging of development and fiscal/financial/commercial feasibility, as set out in the submission.
William Cornelis Engelander
FS160.001
Oppose Reject The further submissions are not related to the matters contained in 913.007.
James Hely and Heather Montgomerie -
FS161.001
Oppose
New Zealand Transport Agency
924.009 Support in part
Amend 3.1 d) v. to read as follows "Identifying the financial feasibility of the development from a Council, infrastructure provider and landowner perspective".
Accept The submission supports 3.1 and the amendments will assist in the clarity, understanding and administration of the Plan.
Tainui Group Holdings Limited
FS196.015
Support Accept FS196.015 is accepted as submission 924.009 has been accepted.
Fonterra Co-operative Group Ltd
1200.007 Oppose Amend 3.1g) (Structure Plans - Purpose) to recognise that future structure plans or similar approaches could be promoted through a resource consent process.
Reject In accordance with the provisions of the RMA 1991, the resource consenting process is not the appropriate method to advance future structure plans or strategic planning frameworks for a particular area or growth cell.
Future Proof Implementation Committee
FS181.003
Oppose Accept FS181.003 and 270.026 are accepted as 1200.007 has been rejected.
New Zealand Transport Agency
FS270.026
Oppose Accept
The Adare Company Ltd
FS272.032
Support Reject FS272.032 is rejected as submission 1200.007 has been rejected.
3.2 Principles
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Future Proof Implementation Committee
608.006 3.2 Principles
Support Supports the retention of the purpose and principles set out in the Structure Plan chapter. Accept in
Part
The submissions support 3.2 and are accepted in part as amendments have been made in response to other submissions See Tracked Changes for Chapter 3. New Zealand
Transport Agency 924.010 Support Retain 3.2 Principles as notified.
Deborah June Fisher
282.020 Support in part
Require structure plans to identify potential effects, positive and negative on the surrounding environment and how these will be mitigated or managed.
Reject In accordance with the RMA and the principles in 3.2, all structure plans would need to demonstrate an understanding of the surrounding context including an understanding of the potential effects that the proposals may have on the surrounding area.
Fonterra Co-operative Group Ltd
1200.008 Support in part
Amend 3.2 (Structure Plan Principles) to also refer to other appropriate strategic planning methods.
Reject In accordance with the provisions of the RMA 1991, the resource consenting process is not considered to be the appropriate method to advance future structure plans or strategic planning frameworks for a particular area or growth cell.
Waikato Regional Council
714.005 Support in part
a) Add an introductory paragraph explaining how the principles are to be taken account of and implemented. b) Add a principle to 3.2(a) as follows: 'How existing values, and valued features of the area (including
Accept in Part
The submission supports 3.2 and is accepted in part as that part of the submission relating to:
Changes to the introductory paragraph have been rejected as the current wording is considered appropriate.
The addition of a new principle to 3.2 a) is accepted as the amendments will improve the effectiveness of the Plan in terms of achieving its stated objective for structure plans
See Tracked Changes for Chapter 3.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 6 of 63
amenity, landscape, natural character, ecological and heritage values, water bodies, high class soils and view catchments), will be managed'
Lynette Joyce Williams
1050.002 Support in part
Principles - Structure Plans - 3.2 a) i. - Replace ‘any land-use constraints and opportunities’ within this paragraph with ‘any land-use considerations’. Support
in Part
The terminology used is consistent with the approach to planning in general and is considered appropriate in the context of chapter 3. In order to ensure an area is properly understood it is neccessary for an analysis to be undertaken of the various strengths, weaknesses, opportunities and constraints that exist. This analysis is then used to inform the development of the plan itself. Furthermore, the Plan actively promotes the preservation and enhancement of heritage sites both built and natural in a number of ways and through the provisions of chapter 19 in accordance with the RMA.
Niall Baker 1158.002 Support in part
3.2 Principles 3.2a) i. delete the text "any land-use constraints and opportunities" and replace with ‘any land-use considerations’.
3.3 Objectives and Policies - General
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Future Proof Implementation Committee
608.007 3.3 Objectives and Policies Structure Plans
Support Retain the Objectives and Policies under 3.3 Structure Plans Accept in Part
This submission is in support of 3.3. It is accepted in part as the provisions that the submission seeks to retain have been amended in response to other submissions See Tracked Changes for Chapter 3.
Chedworth Properties Ltd
1171.007 Support in part
3.3 Objectives and Policies Structure Plans - amend introductory sentence as set out in submission by deleting the work "must" and replacing with 'shall'; and to incorporate the concept of 'general accordance'. Accept in
Part
The introductory paragraph to Rule 3.3 I has been amended so as to not be in conflict with the RMA and that consent applications “consider” the relevant objectives and policies See Tracked Changes for Chapter 3. Tainui Group
Holdings Ltd 913.008 Support in
part Amend the introduction for 3.3 Objectives and Policies Structure Plans by deleting the word 'must' and replace with 'shall' and add the word 'general' as set out in the submission.
William Cornelis Engelander
FS160.001
Oppose Reject
Further submissions 160.001 and 161.001 are not related to the matters contained in 913.008. James Hely and Heather Montgomerie -
FS161.001
Oppose Reject
New Zealand Transport Agency
FS270.018
Oppose Reject FS270.018 is rejected as 913.008 has been accepted in part.
PRS Planning Services Limited
929.012 Oppose Amend the introductory paragraph to Rule 3.3 (Objectives and Policies, Structure Plans) to be consistent with that used in Rule 2.2 (as sought to be amended by this submission).
Accept The introductory paragraph to Rule 3.3 is amended so as to not be in conflict with the RMA and that consent applications “consider” the relevant objectives and policies This issue has been submitted on in other chapters of the Plan, for example chapter 2 (Strategic Framework). In line with the approach taken there, it is accepted that the introduction paragraph set a higher threshold than s104D of the RMA, 1991 and it is appropriate to amend the rule so that all consents within a structure plan area ‘consider where relevant’ the objectives and policies of the Plan See Tracked Changes for Chapter 3.
McCracken Surveys Limited
1206.013 Oppose That the introductory sentence to Rule 3.3 is amended as follows: “Any discretionary or non‐complying activity should not be contrary to the objectives and policies below”.
Accept in Part
Amendments to the wording of the paragraph limiting the consideration of the objectives and policies to discretionary and non‐complying activities only is not supported as this would exclude controlled or restricted discretionary consents.
Property Council New Zealand
938.011 Oppose Amend 3.3 (Objectives and Policies - Structure Plans) so that “Any discretionary or non-complying activity should not be contrary to the objectives and policies below”.
Accept in Part
The introductory paragraph to Rule 3.3 is amended so as to not be in conflict with the RMA and that consent applications “consider” the relevant objectives and policies This issue has been submitted on in other chapters of the Plan, for example Chapter 2 (Strategic Framework). In line with the approach taken there, it is accepted that the introduction paragraph set a higher threshold than s104D of the RMA, 1991 and it is appropriate to amend the rule so that all consents within a structure plan area ‘consider where relevant’ the objectives and policies of the Plan See Tracked Changes for Chapter 3.
Andrew Yeoman FS2.012
Support Reject FS2.012 is not related to the matters contained in 913.011.
Peter John Findlay et al (Baruchel Developments
FS242.001
Support Accept in Part
FS242.001 and FS277.001 are accepted in part as 938.011 is accepted in part.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 7 of 63
Ltd)
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.001
Support
Waikato District Council
1211.006 Support in part
Include new objective and policy framework to support the establishment of business and industrial activities and development within structure plan areas that is also consistent with the industrial land allocation and the hierarchy of major commercial centres for Hamilton City provided for in the Proposed Regional Policy Statement.
Reject An additional set of objectives and policies to support the establishment of business and industrial activities is considered to be an unnecessary duplication of objectives and policies elsewhere in the Plan. The establishment of a centres hierarchy is an important theme and approach advocated by the Plan. Chapters 2 and 6 set the policy framework for this and in particular objective 2.2.4 and related policies promote the hierarchy of major commercial centres including the land allocation for industrial activity, consistent with the provisions of the PRPS. Whilst a Structure Plan is not a full zoning plan, it does provide overall direction and the expectation is that any proposal for a new business or industrial node within an existing or proposed structure plan will need to be aligned with the policy framework of the Plan and with documents such as HUGS, Future Proof and the PRPS.
Objective 3.3.1 and Policies a-d
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Waikato Regional Council
714.006 3.3.1 Objective and Policies
Support Retain the Objectives and Policies under 3.3.1 Structure Plans Accept in Part
This submission supports 3.3.1 and associated policies. It is only accepted in part as the provisions that the submission seeks to retain have been amended in response to other submissions See Tracked Changes for Chapter 3
Waikato-Tainui Te Kauhanganui Inc
771.011 Support Support the Structure Planning Objective 3.3.1 “Optimised, long-term, positive, environmental, economic social and cultural effects of Greenfield development”.
Accept This submission supports 3.3.1 and is accepted because there are no other submissions seeking amendments to the objective.
Deborah June Fisher
282.021 Support in part
Objective 3-3-1 to be amended to provide for any positive effect or adverse effects.
Reject The objective (3.3.1) has been formulated with the purpose of ensuring that cumulatively, development is carried out in a sustainable, responsible manner. Both the objective and policies have been developed to ensure adverse effects are avoided where possible.
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.003
Oppose Accept FS180.003 is accepted as submission 282.021 has been rejected.
New Zealand Transport Agency
924.011 Support in part
Amend Policy 3.3.1a to remove the word ‘general’ so that it reads 'in accordance with the relevant structure plan'. This should apply throughout the Plan.
Reject A structure plan does not represent a ‘blueprint’ for an area and is intended to guide and illustrate a possible future development pattern. The very nature of structure planning requires that there is a degree of flexibility built into the various elements and provisions. The use of the phrase ‘in general accordance’ is considered to be the correct approach acknowledging the uncertainty that comes with the implementation of longer term planning proposals.
Tainui Group Holdings Limited
FS196.014
Oppose
Accept Further submissions 196.014, 249.004 and 272.029 are accepted as submission 924.011 is rejected. Property Council New Zealand
FS249.004
The Adare Company Ltd
FS272.029
Mark Thomson Mitchell
709.001 Oppose Delete Policy 3.3.1b (Objectives and Policies - Structure Plans - housing densities)
Reject This submission is rejected because the deletion of these policies will reduce the effectiveness of the plan in terms of achieving compliance with PRPS. As reflected in the s42A reports the Plan has been drafted in response to the density targets of the Future Proof sub-regional growth management strategy and the PRPS. The strategic approach is a blend of compact settlement and concentrated growth. The Plan supports the fundamental shift in growth management from focusing largely on accommodating low-density suburban residential development to supporting a more compact urban form. It recognises the benefits of a compact urban environment. The PRPS sets out dwelling targets that will be achieved through management of lot sizes in existing residential areas and yield limits in structure plan areas. This objective and its policies set the manner in which residential densities targets are to be achieved and also set out the policy framework of controlling density to reinforce a compact and sustainable city.
Tainui Group Holdings Ltd
913.009 Support in part
Retain Structure 3.3.1 Objective and Policies with amendments to recognise that housing density targets will be achieved over time and will exclude roads and open space zoned land. Include an explanation of achieving higher densities (as set out in the submission).
Accept in Part
This submission is accepted in part as other submitters have also sought amendments to Policy 3.3.1b and collectively amendments have been made. See Tracked Changes for Chapter 3.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 8 of 63
Make amendments to policy for interim land use to allow low density residential development and to focus on future land use patterns rather than the long term vision.
The amendments will assist in aligning the policy framework with the RPS and will improve the internal consistency, understanding and administration of the Plan.
William Cornelis Engelander
FS160.001
Oppose
Reject Further submissions 160.001 and 161.001 are not related to the matters contained in 913.009. James Hely and Heather Montgomerie -
FS161.001
Oppose
The Adare Company Ltd
FS272.015
Support Accept in Part
FS272.015 is accepted in part as 913.009 is accepted in part.
PRS Planning Services Limited
929.013 Oppose 3.3.1Objectives and Policies - Structure Plans: Amend Policy 3.3.1bi. to reflect the intention that densities per hectare are to be achieved exclusive of roads by rewording (new text in brackets) as follows: '16 dwellings per hectare (excluding land to be vested as roads and reserve) for greenfield development.' Delete Policy 3.3.1b ii) in its entirety.
Accept in part
These submissions are accepted in part as other submitters have also sought amendments to Policy 3.3.1b and collectively amendments have been accepted (see Tracked Changes for Chapter 3). The amendments will assist in aligning the policy framework with the RPS and will improve the internal consistency, understanding and administration of the Plan.
Property Council New Zealand
938.012 Oppose Amend Policy 3.3.1b to read: “Housing densities in greenfield locations should achieve over time a gross density excluding roads of 16 dwellings per hectare”
Andrew Yeoman FS2.012
Support Reject FS2.012 is not related to the matters contained in 938.
Peter John Findlay et al (Baruchel Developments Ltd)
FS242.001
Support
Accept in Part
FS242.001 and FS277.001 are accepted in part as 938.012 is accepted in part. Peter John
Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.001
Support
Rotokauri Developments Ltd
1015.001 Oppose Amend Policy 3.3.1b to recognise average gross density targets can be achieved over time: 'Housing densities in greenfield locations should achieve over time an average gross density target, excluding roads and Open Space zoned land of 16 dwellings per hectare.'
Accept in Part
These submissions are accepted in part as other submitters have also sought amendments to Policy 3.3.1b and collectively amendments have been accepted (see Tracked changes for Chapter 3). The amendments will assist in aligning the policy framework with the RPS and will improve the internal consistency, understanding and administration of the Plan
Hounsell Holdings Ltd
1104.005 Oppose 3.3.1 (b) Objective and Policies - Structure Plans. Reword 3.3.1 (b) to include the word 'progressively' so that the first line reads "Housing densities should progressively achieve."
Barry Harris (Hamilton City Council)
1146.003 Support in part
Amend Policy 3.3.1b i., as set out in the submission, to reflect the intention that densities are an overall target for the Structure Plan Area as opposed to an absolute requirement for every individual development. Delete policy 3.3.1b ii.
Hamilton JV Investment Company Ltd
1170.005 Oppose 3.3.1 Objective and Policies - Structure Plans. Amend Policy 3.3.1bas set out in submission by rewording the first sentence "Housing densities should progressively achieve:" to ensure density is expressed as an intention to be met progressively and through a range of policy measures.
Chedworth Properties Ltd
1171.008 Support in part
Amend Policy 3.3.1 b and the Explanation to that policy (Structure Plans - Housing densities) as set out in submission to delete the words 'should achieve' and add the words 'shall seek to achieve over time the
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 9 of 63
following average gross density targets excluding roads and Open Space zoned land', and add explanatory text as set out in the submission.
McCracken Surveys Limited
1206.014 Oppose Amend Policy 3.3.1b to read: “Housing densities in greenfield locations should achieve over time a gross density excluding roads of 16 dwellings per hectare”
The Adare Company Ltd
482.004 Oppose Remove Policy 3.3.1(b) (Structure Plans - Housing densities) as it relates to greenfield development of the Peacocke area and rely on the Master Plan exercise and minimum net site area subdivision provisions for the Peacocke Character Areas to determine the appropriate density. Any consequential and/or similar amendments that would have the same effect.
ANG & SL Clarke 951.006 Oppose Exclude the Large Lot Residential Zone from Policy 3.3.1b (Objectives and Policies - Structure Plans - housing density)
Accept The submission supports 3.3 and is accepted in part as that part of the submission relating to:
Retention of 3.3.1 Objective is accepted Amendments to the policies; an increase in the required density from 16 to 18 dwellings per hectare for greenfield development; and the amendments to 3.3.1c are rejected because the amendments will reduce the effectiveness of the plan in terms of achieving compliance with Future Proof, HUGS and the PRPS.
Waikato District Council
1211.007 Support in part
Retain 3.3.1 Objective and Policies with amendments to: remove reference to the word 'general' in both 3.3.1 and elsewhere in the district plan; to increase the required density from 16 to 18 dwellings per hectare for greenfield development; to remove reference to development providing population density to support passenger transport and amend to support integrated and efficient passenger transport.
Accept in part
The submission supports 3.3 and is accepted in part as that part of the submission relating to:
Retention of 3.3.1 Objective is accepted Amendments to the policies; an increase the required density from 16 to 18 dwellings per hectare for greenfield development; and the amendments to 3.3.1c are rejected because the amendments will reduce the effectiveness of the plan in terms of achieving compliance with Future Proof, HUGS and the PRPS.
Objective 3.3.2 and Policies a-e
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Population Health, Waikato DHB
1273.004 3.3.2 Objective and Policies
Support Retain and adopt the Objectives and Policies under 3.3.2 Structure Plans as notified.
Accept in Part
This submission supports 3.3.2 and is accepted in part as amendments to the policies have been made in response to other submissions See Tracked Changes for Chapter 3
Waikato District Council
1211.008 Support in part
3.3.2 Objective and Policies - Structure Plans - Clarify at what stage and by whom social infrastructure will be provided.
Reject The clarification sought by the submitter is already provided for by the explanation text under objective 3.3.2. Social infrastructure (including libraries, pools and community halls) programmes are captured in both the Long Term and Annual Plans. Where development occurs outside of this programme, it is anticipated that the developer will bear the initial cost of infrastructure provision. The recovery of this cost is dependent on the specifics of each agreement entered into with Council, which may differ from project to project. Whilst there are a number of variables at play, delivery is ultimately dependent on the needs of an established resident community who will use the facilities on a day to day basis.
Waikato Regional Council
714.007 Support in part
Retain Objective 3.3.2 under Structure Plans with amendment to Policy 3.3.2c to ensure connection of transport modes, connectivity of industrial areas to the transport network, integration of transport networks over district boundaries and to ensure development does not hinder future infrastructure requirements.
Accept in Part
The submission support 3.3.2. It is accepted in part as that part of the submission relating to:
The retention of objective 3.3.2 is accepted
The amendment of policy 3.3.2c has been rejected. The addition of a number of policies relating to the transportation network is considered an unnecessary duplication of objectives and policies elsewhere in the Plan.
Future Proof Implementation Committee
FS181.008
Support Accept in Part
FS181.008 and FS270.011 are accepted in part as 714.007 is accepted in part. New Zealand
Transport Agency
FS270.011
Support Accept in Part
New Zealand Transport Agency
924.012 Support in part
Amend Policy 3.3.2(a) (Structure Plans) and associated Explanation to ensure they apply to a broader range of infrastructure than that for which Council is responsible by making amendments as set out in the submission.
Accept in Part
This submission supports 3.3.2. The proposed amendments will improve the:
Internal consistency of the Plan
Clarity of the Plan for users See Tracked Changes for Chapter 3
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 10 of 63
Reference to effects on Council’s planned infrastructure is unnecessary, and a broadening of the scope of the policy will assist in the implementation of objective 3.3.2.
Fonterra Co-operative Group Ltd
1200.009 Support in part
Amend Policy 3.3.2a to delete reference to ensuring the servicing of the land does not compromise the efficiency and sustainability of Council’s planned infrastructure.
Reject The submission points seek amendments that would reduce consistency of the Plan with the PRPS in terms of the enhancement of the safe and efficient functioning of existing or planned infrastructure. Whilst ‘efficiency’ and ‘sustainability’ are not defined by the Plan, they reinforce the approach that the provision of infrastructure needs to be coordinated and delivered in a sustainable manner. The proposed amendments would not change the general approach that developers are responsible for mitigating effects generated by their development.
Future Proof Implementation Committee
FS181.004
Oppose Accept FS181.004 is accepted as submission 1200.009 is rejected.
The Adare Company Ltd
FS272.033
Support Reject FS272.033 is rejected 1200.009 has been rejected.
Chedworth Properties Ltd
1171.009 Support in part
3.3.2 Objective and Policies (Structure Plans) - Amend Policies 3.3.2a and 3.3.2e as set out in the submission; Delete Policy 3.3.2d to ensure consistency with the Proposed Regional Policy Statement.
Accept in part
The submissions support 3.3.2. They have only been accepted in part as other submissions sought amendments to the provisions that this submission relates to. The proposed amendments will improve the:
Consistency of the Plan with the PRPS in terms of the enhancement of the safe and efficient functioning of existing or planned infrastructure.
Internal consistency and clarity of the Plan for users See Tracked Changes for Chapter 3
Tainui Group Holdings Ltd
913.010 Support in part
Amend Policy 3.3.2a and delete Policy 3.3.2d to regarding infrastructure requirements for development. Amend Policy 3.3.2e so that the staging and sequencing of development only has to be in general accordance with staging indicated on the relevant structure plan.
Accept in Part
University of Waikato
FS47.002
Oppose Reject FS47.002 is rejected as 913.010 is accepted in part.
William Cornelis Engelander
FS160.001
Oppose
Reject FS160.001 and 161.001 do not relate to the matters in 913.010. James Hely and Heather Montgomerie -
FS161.001
Oppose
The Adare Company Ltd
FS272.016
Support Accept in part
FS272.016 is accepted in part as 913.010 has been accepted in part.
ANG & SL Clarke 951.006 Oppose Add new objectives and policies to 3.3.2 for Large Lot Residential and Future Urban zoned areas where reticulated infrastructure is not available as the current objectives and policies are more relevant to urban development with reticulated services.
Reject The provision of on-site infrastructure solutions is a detail issue that is not dealt with or considered by chapter 3. Objectives and Policies for these zones are provided in chapters 4 and 14 of the Plan. A structure plan only provides overall guidance on the provision of infrastructure. The detailed design of reticulation solutions is discussed and managed through the resource consenting process.
Objective 3.3.3 and Policies a and b
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Population Health, Waikato DHB
1273.005 3.3.3 Objective and Policies
Support Retain and adopt Objectives and Policies under 3.3.3 Structure Plans as notified.
Accept in part
This submission supports 3.3.3 and is accepted in part as amendments have been made in response to other submissions. See Tracked Changes for Chapter 3
Waikato Regional Council
714.008 Support in part
Retain Objective and Policies under 3.3.3 Structure Plans with amendments to include the safeguarding and enhancement of freshwater bodies and additions to the list of matters under policy 3.3.3b for Integrated Catchment Management Plans.
PRS Planning Services Limited
929.015 Oppose Amend Policy 3.3.3b: (Objectives and Policies - Structure Plans) to clearly identify when Integrated Catchment Management Plans are required.
Robert Gordon Bell
1268.001 Support in part
Retain Structure Plans 3.3.3 Objective and Policies with amendments to require Integrated Catchment Management Plans before Policies and Rules are set.
Objective 3.3.4 and Policies a-g
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Population Health, Waikato
1273.006 3.3.4 Objective
Support Retain and adopt Objectives and Policies under 3.3.4 Structure Plans as notified.
Accept in part
This submission supports 3.3.4 and is accepted in part as amendments have been made in response to other submissions See Tracked Changes for Chapter 3
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 11 of 63
DHB and Policies
Waikato Regional Council
714.009 Support in part
Retain Objective and Policies under 3.3.4 Structure Plans with amendments, as set out in the submission, to include the improvement of safety of the transportation network under policy 3.3.4g and to clarify that adverse effects from building new transport infrastructure need to be avoided, as well as minimised in 3.3.4f.
Accept in part
The submission supports 3.3.4. It is accepted in part as that part of the submission relating to:
The retention of objective 3.3.4 is accepted
The amendment to 3.3.4f is rejected as it is considered that the relief sought is inconsistent with the objectives of the Plan.
The amendment to 3.3.4g is accepted as the provision of safe transportation networks is supported by the Plan See Tracked Changes for Chapter 3
New Zealand Transport Agency
FS270.012
Support Accept in part
FS270.012 is accepted in part as 714.009 has been accepted in part.
New Zealand Transport Agency
924.013 Support in part
Amend Objective 3.3.4 by deleting the word "Council". Amend Policy 3.3.4a: as set out in the submission to also refer to the defined range of considerations included in a ‘Broad Integrated Transport Assessment’ as set out in the definitions in Part 2. The Explanation will also require amending to reflect this requested change. Amend Policy 3.3.4b: to also refer to the defined range of considerations included in a ‘Broad Integrated Transport Assessment’ as set out in the definitions in Part 2. The Explanation will also require amending to reflect this requested change. Amend this policy as requested to promote clarity and ensure that the policy is consistent with the subsequent Explanation. Insert a new policy as set out in the submission, to ensure that financial impacts are minimised alongside environmental considerations.
Accept in part
The submission supports 3.3.4. It is accepted in part as that part of the submission relating to:
The amendment of Objective 3.3.4 is accepted as this will improve the internal consistency of the Plan.
The amendments to policies 3.3.4a, 3.3.4b are rejected. In terms of this matter, Integrated Transport Assessments (ITA) are carried out to determine the impact of a specific development on the transportation network and are a factor in assessing whether a consent should be granted or not. In the context of chapter 3, which is concerned with the overall network efficiency, it is considered unnecessary for the policies to reference ITA’s. However, it is considered that there is merit in broadening the explanation text as this will improve the integration, internal consistency and cross referencing within the Plan.
The amendment to the associated explanation text is accepted in part as this will improve the cross referencing within the Plan.
