Chapter 2 Problem Solving Tools

Embed Size (px)

Citation preview

  • 7/28/2019 Chapter 2 Problem Solving Tools

    1/67

    PROBLEM-SOLVING TOOLS

  • 7/28/2019 Chapter 2 Problem Solving Tools

    2/67

    Exploratory Tools Pareto Analysis

    Fish Diagrams

    Gantt Chart PERT Chart

    Job / Worksite Analysis Guide

  • 7/28/2019 Chapter 2 Problem Solving Tools

    3/67

    Pareto Analysis Items identified and ordered on

    common scale in decreasingfrequency, creating a cumulative

    distribution 80/20 Rule: 20% of the items account

    for 80% of the problems

    Allows the company to concentrateresources on the jobs with the mostproblems

  • 7/28/2019 Chapter 2 Problem Solving Tools

    4/67

    Pareto Analysis

    20

    80

    20

    80

    Causes Problems

  • 7/28/2019 Chapter 2 Problem Solving Tools

    5/67

    Pareto Analysis Example Diagram

  • 7/28/2019 Chapter 2 Problem Solving Tools

    6/67

    Pareto Analysis

    80

    58

    42 42

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    200

    220

    1 2 3 4

    FrekuensiKu

    mulatif

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    ProsentaseKumulatif

    Keterangan:

    1 = Pergantian sistem penyimpanan status

    2 = Pasien lama tidak bawa kartu

    3 = Status baru terlalu banyak

    4 = Status lama tidak ketemu

    Keterangan:

    1 = Pergantian sistem penyimpanan status

    2 = Pasien lama tidak bawa kartu

    3 = Status baru terlalu banyak

    4 = Status lama tidak ketemu

    3124

    19 16

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    200

    220

    1 2 3 4

    FrekuensiKu

    mulatif

    0%

    50%

    100%

    150%

    200%

    ProsentaseKumulatif

  • 7/28/2019 Chapter 2 Problem Solving Tools

    7/67

    Fishbone Diagrams Cause-and-effect diagrams

    Identified problem or undesirable resultis the head

    Contributing factors are the bones

    Typical categories include: Human,

    machine, methods, materials,environment, and administrative

    Estimates associated probabilities

  • 7/28/2019 Chapter 2 Problem Solving Tools

    8/67

    Fishbone Diagrams Example Diagram

    Figure 2-3

  • 7/28/2019 Chapter 2 Problem Solving Tools

    9/67

    Gantt Chart

    Used for planning of complex projects

    Shows expected start and completiontimes, also duration of events

    Similarly, major events can be broken intosmaller sub-tasks

    Shade the bars to show actual completiontime

  • 7/28/2019 Chapter 2 Problem Solving Tools

    10/67

    Gantt Chart Example Diagram

    Figure 2-4

  • 7/28/2019 Chapter 2 Problem Solving Tools

    11/67

    PERT Chart Program Evaluation and Review Technique

    (PERT) is a planning and control tool

    Also known as Network Diagram or Critical

    Path

    Graphically portrays the optimum way toobtain a desired objective with respects to

    time

    Optimistic, average, and pessimistic timeestimates utilized

  • 7/28/2019 Chapter 2 Problem Solving Tools

    12/67

    PERT Chart

  • 7/28/2019 Chapter 2 Problem Solving Tools

    13/67

    Job / WorksiteAnalysis Guide

    Perform a walkthrough observing thearea, worker, task, environment,administrative constraints, etc.