The amendment of policy 3.3.4b is rejected as this is an unnecessary duplication of the provisions elsewhere in the Plan.
PRS Planning Services Limited
929.016 Oppose 3.3.4 Objective and Policies (Structure Plans) That Policies 3.3.4a and 3.3.4b be deleted
Reject
The deletion of policies 3.3.4a and 3.3.4b is rejected. In terms of this matter, Integrated Transport Assessments (ITA) are carried out to determine the impact of a specific development on the transportation network and are a factor in assessing whether a consent should be granted or not. In the context of chapter 3, which is concerned with the overall network efficiency, it is considered unnecessary for the policies to reference ITA’s. However, it is considered that there is merit in broadening the explanation text as this will improve the integration, internal consistency and cross referencing within the Plan.
Chedworth Properties Ltd
1171.010 Oppose Delete policy 3.3.4b (Policy - Structure Plans).
Tainui Group Holdings Ltd
913.011 Oppose Delete Policy 3.3.4b
William Cornelis Engelander
FS160.001
Oppose
Reject FS 160.001 and 161.001 are not related to the matters contained in 913.011. James Hely and Heather Montgomerie -
FS161.001
Oppose
The Adare Company Ltd
FS272.017 Support Reject FS272.017 is rejected as 1171.010 has been rejected.
Objective 3.3.5 and Policies a and b
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Deborah June Fisher
282.022 3.3.5 Objective and Policies
Oppose Policies 3.3.5a) and b) to be amended to "avoid" adverse effects Reject The submission seeks amendments that would reduce the effectiveness of the Plan in terms of achieving its stated objectives and policies. Policy 3.3.5a relates to methods that can be used to manage reverse sensitivity along zone boundaries and it is applicable to both structures and activities. In the context of chapter 3, the policy is considered to be correctly worded. Further detail provisions to ensure that reverse sensitivity is properly managed, are provided in other chapters through the Plan.
The Church of Jesus Christ of Latter Day
FS180.004
Oppose Accept FS180.004 is accepted as 282.022 has been rejected.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 12 of 63
Saints Trust Board
Fonterra Co-operative Group Ltd
1200.010 Support in part
Amend Policy 3.3.5b by adding 'and regionally significant industry' Reject The policy is considered to be correctly worded and the proposed amendment is too narrowly focused on industrial activity.
New Zealand Transport Agency
924.014 Support in part
Amend Policy 3.3.5b by deleting the word 'Sensitive' so that it reads as follows: "Land uses shall avoid effects on and from regionally significant infrastructure".
Reject The submission seeks amendments that would reduce the effectiveness of the Plan in terms of achieving its stated objectives and policies in terms of managing the adverse effects that buildings and activities can have on each other.
Tainui Group Holdings Limited
FS196.017
Oppose
Accept FS196.017 and FS249.028 are accepted as 924.014 has been rejected. Property Council
New Zealand FS249.028
Oppose
Transpower New Zealand Ltd
1083.006 Support in part
3.3.5 Objective and Policies - Amend 3.3.5b by inserting the word 'adverse' as set out in the submission: 'Sensitive land uses shall avoid adverse effects on and from regionally significant infrastructure'. Insert a new Policy 3.3.5c 'Manage subdivision, use and development to avoid adverse effects on the safe, efficient and effective operation and use of existing or planned infrastructure'. Adopt any other such relief, including additions, deletions or consequential amendments necessary as a result of the matters raised in these submissions, as necessary to give effect to this submission.
Accept in Part
The submission supports 3.3.5. It is accepted in part as that part of the submission relating to:
The amendment to 3.3.5b is accepted
The addition of a new policy 3.3.5c is accepted in part. See Tracked Changes for Chapter 3 The amendments will assist in the clarity, understanding and administration of the Plan The addition of a new policy is supported (albeit with minor changes to the wording for clarity only) as this would help ensure that development within a structure plan area is integrated with existing and planned regionally significant infrastructure.
New Zealand Transport Agency
FS270.024
Support Accept in part
FS270.024 is accepted in part as submission 1083.006 has been accepted in part.
Barry Harris (Hamilton City Council)
1146.004 Support in part
3.3.5 Objective and Policies - Structure Plans. Amend the last paragraph of the explanation as set out in the submission to include reference to 'other sensitive' land uses.
Accept The minor amendments are necessary and will assist in the clarity, understanding and administration of the Plan.
Objective 3.3.6 and Policies a-d
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary
Decision Reasoning
Deborah June Fisher
282.023 3.3.6 Objective and Policies
Support in part
Add policy to recognise "adjoining land uses" Accept in Part
As this is specifically mentioned within Objective 3.3.6 and the associated explanation text, the submission is accepted but rather than the addition of a new policy as proposed by the submitter, an amendment to the wording of 3.3.6d has been made to deal with the concerns raised.
Waikato Regional Council
714.010 Support in part
a) Amend Policy 3.3.6a so that loss of SNAs is avoided, and opportunities for restoration and enhancement of indigenous vegetation are sought wherever possible. b) Amend Policy 3.3.6c to delete the words 'where practicable'. c) Add a new policy 3.3.6e that recognises the importance of, and provides for, well connected and ecologically functioning natural systems, based around the core ecological framework of the Waikato River and gully system. d) Add a policy on biodiversity restoration and enhancement through structure plans as follows: “Develop constructed wetlands and other green infrastructure in new growth areas to deal with urban stormwater issues and to provide for increased habitat and ecosystems.”
Reject
It is considered that the existing policy wording achieves the stated objective whilst ensuring there is a degree of flexibility. The concerns raised by the submitter are therefore unfounded. On this basis, the amendments to both policies are not supported. Whilst WRC sought additional new policies to 3.3.6, it is considered that the intent of the submission and the concerns raised, are managed in other chapters of the Plan, namely, chapter 21 regarding the River and Gully system and chapter 25 (25.13, Three Waters) regarding appropriate policies addressing stormwater. The introduction of two new policies is therefore considered an unnecessary duplication.
Hounsell Holdings Ltd
1104.006 Oppose 3.3.6(b) Objective and Policies - Structure Plans: Reword Policy 3.3.6(b) to include the wording "..Retains features of the landscape identified on structure plans".
Accept The minor amendments are necessary and will assist in the clarity, understanding and administration of the Plan
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 13 of 63
Porter Properties Ltd
1164.005 Oppose Amend Policy 3.3.6b in Objective and Policies for Structure Plans to clarify "identified features" will be identified on structure plans
Hamilton JV Investment Company Ltd
1170.006 Oppose 3.3.6 Objective and Policies - Structure Plans Amend Policy 3.3.6b) by rewording as set out in submission to insert text "retain features of the landscape identified on structure plans".
Lynette Joyce Williams
1050.003 Support in part
3.3.6 Objective and Policies - Structure Plans - Insert an additional policy statement in regard to the recognition and protection of heritage features.
Reject The addition of a policy statement in regard to the recognition and protection of heritage features is considered an unnecessary duplication of policies identified elsewhere in the Plan. Niall Baker 1158.003 Support in
part 3.3.6 Objective and Policies - Structure Plans. Insert an additional policy statement in regard to the recognition and protection of heritage features.
Objective 3.3.7 and Policies a-c
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
New Zealand Transport Agency
924.015 Support Retain 3.3.7 Objective and Policies - Structure Plans as notified. Accept in part
This submission supports 3.3.7 objective and policies. It is only accepted in part as the provisions that the submission supports have been amended in response to other submissions See Tracked Changes for Chapter 3.
PRS Planning Services Limited
929.019 Oppose Amend 3.3.7 Objective and Policies (Structure Plans) to clarify the status of the referenced Open Space Plan/Strategy. If this is unavailable then the Policy should be deleted or replaced with one that references the future reserves identified on the relevant structure plan.
Accept An additional reference to the Hamilton City Open Space Plan is considered beneficial and will assist in the clarity and understanding of the Plan.
Waikato Regional Council
714.011 3.3.7 Objective and Policies
Support in part
3.3.7 Objective and Policies (Structure Plans). Amend Policy 3.3.7b iv. by deleting the words 'Significant Natural Areas' and replacing with the words: "areas where recreation use is compatible with conservation values".
Reject
The submission points seek amendments that would reduce the effectiveness of the Plan in terms of achieving its stated objectives and policies. Policy 3.3.7b is not an absolute requirement and will not imply the damage to or that cultural or natural heritage values would be sacrificed to the advantage of other requirements. It only alludes to a certain principles that should be considered at the structure plan level. A structure plan only provides the broad direction and overarching proposals with regard to a number of issues including the identification and provision of community facilities and areas with natural and built heritage value that can be used to support local identity, changes to more intensive forms of development and the land required for active or passive recreation and public access to water. The co-location of recreational activities with cultural and heritage sites is something that should only be considered. Before a final decision is made a number factors would need to be evaluated and considered, such as the potential for this to damage or destroy archaeological sites. Seen against the backdrop of chapter 3, it is considered that the policy is appropriately worded.
Lynette Joyce Williams
1050.004 Oppose 3.3.7 Objective and Policies - Structure Plans: Policy 3.3.7b - Review this section to ensure cultural heritage values are not to be sacrificed to open space requirements.
Niall Baker 1158.004 Oppose Review section 3.3.7 Objectives and Policies - Structure Plans - to ensure cultural heritage values are not to be sacrificed to open space requirements.
Submissions regarding Shall vs. Should
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary
Decision Reasoning
PRS Planning Services Limited
929.014 3.3.2 Objectives and Policies
Oppose That the word "shall" in Policies 3.3.2a, 3.3.2b, 3.3.2c, 3.3.2e (Structure Plans) be replaced with the word "should".
Accept in part
The deletion of the word ‘shall’ provides for better objectives and policies for the plans framework and workability. These submissions are accepted in part and the changes to the policies reflect the consistent approach taken through this submission process See Tracked Changes for Chapter 3.
Waikato Chamber of Commerce
698.003 Support in part
3.3.2 Objectives and Policies - Amend Policies 3.3.2b, 3.3.2c and 3.3.2e by deleting the word 'shall' and replacing with 'must have regard to'.
McCracken Surveys Limited
1206.015 Oppose 3.3.2 Objective and Policies - Structure Plans: Replace reference to 'shall' with 'should' in Policies 3.3.2b, 3.3.2c and 3.3.2e.
Property Council New Zealand
938.013 Oppose Amend Policies 3.3.2b, 3.3.2c, and 3.3.2e by replacing the word 'shall' with 'should'.
Andrew Yeoman FS2.012
Support
Reject FS2.012 and FS242.001 are not related to the matters contained in 938.013 Peter John Findlay et al (Baruchel Developments Ltd)
FS242.001
Support
Peter John Findlay et al (Baruchel
FS242.012
Support Accept in part
FS242.012 is accepted in part as 938.013 has been accepted in part.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 14 of 63
Developments Ltd)
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.001
Support Reject FS277.001 is not related to the matters contained in 938.013
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.012
Support Accept in part
FS277.012 is accepted in part as 938.013 has been accepted in part.
McCracken Surveys Limited
1206.016 3.3.4 Objectives and Policies
Oppose 3.3.4 Objective and Policies - Structure Plans. Replace reference to 'shall' with 'should' in Policies 3.3.4a, 3.3.4b, 3.3.4c, 3.3.4e, 3.3.4f, 3.3.4g
Accept in part
The deletion of the word ‘shall’ provides for better objectives and policies for the plans framework and workability. These submissions are accepted in part and the changes to the policies reflect the consistent approach taken through this submission process. See Tracked Changes for Chapter 3.
PRS Planning Services Limited
929.016 Oppose 3.3.4 Objective and Policies (Structure Plans) That the word "shall" in Policies 3.3.4c, 3.3.4d, 3.3.4e, 3.3.4f, and 3.3.4g are replaced with the word "should".
Property Council New Zealand
938.014 Oppose Amend Policies 3.3.4a to 3.3.4c and 3.3.4e, to 3.3.4g by replacing the word “shall” with “should”.
Andrew Yeoman FS2.012
Support
Reject FS2.012 and FS242.001 are not related to the matters contained in 938.014 Peter John Findlay et al (Baruchel Developments Ltd)
FS242.001
Support
Peter John Findlay et al (Baruchel Developments Ltd)
FS242.013
Support Accept in part
FS242.013 is accepted in part as 938.014 has been accepted in part.
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.001
Support Reject FS277.001 is not related to the matters contained in 938.014
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.013
Support Accept in part
FS277.013 is accepted in part as 938.014 has been accepted in part.
McCracken Surveys Limited
1206.017 3.3.5 objectives and Policies
Oppose 3.3.5 Objective and Policies - Structure Plans. Replace reference to “shall” with “should” in Policies 3.3.5a and 3.3.5b.
Accept in part
The deletion of the word ‘shall’ provides for better objectives and policies for the plans framework and workability. These submissions are accepted in part and the changes to the policies reflect the consistent approach taken through this submission process See Tracked Changes for Chapter 3
PRS Planning Services Limited
929.017 Oppose 3.3.5 Objective and Policies (Structure Plans): That the word "shall" in Policies3.3.5a, 3.3.5b be replaced with the word "should".
Property Council New Zealand
938.015 Oppose Amend Policies 3.3.5a and 3.3.5b by replacing the word “shall” with “should”.
Andrew Yeoman FS2.012
Support
Reject FS2.012 and FS242.001 are not related to the matters contained in 938.015. Peter John Findlay et al (Baruchel
FS242.001
Support
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 15 of 63
Developments Ltd)
Peter John Findlay et al Ltd)
FS242.014
Support Accept in part
FS242.014 is accepted in part as 938.015 has been accepted in part.
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.001
Support Reject FS277.001 is not related to the matters contained in 938.015.
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.014
Support Accept in part
FS277.014 is accepted in part as 938.015 has been accepted in part.
McCracken Surveys Limited
1206.018 3.3.6 Objectives and Policies
Oppose 3.3.6 Objective and Policies - Structure Plans - Replace reference to “shall” with “should” in Policies 3.3.6a, 3.3.6b, 3.3.6c, and 3.3.6d.
Accept in part
The deletion of the word ‘shall’ provides for better objectives and policies for the plans framework and workability. These submissions are accepted in part and the changes to the policies reflect the consistent approach taken through this submission process See Tracked Changes for Chapter 3.
PRS Planning Services Limited
929.018 Oppose 3.3.6 Objective and Policies (Structure Plans): That the word 'shall' in Policies 3.3.6a, 3.3.6b, 3.3.6c, 3.3.6d be replaced with the word 'should'.
Property Council New Zealand
938.016 Oppose Amend Policies 3.3.6a to 3.3.6d by replacing the word “shall” with “should”.
Andrew Yeoman FS2.012
Support
Reject FS2.012 and FS242.001 are not related to the matters contained in 938.016 Peter John Findlay et al (Baruchel Developments Ltd)
FS242.001
Support
Peter John Findlay et al (Baruchel Developments Ltd)
FS242.015
Support Accept in part
FS242.015 is accepted in part as 938.016 has been accepted in part.
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.001
Support Reject FS277.001 is not related to the matters contained in 938.016
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.015
Support Accept in part
FS277.015 is accepted in part as 938.016 has been accepted in part.
McCracken Surveys Limited
1206.019 3.3.7 Objective and Policies
Oppose 3.3.7 Objective and Policies - Structure Plans - Replace reference to “shall” with “should” in Policies 3.3.7a and 3.3.7b.
Accept in part
The deletion of the word ‘shall’ provides for better objectives and policies for the plans framework and workability. These submissions are accepted in part and the changes to the policies reflect the consistent approach taken through this submission process. See Tracked Changes for Chapter 3.
Property Council New Zealand
938.017 Oppose Amend Policies 3.3.7a and 3.3.7b by replacing the word “shall” with “should”.
Andrew Yeoman FS2.012
Support Reject FS2.012 is not related to the matters contained in 938.017.
Peter John Findlay et al (Baruchel Developments Ltd)
FS242.001
Support Reject FS242.001 is not related to the matters contained in 938.017.
Peter John Findlay et al
FS242.016
Support Accept in part
FS242.016 is accepted in part as 938.017 has been accepted in part.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 16 of 63
(Baruchel Developments Ltd)
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.001
Support Reject FS277.001 is not related to the matters contained in 938.017.
Peter John Findlay et al (Peter Findlay, Peter Findlay & Associates Ltd)
FS277.016
Support Accept in part
FS277.016 is accepted in part as 938.017 has been accepted in part.
Submissions regarding Safety
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Starship Trauma Service
182.009 3.2 Principles
Support in part
Submitter seeks an additional Key Principle in Section 3.2 (Principles for Structure Plans) as follows: "Safety: The layout of any future residential development considers the physical safety of children. This design will include vehicular access in relation to the dwelling and any adjacent garden area to minimise the risk of injury/fatality from causes such as child driveway run overs".
Reject
Whilst the concerns are noted, it is not appropriate to reference child safety within chapter 3 dealing with structure planning issues. Structure planning is a valuable way to achieve integrated management of the effects of developing large land areas. It is a way of addressing the sustainable management of natural physical resources, particularly in an urban context. Structure Plans provide an important tool for Council in helping to identify appropriate services, infrastructure, open space, densities, residential and business areas, significant cultural, natural and historic or heritage features and urban design needs for a particular area or locality. Ensuring the safety of the most vulnerable members of the community is most effectively done through a number of other mechanisms and community organizations. At a more detailed level, the Plan identifies ‘safety’ as one of the qualities and attributes important in a residential environment. For example Policy 4.1.5b) which is applicable to all residential zones, focuses specifically on the matters to ensure an enjoyable living environment, which includes the safety of the area. Apart from the proposed amendment to policy 3.3.1c (submission 182.004) the concerns raised are detailed in nature and cannot be managed through the objectives and policies of chapter 3.
Waikato Child and Youth Mortality Review Group
1003.001 Support in part
Amend 3.2 regarding Structure Plan Principles to insert a new principle regarding the design of development to maximise child safety.
Waikato Child and Youth Mortality Review Group
1003.002 3.3.1 Objective and Policies
Support in part
Amend Policy 3.3.1c Structure Plans with amendments to include the maximisation of Child Safety and amend the associated explanation to highlight that density targets will not compromise safety requirements.
Starship Trauma Service
182.004 Support in part
Amend policy 3.3.1c to ensure passenger transport is not only efficient by safe by inserting the word 'safe' into the policy text.
Accept This submission seeks amendments that would improve the effectiveness of the Plan in terms of achieving its stated objectives and policies with regard to passenger transport.
Waikato Child and Youth Mortality Review Group
1003.004 3.3.4 Objective and Policies
Support in part
Amend Policy 3.3.4g as set out in the submission, to ensure that arterial routes do not sever safe access between residential and recreational spaces.
Reject Matters relating to design and layout of future residential or development areas including the design of arterial routes to consider and maximise the physical safety of children is a detailed design matter that cannot be managed through the objectives and policies of Chapter 3.
Waikato Child and Youth Mortality Review Group
1003.006 3.3.5 Objective and Policies
Support in part
3.3.5 Objectives and Policies - Structure Plans: Amend Policy 3.3.5a by adding a second sentence: "Any increased risk to safety that may result from these adjacent activities should be considered and mitigated against".
Waikato Child and Youth Mortality Review Group
1003.018 3.5 Rototuna
Support in part
Section 3.5 (Rototuna) - Amend 3.5 b) and 3.5 c) as per submission to explicitly incorporate the aspect of safety into the plan.
Waikato Child and Youth Mortality Review Group
1003.019 Support in part
3.5 - Rototuna Amend 3.5 b) and 3.5 c) to explicitly incorporate the aspect of safety into the plan, as set out in submission.
Waikato Child and Youth Mortality Review Group
1003.020 3.5.1 Objectives and Policies
Support in part
3.5.1 Objectives and Policies - Add a new policy to 3.5.1.4 (Objectives and Policies - Structure Plans) as follows: '3.5.1.4d Provide layout that minimises risk to children (such as slow speed run overs).'
Waikato Child and Youth
1003.021 3.6.1 Objectives
Support in part
Add a new sentence to the end of first paragraph under 3.6.1 “subdivision for residential purposes should give full consideration to
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 17 of 63
Mortality Review Group
and Policies safety such as minimizing risk of driveway run over”.
Waikato Child and Youth Mortality Review Group
1003.022 3.6.2.2 Residential
Support in part
3.6.2.2 Residential - Rotokauri. Amend 3.6.2.2a) to read: "residential development is indicated in four distinct residential environments where the layout will maximise safety to all householders while engendering a sense of community" Amend 3.6.2.2.a)i. by inserting the words 'and safe'
Waikato Child and Youth Mortality Review Group
1003.008 3.4 Peacocke
Support in part
Amend 3.4 c) Concentration, to add at the end of the sentence: "that considers all aspects of child safety". Amend 3.4 by adding an additional key principle as follows: Safety: The layout of any future residential development considers the physical safety of children. This design will include vehicular access in relation to the dwelling and any adjacent garden area to minimise the risk of injury/fatality, such as through slow driveway run over.
Reject The amendments sought are unnecessary as the matters are:
Inherent in the provisions regarding good urban design and accessibility
Already addressed through other provisions in the Plan that focus on site specific proposals (e.g. Chapter 23 Subdivision, Chapter 4 Residential Zone, Chapter 5 Special Character Zone, Chapter 25.14 Transportation, Chapter 25.15 Urban Design)
Not directly relevant to the matters in the provision which they seek to amend
Starship Trauma Service
182.007 3.4 Vision Support in part
Amend the first paragraph of 3.4 to read as follows "The vision for the Peacocke area is that it will become a high quality and safe urban environment that is based on urban design best practice, social well-being, and environmental responsibility."
Reject
The amendments sought are unnecessary as the matters are:
Inherent in the provisions regarding good urban design and accessibility
Already addressed through other provisions in the Plan that focus on site specific proposals (e.g. Chapter 23 Subdivision, Chapter 4 Residential Zone, Chapter 5 Special Character Zone, Chapter 25.14 Transportation, Chapter 25.15 Urban Design)
Waikato Child and Youth Mortality Review Group
1003.010 3.4 Vision Support in part
Amend 3.4 to include reference to "safe" urban environment.
Starship Trauma Service
182.005 3.4.2.1 Community and Recreation Facilities
Support in part
Amend 3.4.2.1 i) i, and j) by inserting references to child safety and safe pedestrian access principles into the criteria for the location of neighbourhood parks within the Peacocke Structure Plan Area.
Waikato Child and Youth Mortality Review Group
1003.012 3.4.2.1 Community and Recreation Facilities
Support in part
Amend 3.4.2.1b), d), and j) to ensure consideration of the need for pedestrian safety.
Waikato Child and Youth Mortality Review Group
1003.013 3.4.2.2 Neighbourhoods
Support in part
Amend 3.4.2.2 b) to ensure the safety of children.
Reject
The amendments sought are unnecessary as the matters are:
Inherent in the provisions regarding good urban design and accessibility
Already addressed through other provisions in the Plan that focus on site specific proposals (e.g. Chapter 23 Subdivision, Chapter 4 Residential Zone, Chapter 5 Special Character Zone, Chapter 25.14 Transportation, Chapter 25.15 Urban Design)
Would be determined as part of the Southern Links notice of requirement
Starship Trauma Service
182.011 3.4.3 Transport Network
Support in part
Amend 3.4.3e) to include "The designated arterial routes should not sever safe access to public recreational spaces."
Waikato Child and Youth Mortality Review Group
1003.014 3.4.3 Transport Network
Support in part
Amend 3.4.3 e) to ensure arterial routes do not sever safe access to public recreational space.
Waikato Child and Youth Mortality Review Group
1003.015 3.4.3 Transport Network
Support in part
Amend 3.4.3 e) to ensure arterial routes do not sever safe access to public recreational space.
Starship Trauma Service
182.008 3.4.1 Structure Plan Components
Support in part
Amend Figure 3-4a, #6 in the key by adding the following text "that are clearly defined as vehicular access and clearly separated from child play areas (public and private)" as set out in the submission.
Reject
The amendments sought are unnecessary as the matters are:
Inherent in the provisions regarding good urban design and accessibility
Already addressed through other provisions in the Plan that focus on site specific proposals (e.g. Chapter 23 Subdivision, Chapter 4 Residential Zone, Chapter 5 Special Character Zone, Chapter 25.14 Transportation, Chapter 25.15 Urban Design)
At a level of detail that is considered inappropriate in the context of a strategic structure plan chapter
Waikato Child and Youth
1003.011 3.4.1 Structure
Support in part
Amend Figure 3.4a, #6 to define a separation between vehicle and pedestrian space.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 18 of 63
Mortality Review Group
Plan Components
Starship Trauma Service
182.013 3.4.4 Interim Subdivision
Support in part
Amend 3.4.4c) to include reference to subdivision layout having consideration to maximise child safety.
Waikato Child and Youth Mortality Review Group
1003.016 Support in part
Amend 3.4.4c) to include reference to subdivision layout having consideration to maximise child safety.
Starship Trauma Service
182.017 3.4.6 Objectives and Policies
Support in part
Amend the Objectives and Policies in 3.4.6 to include child safety principles as set out in the submission.
Starship Trauma Service
182.015 Peacocke Social Wellbeing
Amend 3.4.6 to include child safety principles and the text as set out in the submission
Waikato Child and Youth Mortality Review Group
1003.017 Peacocke Social Wellbeing
Support in part
Amend the introduction to 3.4.6.11 Peacocke Social Wellbeing to insert text to ensure safety, with specific reference to children is identified within the residential areas.
Peacock Structure Plan - General
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Future Proof Implementation Committee
608.008 3.4 Peacocke
Support Retain 3.4 Peacocke. Accept in Part
This submission point supports provisions in 3.4 is accepted in part because amendments have been made in response to other submission points. See 3.4 in Tracked Changes for Chapter 3
Rex Hannam 935.001 Support Retain provisions within the Plan (Parts 3.4, 5.2.8, 5.3-6, 23.3, 23.6 and Appendix 2.2) that manage interim and future development within the Peacocke Structure Plan Area and Peacocke Character Zone.
Accept in Part
This submission point supports provisions in 3.4 is accepted in part because amendments have been made in response to other submission points. See 3.4 in Tracked Changes for Chapter 3
New Zealand Transport Agency
924.016 Support Retain the Peacocke Structure Plan subject to specific amendments requested in the submission.
Accept in Part
This submission point supports in 3.4 and is accepted in part because amendments have been made in response to other submission points and the specific amendments sought by the submitter are addressed separately. See Tracked Changes for Chapter 3.
New Zealand Transport Agency
924.017 3.4.3 Transport Network
Support Retain 3.4.3e) Transport Network as notified Accept in Part
This submission point supports 3.4.3e) and is accepted in part because amendments have been made in response to other submission points. See 3.4 in Tracked Chjanges for Chapter 3.
Russelle Knaap 690.013 3.4.3 Transport Network
Oppose Amend 3.4.4 to give priority to motorists in the development of the Peacocke Transport Network.
Reject This submission point is rejected because 3.4.4 is consistent with the:
Purpose and Principles of the RMA
Objectives and policies of the Plan
Proposed Regional Policy Statement
Regional Walking and Cycling Strategy 2009-2015
Regional Land Transport Strategy 2011-2041
Access Hamilton 2010 and its supporting Action Plans (particularly Travel Demand Action Plan and Active Travel Action Plan)
Future Proof Growth Strategy and Implementation Plan 2009 and the Plan already respond to issues related to the safety of public walkways, so no amendments are necessary.
Transpower’s Hamilton Communication Centre
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Transpower New Zealand Ltd
1083.005 Figure 2-1 Peacocke Structure Plan-Land Use
Support in part
Amend Figure 2-1: Peacocke Structure Plan – Land Use to identify Transpower’s Hamilton Communications Centre and remove the indicative transport corridor link from traversing the site.
Accept Amendments have been made to identify the Hamilton Communications Centre on the Peacocke Structure Plan and to move the indicative transport corridor off the site. These amendments:
Improve the clarity and administration of the Plan.
Avoid confusion regarding future transport corridor expectations.
Recognise the Hamilton Communications Centre in the Structure Plan as significant infrastructure and a physical resource critical to providing for the social and economic wellbeing of the country.
See Figure 2-1, Figure 2.2 and Figure 15-5e in Tracked Changes for Chapter 3 (1083.005)
Transpower New Zealand Ltd
1083.007 3.4.1.1 Natural
Support in part
Amend 3.4.1.1c) to make reference to the Transpower’s National Control Centre in Hall Road.
Reject The amendments sought to 3.4.1.1c) are rejected because they would:
Be out of context as they seek to recognise and protect regionally significant infrastructure, not natural character, which would
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 19 of 63
Character Areas
reduce the clarity of the Plan.
The provisions of the Plan (Master Plan process, Objective 3.3.5 and Policy 3.3.6b (Structure Plans), Objective 25.7.2.1 and Policies 25.7.2.1b, 25.7.2.1f (Network Utilities and Electricity Transmission Corridors), 23.2.2a x. and xi. (Subdivision) directly address reverse sensitivity effects and adverse effects of subdivision, use and development on network utilities.
Amendments have been made to the Plan in response to other submission points (1083.005) that provide recognition of the Hamilton Communications Centre.
Transpower New Zealand Ltd
1083.008 Peacocke Built Environment
Support in part
Insert new objectives and policies, as set out in the submission, into 3.4.6.4 Peacocke Built Environment to ensure that existing regionally significant infrastructure is not compromised by the development of the structure plan area.
Reject The amendments sought are rejected because:
The provisions of the Plan (Master Plan process, Objective 3.3.5 and Policy 3.3.6b (Structure Plans), Objective 25.7.2.1 and Policies 25.7.2.1b, 25.7.2.1f (Network Utilities and Electricity Transmission Corridors), 23.2.2a x. and xi. (Subdivision) directly address reverse sensitivity effects and adverse effects of subdivision, use and development on network utilities, so no amendments are necessary.
Amendments have been made to the Plan in response to other submission points (1083.005) that provide recognition of the Hamilton Communications Centre.
3.4.2 Nodes
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
The Adare Company Ltd
482.006 3.4.2.3 Commercial Community Nodes
Support in part
Amend 3.4.2.3 to provide flexibility in the number of community nodes within the Peacocke Area.
Reject This submission point is rejected because the amendment would:
Be contrary to Policy 3.3.1a.
Make the Plan internally inconsistent.
Reduce the clarity the Plan.
Create administrative uncertainty. The Master Plan process provides appropriate flexibility to adjust the form and location of the community focal points for those neighborhood areas containing a node.
The Ministry of Education
838.001 3.4.2.3 Commercial Community Nodes
Oppose Amend 3.4.2.3 to remove references and identification of a secondary school site in Peacocke Area.
Reject This submission point is rejected because 3.4.2.3a) i. does not pre-empt any decision by the Ministry of Education on the need, timing or location of any future secondary school and the deletion of the reference would leave no guidance for organisations with interests in providing for educational needs.
The Adare Company Ltd
FS272.013
Oppose Accept FS272.013 has been accepted because the submission point (838.001) which it opposes has been rejected.
Peacocke Stage 1 - Indicative Collector Transport Corridor
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Summerset Villages (Hamilton) Ltd
814.001 3.4 Peacocke
Support in part
Amend the Peacocke Structure Plan to relocate the collector road away from the submitters site or provide flexibility to allow structure plan features to be located in different areas or in modified form from that shown in the structure plan.
Accept in part
It is accepted that the indicative collector road be removed from the Peacocke Structure Plan for the following reasons:
Limited adverse transport effects will be generated as a consequence of its removal
An alternative collector road and local road will provide adequate connectivity within the locality
It is unlikely that the indicative collector road would attract a high enough volume of traffic to justify retaining a collector road status
Whilst the removal of road will necessitate changes to the Goan consent this may present an opportunity to improve aspects of the development layout
Feasible alternate access arrangements can be made
Paul Dermott and Elizabeth Maria Corboy
FS37.001
Support Accept in part
FS37.001 is acceped in part as submission 814.001 has been accepted in part
Dixon Homes Ltd FS78.001
Oppose Accept in part
FS78.001 is accepted in part as submission 814.001 has been accepted in part
Goan Holdings Ltd
FS80.001
Oppose Accept in part
FS80.001 is accepted in part as submission 814.001 has been accepted in part
Northview Partnership Ltd
FS163.001
Support Accept in part
FS163.001 is accepted in part as submission 814.001 has been accepted in part
Summerset Villages (Hamilton) Ltd
814.002 Figure 2-1 Peacocke Structure Plan-Land Use
Support in part
Amend Figure 2-1 Peacocke Structure Plan - Land Use to relocate indicative collector road in Stage 1 of Peacocke as set out in the submission.
Accept in part
It is accepted that the indicative collector road be removed from the Peacocke Structure Plan for the following reasons: • Limited adverse transport effects will be generated as a consequence of its removal • An alternative collector road and local road will provide adequate connectivity within the locality • It is unlikely that the indicative collector road would attract a high enough volume of traffic to justify retaining a collector road status • Whilst the removal of road will necessitate changes to the Goan consent this may present an opportunity to improve aspects of the development layout
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 20 of 63
• Feasible alternate access arrangements can be made
Paul Dermott and Elizabeth Maria Corboy
FS37.001
Support Accept in part
FS37.001 is accepted in part as submission 814.002 is accepted in part.
Dixon Homes Ltd FS78.002
Oppose Accept in part
FS78.002 is rejected as submission 814.003 is accepted in part.
Goan Holdings Ltd
FS80.002
Oppose Accept in part
FS80.002 is rejected as submission 814.003 is accepted in part.
Summerset Villages (Hamilton) Ltd
814.003 Figure 2-2 Peacocke Structure Plan-Staging and Transport Network
Support in part
Amend Figure 2-2 Peacocke Structure Plan - Staging and Transport Network to relocate indicative collector road in Stage 1 of Peacocke as set out in the submission.
Accept in part
It is accepted that the indicative collector road be removed from the Peacocke Structure Plan for the following reasons: • Limited adverse transport effects will be generated as a consequence of its removal • An alternative collector road and local road will provide adequate connectivity within the locality • It is unlikely that the indicative collector road would attract a high enough volume of traffic to justify retaining a collector road status • Whilst the removal of road will necessitate changes to the Goan consent this may present an opportunity to improve aspects of the development layout • Feasible alternate access arrangements can be made
Paul Dermott and Elizabeth Maria Corboy
FS37.001
Support Accept in part
FS37.001 is accepted in part as submission 814.003 is accepted in part.
Dixon Homes Ltd FS78.003
Oppose Accept in part
FS78.003 is rejected as submission 814.003 is accepted in part.
Goan Holdings Ltd
FS80.003
Oppose Accept in part
FS80.003 is rejected as submission 814.003 is accepted in part.
Summerset Villages (Hamilton) Ltd
814.004 Figure 2-3 Peacocke Structure Plan-Character Areas and Neighbourhoods
Support in part
Amend Figure 2-3 Peacocke Structure Plan - Character Areas and Neighbourhoods to relocate indicative collector road in Stage 1 of Peacocke as set out in the submission.
Accept in part
It is accepted that the indicative collector road be removed from the Peacocke Structure Plan for the following reasons: • Limited adverse transport effects will be generated as a consequence of its removal • An alternative collector road and local road will provide adequate connectivity within the locality • It is unlikely that the indicative collector road would attract a high enough volume of traffic to justify retaining a collector road status • Whilst the removal of road will necessitate changes to the Goan consent this may present an opportunity to improve aspects of the development layout • Feasible alternate access arrangements can be made
Paul Dermott and Elizabeth Maria Corboy
FS37.001
Support Accept in part
FS37.001 is accepted in part as submission 814.004 is accepted in part
Dixon Homes Ltd FS78.004
Oppose Accept in part
FS78.004 is accepted in part as submission 814.004 is accepted in part
Goan Holdings Ltd
FS80.004
Oppose Accept in part
FS80.004 is accepted in part as submission 814.004 is accepted in part
Arterial Transport Corridor Protection Area
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Rex Hannam 935.008 Figure 2-2 Peacocke Structure Plan-Staging and Transport Network
Oppose Seeks the deletion of provisions in 25.14.3 and 25.14.5 relating to Arterial Transport Corridor Protection Areas and amend Appendix 2 Structure Plans to replace Arterial Transport Corridor Protection Area with designations or Indicative Future Arterial Corridors.
Accept in Part
This submission point has been accepted in part as given the evidence presented, and recognising that a significant portion of the ATCPA is no longer necessary given the protection afforded by lodged notices of requirement and that the remaining ATCPA is mostly on land zoned Future Urban Zone (with limited urban development) or in the majority ownership of a few parties (Ruakura Structure Plan Area) the ATCPA and its associated provisions should be deleted from the Plan. The deletion of Appendix 1.2 B3 is not appropriate however as the criteria is relevant to matters other than the ATCPA. See Tracked Changes for Appendix 1 (definitions) and tracked changes for Chapter 25.14
The Adare Company Ltd
FS272.024
Oppose Accept in Part
FS270.024 has been accepted in part because the submission point (935.008) which it opposes has been accepted in part.
David John Rushbrooke
251.004 Figure 2-2 Peacocke Structure Plan-Staging and Transport Network
Oppose Figure 2-2 Peacocke Structure Plan - Staging and Transport Network: Delete the Arterial Transport Corridor Protection Area from the Proposed District Plan.
Accept in Part
This submission point has been accepted in part as given the evidence presented, and recognising that a significant portion of the ATCPA is no longer necessary given the protection afforded by lodged notices of requirement and that the remaining ATCPA is mostly on land zoned Future Urban Zone (with limited urban development) or in the majority ownership of a few parties (Ruakura Structure Plan Area) the ATCPA and its associated provisions should be deleted from the Plan. The deletion of Appendix 1.2 B3 is not appropriate however as the criteria is relevant to matters other than the ATCPA. See Tracked Changes for Appendix 1 (definitions) and tracked changes for Chapter 25.14
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 21 of 63
Barry Harris (Hamilton City Council)
1146.115 Figure 2-2 Peacocke Structure Plan-Staging and Transport Network
Support in part
Amend Figure 2-2 Peacocke Structure Plan to remove the Arterial Transport Corridor Protection Area (ATCPA) that falls outside the Peacocke Structure Plan Area.
Arterial Transport Corridor alignment and Southern Links
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision
Sub. Type Summary Decision Reasoning
Richard Ward 325.001 Figure 2-2 Peacocke Structure Plan-Staging and Transport Network
Oppose Revert back to the location of the "Eastern Link" Major Arterial Transport Corridors as shown in the Peacocke Structure Plan within the Operative District Plan and use the existing designation for the minor arterial roads.
Reject This submission point is rejected because the location, form and function of the arterial transport corridor network represented in the Peacocke Structure Plan is contingent on the completion of the Southern Links designation project, notices of requirements for which has been lodged.
New Zealand Transport Agency
FS270.081
Oppose Accept FS270.081 has been accepted because the submission point (325.001) which it opposes has been rejected.
Richard Ward 325.002 3.4.3 Transport Network
Oppose Amend 3.4.3 to align with the "Eastern Link" within Variation 14. Reject This submission point is rejected because the location, form and function of the arterial transport corridor network represented in the Peacocke Structure Plan is contingent on the completion of the Southern Links designation project, notices of requirements for which has been lodged.
The Adare Company Ltd
FS272.003
Support Reject FS272.003 has been rejected because the submission point (325.002) which it supports has been rejected.
Northview Partnership Ltd
540.001 3.4.3 Transport Network
Oppose Amend 3.4.3 to indicate that the roading layout within Stage 1 may change as a result of the Southern Links Designation process.
Accept in Part
This submission point is accepted in part because:
The location, form and function of the arterial transport corridor network represented in the Peacocke Structure Plan is contingent on the completion of the Southern Links designation project, notices of requirements for which has been lodged.
No amendments to the plan are necessary as the Plan already makes reference to the Southern Links designation process (3.4.3e) and, once confirmed, the designation will be incorporated into the Planning Maps.
The Adare Company Ltd
FS272.005
Support Accept in Part
FS272.005 has been accepted in part because the submission point (540.001) which it supports has been accepted (in part).
Gillian James 875.001 3.4.3 Transport Network
Oppose Amend 3.4.3 to re-route the Arterial Route shown on the western side of the Mangakotukutuku Gulley as set out in the submission.
Reject These submission points are rejected because the location, form and function of the arterial transport corridor network represented in the Peacocke Structure Plan is contingent on the completion of the Southern Links designation project, notices of requirements for which has been lodged.
875.002 Figure 2-2 Peacocke Structure Plan-Staging and Transport Network
Oppose Amend Figure 2-2 Peacocke Structure Plan - Staging and Transport Network to re-route the Major Arterial Transport Corridor Route shown on the western side of the Mangakotukutuku Gulley as set out in the submission.
The Adare Company Ltd
FS272.014
Oppose Accept FS272.014 has been accepted because the submission point (875.002) which it opposes has been rejected.
The Adare Company Ltd
482.001 Figure 2-1 Peacocke Structure Plan-Land Use
Support in part
Retain Figure 2-1 Peacocke Structure Plan - Land Use while providing the opportunity for changes to Figures 2-1 to 2-3 to reflect the designated Southern Links alignment.
Accept in Part
These submission points are accepted in part because:
The location, form and function of the arterial transport corridor network represented in the Peacocke Structure Plan is contingent on the completion of the Southern Links designation project, notices of requirements for which has been lodged.
No amendments to the plan are necessary as the Plan already makes reference to the Southern Links designation process (3.4.3e) and, once confirmed, the designation will be incorporated into the Planning Maps.
Amendments have been made to Figures 2-1 and Figure 2-2 in response to other submissions See Tracked Changes for Chapter 3
482.002 Figure 2-2 Peacocke Structure Plan-Staging and Transport Network
Support in part
Retain Figure 2-2 Peacocke Structure Plan – Staging and Transport Network while providing the opportunity for changes to Figures 2-1 to 2-3 to reflect the designated Southern Links alignment.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 22 of 63
482.003 Figure 2-3 Peacocke Structure Plan-Character Areas and Neighbourhoods
Support in part
Retain Figure 2-3 Peacocke Structure Plan – Character Areas and Neighbourhoods while providing the opportunity for changes to Figures 2-1 to 2-3 to reflect the designated Southern Links alignment.
J.C Johnson Family Trust
635.002 Figure 2-1 Peacocke Structure Plan-Land Use
Support Retain Figure 2-1 Peacocke Structure Plan - Land Use as notified.
Accept in Part
These submission points are accepted in part because:
The location, form and function of the arterial transport corridor network represented in the Peacocke Structure Plan is contingent on the completion of the Southern Links designation project, notices of requirements for which has been lodged.
No amendments to the plan are necessary as the Plan already makes reference to the Southern Links designation process (3.4.3e) and, once confirmed, the designation will be incorporated into the Planning Maps.
Amendments have been made to Figures 2-1 and Figure 2-2 in response to other submissions See Tracked Changes for Chapter 3
635.003 Figure 2-2 Peacocke Structure Plan-Staging and Transport Network
Support in part
Retain Figure 2-2 Peacocke Structure Plan - Staging and Transport Network as notified.
635.004 Figure 2-3 Peacocke Structure Plan-Character Areas and Neighbourhoods
Support Retain Figure 2-3 Peacocke Structure Plan - Character Areas and Neighbourhoods as notified.
Rex Hannam 935.005 Figure 2-1 Peacocke Structure Plan-Land Use
Oppose Amend Appendices 2.1-3 Peacocke Structure Plan Maps by relocating the Proposed Southern Links Arterial Corridors and amending the neighbourhood and character areas as set out in the submission.
Accept in Part
That part of this submission point seeking amendments to the location of the arterial transport corridor network is rejected because:
The location, form and function of the arterial transport corridor network represented in the Peacocke Structure Plan is contingent on the completion of the Southern Links designation project, notices of requirements for which has been lodged. Once the final alignment is confirmed the designation will be incorporated into the Planning Maps.
That part of this submission point regarding a new neighbourhood area in Figure 2-3 is accepted in part because:
Amendments have been made to Figure 2-3 to identify a new neighbourhood area aligning the boundaries of Neighbourhood Areas 1 and 3 with the arterial transport corridor network in Figure 2.2 and extending the Hills Character Area to align with the the Minor Arterial Transport Corridor to provide a logical boundary .
See Tracked Changes for Appendix 2.
The Adare Company Ltd
FS272.023 Oppose Accept in Part
FS272.023 has been accepted in part because the submission point (935.005) which it opposes has been accepted in part.
Rex Hannam 935.009 Figure 2-3 Peacocke Structure Plan-Character Areas and Neighbourhoods
Oppose Amend Appendices 2.1-3 Peacocke Structure Plan Maps by relocating the Proposed Southern Links Arterial Corridors and amending the neighbourhood and character areas as set out in the submission
Accept in Part
That part of this submission point seeking amendments to the location of the arterial transport corridor network is rejected because:
The location, form and function of the arterial transport corridor network represented in the Peacocke Structure Plan is contingent on the completion of the Southern Links designation project, notices of requirements for which has been lodged. Once the final alignment is confirmed the designation will be incorporated into the Planning Maps.
That part of this submission point regarding a new neighbourhood area in Figure 2-3 is accepted in part because:
Amendments have been made to Figure 2-3 to identify a new neighbourhood area aligning the boundaries of Neighbourhood Areas 1 and 3 with the arterial transport corridor network in Figure 2.2 and extending the Hills Character Area to align with the the Minor Arterial Transport Corridor to provide a logical boundary .
See Tracked Changes for Appendix 2.
The Adare Company Ltd
FS272.025 Oppose Accept in Part
FS272.025 has been accepted in part because the submission point (935.009) which it opposes has been accepted (in part). Oppose Rejected in Part FS272.025 has been rejected in part because the submission point (935.009) which it opposes has been accepted (in part).
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 23 of 63
Infrastructural Development Programme and Residential Development Staging
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary
Decision Reasoning
New Zealand Transport Agency
924.018 3.4.5 Indicative Infrastructural Development Programme
Support Retain Rule 3.4.5 Indicative Infrastructural Development Programme as notified.
Accept This submission supports Rule 3.4.5 and is accepted because there are no other submissions seeking amendments to this provision.
The Adare Company Ltd
FS272.028
Support Accept in Part
FS272.028 has been accepted in part because the submission point (924.018) which it supports has been accepted (in part) and amendments sought by the submission are beyond the scope of the principal submission.
Blue Wallace Surveyors Ltd
32.001 3.4.5.1 Proposed Staging of Residential Development
Oppose Delete Rule 3.4.5.1 b) and c) ii as it relates to staging of residential development for Peacockes Structure Plan
Accept in Part
This submission point is accepted in part because amendments have been made that deletes part of Rule 3.4.5.1b). Complete deletion of Rules 3.4.5.1 b) and c) ii are premature and would reduce the effectiveness of the Plan in relation to mitigating the adverse transportation safety effects caused by the development of Stage 1. See Rule 3.4.5.1b) of Tracked Changes for Chapter 3(32.001)
Andrew Yeoman FS2.002
Support Reject FS2.002 is not related to the matters contained in 32.001.
The Adare Company Ltd
FS272.031
Oppose Accept in Part
FS272.031 has been accepted in part because the submission point (32.001) which it opposes has been accepted in part
New Zealand Transport Agency
924.019 3.4.5.1 Proposed Staging of Residential Development
Support in part
Amend Rule 3.4.5.1 to ensure that the Proposed Staging of Residential Development provisions have the status of a rule. Amend Rule 3.4.5.1 b) ii to clarify that the 80% dwelling trigger for Stage 1b development relates to consented dwellings (not occupied dwellings). Amend Rule 3.4.5.1 c) ii to recognise that the solution for the transport effects on the Dixon Road / State Highway 3 intersection may require works elsewhere.
Accept in part
Amendments have been made that clarifies the status of 3.4.5.1 as a rule which will improve the clarity and administration of the Plan. That part of this submission point regarding Rule 3.4.5.1 c) ii is accepted because:
The amendment proposed to Rule 3.4.5.1 c) ii would provide a level of certainty as to the extent of responsibility for the implementation of the Dixon Road / State Highway 3 intersection solution.
Consistent with the intent of the Variation 14 settlement package. See Rule 3.4.5.1 in Tracked Changes for Chapter 3 (924.019) That part of this submission point regarding Rule 3.4.5.1 b) ii is rejected because:
That part of Rule 3.4.5.1 b) ii has been deleted in response to another submission point.
Northview Partnership Ltd
FS163.002
Oppose Reject FS163.002 has been rejected in part because the submission point (924.019) which it opposes has been accepted
Barry Harris (Hamilton City Council)
1146.005 3.4.5.1 Proposed Staging of Residential Development
Support in part
Amend 3.4.5.1 b) Proposed Staging of Residential Development i) to refer to 'residential lots' rather than 'dwellings'.
Reject This submission point is rejected because the amendments would exclude residential development not involving subdivision, this would reduce the effectiveness of the Plan in relation to mitigating the adverse transportation safety effects caused by the development of Stage 1.
Future Reserve Land – 217 Peacocke Road
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary
Decision Reasoning
Jason Hennessey 328.001 Figure 2-1 Peacocke Structure Plan-Land Use
Oppose Remove the 'future reserve' land use from property Lot 2 312185 (217 Peacocke Road) as shown on Figure 2-1 Peacocke Structure Plan - Land Use.
Accept in Part
The amendment to the future reserve will reflect the current situation in relation to proposed roading infrastructure and the existing residential development on the site.
The Adare Company Ltd
FS272.004
Oppose Accept in part
FS272.004 has been accepted in part because the submission point (328.001) which it opposes has been accepted (in part)
Corrections, Cross referencing and Clarifications
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Barry Harris (Hamilton City Council)
1146.006 Peacocke Cultural Environment
Support in part
Amend the numbering of the first Policy of Objective 3.4.6.16 to correct an error.
Accept This is amendment would constitute a minor error under Clause 16(2) of the First Schedule of the Act and will improve the clarity of the Plan.
The Adare Company Ltd
482.005 3.4.1.1 Natural Character Areas
Support in part
Renumber Figures 3.4a and 3.4b to reflect the section within which they are located (Section 3.4.1).