    Develop an overall perspective of thesituation

    Particularly useful in workstationredesign

  • 7/28/2019 Chapter 2 Problem Solving Tools

    14/67

    Job / WorksiteAnalysis Guide Example Guide

    Figure 2-6

  • 7/28/2019 Chapter 2 Problem Solving Tools

    15/67

    Recording andAnalysis Tools

    Operation Process Chart

    Flow Process Chart

    Flow Diagram Worker and Machine Process Charts

    Gang Process Charts

  • 7/28/2019 Chapter 2 Problem Solving Tools

    16/67

    Operation ProcessChart

    Chronological sequence of alloperations, inspections, timeallowances, materials

    Depicts entrance and exit of allcomponents and sub-assemblies andproducts

    Provides information on the number ofemployees required time for jobs andinspections

  • 7/28/2019 Chapter 2 Problem Solving Tools

    17/67

    Basic Symbols

    process symbol

    Operasi

    transportasi

    Delay

    Inspeksi

    Storage

  • 7/28/2019 Chapter 2 Problem Solving Tools

    18/67

    Operation Process Chart

  • 7/28/2019 Chapter 2 Problem Solving Tools

    19/67

  • 7/28/2019 Chapter 2 Problem Solving Tools

    20/67

    OperationProcess Chart

    Example DiagramFigure 2-8

  • 7/28/2019 Chapter 2 Problem Solving Tools

    21/67

    Flow Process Chart More detailed, fit for closer observation

    of smaller components or assemblies

    Shows all moves (distances) and storagedelays (times) for product movement inplant

    Aids in the reduction of hidden costs,

    Muda. Can be beneficial for plant layout

    suggestions

  • 7/28/2019 Chapter 2 Problem Solving Tools

    22/67

    ypes o

  • 7/28/2019 Chapter 2 Problem Solving Tools

    23/67

    ypes oFlow Process Chart

    Currently Use

    Product/material

    (see figure 2-11)

    Operative/person

    (see figure 2-12)

  • 7/28/2019 Chapter 2 Problem Solving Tools

    24/67

    Flow ProcessChart

    Example DiagramFigure 2-11

    Fl P

  • 7/28/2019 Chapter 2 Problem Solving Tools

    25/67

    Flow ProcessChart

    Example Diagram

    Figure 2-12

  • 7/28/2019 Chapter 2 Problem Solving Tools

    26/67

    Flow Diagram Pictorial representation of the layout

    of the plant

    Good supplement to the Flow Process Chart

  • 7/28/2019 Chapter 2 Problem Solving Tools

    27/67

    Flow Diagram

    PRODUKSI GUDANG

    1 2 3 45

  • 7/28/2019 Chapter 2 Problem Solving Tools

    28/67

    Flow Diagram Example Diagram Figure 2-13

  • 7/28/2019 Chapter 2 Problem Solving Tools

    29/67

    Worker and MachineProcess Charts

    Used to study, analyze, and improveone workstation

    Shows the time relationship betweenworking cycle of the person and theoperating cycle of the machine

    Reveals idle time for both machinesand workers

    W k d

  • 7/28/2019 Chapter 2 Problem Solving Tools

    30/67

    Worker andMachineProcess Charts

    Example DiagramFigure 2-15

  • 7/28/2019 Chapter 2 Problem Solving Tools

    31/67

    Gang Process Chart Example Diagram Figure 2-16

  • 7/28/2019 Chapter 2 Problem Solving Tools

    32/67

    Quantitative Tools Synchronous Servicing

    Random Servicing

    Complex Relationships

    Line Balancing

  • 7/28/2019 Chapter 2 Problem Solving Tools

    33/67

    SYNCHRONOUSSERVICING

    Assigning more than one machine

    to an operator seldom results in ideal case where both the workerand the machine are occupied during the whole cycle.

    n = l + m

    l

    n = Number of machine the operator is assigned

    l = Total operator loading and unloading

    (servicing) time per machine

    m = Totalmachine running time (automatic

    power feed).

    Synchronous

  • 7/28/2019 Chapter 2 Problem Solving Tools

    34/67

    SynchronousServicing

    Example: assume a total cycle time offour minutes to produce a product, asmeasured from the start of theunloading of the previously completed

    product to the end of the machine cycletime. Operator servicing, which includesboth the unloading of the completedproduct and the loading of the rawmaterials is one minute,while the cycletime of the automatic machince cycle isthree minutes.

  • 7/28/2019 Chapter 2 Problem Solving Tools

    35/67

    wl

    mlN1

    N = number of machines

    m = total machine running time

    w = walking time

    l = loading and unloading time

  • 7/28/2019 Chapter 2 Problem Solving Tools

    36/67

    Total Expected Cost

    1

    211 ))((1

    N

    KNKmlTECN

    K1 = operator rateK2 = cost of machine

    ))(( 2212 KNKwlTECN

  • 7/28/2019 Chapter 2 Problem Solving Tools

    37/67

    Alternate Approach:

    R

    KNKTECN)( 211

    1

    ))(( 2212 KNKwlTECN

    11

    Nxml

    R

    wl

    R

    1

  • 7/28/2019 Chapter 2 Problem Solving Tools

    38/67

    contoh so al

    proses Time(minute)

    Pick up plate into press dies 0,1

    Lubricate dies in press 0,3

    Press 1,2

    Walk to next press 0,1

    $ worker (K1) = $ 12 / hour

    $ machine (K2) = $ 10 / hour

  • 7/28/2019 Chapter 2 Problem Solving Tools

    39/67

    Ditanya:

    Jumlah mesin yang dibutuhkan

    TEC tiap kemungkinan jumlah mesin

  • 7/28/2019 Chapter 2 Problem Solving Tools

    40/67

    Jawaban:

    N = (l+m)/(l+w) = (0.4+1.2)/ (0.4+0.1) = 3.2

    Sehingga jumlah mesin yang mungkinadalah 3 atau 4 mesin

  • 7/28/2019 Chapter 2 Problem Solving Tools

    41/67

    Jawaban TEC3 = (l+m)(K1+n1K2)/n1

    = (0.4+1.2)(12+3 x 10)/3/60

    = $ 0.3733/ unit

    TEC4 = (l+w)(K1+n2K2)= (0.4+0.1)(12+4x 10)/60= $ 0.4333 /unit

    Synchronous Servicing

  • 7/28/2019 Chapter 2 Problem Solving Tools

    42/67

    Synchronous Servicingin Design Tools

    Worker 1

    Machine 1Machine 2

    Machine 3

    Machine 4

    Answer:n = l + m = 1 + 3 = 4 machines

    l 1

    Worker Working

    Loading/unloading

    Machine running

    Legend:

    Idle Time

  • 7/28/2019 Chapter 2 Problem Solving Tools

    43/67

    RANDOM SERVICING

    Helps to determine the number ofmachines to assign to an operatorwhen it is not known exactly when each

    machine needs to be serviced or forhow long

    The binomial expansion give a useful

    approximation of the machine downprobability

  • 7/28/2019 Chapter 2 Problem Solving Tools

    44/67

    Assuming that each machine is down atrandom times during the day and that theprobability of the down time isp and theprobability of runtime is q = (1-p). Each term

    of the binomial expansion can be expressedas a probability of m (out of n) machinesdown:

    P(m of n) = n !

    m! (n-m)!

    pm qn-m

  • 7/28/2019 Chapter 2 Problem Solving Tools

    45/67

    Total Expected Cost (TEC):

    K1 = hourly rate of the operator

    K2 = hourly rate of the machine

    N = number of machines assignedR = rate of production, pieces from N

    machines per hour

    R

    NKKTEC

    )( 21

    COMPLEX

  • 7/28/2019 Chapter 2 Problem Solving Tools

    46/67

    COMPLEXRELATIONSHIPS

    Here the servicing time is relativelyconstant, but the machines areserviced randomly

  • 7/28/2019 Chapter 2 Problem Solving Tools

    47/67

    For seven or more machines, WrightsFormula can be used:

    I = interference, expressed as apercentage of the mean servicing time

    X = ratio of mean machine running time tomean machine servicing time

    N = number of machine units assigned toone operator

    NXNNXI

    12150

    2

  • 7/28/2019 Chapter 2 Problem Solving Tools

    48/67

    LINE BALANCING

    Helps to determine the ideal number ofworkers to be assigned to a productionline

    Computer software is available toeliminate the calculations

    100

    .