Accept Amendments have been made that will improve the clarity of the Plan. See 3.4.1, 3.4.2 and 3.4.3 in Tracked Changes for Chapter 3 (482.005)
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 24 of 63
Objectives and Policies - Natural Environments, Built Environments, and Social Wellbeing
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
The Adare Company Ltd
482.007 3.4.6 Objectives and Policies
Support in part
Amend 3.4.6 by adding Objectives and Policies for the Peacocke Natural Systems, as set out in the submission and derived from the objectives and policies in Parts 9.2.3a, b and c of the Operative District Plan.
Reject The matters raised in this submission are addressed through other provisions in the Plan, so no amendments are necessary. For example objectives and policies can be found within chapter 25 – Earthworks and Vegetation Removal, Chapter 3 – Structure Plans, Chapter 5 – Special Character Zones, Chapter 23 – Subdivision and Chapter 25 - Transportation.
Waikato Regional Council
714.012 Peacocke Natural System
Support in part
Replace Objective 3.4.6.1 with an objective that provides for the protection and enhancement of all remnant natural areas within the growth cell, as well as ecosystem functions and processes (including connectivity), indigenous habitats and species requirements, and natural character. Amend Policy 3.4.6.1a by removing reference to stormwater functions of the Mangakotukutuku Gully and Waikato River margins, and adding references to ecological functions, indigenous biodiversity and habitats. Amend Policy 3.4.6.1b by adding reference to opportunities for ecological and habitat enhancement and for restoration of natural character Amend Policy 3.4.6.1c to provide for the ecological restoration and enhancement (including revegetation with appropriate native species) of gullies and river margins. Amend Policy 3.4.6.1e to enhance riparian and aquatic habitat and control adverse effects on stream water quality and habitat. Add a new Policy to 3.4.6.1 that preserve the natural character of the Mangakotukutuku Gully and Waikato River margins and protect it from inappropriate development and where natural character has already been compromised utilise opportunities to restore and enhance it. Add a new Policy to 3.4.6.1 that provides for a specific ecological restoration fund from financial or development contributions from development adjacent to the river and gully edges. Amend Objective 3.4.6.2 to Maintain and enhance the ecological and open space links to the river provided by the Mangakotukutuku Gully. Amend Policy 3.4.6.2a to Maintain the extent and enhance the quality of ecological (green) corridors of the Mangakotukutuku Gully and Waikato River margins. Amend Policy 3.4.6.2b to ensure the alignment of the roading network maintains and enhances the ecological, physical and visual connections of the Mangakotukutuku Gully system and its connection to the Waikato River. Amend Policy 3.4.6.2c to maintain and enhance the green corridor along the Waikato River to provide for natural character, ecological functions, riparian and aquatic habitat and for public access and amenity. Retain Objective 3.4.6.3 and Policies 3.4.6.3a and 3.4.6.3b Add a new Policy to 3.4.6.3 to protect gully landform, natural feature and landscape elements from modification.
Accept in Part
That part of this submission point: 1. Supporting Objective 3.4.6.3 and Policies 3.4.6.3a and 3.4.6.3b is accepted because while other submissions have sought amendments they have been rejected. 2. Seeking amendments to objectives and policies in 3.4 is rejected because the matters raised in this submission are either already addressed through other provisions in the Plan or have been considered and determined as part of submission points of the submitter to other parts of the Plan.
The Adare Company Ltd
FS272.009
Oppose Accept in Part
FS272.009 has been accepted in part because the submission point (714.012) which it opposes has been accepted (in part)
Waikato Regional 714.013 Peacocke Built Oppose Amend Objective 3.4.6.4, as set out in the submission, to include Reject That part of this submission point seeking amendments to objectives and policies in 3.4 is rejected because the matters raised in this
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 25 of 63
Council Environment reference to maintains or enhances ecological connectivity. Amend Policy 3.4.6.4d to support changes to Objective 3.4.6.4 by avoiding or reducing the impact of movement routes on the ecological functions and connectivity of the Mangakotukutuku Gully and the Waikato River.
submission are either already addressed through other provisions in the Plan or have been considered and determined as part of submission points of the submitter to other parts of the Plan.
The Adare Company Ltd
FS272.010
Oppose Accept FS272.010 has been accepted because the submission point (714.013) which it opposes has been rejected.
Waikato Regional Council
714.014 Peacocke Social Wellbeing
Support in part
Amend Policy 3.4.6.13a by inserting the following text into the policy "for enhancement or re-creation of habitats, ecological and physical" as set out in the submission.
Reject That part of this submission point seeking amendments to objectives and policies in 3.4 is rejected because the matters raised in this submission are either already addressed through other provisions in the Plan or have been considered and determined as part of submission points of the submitter to other parts of the Plan.
The Adare Company Ltd
FS272.011
Oppose Accept FS272.011 has been accepted because the submission point (714.014) which it opposes has been rejected.
Mangakotukutuku Stream Care Incorporated Group
1040.002 Peacocke Natural System
Support in part
Amend Objective 3.4.6.1 to maintain connectivity for movement of native animals, including passage for fish and bats" Add a new policy to 3.4.6.1 to ensure unimpeded movement for native animals (e.g. fish and bats) through the stream and gull network, including road crossings; Amend policy 3.4.6.1a by inserting the word 'natural'; Amend policy 3.4.6.1e by inserting the word 'avoid'.
Reject That part of this submission point seeking amendments to objectives and policies in 3.4 is rejected because the matters raised in this submission are either already addressed through other provisions in the Plan or have been considered and determined as part of submission points of the submitter to other parts of the Plan. Chapter 3 provides several guiding principles and strategic objectives, policies, and rules for the staging and development of Structure Plan Areas. It must be read in conjunction with the rest of the Plan as it is not the Plan’s approach to extensively duplicate provisions that exist in other relevant chapters. In the Peacocke Character Zone subdivision to an urban density is a Non-complying activity without an approved Master Plan (see Rule 5.3.2, Appendix 1.5.19). The absence of a Master Plan also affects the activity status of land use and development. The preparation of a Master Plan is a Discretionary Activity (Rule 5.3.2.4 a)), or Non-complying when it proposes a Non-complying activity in the related column of the activity status table (Rule 5.3.2.4). Master Plans specifically require consideration of the natural environment and open space networks. It is considered that the matters raised in these submissions are already appropriately reflected in the provisions of the Plan, including the objectives, policies and rules of the following chapters:
2 Strategic Framework
3 Structure Plans
5 Special Character Zones
15 Open Space Zones
20 Natural Environments
21 Waikato River Corridor and Gully Systems
23 Subdivision
25.2 Earthworks and Vegetation Removal
25.13 Three Waters
Department of Conservation
1110.001 Peacocke Natural System
Support Retain Objectives 3.4.6.1, 3.4.6.2 and 3.4.6.3 and related policies as notified
Accept That part of this submission point supporting Objectives and Policies in 3.4.6.1, 3.4.6.2 and 3.4.6.3 is accepted because while other submissions have sought amendments they have been rejected.
General Submissions
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary
Decision Reasoning
Future Proof Implementation Committee
608.009 3.5 Rototuna Support Future Proof supports the retention as notified of the provisions relating to the Rototuna and Rotokauri Structure Plan.
Accept The submission point supports the retention of the Rototuna Structure Plan.
New Zealand Transport Agency
924.020 Support in part
Amend 3.5 to strengthen the weight given to the provisions (Rototuna Structure Plan).
Reject The amendment sought would not support the purpose of structure plans within the policy framework of the plan. As set out in section 3.1 Purpose a structure plan illustrates the proposed layout of a future development area. As set out in section 3.1d) the purpose of a structure plan is to plan for the future in an integrated manner along with having guiding principles specific to individual structure plan areas along with mapping that shows the intended pattern of development. Under the purpose it clearly indicates that the information is at a high level and does not typically go into such detail. A structure plan does not control development, it indicates future land uses. The actual development of the land areas are managed through the controls of the underlying zones that are set out through the zoning chapters of the Plan. Accordingly, as the whole intent of a structure plan is to set the scene and not to drill down into the final design format, leaving that to the subdivision, land use activities via resource consent the language of section 3.5c) is appropriate
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 26 of 63
3.5 Vision
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
New Zealand Transport Agency
924.021 3.5 Vision Support Retain ‘Vision’ for Rototuna in section 3.5 as notified. Accept Submission is accepted as it supports 3.5 Vision.
3.5.1 Objective and Policies
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Jacqueline, Steward Charles Jeffery Peters
334.005 3.5.1 Objectives and Policies
Support 3.5.1 Rototuna Structure Plan Objectives and Policies. Supports Policy 3.5.1a; Seeks a pedestrian/cycle path at a midway point between where Kay Road and Horsham Downs Road cross the Expressway.
Accept The submission point is accepted as it will:
Support the objectives and policies of the plan;
The inclusion of the pedestrian and cycle network ensures consistency of multi modal transport network through out the Rototuna Structure Plan area.
Kirkdale Investments Limited and Kimbrae Farms Limited
FS178.008
Support Accept The further submission is accepted because the submission point (334.005) to which this further submission relates has been accepted
Waikato Regional Council
714.015 Support in part
3.5.1 Objectives and Policies (Rototuna Structure Plan) - Retain objective 3.5.1.3 and policy 3.5.1.3a in relation to ensuring the transport network is managed and developed in a way that provides for all modes of transport in an integrated manner. Add new objective and policies to address landscape features and natural features, ecological corridors, ecological enhancement, retention of existing indigenous vegetation and habitat required to contribute to the viability of ecological fragments.
Accept in Part
The submission point is accepted in part because: The support for the retention of Objective 3.5.1.3 and policy 3.5.1.3a is accepted Addition of a new objective and policies to address viability of ecological fragments in the Rototuna Structure Plan is rejected as there area already adequate policy framework though out the plan to address the concerns.
New Zealand Transport Agency
FS270.013
Support Accept in Part
The further submission is accepted in part as the submission point (714.015) to which this further submission relates has also been accepted in part.
New Zealand Transport Agency
924.022 Support Retain Objective 3.5.1.4 (Rototuna Structure Plan) and policies 3.5.1.4b and 3.5.1.4c as notified.
Accept Submission is accepted as it supports Objective 5.5.1.4.
Structure Plan Components 3.5.2.4 Transportation Network
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
New Zealand Transport Agency
924.023 3.5.2.4 Transportation Network
Support Retain 3.5.2.4 a), c), d), e), f) and g). Amend the Plan to recognise that a blanket approach to mitigation will not be appropriate for development to the north-east of the Waikato Expressway Designation (aligned with our specific submission points on Chapter 13) and that 3.5.2.4 b) is amended to ensure this is made clear.
Accept in Part
The submission is accepted in part because:
There is support to retain 3.5.2.4a), c), d), e), f) and g)
The relief sought to modify 3.5.2.4b) is rejected.
Kirkdale Investments Limited and Kimbrae Farms Limited
FS178.011
Oppose Accept The further submission is accepted because the submission point (924.023) pertaining to 3.5.2.4b) to which this further submission relates has been rejected.
Structure Plan Components 3.5.2.5 Stormwater
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Barry Harris (Hamilton City Council)
1146.007 3.5.2.5 Stormwater
Support in part
Amend 3.5.2.5 f) (Stormwater, Rototuna Structure Plan) as set out in the submission to delete reference to the avoidance of attenuation ponds.
Accept The submission point seeking amendment to 3.5.2.5f) be accepted as:
the intent of the Plan is not affected
clear guidance will be provided to plan users
alignment with the anticipated storm water attenuation in the Te Awa o Katapaki Lower Catchment will be achieved
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 27 of 63
Alignment with the catchment management requirements of the Waikato Regional Council will be achieved.
Structure Plan Components 3.5.2.6 Water and Wastewater
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Barry Harris (Hamilton City Council)
1146.008 3.5.2.6 Water and Wastewater
Support in part
Amend 3.5.2.6 d) (Water and Wastewater - Rototuna Structure Plan) as set out in the submission by adding reference to Council in terms of early interaction with developers.
Accept The submission point seeking amendment to 3.5.2.6d) be accepted as:
the intent of the Plan is not affected
clear guidance will be provided to plan users
Structure Plan Components 3.5.2.7 Schools
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
The Roman Catholic Bishop of the Diocese of Hamilton
953.001 3.5.2.7 Schools Support in part
Retain 3.5.2.7 (a) (Schools in Rototuna Structure Plan area) with amendment to reference future plans of the Roman Catholic Bishop of the Diocese of Hamilton (RCBDH).
Accept The modifications will provide more clarity for plan users of the expected school to be anticipated in the Rototuna area.
Appendix 2 Figure 2-4, 2-5, and 2-6
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Borman Parkside LP
874.001 Figure 2-4 Rototuna Structure Plan-Land Use
Oppose Figure 2-4 Rototuna Structure Plan-Land Use - Seeks the deletion of 'The Transport Corridor' on Figure 2-4 and 'The Local Transport Corridor' on Figure 2-5.
Reject The submission point is rejected as it is fundament for the key development elements of a structure plan to be identified to ensure:
Clarity and guidance to plan users
Alignment with the objective and policy framework of the plan The overarching purpose of a structure plan and all corresponding maps, figures, diagrams is to set the scene of how the area is intended to be developed, and to ensure development is undertaken in a manner to safeguard integrated planning of the area. Key elements of enabling this to occur are via the structure plan identifying nodes, networks and zoning areas. Figure 2-4 of the Rototuna Structure Plan suite identifies the land uses (Figure 2-5 identifies transport networks and Figure 2-6 cycling and walking networks). The transport network is also important to ensure a high level of connectivity is achieved. In addition, the placement of these key elements within both Figure 2-4 and 2-5 have not been altered from that confirmed through the decisions to V12 and are considered to inform developers of the expectations and overall configuration of the networks in which they are to develop within. The submitter also correctly identifies that their property must be developed via a comprehensive development plan. . It is considered appropriate that Figure 2-4 remain unaltered.
New Zealand Transport Agency
924.198 Support Retain Figure 2-4 Rototuna Structure Plan - Land Use as notified, subject to changes requested in the wider submission.
Accept in Part
The submission point is accepted as it supports the retention of Figure 2-4.
Transpower New Zealand Ltd
1083.003 Support a) Retain Figure 2-4: Rototuna Structure Plan – Land Use in Appendix 2 including the identification of Transpower’s existing electricity transmission lines and the electricity transmission corridor without modification. b) Adopt any other such relief, including additions, deletions or consequential amendments necessary as a result of the matters raised in these submissions, as necessary to give effect to this submission
Accept The submission point is accepted as it supports the retention of Figure 2-4.
Borman Parkside LP
874.002 Figure 2-5 Rototuna Structure Plan-Transport Network
Support in part
Figure 2-5 Rototuna Structure Plan-Transport Network - Seeks the deletion of 'The Transport Corridor' on Figure 2-4 and 'The Local Transport Corridor' on Figure 2-5.
Reject The submission point is rejected as it is fundament for the key development elements of a structure plan to be identified to ensure:
Clarity and guidance to plan users
Alignment with the objective and policy framework of the plan Figure 2-5 identifies transport networks that are important to ensure a high level of connectivity is achieved and as such in a structure plan context is important, along with the other key elements (such as land uses, multimodal transport networks, cycling and walking) are important, and regarded as necessary to include in the Structure Plan. It is unclear as to the submitter’s direct concerns and desire to have Figure 2-5 deleted when support for the notation is indicated. Therefore, without this clarity, and the importance of keeping the transport network information to ensure a completeness of information is available to plan users it is considered that Figure 2-5 remain unaltered.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 28 of 63
New Zealand Transport Agency
924.199 Support in part
Amend Figure 2-5 to include proposed/indicative Pubic Transport networks in the Rototuna Structure Plan area transport plan as per the maps in Variation 12 (Plan Change 1, Operative District Plan).
Reject The submission is rejected as the addition of information proposed by the submitter that Council does not have control over would impact on the administration of the plan. The determination of the bus network and route management is the responsibility of the Waikato Regional Council. Nevertheless, the routes, in most cases follow the collector road network set out through the transport hierarchy determined by the City. The retention or modification of these routes is at the sole discretion of the Regional Council as so if that information was also imbedded into the Plan there would be an issue of having to update the Plan. Accordingly, it is not considered appropriate to specifically identify PT network within the Plan.
Borman Parkside LP
874.003 Figure 2-6 Rototuna Cycling and Walking Network
Support Figure 2-6 Rototuna Cycling and Walking Network - In the submitter's view, Figure 2-6 indicates a cycling and walking network path(s) along the north side of Future Reserve. Should these objections not be upheld in their submission, Council as the future owner of the reserve will be expected to provide the major funding for the corridors.
Accept in part
This submission is accepted in part as although there is support for the retention of Figure 2-6, there is also a question raised about funding and who is responsible which is out side of the scope of this First Schedule process.
New Zealand Transport Agency
924.200 Support in part
Amend Figures 2-4 (Rototuna Structure Plan - Land Use), 2-5 (Rototuna Structure Plan - Transport Network), and 2-6 (Rototuna Cycling and Walking Network) to correctly show consistent walking and cycling networks.
Accept The amendments to Figure 4-5 corrects an editorial error and ensures consistency of information that will improve plan administration.
Maps
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Rototuna Holdings Ltd
1032.001
Zoning Map 3A
Support in part
Retain the Large Lot Residential zoning for the land on the northern side of the Waikato Expressway, as shown on Maps 3, 4, 5 and 11; Amend Maps 3, 4, 5 and 11 to include a 20m wide strip of Neighbourhood Open Space zone to separate the Large Lot Residential zone and the Waikato Expressway designation; Such other additional or consequential relief as is necessary to achieve consistency with the above and to satisfy the concerns of the submitter.
Accept in part
Whilst the submission sought to retain the large lot residential zone on the northern side of the Waikato Expressway as a consequence of Variation 12 being resolved through the Environment Court agreement has been reached between all the parties to zone the land as Special Character Zone and an open space area will be identified on the Structure Plan.
Kirkdale Investments Limited and Kimbrae Farms Limited
FS178.001
Support Accept in part
FS178.001 is accepted in part as submissn 1032.001 is accepted in part
Nancy Cooper
FS255.001
Support Accept in part
FS255.001 is accepted in part as submissn 1032.001 is accepted in part
Roland Olliver Cooper
FS281.001
Support Accept in part
FS281.001 is accepted in part as submissn 1032.001 is accepted in part
Rototuna Holdings Ltd
1032.002 Zoning Map 4A
Support in part
Retain the Large Lot Residential zoning for the land on the northern side of the Waikato Expressway, as shown on Maps 3, 4, 5 and 11; Amend Maps 3, 4, 5 and 11 to include a 20m wide strip of Neighbourhood Open Space zone to separate the Large Lot Residential zone and the Waikato Expressway designation; Such other additional or consequential relief as is necessary to achieve consistency with the above and to satisfy the concerns of the submitter.
Accept in part
Whilst the submission sought to retain the large lot residential zone on the northern side of the Waikato Expressway as a consequence of Variation 12 being resolved through the Environment Court agreement has been reached between all the parties to zone the land as Special Character Zone and an open space area will be identified on the Structure Plan.
Kirkdale Investments Limited and Kimbrae Farms Limited
FS178.001
Support Accept in part
FS178.001 is accepted in part as submission 1032.002 is accepted in part
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 29 of 63
Nancy Cooper
FS255.002
Support Accept in part
FS255.002 is accepted in part as submission 1032.002 is accepted in part
Roland Olliver Cooper
FS281.002
Support Accept in part
FS281.002 is accepted in part as submission 1032.002 is accepted in part
Rototuna Holdings Ltd
1032.003 Zoning Map 5A
Support in part
Retain the Large Lot Residential zoning for the land on the northern side of the Waikato Expressway, as shown on Maps 3, 4, 5 and 11; Amend Maps 3, 4, 5 and 11 to include a 20m wide strip of Neighbourhood Open Space zone to separate the Large Lot Residential zone and the Waikato Expressway designation; Such other additional or consequential relief as is necessary to achieve consistency with the above and to satisfy the concerns of the submitter.
Accept in part
Whilst the submission sought to retain the large lot residential zone on the northern side of the Waikato Expressway as a consequence of Variation 12 being resolved through the Environment Court agreement has been reached between all the parties to zone the land as Special Character Zone and an open space area will be identified on the Structure Plan.
Kirkdale Investments Limited and Kimbrae Farms Limited
FS178.001
Support Accept in part
FS178.001 is accepted in part as submission 1032.003 is accepted in part
Nancy Cooper
FS255.003
Support Accept in part
FS255.003 is accepted in part as submission 1032.003 is accepted in part
Roland Olliver Cooper
FS281.003
Support Accept in part
FS281.003 is accepted in part as submission 1032.003 is accepted in part
Rototuna Holdings Ltd
1032.004 Zoning Map 11A
Support in part
Retain the Large Lot Residential zoning for the land on the northern side of the Waikato Expressway, as shown on Maps 3, 4, 5 and 11; Amend Maps 3, 4, 5 and 11 to include a 20m wide strip of Neighbourhood Open Space zone to separate the Large Lot Residential zone and the Waikato Expressway designation; Such other additional or consequential relief as is necessary to achieve consistency with the above and to satisfy the concerns of the submitter.
Accept in part
Whilst the submission sought to retain the large lot residential zone on the northern side of the Waikato Expressway as a consequence of Variation 12 being resolved through the Environment Court agreement has been reached between all the parties to zone the land as Special Character Zone and an open space area will be identified on the Structure Plan.
Kirkdale Investments Limited and Kimbrae Farms Limited
FS178.001
Support Accept in part
FS178.001 is accepted in part as submission 1032.004 is accepted in part
Nancy Cooper
FS255.004
Support Accept in part
FS255.004 is accepted in part as submission 1032.004 is accepted in part
New Zealand Transport Agency
FS270.087
Oppose Accept in part
FS270.087 is accepted in part as submission 1032.004 is accepted in part
Roland Olliver Cooper
FS281.004
Support Accept in part
FS281.004 is accepted in part as submission 1032.004 is accepted in part
3.6 Rotokauri
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Future Proof Implementation
608.010 3.6 Rotokauri Support Retain section 3.6 Rotokauri Structure Plan Accept in part
Other submissions sought amendments or deletions to the provisions that this submission relates to. These other submissions have been declined for the reasons stated.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 30 of 63
Committee
Hounsell Holdings Ltd
1104.015 3.6 Rotokauri Oppose Provide Rules in all zones so that any activity that compromises the ability to give effect to a structure plan outcome requires consent as a Restricted Discretionary Activity. Discretion would be restricted to matters relating to alternative methods and locations that can avoid adverse effects on structure plan outcomes, and include conditions that limit consent duration.
Accept in Part
Chapter 3 sets out objectives and policies that apply to all Structure Plan areas. When subdivision and/or development are proposed within a Structure Plan area it must be in accordance with these objectives and policies. Under the analysis of submissions to Objective 3.3 in the Objectives and Policies section above, it has been determined that this wording change from being ‘in accordance’ to ‘consider where relevant’. A Structure Plan is not meant to be a blueprint and therefore some flexibility is provided in the way in which the provisions of the Structure Plan are given effect to, particularly if some objectives and policies are not relevant. See Tracked Changes for Chapter 3.
Porter Properties Ltd
1164.011 3.6 Rotokauri Oppose Amend the Plan so that any activity that compromises the ability to give effect to a structure plan outcome requires consent as a Restricted Discretionary Activity with discretion restricted to matters relating to alternative methods and locations that can avoid adverse effects on structure plan outcomes, and include conditions that limit consent duration.
Accept in Part
Chapter 3 sets out objectives and policies that apply to all Structure Plan areas. When subdivision and/or development are proposed within a Structure Plan area it must be in accordance with these objectives and policies. Under the analysis of submissions to Objective 3.3 in the Objectives and Policies section above, it has been determined that this wording change from being ‘in accordance’ to ‘consider where relevant’. A Structure Plan is not meant to be a blueprint and therefore some flexibility is provided in the way in which the provisions of the Structure Plan are given effect to, particularly if some objectives and policies are not relevant. See Tracked Changes for Chapter 3.
Hamilton JV Investment Company Ltd
1170.015 3.6 Rotokauri Oppose Amend the Plan so that any activity that compromises the ability to give effect to a structure plan outcome requires consent as a Restricted Discretionary Activity with discretion restricted to matters relating to alternative methods and locations that can avoid adverse effects on structure plan outcomes, and include conditions that limit consent duration.
Accept in part
Chapter 3 sets out objectives and policies that apply to all Structure Plan areas. When subdivision and/or development are proposed within a Structure Plan area it must be in accordance with these objectives and policies. Under the analysis of submissions to Objective 3.3 in the Objectives and Policies section above, it has been determined that this wording change from being ‘in accordance’ to ‘consider where relevant’. A Structure Plan is not meant to be a blueprint and therefore some flexibility is provided in the way in which the provisions of the Structure Plan are given effect to, particularly if some objectives and policies are not relevant. See Tracked Changes for Chapter 3.