    ..

    X

    MA

    MS

    E

    E = EficiencySM = Standard minute per operation

    AM = Allowed standard minutes per operation

  • 7/28/2019 Chapter 2 Problem Solving Tools

    49/67

    DefinisiLine balancingmerupakan suatu metode

    penugasan sejumlah pekerjaan yangsaling berkaitan dalam satu lini produksisehingga setiap stasiun kerja memiliki

    waktu yang tidak melebihi waktu siklusdari stasiun kerja tersebut.

    Line balancingberusaha menyeimbangkanseluruh lintasan yang ada dalam lini

    perakitan sehingga aliran produksiberjalan lancar.

    How to Calculate Line Efficiency ?

  • 7/28/2019 Chapter 2 Problem Solving Tools

    50/67

    Operator 1Operator 2

    Operator 3

    Operator 4

    Operator 5

    Operator

    Standard Minutes

    to Perform

    Operation

    1 0.49

    2 0.31

    3 0.25

    4 0.44

    5 0.54

    How to Calculate Line Efficiency ?

    Line Efficiency ?

  • 7/28/2019 Chapter 2 Problem Solving Tools

    51/67

    100

    .

    ..

    5

    1

    5

    1

    X

    MA

    MS

    E

    Operator

    Standard Minutes

    to Perform

    Operation

    Wait Time Based on

    Slowest Operator

    Allowed

    Standard

    Minutes

    1 0.49 0.05 0.54

    2 0.31 0.23 0.54

    3 0.25 0.29 0.54

    4 0.44 0.1 0.54

    5 0.54 0 0.54

    2.03 2.7

    Line Efficiency ?

    Opportunities for Improvements ?

  • 7/28/2019 Chapter 2 Problem Solving Tools

    52/67

    0.490.31

    0.25

    0.44

    0.54

    Operator

    Standard Minutes

    to Perform

    Operation

    Wait Time Based on

    Slowest Operator

    Allowed

    Standard

    Minutes

    1 0.49 0.05 0.54

    2 0.31 0.23 0.54

    3 0.25 0.29 0.54

    4 0.44 0.1 0.54

    5 0.54 0 0.54

    2.03 2.7

    Efficiency 75.19%

    Opportunities for Improvements ?

  • 7/28/2019 Chapter 2 Problem Solving Tools

    53/67

    Operation Standard Minutes

    1 1.5

    2 2.25

    3 1.25

    4 2.5

    5 3

    6 2.757 1.75

    Assembly Line

    (7 operations)

  • 7/28/2019 Chapter 2 Problem Solving Tools

    54/67

    Desired Rate of Production = 1000/day

    Efficiency = 95%

    1 day = 10 hours = 600 minutes

    Thus R = 1000/600 = 1.67 units/minute

    Numbers of Operator Neededin Assembly Line?

  • 7/28/2019 Chapter 2 Problem Solving Tools

    55/67

    E

    SMRAMRN

    27 operators

    Operation Standard Minutes

    1 1.5

    2 2.25

    3 1.25

    4 2.5

    5 3

    6 2.75

    7 1.75

    minutes/unit 0.6

    SM 15R 1.67

    E 0.95

    26.36842105

    Output?1.5/0.6

    2 25/0 6

  • 7/28/2019 Chapter 2 Problem Solving Tools

    56/67

    Operation Standard Minutes

    (standard

    minutes)/(minutes/u

    nit)

    Operators

    1 1.5 2.5 32 2.25 3.75 4

    3 1.25 2.083333333 2

    4 2.5 4.166666667 5

    5 3 5 5

    6 2.75 4.583333333 5

    7 1.75 2.916666667 3

    inutes/unit 0.6 27

    Output? 2.25/0.6Dst.