Natural Areas and Lake Waiwhakareke
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Waikato Regional Council
714.016 3.6.1 Objectives and Policies
Support in part
3.6.1 Objectives and Policies (Rotokauri Structure Plan). a) Amend Objective 3.6.1.1 by referencing protection and enhancement of the ecological functioning of key natural areas. b) Add new Policy 3.6.1.1c as follows: 'Subdivision and development provide for the protection and enhancement of ecological connections to, and ecological functioning of, Lake Waiwhakareke'.
Reject This submission point seeks amendments that would duplicate other provisions of the Plan, in particular Objective 20.2.1, and reduce the effectiveness and efficiency of the Plan in terms of achieving its stated objectives and policies and the purpose and principles of the RMA.
It is considered that the objective and policy framework in relation to the Natural Open Space Zone, Natural Environments and Special Character Zones (Special Natural Zone) is sufficient to ensure that subdivision and development recognizes and enhances the natural values of Lake Waiwhakareke, and therefore no changes are madein relation to this submission.
Barry Laurence Flay
350.005 Figure 2-8 Rotokauri Structure Plan-Land Use
Support Supports the inclusion of Lot 2 D P 425316 as part of the Future Reserves namely the Waiwhakareke Natural Heritage Park.
Defer This matter is deferred and the matter will be reconvened at a later date
Environmental Research Institute, University of Waikato
1008.004 3.6.1 Objectives and Policies
Support in part
Amend Objective 3.6.1.1 (Rotokauri Structure Plan) to include the protection and enhancement of the ecological functioning of key natural areas.
Reject This submission point seeks amendments that would duplicate provisions of the Plan, in particular Objective 20.2.1 and reduce the effectiveness and efficiency of the Plan in terms of achieving its stated objectives and policies and the purpose and principles of the RMA. It is considered that Objective 20.2.1 already provides for the relief sought by the Environmental Research Institute to the Rotokauri Structure Plan Chapter. The Natural Open Space Zone also contains objectives and policies relating to ecological issues. The submissions are therefore rejected as the matters raised within them are already appropriately dealt with in other sections of the Plan.
Iris & Fred Bryant
972.002 Figure 2-8 Rotokauri Structure Plan-Land Use
Oppose Seeks confirmation of the Future Reserves surrounding Lake Waiwhakareke in its entirety as shown on the Rotokauri Structure Plan and on Zoning Map 33A
Defer This matter is deferred and the matter will be reconvened at a later date
Janice Ann Verran
854.004 Zoning Map 24A
Oppose Map 24A-Retain land at 173 Rotokauri Road as Residential. Defer This matter is deferred and the matter will be reconvened at a later date
Max Walker Verran
855.005 Zoning Map 24A
Oppose Map 24A-Retain land at 173 Rotokauri Road as Residential. Defer This matter is deferred and the matter will be reconvened at a later date
Michelle Le Prou
201.001 Zoning Map 33A
Support Map 33A and Figure 2-10: Rotokauri Structure Plan - Reserve Network - Confirm Future Reserves surrounding Lake Waiwhakareke.
Defer This matter is deferred and the matter will be reconvened at a later date William Wie & Patricia Tekore Moana
352.004 Zoning Map 33A
Support in part
Map 33A and Rotokauri Structure Plan - Retain the Open Space Zoning surrounding Lake Waiwhakareke.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 31 of 63
Barry James Crawshaw
870.001 Zoning Map 33A
Support Map 33A and Rotokauri Structure Plan - Confirm Future Reserves surrounding Lake Waiwhakareke.
School Notation
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Hounsell Holdings Ltd
1104.008 3.6.2.1 Suburban Centres Concept Plan
Oppose The notation of School on the submitter's land be deleted from Figure 2-11 (Rotokauri Neighbourhood Centre) or is clearly shown as “indicative” in the text and maps. Specific provision be made for a school shown on a Structure Plan as a Permitted Activity.
Accept in Part
Amendments clarify the indicative nature of the location of future school provision in the Rotokauri Structure Plan area. The amendments will improve the internal consistency of the Plan and the clarity of the Plan for users. Amendments to make schools in the Structure Plan area a permitted activity are not accepted as the relief sought is not considered to be a valid resource management approach.
Hamilton JV Investment Company Ltd
1170.008 3.6.2.1 Suburban Centres Concept Plan
Oppose The notation of School on the submitters land be deleted from Figure 2-11 or is clearly shown as “indicative” in the text and maps. Specific provision be made for a school shown on a Structure Plan as a Permitted Activity.
Accept in Part
Amendments clarify the indicative nature of the location of future school provision in the Rotokauri Structure Plan area. The amendments will improve the internal consistency of the Plan and the clarity of the Plan for users. Amendments to make schools in the Structure Plan area a permitted activity are not accepted as the relief sought is not considered to be a valid resource management approach.
Suburban Centre
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Rotokauri Developments Ltd
1015.016 3.6.2.3 Suburban Centre
Oppose 3.6.2.3 Suburban Centre - Delete 3.6.2.3c
Accept It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed.
The Structure plan identified the areas for employment (industrial zone), suburban centre (business 5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps.
As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties.
Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e).
See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Hounsell Holdings Ltd
1104.009 3.6.2.3 Suburban Centre
Oppose 3.6.2.3 Suburban Centre - Remove staging from Rotokauri Suburban Centre.
Accept It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed.
The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps.
As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties.
Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e).
See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Hamilton JV Investment Company Ltd
1170.009 3.6.2.3 Suburban Centre
Oppose 3.6.2.3 (c). Remove staging from Rotokauri Suburban Centre.
Accept It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed.
The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps.
As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties.
Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e).
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 32 of 63
See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Rotokauri Developments Ltd
1015.015 Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network
Oppose Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network - Amend Figure 2-9 to include the entire suburban centre zone within Stage 1.
Accept It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed.
The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps.
As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties.
Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e).
See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Fonterra Co-operative Group Limited
FS89.001 Oppose Accept FS89.001 is accepted as submission 1015.015 is accepted
Passenger Transport Facility
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
KiwiRail Holdings Limited
366.002 3.6.2.6 Passenger Transport Facility
Support KiwiRail supports the provision of PT facilities in the Structure Planning for Rotokauri.
Accept Other submissions sought amendments or deletions to the provisions that this submission relates to. These other submissions have been declined for the reasons stated specifically.
Hamilton JV Investment Company Ltd
1170.064 Figure 2-8 Rotokauri Structure Plan-Land Use
Oppose Amend Figure 2-8 Rotokauri Structure Plan-Land Use in accordance with the new figure attached to the submission, including by: • Adding staging boundaries. • Labelling school sites as “indicative only”. • Accurately reflecting the location of the Passenger Transport Location on Figure 3.6.2b. • Either remove the Future Reserve notation from the submitters land or designate the land. • Show the Tasman Road link remaining to align with Figure 3.6.2b.
Accept in part
The location of the Passenger Transport Location shown on Figure 3.6.2b is not inconsistent with the southern location shown on Figure 2-8 and therefore no change is required. The submitter appears to have incorrectly interpreted the Structure Plan boundary notation, shown as a dashed black line on Figures 2-8 and 2-9 as representing road stopping of part of Tasman Road which is not the case. No changes to Figures 2-8 or 2-9 are required in response to the submissions. The Proposed Plan outlines that a location on Tasman Road, adjacent to The Base has been identified as the preferred site to accommodate the progressive development of a bus-based passenger transport facility (PT Facility) and its longer term integration with rail. It is also stated that there is potential for a second PT facility further north at the junction of Te Kowhai Road and Tasman Road, to integrate the passenger transport network with the surrounding land use activities. Figures 3.6.2a and 3.6.2b illustrate how the establishment of an integrated bus/rail facility could be achieved in the Tasman Road location adjacent to The Base. The illustrations provide for an eventual facility. Both of the illustrated locations would eventually require land outside of the current road and rail reserve. Consequently, it is anticipated that the additional land requirements may need to be safeguarded through the designation process. As identified above it is accepted that the identified area for the suburban centre on the structure plan be included within stage 1. The locations of the public transport facilities were determined via consent order in settlement of an appeal to Variation 18. The location shown on Figure 3.6.2b is not inconsistent with the southern location shown on Figure 2-8 and therefore no change is required The submitter appears to have incorrectly interpreted the Structure Plan boundary notation, shown as a dashed black line on Figures 2-8 and 2-9 as representing road stopping of part of Tasman Road which is not the case. No changes to Figures 2-8 or 2-9 are required in response to the submissions.
Hamilton JV Investment Company Ltd
1170.065 Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network
Oppose Amend Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network by: • Adding areas to the north and west of the suburban centre as Part of Stage 1 as shown on submission attachments. • Provide an alternative route for the central north south collector that avoids the need for a large cut and overpass. • Show the Tasman Road link remaining to align with Figure 3.6.2b.
Infrastructure
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Hounsell Holdings Ltd
1104.014 3.6.3.1 Water, Wastewater and Stormwater Services
Oppose Amend 3.6.3.1 Water, Wastewater and Stormwater Services (Rotokauri) to ensure up-to-date commentary that reflects work/studies undertaken to date (i.e. the extension of the wastewater interceptor/stormwater management recent modeling and catchment planning).
Accept
This submission point seeks amendments that would update the provisions to reflect recent developments and would improve the effectiveness and efficiency of the Plan in terms of achieving its stated objectives and policies and the purpose and principles of the RMA.
Porter Properties Ltd
1164.010 3.6.3.1 Water, Wastewater and Stormwater Services
Oppose 3.6.3.1 Water, Wastewater and Stormwater Services (Rotokauri). Amend the text to ensure up-to-date commentary on matters relating to Rotokauri, such as the extension of the wastewater interceptor and stormwater management relating to outcomes of recent modelling and catchment planning.
Accept This submission point seeks amendments that would update the provisions to reflect recent developments and would improve the effectiveness and efficiency of the Plan in terms of achieving its stated objectives and policies and the purpose and principles of the RMA.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 33 of 63
Hamilton JV Investment Company Ltd
1170.014 3.6.3.1 Water, Wastewater and Stormwater Services
Oppose 3.6.3.1 Water, Wastewater and Stormwater Services (Rotokauri Structure Plan). Update commentary to reflect events that have occurred already at Rotokauri such as the extension of the wastewater interceptor and stormwater management outcomes of recent modelling and catchment planning.
Accept This submission point seeks amendments that would update the provisions to reflect recent developments and would improve the effectiveness and efficiency of the Plan in terms of achieving its stated objectives and policies and the purpose and principles of the RMA.
New Zealand Transport Agency
924.025 3.6.3.2 Roading Support in part
Amend 3.6.3.2 d) as set out in the submission to remove reference to the 4-laning on Avalon Drive as this is now complete.
Accept This submission point seeks amendments that would update the provisions to reflect recent developments and would improve the effectiveness and efficiency of the Plan in terms of achieving its stated objectives and policies and the purpose and principles of the RMA.
Porter Properties Ltd
1164.051 Features Map 15B
Oppose Features Map 15B - Designate the collector road between Ruffell Road and Gilchrist Street not covered by an approved CDP
Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA. Further, Section 3.6.2.7 (d) (Transportation Network) clarifies that Council utilises the designation process for new arterial corridors. This does not include collector roads.
Hamilton JV Investment Company Ltd
1170.077 Features Map 24B
Oppose Amend Features Map 24B by including a designation for the Green Central Corridor. Designate the remaining collector road link between Ruffell Road and Gilchrist Street.
Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA.
Hamilton JV Investment Company Ltd
1170.078 Features Map 15B
Oppose Amend Features Map 15B by designating the remaining collector road link between Ruffell Road and Gilchrist Street.
Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA. Further, Section 3.6.2.7 (d) (Transportation Network) clarifies that Council utilises the designation process for new arterial corridors. This does not include collector roads.
Hounsell Holdings Ltd
1104.011 3.6.2.7 Transportation Network
Oppose 3.6.2.7 Transportation Network (Rotokauri Structure Plan): Enable use of designation process for protection and acquisition of any transport corridors in order to achieve network outcomes.
Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA. Further, Section 3.6.2.7 (d) (Transportation Network) already clarifies that Council utilises the designation process for new arterial corridors.
Porter Properties Ltd
1164.008 3.6.2.7 Transportation Network
Oppose 3.6.2.7 Transportation Network. Enable use of designation process for protection and acquisition of any transport corridors in order to achieve network outcomes.
Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA. Further, Section 3.6.2.7 (d) (Transportation Network) already clarifies that Council utilises the designation process for new arterial corridors.
Porter Properties Ltd
1164.052 Features Map 24B
Oppose Features Map 24B - Designate the collector road between Ruffell Road and Gilchrist Street not approved by a CDP.
Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA. Further Section 3.6.2.7 (d) (Transportation Network) clarifies that Council utilises the designation process for new arterial corridors. This does not include collector roads.
Porter Properties Ltd
1164.046 Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network
Oppose Amend Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network to: • Remove road loop from structure plan and consider alternative local network layout. • Realign loop road to the east of the north south collector to the layout approved in the Te Kowhai Comprehensive Development Cell Comprehensive Development Plan.
Accept The submission point is accepted and that the collector road from the Te Kowhai Road north to its connection with Ruffell Road is deleted from the structure plan. The removal of the structure plan road is considered appropriate as all of the site that the proposed road was to go through is owned by the submitter and is currently being developed for the submitter’s activities. Removal of the road does not compromise future development as the subject land is in one ownership. The removal of the structure plan road result in the efficient use of the existing resources such as the existing road corridors and associated services located within such corridors.
New Zealand Transport Agency
FS270.086 Oppose Reject The proposed amendment will provide the necessary connectivity and ensure efficient functioning of the transport network.
B.W & I.V Parsons
607.001 Figure 2-8 Rotokauri Structure Plan-Land Use
Oppose That Figure 2-8 (Rotokauri Structure Plan-Land Use) be amended to delete reference to a Transport Corridor crossing Lot 2 DPS 79420 and any other land that is outside of the Rotokauri Structure Plan area.
Reject The collector road is a necessary component of the overall transport network in the area. This submission point seeks amendments that would reduce the effectiveness and efficiency of the Plan in terms of achieving its stated objectives and policies and the purpose and principles of the RMA. Given that there is still development yet to occur in this area, the ability to require a collector road formation to ensure that The Boulevard continues so that it will in time connect to Ruffell Road is an important aspect of the overall network planning. The future collector road is also shown on Figure 15-5B, the Transport Corridor Hierarchy Plan in Appendix 15-5. The requirement under the Structure Plan chapters to be in general accordance with the provisions shown on structure plans is necessary in order to ensure that the Collector Road is developed at such a time as the site is developed. Without a collector road link, The Boulevard remains a cul-de-sac with all traffic movements required to head south to the Te Kowhai Road roundabout. The future collector road is shown on the Rotokauri Structure Plan in the Operative District Plan as a result of its consideration as part of the Rotokauri Structure Plan Variation 18 to the then Proposed District Plan 2001
B.W & I.V Parsons
607.002 Figure 2-9 Rotokauri
Oppose That Figure 2-9 (Rotokauri Structure Plan-Staging and Transport Network) be amended to delete reference to a Collector Transport
Reject The collector road is a necessary component of the overall transport network in the area. This submission point seeks amendments that would reduce the effectiveness and efficiency of the Plan in terms of achieving its stated objectives and policies and the purpose
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 34 of 63
Structure Plan-Staging and Transport Network
Corridor crossing Lot 2 DPS 79420 and any other land (including those identified as containing a Major Arterial Transport Corridor) that is outside of the Rotokauri Structure Plan area.
and principles of the RMA. Given that there is still development yet to occur in this area, the ability to require a collector road formation to ensure that The Boulevard continues so that it will in time connect to Ruffell Road is an important aspect of the overall network planning. The future collector road is also shown on Figure 15-5B, the Transport Corridor Hierarchy Plan in Appendix 15-5. The requirement under the Structure Plan chapters to be in general accordance with the provisions shown on structure plans is necessary in order to ensure that the Collector Road is developed at such a time as the site is developed. Without a collector road link, The Boulevard remains a cul-de-sac with all traffic movements required to head south to the Te Kowhai Road roundabout. The future collector road is shown on the Rotokauri Structure Plan in the Operative District Plan as a result of its consideration as part of the Rotokauri Structure Plan Variation 18 to the then Proposed District Plan 2001
Wintec
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Wintec 707.012 Figure 2-11 Rotokauri Neighbourhood Centre
Oppose Figure 2-11 Rotokauri Neighbourhood Centre. That figure 2-11 be amended as per Appendix 2 attached to the submission. Figure 2-11 shows the “triangle” (Pt Lot 1 DPS 16911) as part of Wintec. This site has been zoned Industrial within the proposed plan and is within the Rotokauri Employment Area. Therefore Figure 2-11 should be amended to reflect this.
Accept The submission would clarify the proposed use of the land and provide consistency between Figure 2-11, Figure 2-8 (Rotokauri Structure Plan – Land Use) and the zoning maps.
Barry Harris (Hamilton City Council)
1146.116 Figure 2-11 Rotokauri Neighbourhood Centre
Support in part
Amend Figure 2-11 to reflect land use and ownership changes that have occurred in relation to WINTEC and the Employment Area.
Accept The submission would clarify the proposed use of the land and provide consistency between Figure 2-11, Figure 2-8 (Rotokauri Structure Plan – Land Use) and the zoning maps.
Everton Trust 344.003 Figure 2-8 Rotokauri Structure Plan-Land Use
Oppose Amend Figure 2-8 to provide for the intended future use of the property recognised as Lot 1 DP 450285 for Residential purposes.
Accept The submission would clarify the proposed use of the land. There are no sound resource management grounds for excluding Lot 1 from being identified for residential use. The amendment to Figure 2-8 will reflect the decision under 344.001 and 344.002 to re-zone the property to Residential.
Staging - Industrial
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Modern Transport Limited
323.002 Figure 2-8 Rotokauri Structure Plan-Land Use
Support Supports land described as Lot 2 DPS 15248 (SA13B/395) at Te Kowhai Road being identified for industrial land uses in the Figure 2-8 Rotokauri Structure Plan - Land Use.
Accept The proposed amendment provides a sensible and practical staging boundary.
Modern Transport Limited
323.003 Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network
Oppose Requests that Lot 2 DPS 15248 (SA13B/395) at Te Kowhai Road be included within Stage 1 of the Figure 2-9 Rotokauri Structure Plan – Staging and Transport Network.
Accept The proposed amendment provides a sensible and practical staging boundary.
Hounsell Holdings Ltd
1104.055 Zoning Map 15A Oppose Amend Map 15A to extend Stage 1 Rotokauri to include additional industrial land to the south of the Te Kowhai Road Extension.
Accept in part
Inclusion of the additional land within the Stage 1 boundary is accepted, however the amended Stage 1 boundary should include be amended to include all properties to be re-zoned Industrial as a result of submissions 914.001, 914.002914.001, 914.002, 916.002, 229.002, 323.001, 323.002, and 323.003.
Hamilton JV Investment Company Ltd
1170.074 Zoning Map 15A Oppose Map 15A- Increase Stage 1 Rotokauri to include additional industrial land to the south of the Te Kowhai Road extension.
Accept in part
Inclusion of the additional land within the Stage 1 boundary is accepted, however the amended Stage 1 boundary should be amended to include all properties to be re-zoned Industrial as a result of submissions 914.001, 914.002914.001, 914.002, 916.002, 229.002, 323.001, 323.002, 323.003.
Proposed New Business 7 Zone
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Porter Properties Ltd
1164.050 Zoning Map 15A Oppose Map 15A-amend by including an additional Business 7 Zone Neighbourhood Centre in the Te Kowhai CPD area.
Accept in Part
It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (Industrial Zone), suburban centre (Business 5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 35 of 63
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
New Zealand Transport Agency
924.024 3.6 Rotokauri Support in part
The submission point seeks amendments to Policy 3.6.1.2 (a), sections 3.6.1.2(a), 3.6.2.9(a) and 3.6.3.2 that would accurately reflect the current situation given that the Te Rapa Bypass is open and operational and would assist with the clarity of the Plan for users. An amendment is required to Figure 2-9 to reflect the change in function of the western portion of Koura Drive from minor to major arterial.
Accept The submission point seeks amendments to Policy 3.6.1.2 (a), sections 3.6.1.2(a), 3.6.2.9(a) and 3.6.3.2 that would accurately reflect the current situation given that the Te Rapa Bypass is open and operational and would assist with the clarity of the Plan for users. An amendment is required to Figure 2-9 to reflect the change in function of the western portion of Koura Drive from minor to major arterial.
Porter Properties Ltd
1164.006 3.6.1 Objectives and Policies
Oppose The submission point seeks amendments to Policy 3.6.1.2 (a) that would accurately reflect the current situation given that the Te Rapa Bypass is open and operational and would assist with the clarity of the Plan for users.
Accept The submission point seeks amendments to Policy 3.6.1.2 (a) that would accurately reflect the current situation given that the Te Rapa Bypass is open and operational and would assist with the clarity of the Plan for users.
Porter Properties Ltd
1164.009 3.6.2.9 Staging Oppose The submission point seeks amendments to Policy 3.6.1.2 (a) that would accurately reflect the current situation given that the Te Rapa Bypass is open and operational and would assist with the clarity of the Plan for users.
Accept The submission point seeks amendments to Policy 3.6.1.2 (a) that would accurately reflect the current situation given that the Te Rapa Bypass is open and operational and would assist with the clarity of the Plan for users.
Green Corridor
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Hounsell Holdings Ltd
1104.007 3.6.1 Objectives and Policies
Oppose 3.6.1 Objectives and Policies (Rotokauri Structure Plan): 3.6.1.1b Clarify terminology and/or identify the location of the central green corridor on Figure 2-10 3.6.1.2a Delete second sentence in policy.
Accept in part
The submission point seeks amendments to Figure 2-10 in relation to the central green corridor that will improve the internal consistency of the Plan, the clarity of the Plan for users and the administration and implementation of the Plan. The submission point seeks amendments to Policy 3.6.1.2 (a) that would accurately reflect the current situation given that the Te Rapa Bypass is open and operational and would assist with the clarity of the Plan for users.
Hamilton JV Investment Company Ltd
1170.007 3.6.1 Objectives and Policies
Oppose 3.6.1.1b (Rotokauri Structure Plan) - Clarify terminology and/or identify the location of the central green corridor on Figure 2-10. 3.6.1.2a (Rotokauri Structure Plan) - Delete second sentence in policy as the Te Rapa Bypass is now open and operational.
Accept in part
The submission point seeks amendments to Figure 2-10 in relation to the central green corridor that will improve the internal consistency of the Plan, the clarity of the Plan for users and the administration and implementation of the Plan. The submission point seeks amendments to Policy 3.6.1.2 (a) that would accurately reflect the current situation given that the Te Rapa Bypass is open and operational and would assist with the clarity of the Plan for users.
Porter Properties Ltd
1164.007 3.6.2.5 Open Space Network
Oppose 3.6.2.5 Open Space Network (Rotokauri) - Seeks the review of the reference to the central green corridor by clarifying terminology and/or identifying the location of the central green corridor on Figure 2-10.
Accept in part
The submission point seeks amendments to Figure 2-10 in relation to the central green corridor that will improve the internal consistency of the Plan, the clarity of the Plan for users and the administration and implementation of the Plan. The submission point seeks amendments to Policy 3.6.1.2 (a) that would accurately reflect the current situation given that the Te Rapa
Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Hamilton JV Investment Company Ltd
1170.071 Zoning Map 14A Oppose Map14A-Amend to add a Business 7 Zone Neighbourhood Centre to provide accessible local services to the northern areas within the Rotokauri Structure Plan; amend the extent of Stage 1 Rotokauri Structure Plan to increase.
Accept in Part
It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (industrial zone), suburban centre (Business 5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties. Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Te Rapa Bypass
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 36 of 63
Bypass is open and operational and would assist with the clarity of the Plan for users.
Hounsell Holdings Ltd
1104.013 3.6.2.8 Industrial
Oppose 3.6.2.8 Industrial (Rotokauri Structure Plan). Clarify terminology and/or identify the location of the central green corridor on Figure 2-10.
Accept in part
The submission point seeks amendments in relation to the central green corridor that will improve the internal consistency of the Plan, the clarity of the Plan for users and the administration and implementation of the Plan.
Hamilton JV Investment Company Ltd
1170.013 3.6.2.8 Industrial
Oppose 3.6.2.8 Industrial (Rotokauri Structure Plan). Clarify terminology and/or identify the location of the central green corridor on Figure 2-10.
Accept in part
The submission point seeks amendments in relation to the central green corridor that will improve the internal consistency of the Plan, the clarity of the Plan for users and the administration and implementation of the Plan.
Hounsell Holdings Ltd
1104.048 Figure 2-11 Rotokauri Neighbourhood Centre
Oppose Amend Figure 2-11 Rotokauri Neighbourhood Centre to show the indicative proposal for stormwater drainage through suburban centre including • Stormwater directed to the north of the suburban centre • Neighbourhood green located to the north and having a dual stormwater purpose.
Accept in part
The detailed stormwater solution will be determined by more detailed modeling at such a time as the area was developed. Notating Figure 2-11 (Rotokauri Neighbourhood Centre) as being ‘indicative’ only will provide clarification for Plan users.
Hamilton JV Investment Company Ltd
1170.067 Figure 2-11 Rotokauri Neighbourhood Centre
Oppose Amend Figure 2-11 Rotokauri Neighbourhood Centre to show the indicative proposal for stormwater drainage through suburban centre including • Stormwater directed to the north of the suburban centre • Neighbourhood green located to the north and having a dual stormwater purpose.
Accept in part
The detailed stormwater solution will be determined by more detailed modeling at such a time as the area was developed. Notating Figure 2-11 (Rotokauri Neighbourhood Centre) as being ‘indicative’ only will provide clarification for Plan users.
Hounsell Holdings Ltd
1104.050 Figure 2-13 Rotokauri Suburban Centre Primary Frontages
Oppose Amend Figure 2-13 Rotokauri Suburban Centre Primary Frontages to show the indicative proposal for stormwater drainage through suburban centre including • Stormwater directed to the north of the suburban centre • Neighbourhood green located to the north and having a dual stormwater purpose.
Accept in part
The detailed stormwater solution will be determined by more detailed modeling at such a time as the area was developed. Notating Figure 2-11 (Rotokauri Neighbourhood Centre) as being ‘indicative’ only will provide clarification for Plan users.
Hamilton JV Investment Company Ltd
1170.069 Figure 2-13 Rotokauri Suburban Centre Primary Frontages
Oppose Amend Figure 2-13 Rotokauri Suburban Centre Primary Frontages to show the indicative proposal for stormwater drainage through suburban centre including • Stormwater directed to the north of the suburban centre • Neighbourhood green located to the north and having a dual stormwater purpose.
Accept in part
The detailed stormwater solution will be determined by more detailed modeling at such a time as the area was developed. Notating Figure 2-11 (Rotokauri Neighbourhood Centre) as being ‘indicative’ only will provide clarification for Plan users.
Hounsell Holdings Ltd
1104.049 Figure 2-12 Rotokauri Interface Areas
Oppose Amend Figure 2-12 Rotokauri Interface Areas to show the indicative proposal for stormwater drainage through suburban centre including • Stormwater directed to the north of the suburban centre • Neighbourhood green located to the north and having a dual stormwater purpose.
Accept in part
The detailed stormwater solution will be determined by more detailed modeling at such a time as the area was developed. Notating Figure 2-11 (Rotokauri Neighbourhood Centre) as being ‘indicative’ only will provide clarification for Plan users.
Hamilton JV Investment Company Ltd
1170.068 Figure 2-12 Rotokauri Interface Areas
Oppose Amend Figure 2-12 Rotokauri Interface Areas to show the indicative proposal for stormwater drainage through suburban centre including • Stormwater directed to the north of the suburban centre • Neighbourhood green located to the north and having a dual stormwater purpose.
Accept in part
The detailed stormwater solution will be determined by more detailed modeling at such a time as the area was developed. Notating Figure 2-11 (Rotokauri Neighbourhood Centre) as being ‘indicative’ only will provide clarification for Plan users.
Hounsell Holdings Ltd
1104.057 Features Map 23B
Oppose Amend Features Map 23B by including a designation for the Green Central Corridor.
Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA.
Hamilton JV 1170.076 Features Map Oppose Amend Features Map 23B by including a designation for the Green Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 37 of 63
Investment Company Ltd
23B Central Corridor. requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA.
Hounsell Holdings Ltd
1104.058 Features Map 24B
Oppose Amend Features Map 24B by including a designation for the Green Central Corridor.
Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA.
Hamilton JV Investment Company Ltd
1170.077 Features Map 24B
Oppose Amend Features Map 24B by including a designation for the Green Central Corridor. Designate the remaining collector road link between Ruffell Road and Gilchrist Street.
Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA.
Hounsell Holdings Ltd
1104.056 Features Map 14B
Oppose Amend Features Map 14B by including a designation for the Green Central Corridor.
Reject The outcome sought by the submission is beyond the scope of the District Plan submission process. In accordance with the requirements of the RMA any new or altered designation must be initiated by the relevant requiring authority and is subject to sections 166 to 186 of the RMA.
Open Space Network
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Hounsell Holdings Ltd
1104.010 3.6.2.5 Open Space Network
Support in part
3.6.2.5 Open Space Network (Rotokauri): Clarify terminology and/or identify the location of the central green corridor on Figure 2-10. Include policy on the form and function of the “Central North South Collector Transport Corridor”. Clarify terminology and/or identify the location of the central green corridor on Figure 2-10 The reference to the 50m central green corridor requires review given that the stormwater system has proven to be impractical. Add as 3.6.2.5 v) “School sites – sports fields and other informal recreation space available for public use.”
Accept in part
The submission point seeks amendments to Figure 2-10 in relation to the central green corridor that will improve the internal consistency of the Plan, the clarity of the Plan for users and the administration and implementation of the Plan. Amendment to 3.6.2.5(b) to clarify the role of the Central North-South Collector Transport Corridor will assist with the administration and implementation of the Plan. Amendment to 3.6.2.5 (b) to delete reference to the 50 m width of the central green corridor more accurately reflects that the actual width will be determined by more detailed modelling at the time of development. The requested to add reference to school sites to 3.6.2.5 v) is not accepted as school sites are private property and do not contribute to the level of service for open space provision.
Hamilton JV Investment Company Ltd
1170.010 3.6.2.5 Open Space Network
Support in part
3.6.2.5 Open Space Network Amend, as set out in submission: Clarify terminology and/or identify the location of the central green corridor on Figure 2-10. Add a policy on the form and function of the “Central North South Collector Transport Corridor”. Clarify terminology and/or identify the location of the central green corridor on Figure 2-10 Add the following to 3.6.2.5a) "v) School sites – sports fields and other informal recreation space available for public use.”
Accept in part
The submission point seeks amendments to Figure 2-10 in relation to the central green corridor that will improve the internal consistency of the Plan, the clarity of the Plan for users and the administration and implementation of the Plan. Amendment to 3.6.2.5(b) to clarify the role of the Central North-South Collector Transport Corridor will assist with the administration and implementation of the Plan. The requested to add reference to school sites to 3.6.2.5 v) is not accepted as school sites are private property and do not contribute to the level of service for open space provision.
Hounsell Holdings Ltd
1104.047 Figure 2-10 Rotokauri Structure Plan-Reserve Network
Oppose Amend Figure 2-10 Rotokauri Structure Plan-Reserve Network title to 'Open Space Network' to: Show specific location of central green corridor; Show the stormwater drainage pattern that has been developed as part of the Catchment Management Plan for Rotokauri; Show the “recreational nodes” on the Figure and include in the legend with separate symbol. Clarify terminology and/or identify the location of the central green corridor on Figure 2-10. The green central corridor route should be designated.
Accept in part
The submission point seeks amendments to Figure 2-10 in relation to the central green corridor that will improve the internal consistency of the Plan, the clarity of the Plan for users and the administration and implementation of the Plan. Amendment to 3.6.2.5(b) to clarify the role of the Central North-South Collector Transport Corridor will assist with the administration and implementation of the Plan. It is considered appropriate to reflect the provisions of the draft Integrated Catchment Management Plan and the works that have already occurred on Figure 2-8 (Rotokauri Structure Plan – Land Use) and Figure 2-10 (Open Space Network) and delete the previous green drainage corridor shown in that location. Showing recreational nodes on Figure 2-10 would be inconsistent with other Structure Plans and would not accurately reflect the recreational provision in the Structure Plan. It is not considered that a change to Figure 2-10 is required.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 38 of 63
Include policy on the form and function of the “Central North South Collector Transport Corridor”.
Hamilton JV Investment Company Ltd
1170.066 Figure 2-10 Rotokauri Structure Plan-Reserve Network
Oppose Amend Figure 2-10 Rotokauri Structure Plan-Reserve Network by: • Changing the title to “Open Space Network”. • Show specific location of central green corridor. • Show the stormwater drainage pattern that has been developed as part of the Catchment Management Plan for Rotokauri. • Show the “recreational nodes” on the Figure and include in the legend with separate symbol. • Clarify terminology and/or identify the location of the central green corridor on Figure 2-10 and designate the route. Include policy on the form and function of the “Central North South Collector Transport Corridor”.
Accept in part
The change to the title of Figure 2-10 is accepted as the amendment will improve the internal consistency and usability of the Plan. The submission point seeks amendments to Figure 2-10 in relation to the central green corridor that will improve the internal consistency of the Plan, the clarity of the Plan for users and the administration and implementation of the Plan. It is considered appropriate to reflect the provisions of the draft Integrated Catchment Management Plan and the works that have already occurred on Figure 2-8 (Rotokauri Structure Plan – Land Use) and Figure 2-10 (Open Space Network) and delete the previous green drainage corridor shown in that location. Showing recreational nodes on Figure 2-10 would be inconsistent with other Structure Plans and would not accurately reflect the recreational provision in the Structure Plan. It is not considered that a change to Figure 2-10 is required.
Additional residential development in Stage One and general structure plan matters
Sub. Name FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary Decision Reasoning
Hounsell Holdings Ltd
1104.045 Figure 2-8 Rotokauri Structure Plan-Land Use
Oppose Figure 2-8 Rotokauri Structure Plan-Land Use - Amend Figure 2-8 in accordance with the attached Figure set out in the submission to show Medium density residential development extending to the north of the Suburban Centre; and Include staging boundary on Figure 2-8.
Accept in Part
It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties. Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Hounsell Holdings Ltd
1104.046 Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network
Oppose Amend Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network to include additional areas to the north and west of the suburban centre as Part of Stage 1 as shown on attachments set out in the submission. Provide an alternative route for the central north south collector that avoids the need for a large cut and overpass.
Accept In Part
It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties. Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15. The alignment of the central north-south collector is considered to be the best available alternative. The Structure Plan is not a blueprint and the exact alignment of the collector road can change as long as there is a continuous route provided which delivers the required connectivity and outcomes.
Hamilton JV Investment Company Ltd
1170.012 3.6.2.9 Staging Oppose 3.6.2.9 Staging (Rotokauri Structure Plan) Amend as set out in the submission to: Include reference to where the various cross sections apply (Figures 3.6.2a - g); Delete second sentence in policy; Include additional areas to the north and west of the suburban centre as Part of Stage 1.; Include the text to fully explain the rationale of staging: “The extent of Stage 1 will facilitate efficient development of infrastructure and provide necessary critical mass for the provision of local services. The extent of Stage 1 will facilitate completion of a road
Accept in part
Clarifying the location of the various cross sections will assist Plan users. The submission point seeks amendments to 3.6.2.9 and is accepted it accurately reflects the current situation given that the Te Rapa Bypass is open and operational and would assist with the clarity of the Plan for users. It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 39 of 63
network with a desirable level of connectivity.” prior to any further development of stage 1, which is to involve multiple parties. Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
New Zealand Transport Agency
FS270.025
Oppose Accept in part
The submission is only accepted in part because amendments have been made in response to part of the submission 1170.012.
Hounsell Holdings Ltd
1104.012 3.6.2.9 Staging Oppose 3.6.2.9 Staging (Rotokauri Structure Plan) and Figures 3.6.2a, 3.6.2b, 3.6.2c, 3.6.2d, 3.6.2e, 3.6.2f, and 3.6.2g. For each Figure include reference to where the various cross sections apply. Delete second sentence in policy 3.6.2.9 Include additional areas to the north and west of the suburban centre as Part of Stage 1. Include commentary that fully explains the rationale of staging: “The extent of Stage 1 will facilitate efficient development of infrastructure and provide necessary critical mass for the provision of local services. The extent of Stage 1 will facilitate completion of a road network with a desirable level of connectivity.”
Accept in part
Clarifying the location of the various cross sections will assist Plan users. The submission point seeks amendments to 3.6.2.9 and is accepted as it accurately reflect s the current situation given that the Te Rapa Bypass is open and operational and would assist with the clarity of the Plan for users. The proposed amendment to staging would be inconsistent with the Proposed Regional Policy Statement (Decisions Version November 2012), Future Proof, and the Hamilton Urban Growth Strategy.
Hounsell Holdings Ltd
1104.054 Zoning Map 24A Oppose Map 24A-increase the extent of Stage 1 to include additional residential areas to the north and west of the existing first stage. Medium density residential zoning to be shown extending to the north of the Suburban Centre. Any loss of employment land can be addressed through an extension to the north of Ruffell Road, which is currently shown outside the structure plan area.
Accept in Part
It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (industrial zone), suburban centre (Business 5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties. Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Hamilton JV Investment Company Ltd
1170.073 Zoning Map 24A Oppose Map 24A- Extend Stage 1 of Rotokauri Structure Plan. Extend medium density residential zoning. Extend employment land to the north of Ruffell Road. Buffer area adjacent to the Suburban Centre crosses the intended road alignment. The Special Natural Zone/Ridgeline Character Area extends too far down Lee Road. The residential Zone will provide an appropriate transition to medium density residential. Zone all of Commercial centre Business 5.
Accept in Part
It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties. Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Hounsell Holdings Ltd
1104.053 Zoning Map 23A Oppose Map 23A-increase the area of Stage 1 Rotokauri Structure Plan. The Special Natural Zone/Ridgeline Character Area extends too far down Lee Road. The residential Zone will provide an appropriate transition to medium density residential.
Accept in Part
It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 40 of 63
Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Hamilton JV Investment Company Ltd
1170.072 Zoning Map 23A Oppose Map 23A- Stage 1 Rotokauri Structure Plan should be increased to include additional residential areas to the north and west of the existing first stage. The Special Natural Zone/Ridgeline Character Area extends too far down Lee Road. The residential Zone will provide an appropriate transition to medium density residential.
Accept in Part
It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties. Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Hounsell Holdings Ltd
1104.052 Zoning Map 14A Oppose Amend Map 14A to add land to Stage 1 of Rotokauri Structure Plan. Accept in Part
It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties. Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15.
Hamilton JV Investment Company Ltd
1170.065 Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network
Oppose Amend Figure 2-9 Rotokauri Structure Plan-Staging and Transport Network by: • Adding areas to the north and west of the suburban centre as Part of Stage 1 as shown on submission attachments. • Provide an alternative route for the central north south collector that avoids the need for a large cut and overpass. • Show the Tasman Road link remaining to align with Figure 3.6.2b.
Accept in Part
It is accepted that Stage 1 of the Rotokauri Structure Plan is enlarged as the proposed District Plan enables development whereby Development Agreements are provided for if infrastructure is not funded by Council to allow development to proceed. The Structure plan identified the areas for employment (industrial zone), suburban centre (business5 Zone), residential and ridgeline character area (Special Natural Zone) and has been carried through to the planning maps. As part of accepting the expansion of stage 1 it is imperative that a full Integrated Catchment Management Plan (ICMP) be developed prior to any further development of stage 1, which is to involve multiple parties. Figure 6.1 Rotokauri Stage 1 Comprehensive Development Plan Cell is expanded to show the Employment Area and Figure 15-8a is expanded to apply which requires specific Integrated Transport Requirements by rule 25.14.4.3 (e). See Tracked Changes for Chapter 3 Structure Plans, Chapter 25.13 Three Waters, and Appendix 6 and 15
Hamilton JV Investment Company Ltd
1170.064 Figure 2-8 Rotokauri Structure Plan-Land Use
Oppose Amend Figure 2-8 Rotokauri Structure Plan-Land Use in accordance with the new figure attached to the submission, including by: • Adding staging boundaries. • Labelling school sites as “indicative only”. • Accurately reflecting the location of the Passenger Transport Location on Figure 3.6.2b. • Either remove the Future Reserve notation from the submitters land or designate the land. • Show the Tasman Road link remaining to align with Figure 3.6.2b.
Reject The location of the Passenger Transport Location shown on Figure 3.6.2b is not inconsistent with the southern location shown on Figure 2-8 and therefore no change is required. This submission is therefore rejected. The submitter appears to have incorrectly interpreted the Structure Plan boundary notation, shown as a dashed black line on Figures 2-8 and 2-9 as representing road stopping of part of Tasman Road which is not the case. No changes to Figures 2-8 or 2-9 are required in response to the submission.
Myra Evans-McLeod
219.001 Map 33A Oppose Obtrusive to outlook. Reject This submission point does not clearly state the relief sought.
Fonterra Co-operative Group Ltd
1200.057 Features Map 25B
Support Retain Features Map 25B as notified. Accept This submission supports Features Map 25B and is accepted because there are no other submissions seeking amendments to that Map.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 41 of 63
3.7 Ruakura
Sub. Name
FS. Name
Sub. Point FS. Point
Plan Provision Sub. Type
Summary
Decision Reasoning
Wei Lee 763.001 3 Structure Plans
Oppose Amend the Plan to a) retain the area as rural residential without reference to any logistics in the future b) Provide a 100m buffer around Percival and Ryburn Roads with a 4m high planted bund c) Ensure freight movements use an alternative road to Percival Road d) Ensure development rights are the same as provided for in the large lot residential zone for the southern end of the Structure Plan
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Ming-San (Arvin) & Meng-Chu (Anna) Tang
764.003 3 Structure Plans
Oppose Amend the Plan to a) retain status quo for the area b) Provide a 100m buffer between the area and the Logistics Zone c) Council purchase the properties
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Ken & Hong Shang & Wang
827.001 3 Structure Plans
Oppose Amend the Plan to a) retain the current rural residential zoning and subdivision rights b) Provide a 100m buffer around Percival and Ryburn Roads
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Kung-Yao Lin 831.002 3 Structure Plans
Oppose Amend the Plan to: a) retain the rural residential and development rights including subdivision that exist for the area. b) Provide a 100m buffer around Percival and Ryburn Roads with an earth bund. c) Retain more land around the university for supporting uses. d) concentrate development on land located near existing facilities and industry instead of creating new areas. e) Allow subdivision of the Percival and Ryburn Road area to 1000m2 lots to keep maintain the low density residential lifestyle and quality.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Derrick Ross & Robyn Mary Marsters
835.001 3 Structure Plans
Oppose Amend the Plan to: a) Retain the Rural Residential zoning without reference to industrial in the future. b) Provide a 100m buffer around Ryburn and Percival Roads with a 4m high planted bund. c) ensure freight movements use an alternative road to Percival Road. d) ensure the development rights are the same as provided for in the Large Lot Residential Zone for the southern end of the Structure Plan.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Allan Liang-chitz & Shirley Tzu-ling Wan
861.001 3 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning with right to subdivide to 2500m2. b) Provide a 100m buffer around Percival and Ryburn Roads with a 4m high planted bund. c) ensure freight movements use an alternative road to Percival Road. d) Delete reference to any logistics uses in the future.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Raylene & Saul Cowie & Spriggs
864.001 3 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning with right to subdivide to 2500m2. b) Provide a 100m planted buffer and bund around Percival and Ryburn Roads. c) Require that Tainui Group Holdings or Council purchase the property.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Bryce & Natasha Carmichael
910.001 3 Structure Plans
Oppose Amend the Plan to: a) Retain as rural residential and development rights b) provide a 100m buffer between large lot residential and logistics/industrial park zones c) remove reference to any logistics in the future d) ensure lighting and vibration does not adversely affect quality of life e) ensure freight movements use an alternative road to Percival Road f) purchase property.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Roy Cowie
928.001 3 Structure Plans
Oppose Amend the Plan to: a) Provide a 100m buffer with 4m high planted earth bund. b) Remove the deferred logistics zoning and retain a large lot residential zoning with subdivision to 2500m2.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Deanna - Rose Alexander
979.001 3 Structure Plans
Oppose Amend the Plan to ensure no logistics or industrial activities are permitted within 100m of the large lot zone boundary; or purchase property.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Bee Chiew Phee 1004.007 3 Structure Plans
Oppose Purchase the residents property or amend the Plan to: a) retain rural residential zoning and allow subdivision to 2500m2. b) Provide a 100m buffer and planted earth bund. c) Ensure no heavy vehicles access to industrial properties from Percival/Ryburn Roads.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Alan Frederick & 1005.001 3 Structure Oppose Amend the Plan to: a) Retain the rural residential zoning and Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 42 of 63
Barbara Winifred Julian
Plans development rights without reference to any logistics in the future. b) Prevent logistics or industrial activities within 100m of the Large Lot Residential Zone. c) Require a 100m buffer and planted earth bund. d) Require screening and buffering for Ryburn Road; or purchase the property.
Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Peter & Barbara Ryan
1006.001 3 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning and development rights without reference to any logistics in the future. b) Prevent logistics or industrial activities within 100m of the Large Lot Residential Zone. c) Require a 100m buffer and planted earth bund. d) Control the use of surrounding land so that nuisance effects are limited to levels that approximate a semi-rural lifestyle area.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Bo & Meggie Han & Wang
1007.001 3 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning and development rights without reference to any logistics in the future. b) Require a 100m landscaped earth bund buffer around the Large Lot Residential Zone. c) Require controls to mitigate light, noise and vibration effects on Ryburn Road.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Shing-long Lee 1224.001 3 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning and development rights without reference to any logistics in the future. b) Provide a 100m buffer around Percival and Ryburn Roads with a 4m high planted earth bund. c) Ensure freight movements use an alternative road to Percival Road. d) Provide development rights same as provided for in the large lot residential zone for the southern end of the structure plan.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Kerry & Donna Willmott
1257.004 3 Structure Plans
Oppose Opposes the Ruakura Industrial zone. Either purchase the property or amend the plan to allow semi-commercial use on 63 Ryburn Road
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Ruakura Residents Group and William Roy Cowie
1275.005 3 Structure Plans
Oppose 3 Structure Plans -amend Ruakura Structure Plan Figure 2-14 to identify land as Large Lot residential; remove reference to transitional use of land as large lot residential and future use as Ruakura Logistics; if unacceptable rezone 100m buffer as Open Space.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Future Proof Implementation Committee
FS181.013
Oppose
Tainui Group Holdings Limited
FS196.053
Oppose
David Evan & Karlene Chibnall
1278.001 3 Structure Plans
Oppose Amend the Plan to: a) retain the existing Rural Residential zoning and associated development rights. b) Provide a 100m buffer around Percival and Ryburn Roads with a planted earth bund. c) ensure continuing vehicle access for commuting; and ensure fair treatment over privately owned land.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Roland & Wendy Spirig
1279.001 3 Structure Plans
Oppose Amend the Plan to: a) Retain the Large Lot Residential zoning with the addition of a 100m planted buffer. b) restrict the operating hours of the port to daylight hours and provide for a way to lodge noise complaints.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
David Murray and Karen Lee Young
1280.001 3 Structure Plans
Oppose Amend the Plan to: a) Retain the existing Rural Residential Zoning with associated development rights. b) Provide a 100m buffer around Percival and Ryburn Roads with a 4m high planted earth bund. c) Remove the deferred logistics zoning from the proposed plan.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Dennis Roy McLeod
56.001 3.7 Ruakura Oppose Opposes the concept of an Inland Port.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Dennis Roy McLeod
FS3.001
Support
Future Proof Implementation Committee
FS181.011
Oppose
Tainui Group FS196.04 Oppose
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 43 of 63
Holdings Limited
Brett Hopkins (Ruakura Motors Tractorparts Ltd)
234.001 3.7 Ruakura Oppose Delete the Ruakura Structure Plan and undertake consultation with the community to develop innovation precinct and residential areas.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing . Simon
Travaglia (Waikato Innovation Park Limited)
FS67.034
Oppose
Deborah June Fisher
282.018 3.7 Ruakura Oppose Delete Ruakura Structure Plan until further consideration of the effects on the surrounding area have been investigated and publicly notified. b) ensure a "Noise Management Plan" is completed prior to inclusion of the Structure Plan.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Josina Wilhelmina Maria Ellis
289.001 3.7 Ruakura Support in part
Oppose Inland Port and Ruakura logistics Zone and seeks residential zoning.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
KiwiRail Holdings Limited
366.003 3.7 Ruakura Support Supports Ruakura Structure Plan
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing . Tainui Group
Holdings Limited
FS196.008
Support
Future Proof Implementation Committee
608.011 3.7 Ruakura Support Supports 3.7 Ruakura Structure Plan and requests it be retained.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Roy and Raewyn Mary Cowie
FS143.011
Oppose
Ruakura Residents Group and William Roy Cowie
FS167.002
Oppose
Tainui Group Holdings Limited
FS196.001
Support
Chedworth Properties Limited
FS197.001
Support
AgResearch Ltd 609.002 3.7 Ruakura Support in part
Amend 3.7b by rewriting to ensure that it is not viewed as compromising the CBD. Delete 3.7h and associated staging rules in Rule 3.7.3.6 as it affects the development of future innovation & research activities and the development of supporting retail & commercial activities.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing . Simon
Travaglia (Waikato Innovation Park Limited)
FS67.006
Support
Waikato Regional Council
714.017 3.7 Ruakura Support in part
Move the Industrial Land Allocation table 3.7f to Chapter 2 Strategic Framework and link the table to relevant parts of the Structure Plan Chapter OR, move the table to the front of the Structure Plan Chapter.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato-Tainui Te Kauhanganui Inc
771.012 3.7 Ruakura Support Supports the Ruakura Structure Plan and landuse identified. Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 44 of 63
James & Heather Hely & Montgomerie
832.001 3.7 Ruakura Support in part
Amend Rules 23.7.3 d),e), f), i), j), k), h) to enable subdivision at 2500m2 in the Large Lot Residential Zone as a Permitted Activity.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Gwyneth Ann Verkerk (and Dr Raymond Thomas Cursons)
FS25.003
Support
Stephen George Bigwood
906.011 3.7 Ruakura Support in part
Amend Chapter 3 or Chapter 11 to add a new rule that classifies development of areas larger than what staging provides for as a non-complying or prohibited activity or, Amend Figure 2-14 to rezone Stages 2 and 3 as 'deferred industrial areas' that can only be development in the years specified. The original submission has been withdrawn therefore no decision is required.