    600/1000

  • 7/28/2019 Chapter 2 Problem Solving Tools

    57/67

    Slowest One?

    Operation Standard Minutes

    (standard

    minutes)/(minutes/unit)

    Operators

    1 1.5 2.5 3 0.5

    2 2.25 3.75 4 0.5625

    3 1.25 2.083333333 2 0.625

    4 2.5 4.166666667 5 0.5

    5 3 5 5 0.66 2.75 4.583333333 5 0.55

    7 1.75 2.916666667 3 0.583333333

    dayhouroutput /960/9625.1

    602

    (2.5/3)*0.6

    (3.75/4)*0.6Dst.

  • 7/28/2019 Chapter 2 Problem Solving Tools

    58/67

    Line Balancing Problem

    A

    B

    C

    4.1mins

    D

    1.7mins

    E

    2.7 mins

    F

    3.3

    mins

    G

    2.6 mins

    2.2 mins

    3.4 mins

  • 7/28/2019 Chapter 2 Problem Solving Tools

    59/67

    1. What process is the bottleneck?

    2. How much is the maximumproduction per hour?

    3. How much the efficiency?

    4. How to minimize work stations?

    5. How should they be grouped? 6. New efficiency?

    Question

  • 7/28/2019 Chapter 2 Problem Solving Tools

    60/67

    Calculate efficiency A. 73.2% B. 56.7%

    C. 69.7% D. 79.6%

    E. 81.2%

    A

    B

    C

    4.1mins

    D

    1.7mins

    E

    2.7 mins

    F

    3.3

    mins

    G

    2.6 mins

    2.2 mins

    3.4 mins

  • 7/28/2019 Chapter 2 Problem Solving Tools

    61/67

    (2.2+3.4+4.1+2.7+1.7+3.3+2.6)4.1x7

    20

    28.7

    69.7%

    1-69.7%=30.3% Balance Delay

  • 7/28/2019 Chapter 2 Problem Solving Tools

    62/67

    t imeyc le t imesa skN

    (bottleneck)20

    4.1

    = 4.88 work stations

    Number of Workstation

    4 Stations 20/24=83 3%

  • 7/28/2019 Chapter 2 Problem Solving Tools

    63/67

    Line Balancing Solution

    A

    B

    C

    4.1

    D

    1.7

    E

    2.7

    F

    3.3

    G

    2.6

    Station 1

    Station 2

    Station 3

    Station 4

    2.2

    3.4

    All under 6 minutes?

    (6.0)

    (5.6)

    (5.8)

    4 Stations 20/24 83.3%

    Max prod./hour60/610 units/hour

    5 Stations

  • 7/28/2019 Chapter 2 Problem Solving Tools

    64/67

    Line Balancing Problem

    A

    B

    C

    4.1mins

    D

    1.7mins

    E2.7 mins

    F

    3.3

    mins

    G

    2.6 mins

    2.2 mins

    3.4 mins5.6

    5.0

    20/5.6x5 = 20/28 = 71.4%

    5 Stations

    Max Prod./hour60/5.6

    10.7 units/hour

  • 7/28/2019 Chapter 2 Problem Solving Tools

    65/67

  • 7/28/2019 Chapter 2 Problem Solving Tools

    66/67

    timecycle

    task timesN

    40+59+84+56+34+45 = 318

    318/84 = 3.78 or 3 work stations

    What is the efficiency with 6 operators?

    100

    timecyclestationsofnumber

    task times%Efficency

    318/6 x 84=

    318/504 =

    63%

    99 secs 3 Stations ?

  • 7/28/2019 Chapter 2 Problem Solving Tools

    67/67

    100timecyclestationsofnumber

    task times%Efficency

    40 secs

    59 secs

    84 secs34 secs

    56 secs 45 secs

    118 secs

    318/3x118

    318/354 = 89.8%101 secs