New Zealand Transport Agency
FS270.016
Support
Hugh and Katie Goodman and Mayes
911.003 3.7 Ruakura Oppose Delete Ruakura Structure Plan and requests consultation occurs with the community.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Tainui Group Holdings Ltd
913.012 3.7 Ruakura Support in part
Amend 3.7b to update land area; reword 3.7d to relate to strengthening the CBD. Amend 3.7f footnote provides flexibility if Waikato Expressway not completed; delete 3.7h and associated staging rules in 3.7.3.6.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
University of Waikato
FS47.003
Oppose
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
Jennifer West FS271.016
Oppose
New Zealand Transport Agency
924.026 3.7 Ruakura Support in part
Retain staging for Ruakura in 3.7 as notified Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Titanium Park Joint Venture
945.001 3.7 Ruakura Oppose Amend 3.7(f) to update the table 'Industrial Land Allocation in the Future Proof Area' to take account of the appeal by Titanium Park Joint Venture to the Waikato Regional Policy Statement.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
ANG & SL Clarke
951.007 3.7 Ruakura Support in part
Amend 3.7a) to add the Large Lot Residential Zone to the Ruakura Structure Plan vision.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Innovation Park Limited
1051.001 3.7 Ruakura Support in part
Amend 3.7d to identify employment opportunities are centred on "innovation and research". Amend 3.7h to enable development of a suburban centre.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing. Tainui Group
Holdings Limited
FS196.024
Support
Fonterra Co-operative Group Ltd
1200.011 3.7 Ruakura Support in part
Amend 3.7f) to include a footnote to the Table that advises the Waikato Proposed Regional Policy Statement is subject of appeals.
Defer The submissions relate to elements of the Ruakura Structure Plan. It is appropriate to defer until the Board of Inquiry issues a decision on the private plan change for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing
Susan Hopkins 1264.003 3.7 Ruakura Oppose Delete 3.7 Ruakura. Withdraw the Ruakura Structure Plan for consultation with the community to occur in order to develop an innovation precinct and residential areas and not a freight and logistics hub.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Ross & Leonie 1265.003 3.7 Ruakura Oppose Delete 3.7 Ruakura Structure Plan and consult with community to Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 45 of 63
Hopkins develop an innovation precinct & residential areas. Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Russell Vincent Cooper
FS240.006
Support
Robert Gordon Bell
1268.004 3.7 Ruakura Support in part
Amend 3.7 a)(iii) to move the inland port or increase buffering between the Knowledge Zone and the Ruakura Logistics Zone and Ruakura Industrial Park Zone.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Robert Gordon Bell
1268.002 Policy 3.3.4c Support in part
Policy 3.3.4c has not been followed in determining the road network in Ruakura. Seeks the removal, as set out in the submission, of the through intersection of the Industrial Park street with Silverdale Rd and make it a cul-de-sac with exit through the main entry point at the corner of Silverdale and Ruakura Roads (Figure 2-15 Appendix 2: Structure Plans).
Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Tainui Group Holdings Limited
FS196.041 Oppose
Kevin Brian Hall 16.001 3.7.1 Structure Plan Components
Support in part
Assurance that no flooding will occur due to Ruakura Structure Plan at the rear of 61A Nevada Rd
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Dennis Roy McLeod
56.005 3.7.1.1 Ruakura Logistics Zone – Inland Port
Oppose Concerned at noise levels from trains and other activities associated with an Inland Port.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Nagarajah Manoharan
218.001 3.7.1.1 Ruakura Logistics Zone – Inland Port
Support in part
Amend 3.7.1.1 to ensure the Greenbelt for the Inland Port is 200m. Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Deborah June Fisher
282.003 3.7.1.1 Ruakura Logistics Zone – Inland Port
Oppose Delete the Ruakura Structure Plan until the full impacts have been fully investigated.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Josina Wilhelmina Maria Ellis
289.002 3.7.1.1 Ruakura Logistics Zone – Inland Port
Oppose Delete the Inland Port and Ruakura logistics Zone. Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Barry Harris (Hamilton City Council)
1146.009 3.7.1.10 Water and Wastewater
Support in part
Amend 3.7.1.10 b) by replacing the word "sewer" with "wastewater" Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Deborah June Fisher
282.004 3.7.1.2 Ruakura Logistics Zone – Logistics
Oppose Delete the Ruakura Structure Plan until the effects on the surrounding environments have been fully investigated.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Regional Council
714.018 3.7.1.2 Ruakura Logistics Zone – Logistics
Support Retain 3.7.1.2.b Structure Plan component of Ruakura Logistics Zone Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Deborah June Fisher
282.005 3.7.1.3 Ruakura Industrial Park Zone
Oppose Delete the Ruakura Structure Plan until the effects on the surrounding environments have been fully investigated.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Lance Edward Kendrick
842.006 3.7.1.3 Ruakura Industrial Park Zone
Support in part
Amend 3.7.1.3 to provide very wide buffer strips between the proposed Industrial areas and existing Residential areas.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Stephen George Bigwood
906.004 3.7.1.3 Ruakura Industrial Park Zone
Support Supports 3.7.1.3 as it indicates outcomes which enable the creation of high quality amenity industrial park zone.
The original submission has been withdrawn therefore no decision is required.
Robert Gordon Bell
1268.005 3.7.1.3 Ruakura Industrial Park Zone
Support in part
Amend 3.7.1.3 to prescribe what high standard amenity entails for the Ruakura Industrial park Zone.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Dennis Roy McLeod
56.002 3.7.1.4 Knowledge Zone
Oppose Opposes the concept of an Inland Port.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Future Proof FS181.012 Oppose
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 46 of 63
Implementation Committee
Deborah June Fisher
282.006 3.7.1.4 Knowledge Zone
Support Retain the Knowledge Zone
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Simon Travaglia (Waikato Innovation Park Limited)
FS67.008
Support
AgResearch Ltd 609.004 3.7.1.4 Knowledge Zone
Support in part
Amend Rule 3.7.4.1 to remove the inference that the knowledge zone will compromise the central city.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing . Waikato
Regional Council
FS72.021
Oppose
Tainui Group Holdings Ltd
913.013 3.7.1.4 Knowledge Zone
Oppose Amend 3.7.1.4b by deleting "in a manner that does not compromise the Central City"
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Regional Council
FS72.024
Oppose
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
Waikato Innovation Park Limited
1051.002 3.7.1.4 Knowledge Zone
Oppose Amend 3.7.1.4b to delete reference to "in a manner that does not compromise the Central City"
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Regional Council
FS72.027
Oppose
Future Proof Implementation Committee
FS181.005
Oppose
Robert Gordon Bell
1268.007 3.7.1.4 Knowledge Zone
Oppose Amend 3.7.1.4b) to provide justification on how the Inland Port attracts 'world class research and development facilities' or this delete this link
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
AgResearch Ltd 609.005 3.7.1.5 Neighbourhood Centre
Support in part
Amend Rule 3.7.1.5 to provide for a Suburban Centre rather than a neighbourhood centre.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing . Waikato
Regional Council
FS72.022
Oppose
Tainui Group Holdings Ltd
913.014 3.7.1.5 Neighbourhood Centre
Oppose Amend 3.7.1.5 to change the Knowledge Zone Neighbourhood Centre to a Suburban Centre.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 47 of 63
Waikato Innovation Park Limited
1051.004 3.7.1.5 Neighbourhood Centre
Oppose Amend 3.7.1.5 to relate to a Suburban Centre Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Robert Gordon Bell
1268.008 3.7.1.5 Neighbourhood Centre
Support Amend 3.7.1.5 to address the need for better connectivity (specifically across Ruakura Road)
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Alexandra Lee Simmons
80.006 3.7.1.6 Residential Zones
Oppose Amend Rule 3.7.1.6. Remove Medium Residential Density zoning and replace with low density residential with the closure of Greenhill Road onto Tramway/Gordonton Roads; and ensure stormwater systems do not utilise local streams as open drains.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Tainui Group Holdings Limited
FS196.039
Oppose
Chedworth Properties Limited
FS197.004
Oppose
Gwyneth Ann Verkerk
293.001 3.7.1.6 Residential Zones
Oppose Oppose Rule 3.7.1.6, setting the staging of residential development within the Ruakura Structure Plan. A full structure plan should be developed. Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Michael John Griffin (n/a)
FS21.001
Support
AgResearch Ltd 609.006 3.7.1.7 Transportation Network
Support in part
Amend 3.7.1.7 Transportation Network to indicate the indicative nature of both the spine road & open space corridor.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Tainui Group Holdings Ltd
913.015 3.7.1.7 Transportation Network
Support in part
Amend 3.7.1.7 to create flexibility for the alignment of the transportation network and open space corridor.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
Porter Developments Limited
FS239.002
Support
Porter Properties Limited
FS241.005
Support
Hounsell Holdings Limited
FS248.004
Support
Hamilton JV Investments Limited
FS254.007
Support
New Zealand Transport Agency
924.027 3.7.1.7 Transportation Network
Support in part
Amend Ruakura structure plan once the location and number of interchanges to the Waikato Expressway are confirmed.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Future Proof Implementation Committee
FS181.007
Support
Wattle Downs Limited
FS280.001
Oppose
Chedworth Properties Ltd
1171.011 3.7.1.7 Transportation
Support in part
Amend 3.7.1.7 Transportation Network to allow flexibility in the location of the network and Spine Road with wording amendments and
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 48 of 63
Network subsequent amendments to Figs 2-14 and 2-15.
Waikato District Council
1211.027 3.7.1.7 Transportation Network
Support in part
Amend Figures 2-14 and 2-15 of the Ruakura Structure Plan to identify Greenhill and Ruakura connections to the Waikato Expressway as proposed interchanges and indicate that Powells, Ryburn and Ruakura Roads are being severed and a new underpass to be undertaken at Percival Road. Designation and road stopping procedures to be undertaken Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Wattle Downs Limited
FS280.017
Support
Gwyneth Ann Verkerk
293.006 3.7.1.8 Open Space Network
Support in part
Amend Rule 3.7.1.8 to include the southern gully areas, cycleways and provide opportunity within the transmission corridors for community gardens. Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Michael John Griffin (n/a)
FS21.001
Support
Laurence John Denny
1094.001 3.7.1.8 Open Space Network
Oppose Amend 3.7.1.8 by adding a new paragraph to relate to the open space network near Silverdale being a high level of landscaping and screening.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Alexandra Lee Simmons
80.003 3.7.1.9 Stormwater
Oppose Amend Rule 3.7.19 to ensure no use of streams for stormwater drainage associated with the Ruakura Structure Plan.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Gwyneth Ann Verkerk (and Dr Raymond Thomas Cursons)
FS25.006
Support
Gwyneth Ann Verkerk
293.009 3.7.1.9 Stormwater
Support 3.7.1.9 Stormwater - request Council work with landowners to develop comprehensive plan for gully's ecological amenity.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing . Michael John
Griffin (n/a) FS21.001
Support
Transpower New Zealand Ltd
1083.009 3.7.1.9 Stormwater
Support in part
Amend 3.7.1.9 to indicate that other land use could adversely affect transmission lines.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Robert Gordon Bell
1268.009 3.7.1.9 Stormwater
Support in part
Amend 3.7.1.9 to ensure all development and impermeable site coverage are subject to Integrated Catchment Management Plan and stormwater network design.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Deborah June Fisher
282.007 3.7.2 Objectives and Policies
Oppose Amend 3.7.2 by inserting additional objectives and policies to protect the environment and amenity values of existing residents.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
AgResearch Ltd 609.007 3.7.2 Objectives and Policies
Support in part
Delete Objective 3.7.2.2 and policy 3.7.2.2(a) and amend objective 3.7.2.4 in relation to the Ruakura Structure Plan and ensure there is no inference it would compromise the Central City.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing . Waikato
Regional Council
FS72.023
Oppose
Waikato Regional Council
714.019 3.7.2 Objectives and Policies
Support in part
Retain Policy 3.7.21b, Amend Policy 3.7.2.1e to include reference to ecological corridors. Amend objective 3.7.2.3 to include " that is supported by the effective and efficient transport links" Add new policy to 3.7.2.3c to read: "A well functioning and efficient transport network is developed to support logistics and freight handling activities".
Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
New Zealand Transport Agency
FS270.014
Support
Stephen George Bigwood
906.005 3.7.2 Objectives and Policies
Support Supports objective 3.7.2.5 and policies 3.7.2.5a and b for the creation of high quality industrial park zone.
The original submission has been withdrawn therefore no decision is required.
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 49 of 63
Tainui Group Holdings Ltd
913.016 3.7.2 Objectives and Policies
Oppose Delete objective 3.7.2.2 and policies 3.7.2.2a, 3.7.2.7a. Amend Objectives and Policies 3.7.2.4, 3.7.2.7 and 3.7.2.7b to remove reference to compromising the Central City, and to replace the Neighbourhood Centre in the Knowledge Zone with a Suburban Centre.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Regional Council
FS72.025
Oppose
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
Future Proof Implementation Committee
FS181.01
Oppose
New Zealand Transport Agency
FS270.019
Oppose
New Zealand Transport Agency
924.028 3.7.2 Objectives and Policies
Support Amend Policy 3.7.2.1b to "optimise" rather than 'maximise' the use of existing infrastructure. Retain Policy 3.7.2.6a as notified.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
ANG & SL Clarke
951.008 3.7.2 Objectives and Policies
Support in part
Amend 3.7.2 to add objective and policies for the Large Lot Residential zone that enable subdivision and development.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Child and Youth Mortality Review Group
1003.023 3.7.2 Objectives and Policies
Support in part
Amend Policy 3.7.2.6.c to ensure the aspects of safety is explicitly incorporated.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Innovation Park Limited
1051.005 3.7.2 Objectives and Policies
Oppose Amend objectives and policies to provide for in "general" accordance with the structure plan; Delete Objective 3.7.2.2 and Policy 3.7.2.2a; Amend Objective 3.7.2.4 so as to remove reference to not compromising the Central City; Amend policy 3.7.2.4a to replace the word ‘shall’ with ‘should’ and reference to the Ruakura Knowledge Zone; Amend objective 3.7.2.7 to reference “suburban catchments”, and “goods, service and employment” instead of retail facilities Delete Policy 3.7.2.7a; Amend policy 3.7.2.7b to replace neighbourhood centre with suburban centre and the word ‘shall’ with ‘should’.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Regional Council
FS72.029
Oppose
Future Proof Implementation Committee
FS181.006
Oppose
New Zealand Transport Agency
FS270.023
Oppose
Robert Gordon Bell
1268.006 3.7.2 Objectives and Policies
Support in part
Amend 3.7.2.5a to prescribe what high standard amenity entails for the Ruakura Industrial park Zone. Amend 3.7.2.1c to provide justification on how the Inland Port attracts 'world class research and development
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 50 of 63
facilities' or this delete this link. Amend 3.7.2.6 to be more realistic to the effects of the Inland Port on the residential environment.
Stephen George Bigwood
906.012 3.7.3 Rules Support in part
Amend Chapter 3 or Chapter 11 to add a new rule that classifies development of areas larger than what staging provides for as a non-complying or prohibited activity or, Amend Figure 2-14 to rezone Stages 2 and 3 as 'deferred industrial areas' that can only be development in the years specified.
The original submission has been withdrawn therefore no decision is required
Deborah June Fisher
282.009 3.7.3.1 Ruakura Structure Plan Area
Oppose Delete the Ruakura Structure Plan until further investigation into its impacts on surrounding areas has been conducted. b) Amend Map 2-15 to reflect the correct status of the Spine Road as a major arterial.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Tainui Group Holdings Ltd
913.017 3.7.3.3 Infrastructure
Oppose Delete 3.7.3.3 in relation to infrastructure
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
New Zealand Transport Agency
FS270.02
Oppose
Chedworth Properties Ltd
1171.012 3.7.3.3 Infrastructure
Oppose Delete 3.7.3.3 Infrastructure Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
AgResearch Ltd 609.008 3.7.3.4 Staging Rules for Ruakura Logistics Zone and Ruakura Industrial Park Zone in the Ruakura Structure Plan Area
Support in part
Amend 3.7.3.4 b)i by rewording to require the Waikato Expressway to be completed and connected to the logistics zone or other suitable means without compromising the transportation network. Delete 3.7.3.4 b) ii and Amend 3.7.3.4 b) iii to ensure the management of development between 2021 & 2041 aligns with the RPS.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
New Zealand Transport Agency
FS270.01
Oppose
Waikato Regional Council
714.020 3.7.3.4 Staging Rules for Ruakura Logistics Zone and Ruakura Industrial Park Zone in the Ruakura Structure Plan Area
Support Retain staging rules for the Ruakura Structure Plan 3.7.3.4a to 3.7.3.4c
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Future Proof Implementation Committee
FS181.009
Support
New Zealand Transport Agency
FS270.015
Support
Lance Edward Kendrick
842.002 3.7.3.4 Staging Rules for Ruakura Logistics Zone
Support in part
Amend Rule 3.7.3.4a by reducing the 20ha ratio. Amend Rule 3.7.3.4b stage 2 to reinstate the connections at Greenhill Road and Ruakura Rd.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 51 of 63
and Ruakura Industrial Park Zone in the Ruakura Structure Plan Area
Stephen George Bigwood
906.016 3.7.3.4 Staging Rules for Ruakura Logistics Zone and Ruakura Industrial Park Zone in the Ruakura Structure Plan Area
Support in part
Amend Rule 3.7.3.4a) v with the removal of the words "or the industrial park area immediately north of the knowledge zone (ie west of the north-south spine road)" or amend Rule 3.7.3.4a) v by adding a proviso that the Fifth Avenue, Five Cross Roads and Boundary Road transport Corridor has been upgraded to four lanes prior to development’
The original submission has been withdrawn therefore no decision is required.
Hugh and Katie Goodman and Mayes
911.004 3.7.3.4 Staging Rules for Ruakura Logistics Zone and Ruakura Industrial Park Zone in the Ruakura Structure Plan Area
Oppose Delete Rule 3.7.3.4a) and undertake a plan variation once NZTA has made a decision on the location and style of interchange on the Waikato Expressway. Delete Rule 3.7.3.4a) relating to release of 80ha of land in Ruakura prior to 2021. Retain Rule 3.7.3.4 b) which supports the release of land post 2021 on completion of the Hamilton Waikato Expressway.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Tainui Group Holdings Ltd
913.018 3.7.3.4 Staging Rules for Ruakura Logistics Zone and Ruakura Industrial Park Zone in the Ruakura Structure Plan Area
Support in part
Amend Rule 3.7.3.4a to provide flexibility in relation to the Waikato Regional Policy Statement. Delete 3.7.3.4(a)(ii) to (iv). Amend Rule 3.7.3.4b amend to provide flexibility for development in relation to the completion of the Waikato Expressway.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing . Waikato
Regional Council
FS72.026
Oppose
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
Susan Hopkins 1264.004 3.7.3.4 Staging Rules for Ruakura Logistics Zone and Ruakura Industrial Park Zone in the Ruakura Structure Plan Area
Oppose Delete Rule 3.7.3.4a) and undertake a plan variation once NZTA has made a decision on the location and style of interchange on the Waikato Expressway. Delete Rule 3.7.3.4a) relating to release of 80ha of land in Ruakura prior to 2021. Retain Rule 3.7.3.4 b) which supports the release of land post 2021 on completion of the Hamilton Waikato Expressway.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Ross & Leonie Hopkins
1265.004 3.7.3.4 Staging Rules for Ruakura Logistics Zone
Oppose Delete Rule 3.7.3.4a) and undertake a plan variation once NZTA has made a decision on the location and style of interchange on the Waikato Expressway. Delete Rule 3.7.3.4a) relating to release of 80ha of land in Ruakura prior to 2021.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 52 of 63
and Ruakura Industrial Park Zone in the Ruakura Structure Plan Area
Retain Rule 3.7.3.4 b) which supports the release of land post 2021 on completion of the Hamilton Waikato Expressway.
Russell Vincent Cooper
FS240.006
Support
Brett Hopkins (Ruakura Motors Tractorparts Ltd)
1266.004 3.7.3.4 Staging Rules for Ruakura Logistics Zone and Ruakura Industrial Park Zone in the Ruakura Structure Plan Area
Oppose Delete Rule 3.7.3.4a) and undertake a plan variation once NZTA has made a decision on the location and style of interchange on the Waikato Expressway. Delete Rule 3.7.3.4a) relating to release of 80ha of land in Ruakura prior to 2021. Retain Rule 3.7.3.4 b) which supports the release of land post 2021 on completion of the Hamilton Waikato Expressway.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Robert Gordon Bell
1268.003 3.7.3.4 Staging Rules for Ruakura Logistics Zone and Ruakura Industrial Park Zone in the Ruakura Structure Plan Area
Support in part
Amend Rule 3.7.3.4 b)(ii) and Fig 2-15 to remove the through intersection of the Industrial Park street with Silverdale Rd and make it a cul-de-sac with exit through the main entry point at the corner of Silverdale and Ruakura Roads.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Simon Travaglia (Waikato Innovation Park Limited)
FS67.01
Oppose
Gwyneth Ann Verkerk
293.007 3.7.3.5 Staging Rules for General Residential Zone and Medium Density Residential Zone in the Ruakura Structure Plan Area
Oppose Review staging rules 3.7.3.5 for the large lot residential zone within the Ruakura Structure Plan
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Michael John Griffin (n/a)
FS21.001
Support
Tainui Group Holdings Ltd
913.019 3.7.3.5 Staging Rules for General Residential Zone and Medium Density Residential Zone in the Ruakura Structure Plan Area
Oppose Delete Rules 3.7.3.5(a) and 3.7.3.5(b) and replace with amended wording to align with the recent decision on the E1 to Cobham Drive, or impacts of the location of connections to the Waikato Expressway.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 53 of 63
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
New Zealand Transport Agency
FS270.021
Oppose
ANG & SL Clarke
951.009 3.7.3.5 Staging Rules for General Residential Zone and Medium Density Residential Zone in the Ruakura Structure Plan Area
Oppose Amend Rule 3.7.3.5 to enable the immediate release of residential zoned land in the Ruakura Structure Plan areas.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Chedworth Properties Ltd
1171.013 3.7.3.5 Staging Rules for General Residential Zone and Medium Density Residential Zone in the Ruakura Structure Plan Area
Oppose Amend Rules 3.7.3.5a) and b) so that development of the Spine Rd is not required as part of the residential development.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
AgResearch Ltd 609.003 3.7.3.6 Staging Rule for the Innovation Park Precinct of the Knowledge Zone in the Ruakura Structure Plan Area
Oppose Delete staging rule for the Innovation Park Precinct of the Knowledge Zone 3.7.3.6 and 3.7(h)
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Simon Travaglia (Waikato Innovation Park Limited)
FS67.007
Oppose
Tainui Group Holdings Limited
FS196.02
Support
Tainui Group Holdings Ltd
913.020 3.7.3.6 Staging Rule for the Innovation Park Precinct of the Knowledge Zone in the Ruakura Structure Plan Area
Oppose Delete Rule 3.7.3.6 Staging rule for Innovation Park Precinct for the Knowledge Zone.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 54 of 63
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
New Zealand Transport Agency
FS270.022
Oppose
Waikato Innovation Park Limited
1051.003 3.7.3.6 Staging Rule for the Innovation Park Precinct of the Knowledge Zone in the Ruakura Structure Plan Area
Oppose Amend staging rules in 3.7.3.6 to enable earlier development of the suburban centre.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Regional Council
FS72.028
Oppose
Tainui Group Holdings Limited
FS196.025
Support
Deborah June Fisher
282.010 3.7.4 Provisions in Other Chapters
Support in part
Delete Discretionary Assessment Criteria A2 - general criteria.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Gavin Smith 224.001 Appendix 2 Structure Plans
Oppose That Lot: 1 DP: S68406 at Te Rapa East Road be included within Stage 1 of the Rotokauri Structure Plan - Staging and Transport Network.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Gaenor Smith 229.001 Appendix 2 Structure Plans
Support Retain figures 2-8 in Appendix 2 (Structure Plans - Rotokauri) in so far as it identifies an industrial land use for Lot 1: DP: S68406 (Te Kowhai East Road).
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Deborah June Fisher
282.002 Appendix 2 Structure Plans
Oppose Remove Ruakura SP until more details are available, an environmental impact report available and the full and future effects on the surrounding environment have been considered.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.002
Oppose
W.J. & M.R. Laverty
313.002 Appendix 2 Structure Plans
Support in part
Include a Structure Plan for Temple View within Appendix 2 - Structure Plans.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.088
Support
W.R & J.M Falconer
360.003 Appendix 2 Structure Plans
Support in part
Amend Volume 2: Appendix 2 - Structure Plans by including a Temple View Structure Plan and make any subsequential changes to other diagrams.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
The Church of Jesus Christ of Latter Day Saints Trust Board
FS180.089
Support
Wei Lee 763.006 Appendix 2 Oppose Amend the Plan to a) retain the area as rural residential without Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 55 of 63
Structure Plans reference to any logistics in the future b) Provide a 100m buffer around Percival and Ryburn Roads with a 4m high planted bund c) Ensure freight movements use an alternative road to Percival Road d) Ensure development rights are the same as provided for in the large lot residential zone for the southern end of the Structure Plan
Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Ming-San (Arvin) & Meng-Chu (Anna) Tang
764.006 Appendix 2 Structure Plans
Oppose Amend the Plan to a) retain status quo for the area b) Provide a 100m buffer between the area and the Logistics Zone c) Council purchase the properties
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Ken & Hong Shang & Wang
827.006 Appendix 2 Structure Plans
Oppose Amend the Plan to a) retain the current rural residential zoning and subdivision rights b) Provide a 100m buffer around Percival and Ryburn Roads
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Kung-Yao Lin 831.005 Appendix 2 Structure Plans
Oppose Amend the Plan to: a) retain the rural residential and development rights including subdivision that exist for the area. b) Provide a 100m buffer around Percival and Ryburn Roads with an earth bund. c) Retain more land around the university for supporting uses. d) concentrate development on land located near existing facilities and industry instead of creating new areas. e) Allow subdivision of the Percival and Ryburn Road area to 1000m2 lots to keep maintain the low density residential lifestyle and quality.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Derrick Ross & Robyn Mary Marsters
835.006 Appendix 2 Structure Plans
Oppose Amend the Plan to: a) Retain the Rural Residential zoning without reference to industrial in the future. b) Provide a 100m buffer around Ryburn and Percival Roads with a 4m high planted bund. c) ensure freight movements use an alternative road to Percival Road. d) ensure the development rights are the same as provided for in the Large Lot Residential Zone for the southern end of the Structure Plan.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Allan Liang-chitz & Shirley Tzu-ling Wan
861.006 Appendix 2 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning with right to subdivide to 2500m2. b) Provide a 100m buffer around Percival and Ryburn Roads with a 4m high planted bund. c) ensure freight movements use an alternative road to Percival Road. d) Delete reference to any logistics uses in the future.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Raylene & Saul Cowie & Spriggs
864.005 Appendix 2 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning with right to subdivide to 2500m2. b) Provide a 100m planted buffer and bund around Percival and Ryburn Roads. c) Require that Tainui Group Holdings or Council purchase the property.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Bryce & Natasha Carmichael
910.006 Appendix 2 Structure Plans
Oppose Amend the Plan to: a) Retain as rural residential and development rights b) provide a 100m buffer between large lot residential and logistics/industrial park zones c) remove reference to any logistics in the future d) ensure lighting and vibration does not adversely affect quality of life e) ensure freight movements use an alternative road to Percival Road f) purchase property.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Roy Cowie
928.006 Appendix 2 Structure Plans
Oppose Amend the Plan to: a) Provide a 100m buffer with 4m high planted earth bund. b) Remove the deferred logistics zoning and retain a large lot residential zoning with subdivision to 2500m2.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Deanna - Rose Alexander
979.006 Appendix 2 Structure Plans
Oppose Amend the Plan to ensure no logistics or industrial activities are permitted within 100m of the large lot zone boundary; or purchase property.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Bee Chiew Phee 1004.005 Appendix 2 Structure Plans
Oppose Purchase the residents property or amend the Plan to: a) retain rural residential zoning and allow subdivision to 2500m2. b) Provide a 100m buffer and planted earth bund. c) Ensure no heavy vehicles access to industrial properties from Percival/Ryburn Roads.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Alan Frederick & Barbara Winifred Julian
1005.006 Appendix 2 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning and development rights without reference to any logistics in the future. b) Prevent logistics or industrial activities within 100m of the Large Lot Residential Zone. c) Require a 100m buffer and planted earth bund. d) Require screening and buffering for Ryburn Road; or purchase the property.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 56 of 63
Peter & Barbara Ryan
1006.006 Appendix 2 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning and development rights without reference to any logistics in the future. b) Prevent logistics or industrial activities within 100m of the Large Lot Residential Zone. c) Require a 100m buffer and planted earth bund. d) Control the use of surrounding land so that nuisance effects are limited to levels that approximate a semi-rural lifestyle area.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Bo & Meggie Han & Wang
1007.006 Appendix 2 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning and development rights without reference to any logistics in the future. b) Require a 100m landscaped earth bund buffer around the Large Lot Residential Zone. c) Require controls to mitigate light, noise and vibration effects on Ryburn Road.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Shing-long Lee 1224.006 Appendix 2 Structure Plans
Oppose Amend the Plan to: a) Retain the rural residential zoning and development rights without reference to any logistics in the future. b) Provide a 100m buffer around Percival and Ryburn Roads with a 4m high planted earth bund. c) Ensure freight movements use an alternative road to Percival Road. d) Provide development rights same as provided for in the large lot residential zone for the southern end of the structure plan.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Dennis Roy McLeod
56.003 Figure 2-14 Ruakura Structure Plan-Land Use
Oppose Insufficient green belt identified adjoining dwellings on the Ruakura Structure Plan - landuse plan
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Graeme Ernest Goodwin Goodwin
180.001 Figure 2-14 Ruakura Structure Plan-Land Use
Oppose Requests Ruakura industrial and logistics zone and Inland Port be rezoned to knowledge and rural residential zones or residential
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Simon Travaglia (Waikato Innovation Park Limited)
FS67.015
Oppose
Future Proof Implementation Committee
FS181.029
Oppose
Pearce Andrew Watson (Wizardsleeve Holdings Limited)
215.005 Figure 2-14 Ruakura Structure Plan-Land Use
Oppose Requests assurance that adverse effects will be avoided, remedied and mitigated from the Ruakura Industrial Park.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Jennifer Rita Bothwell (Fairview Downs Residents)
338.002 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Relocate residential and commercial areas within the Ruakura Structure Plan to avoid industrial views and noise for existing homes. Retain natural stormwater drainage.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Future Proof Implementation Committee
608.035 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Amend Figures 2-14 and 2-15 of the Ruakura Structure Plan to identify Greenhill and Ruakura connections to the Waikato Expressway and indicate that Powells, Ryburn and Ruakura Roads are being severed and a new underpass to be undertaken at Percival Road. Designation and road stopping procedures to be undertaken.
Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Ruakura Residents Group and William Roy Cowie
FS167.006
Oppose
Russell Vincent Cooper
FS240.002
Oppose
New Zealand Transport
FS270.082
Support
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 57 of 63
Agency
Wattle Downs Limited
FS280.003
Oppose
AgResearch Ltd 609.024 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Ruakura Structure Plan - retain interchanges at Greenhill Road and Ruakura Road and delete all other options; delete "Transport Corridors" within Ruakura Research Centre.
Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
New Zealand Transport Agency
FS270.083
Support
Wattle Downs Limited
FS280.004
Oppose
Waikato Regional Council
714.092 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Ruakura Structure Plan- Retain possible interchanges until certainty is provided on the locations.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Wattle Downs Limited
FS280.011
Oppose
Waikato-Tainui Te Kauhanganui Inc
771.025 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Ruakura Structure Plan identifies the Greenhill and Ruakura connections as “proposed” interchanges. Remove 5th Avenue and State highway 26.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
WEL Networks Limited
822.031 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Amend Ruakura Structure Plan-Land Use to provide for a network utilities corridor from Silverdale Road to the Waikato Expressway designation; request provisions to enable network utility connections to transportation networks.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Stephen George Bigwood
906.001 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Ruakura Structure Plan amend connections to be consistent with designations; include staging on the map from staging rules; include 20m reserve along Wairere Dr.
The original submission has been withdrawn therefore no decision is required.
AgResearch Limited
FS244.009
Oppose
Wattle Downs Limited
FS280.012
Oppose
Tainui Group Holdings Ltd
913.098 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Amend Figures 2-14 and 2-15 to identify the Greenhill and Ruakura Waikato Expressway connections as “proposed” interchanges. Remove 5th Avenue and State highway 26 Waikato Expressway connections.
Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
Future Proof Implementation Committee
FS181.028
Support
Jennifer West FS271.013
Oppose
Wattle Downs Limited
FS280.006
Oppose
New Zealand Transport Agency
924.205 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Amend Figure 2-14 upon identification of the preferred location and number of connections to the Waikato Expressway.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 58 of 63
Wattle Downs Limited
FS280.002
Oppose
ANG & SL Clarke
951.004 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Retain the Large Lot Residential Zone. Delete the Open Space notation relating to the secondary stormwater flow path in relation to Lot 3 DP 379687.
Accept in part
It is accepted that the Large Lot Residential Zone be retained. The matter in relation to the extent of the Natural Open Space Zone be deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing.
Waikato Innovation Park Limited
1051.020 Figure 2-14 Ruakura Structure Plan-Land Use
Oppose Ruakura Structure Plan -Amend Figures 2-14 to 2-18 to identify Local Transport Corridors within Waikato Innovation Park as indicative internal accessways and re-align.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Transpower New Zealand Ltd
1083.004 Figure 2-14 Ruakura Structure Plan-Land Use
Support Ruakura Structure Plan – Retain Figure 2-14 Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Laurence John Denny
1094.002 Figure 2-14 Ruakura Structure Plan-Land Use
Oppose Ruakura Structure Plan - add to 3.7.1.8 Open Space Network a new clause to recognise a high level of landscaping and screening.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Chedworth Properties Ltd
1171.050 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Ruakura Structure Plan - Amend Figures 2-14 and 2-15 to identify the Greenhill and Ruakura connections as “proposed” interchanges. Remove 5th Avenue and State highway 26
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing . Gwyneth Ann
Verkerk (and Dr Raymond Thomas Cursons)
FS25.002
Oppose
Wattle Downs Limited
FS280.009
Oppose
Waikato District Council
1211.028 Figure 2-14 Ruakura Structure Plan-Land Use
Support in part
Amend Figures 2-14 and 2-15 of the Ruakura Structure Plan to identify Greenhill and Ruakura connections to the Waikato Expressway as proposed interchanges and indicate that Powells, Ryburn and Ruakura Roads are being severed and a new underpass to be undertaken at Percival Road. Designation and road stopping procedures to be undertaken.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Wattle Downs Limited
FS280.018
Support
Kerry & Donna Willmott
1257.005 Figure 2-14 Ruakura Structure Plan-Land Use
Oppose Opposes the Ruakura Industrial zone. Either purchase the property or amend the plan to allow semi-commercial use on 63 Ryburn Road
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Ruakura Residents Group and William Roy Cowie
1275.004 Figure 2-14 Ruakura Structure Plan-Land Use
Oppose Amend Ruakura Structure Plan Figure 2-14 to identify land as Large Lot residential; remove reference to transitional use of land as large lot residential and future use as Ruakura Logistics; if unacceptable rezone 100m buffer as Open Space. Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Future Proof Implementation Committee
FS181.03
Oppose
David Evan & Karlene Chibnall
1278.006 Figure 2-14 Ruakura Structure Plan-Land Use
Oppose Amend the Plan to: a) retain the existing Rural Residential zoning and associated development rights. b) Provide a 100m buffer around Percival and Ryburn Roads with a planted earth bund. c) ensure continuing vehicle access for commuting; and ensure fair treatment over privately owned land.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Roland & Wendy Spirig
1279.006 Figure 2-14 Ruakura Structure Plan-
Oppose Amend the Plan to: a) Retain the Large Lot Residential zoning with the addition of a 100m planted buffer. b) restrict the operating hours of the port to daylight hours and provide for a way to lodge noise complaints.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 59 of 63
Land Use
David Murray and Karen Lee Young
1280.006 Figure 2-14 Ruakura Structure Plan-Land Use
Oppose Amend the Plan to: a) Retain the existing Rural Residential Zoning with associated development rights. b) Provide a 100m buffer around Percival and Ryburn Roads with a 4m high planted earth bund. c) Remove the deferred logistics zoning from the proposed plan.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Dennis Roy McLeod
56.004 Figure 2-15 Ruakura Structure Plan-Transport Network
Oppose Identification of a greenbelt for the mitigation of noise and lighting on the Ruakura Structure Plan - Transport Network Plan
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
AgResearch Ltd 609.025 Figure 2-15 Ruakura Structure Plan-Transport Network
Oppose Ruakura Structure Plan - Figure 2-15 Delete the “Possible Passenger Transport Route” and delete the "Local Transport Corridor Roads" within AgResearch Centre.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato-Tainui Te Kauhanganui Inc
771.026 Figure 2-15 Ruakura Structure Plan-Transport Network
Support in part
Ruakura Structure Plan - Amend Figures 2-14 and 2-15 to identify the Greenhill and Ruakura connections as “proposed” interchanges. Remove 5th Avenue and State highway 26.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing . Gwyneth Ann
Verkerk (and Dr Raymond Thomas Cursons)
FS25.004
Oppose
Stephen George Bigwood
906.007 Figure 2-15 Ruakura Structure Plan-Transport Network
Support in part
Ruakura Structure Plan Figures 2-14 to 2-18 amend connections to be consistent with designations;
The original submission has been withdrawn therefore no decision is required.
Wattle Downs Limited
FS280.013
Oppose
Tainui Group Holdings Ltd
913.099 Figure 2-15 Ruakura Structure Plan-Transport Network
Support in part
Amend Figures 2-14 and 2-15 to identify the Greenhill and Ruakura Waikato Expressway connections as “proposed” interchanges. Remove 5th Avenue and State highway 26 Waikato Expressway connections. Supports Figures 2-15 and 2-19 regarding infrastructure and staging.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
Jennifer West FS271.014
Oppose
Wattle Downs Limited
FS280.007
Oppose
Parkwood Gateway Limited
977.030 Figure 2-15 Ruakura Structure Plan-Transport Network
Oppose Ruakura Structure Plan - Figure 2-15 amend to delete the Major Arterial Transport Corridor and Arterial Corridor Protection Area from land located outside of the Structure Plan Area.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Portland Park Limited
984.028 Figure 2-15 Ruakura Structure Plan-Transport
Oppose Ruakura Structure Plan - Figure 2.15 amend to delete the Major Arterial Transport Corridor and Arterial Corridor Protection Area from land located outside of the Structure Plan Area.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 60 of 63
Network
Waikato Innovation Park Limited
1051.021 Figure 2-15 Ruakura Structure Plan-Transport Network
Oppose Ruakura Structure Plan - Figures 2-14 to 2-18 amend by identifying the Local Transport Corridors within Waikato Innovation Park as indicative internal accessways and re-align Local Transport Corridors; delete cycleways/walkways shown on Figure 2-15 within Waikato Innovation Park.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Chedworth Properties Ltd
1171.051 Figure 2-15 Ruakura Structure Plan-Transport Network
Support in part
Ruakura Structure Plan - Amend Figures 2-14 and 2-15 to identify the Greenhill and Ruakura connections as “proposed” interchanges. Remove 5th Avenue and State highway 26.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Wattle Downs Limited
FS280.01
Oppose
Waikato District Council
1211.029 Figure 2-15 Ruakura Structure Plan-Transport Network
Support in part
Amend Figures 2-14 and 2-15 of the Ruakura Structure Plan to identify Greenhill and Ruakura connections to the Waikato Expressway as proposed interchanges and indicate that Powells, Ryburn and Ruakura Roads are being severed and a new underpass to be undertaken at Percival Road. Designation and road stopping procedures to be undertaken
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Wattle Downs Limited
FS280.019
Support
AgResearch Ltd 609.026 Figure 2-16 Ruakura Structure Plan-Water Infrastructure
Oppose Delete the Transport Corridors within the AgResearch Centre on the Ruakura Structure Plan Fig 2-16
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato-Tainui Te Kauhanganui Inc
771.027 Figure 2-16 Ruakura Structure Plan-Water Infrastructure
Support in part
Ruakura Structure Plan - Amend Figures 2-14 and 2-15 to identify the Greenhill and Ruakura connections as “proposed” interchanges. Remove 5th Avenue and State highway 26.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Stephen George Bigwood
906.008 Figure 2-16 Ruakura Structure Plan-Water Infrastructure
Support in part
Ruakura Structure Plan - Amend Figs 2-14 to 2-18 to remove possible interchanges which are inconsistent with designations.
The original submission has been withdrawn therefore no decision is required.
Wattle Downs Limited
FS280.014
Oppose
Tainui Group Holdings Ltd
913.100 Figure 2-16 Ruakura Structure Plan-Water Infrastructure
Support in part
Amend Figures 2-14 and 2-15 to identify the Greenhill and Ruakura Waikato Expressway connections as “proposed” interchanges. Remove 5th Avenue and State highway 26 Waikato Expressway connections. Supports Figures 2-15 and 2-19 regarding infrastructure and staging.
Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
New Zealand Transport Agency
FS270.085
Support
Jennifer West FS271.015
Oppose
Wattle Downs Limited
FS280.008
Oppose
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 61 of 63
Parkwood Gateway Limited
977.031 Figure 2-16 Ruakura Structure Plan-Water Infrastructure
Oppose Ruakura Structure Plan - Figure 2.16 amend to delete Stage 1 interim water connection point A from land located outside of the Structure Plan Area, or alternatively that it be made clear that this notation does not relate to either Lots 1 or 3 DP 444645.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Portland Park Limited
984.029 Figure 2-16 Ruakura Structure Plan-Water Infrastructure
Oppose Ruakura Structure Plan - Figure 2.16 amend to delete Stage 1 interim water connection point A from land located outside of the Structure Plan Area, or alternatively that it be made clear that this notation does not relate to either Lots 1 or 3 DP 444645.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Innovation Park Limited
1051.022 Figure 2-16 Ruakura Structure Plan-Water Infrastructure
Oppose Ruakura Structure Plan - Figures 2-14 to 2-18 amend by identifying the Local Transport Corridors within Waikato Innovation Park as indicative internal accessways and re-align Local Transport Corridors.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Chedworth Properties Ltd
1171.052 Figure 2-16 Ruakura Structure Plan-Water Infrastructure
Support in part
Ruakura Structure Plan - Supports infrastructure and staging in Figures 2.15 – 2-19.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato District Council
1211.030 Figure 2-16 Ruakura Structure Plan-Water Infrastructure
Support in part
Ruakura Structure Plan - supports figs 2-15 to 2-19 in relation to the infrastructure and staging.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
AgResearch Ltd 609.027 Figure 2-17 Ruakura Structure Plan-Waste Water Infrastructure
Oppose Ruakura Structure Plan Fig 2-17 - Delete the Transport Corridors within the AgResearch Centre.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato-Tainui Te Kauhanganui Inc
771.028 Figure 2-17 Ruakura Structure Plan-Waste Water Infrastructure
Support in part
Ruakura Structure Plan - supports the infrastructure and staging in Figures 2.15 – 2-19.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Stephen George Bigwood
906.009 Figure 2-17 Ruakura Structure Plan-Waste Water Infrastructure
Support in part
Ruakura Structure Plan -amend Figs 2-14 to 2-18 to remove interchange connections inconsistent with designations.
The original submission has been withdrawn therefore no decision is required. Future Proof
Implementation Committee
FS181.031
Oppose
Wattle Downs Limited
FS280.015
Oppose
Tainui Group Holdings Ltd
913.101 Figure 2-17 Ruakura Structure Plan-Waste Water Infrastructure
Support in part
Supports Figures 2-15 and 2-19 regarding infrastructure and staging.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
Parkwood 977.032 Figure 2-17 Oppose Ruakura Structure Plan - Fig 2-17 delete the Stage 1 interim wastewater Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 62 of 63
Gateway Limited
Ruakura Structure Plan-Waste Water Infrastructure
connection points A & B from land located outside the Structure Plan Area, or make it clear these do not relate to either Lots 1 or 3 DP 444645.
Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Portland Park Limited
984.030 Figure 2-17 Ruakura Structure Plan-Waste Water Infrastructure
Oppose Ruakura Structure Plan - Fig 2-17 delete the Stage 1 interim wastewater connection points A & B from land located outside the Structure Plan Area, or make it clear these do not relate to either Lots 1 or 3 DP 444645.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Innovation Park Limited
1051.023 Figure 2-17 Ruakura Structure Plan-Waste Water Infrastructure
Oppose Amend Figures 2-14 to 2-18 by identifying the Local Transport Corridors within Waikato Innovation Park as indicative internal accessways and re-alignment of the Local Transport Corridors.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Chedworth Properties Ltd
1171.053 Figure 2-17 Ruakura Structure Plan-Waste Water Infrastructure
Support in part
Supports Figures 2-15 and 2-19 infrastructure and staging. Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato District Council
1211.031 Figure 2-17 Ruakura Structure Plan-Waste Water Infrastructure
Support in part
Supports Figures 2-15 and 2-19 infrastructure and staging. Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
AgResearch Ltd 609.028 Figure 2-18 Ruakura Structure Plan-Storm Water Infrastructure
Oppose Figure 2-18: delete the “Transport Corridors” located within the Ruakura Research Centre.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato-Tainui Te Kauhanganui Inc
771.029 Figure 2-18 Ruakura Structure Plan-Storm Water Infrastructure
Support in part
Amend Figures 2-14 and 2-15 to identify the Greenhill and Ruakura connections as “proposed” interchanges. Remove 5th Avenue and State highway 26.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Wattle Downs Limited
FS280.005
Oppose
Stephen George Bigwood
906.010 Figure 2-18 Ruakura Structure Plan-Storm Water Infrastructure
Support in part
Amend Figures 2-14 to 2-18 to remove the possible interchange connections to the Waikato Expressway which are inconsistent with the Waikato Expressway Designation.
The original submission has been withdrawn therefore no decision is required.
Future Proof Implementation Committee
FS181.032
Oppose
New Zealand Transport Agency
FS270.084
Oppose
Wattle Downs Limited
FS280.016
Oppose
Tainui Group Holdings Ltd
913.102 Figure 2-18 Ruakura Structure Plan-Storm Water Infrastructure
Support in part
Supports Figures 2-15 and 2-19 regarding infrastructure and staging.
Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Cornelis Engelander
FS160.001
Oppose
Decisions Report – Chapter 3 Structure Plans, 9 July 2014
Page 63 of 63
James Hely and Heather Montgomerie -
FS161.001
Oppose
Parkwood Gateway Limited
977.033 Figure 2-18 Ruakura Structure Plan-Storm Water Infrastructure
Oppose Figure 2.18 be amended to delete Stage 1 interim stormwater connection point A from land located outside of the Structure Plan Area, or it be made clear this does not relate to either Lots 1 or 3 DP 444645.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Portland Park Limited
984.031 Figure 2-18 Ruakura Structure Plan-Storm Water Infrastructure
Oppose Figure 2.18 be amended to delete Stage 1 interim stormwater connection point A from land located outside of the Structure Plan Area, or it be made clear this does not relate to either Lots 1 or 3 DP 444645.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato Innovation Park Limited
1051.024 Figure 2-18 Ruakura Structure Plan-Storm Water Infrastructure
Oppose Amend Figures 2-14 to 2-18 by identifying the Local Transport Corridors within Waikato Innovation Park as indicative internal accessways and re-alignment of the Local Transport Corridors.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Chedworth Properties Ltd
1171.054 Figure 2-18 Ruakura Structure Plan-Storm Water Infrastructure
Support in part
Amend Figures 2-14 and 2-15 to identify the Greenhill and Ruakura connections as “proposed” interchanges. Remove 5th Avenue and State highway 26.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato District Council
1211.032 Figure 2-18 Ruakura Structure Plan-Storm Water Infrastructure
Support in part
Amend Figures 2-14 and 2-15 of the Ruakura Structure Plan to identify Greenhill and Ruakura connections to the Waikato Expressway and indicate that Powells, Ryburn and Ruakura Roads are being severed and a new underpass to be undertaken at Percival Road. Designation and road stopping procedures to be undertaken.
Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Wattle Downs Limited
FS280.02
Support
Waikato-Tainui Te Kauhanganui Inc
771.030 Figure 2-19 Ruakura Residential Staging
Support in part
Supports Figures 2-15 - 2-19 for infrastructure and staging. Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Tainui Group Holdings Ltd
913.103 Figure 2-19 Ruakura Residential Staging
Support in part
Supports Figures 2-15 and 2-19 regarding infrastructure and staging.
Defer
This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
William Cornelis Engelander
FS160.001
Oppose
James Hely and Heather Montgomerie -
FS161.001
Oppose
Chedworth Properties Ltd
1171.055 Figure 2-19 Ruakura Residential Staging
Support in part
Supports Figures 2-15 and 2-19 infrastructure and staging. Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .
Waikato District Council
1211.033 Figure 2-19 Ruakura Residential Staging
Support in part
Supports Figures 2-15 and 2-19 infrastructure and staging. Defer This matter is deferred until the Board of Inquiry issues a decision on the Plan Change Application for Ruakura to the Operative District Plan which is anticipated in September this year and these matters will be heard by the Commissioners at a reconvened hearing .