    CONSTRUCTION

    TECHNOLOGY II

    CHAPTER 2

    PRELIMINARY WORKS

  • 8/12/2019 Chapter 2 Ctii 1

    2/28

    Preliminary works- Site works that are

    preparatoryand subsidiaryin nature, carried outbefore the actual construction work is executed

    Site Preparation

    Site clearance

    Earthwork

    Site surveying Demolition

    Temporary Facilities

    Site office

    Accommodation, toilet & sanitary

    Storage

    Security

    Laboratory

    Services

  • 8/12/2019 Chapter 2 Ctii 1

    3/28

    2.1 Site Preparation

    Site clearanceHas to be donebeforethe

    construction, clearing undergrowth, bushes,grubbing up & removal of tree roots

    Earthwork

    Work below grounde.g. foundation

    The top layerof the soil is an unsuitablematerial

    Shall be removedandbackfilled

    Earth drain construction, construction of accessroad, levelling of the ground to the required

    platform level

    Site surveyingDetermine theboundaryof the siteand levelling for building, drainage, road, services

  • 8/12/2019 Chapter 2 Ctii 1

    4/28

  • 8/12/2019 Chapter 2 Ctii 1

    5/28

  • 8/12/2019 Chapter 2 Ctii 1

    6/28

  • 8/12/2019 Chapter 2 Ctii 1

    7/28

  • 8/12/2019 Chapter 2 Ctii 1

    8/28

    2.1 Site Preparation (Contd)

    Demolition

    If there is any existing structureto be demolished

    Taking downpartial demolition of a structure &normally to be carried out using hand tools

    Requires a good comprehensive knowledgeofbuilding

    constructionand design, so that load bearing structurescan be identified & supported by struts, props, shoring

    Demolitioncomplete removal of a structure

    A detailed surveyand examinationof the structure

    should be made The condition of the adjoining propertieswhich may be

    affectedby the demolitionshould be considered

    Flammablematerials are removedbefore the demolition

    works commences

  • 8/12/2019 Chapter 2 Ctii 1

    9/28

  • 8/12/2019 Chapter 2 Ctii 1

    10/28

  • 8/12/2019 Chapter 2 Ctii 1

    11/28

    2.2 Temporary Facilities

    Site Office

    Timber huts

    Wall - waterproofing plywood nailed onto sawn

    hardwood timber as stud (vertical) & noggings

    Rooflightweight material (zinc or metal sheeting) Normally for a shortconstruction period

    Mobile cabin or container

    Available in a wide variety of sizes& styles& fully

    equipped Convenient for transportationby using trailer

    Is durable& allow for re-useon other sites for many

    years

  • 8/12/2019 Chapter 2 Ctii 1

    12/28

  • 8/12/2019 Chapter 2 Ctii 1

    13/28

  • 8/12/2019 Chapter 2 Ctii 1

    14/28

    2.2 Temporary Facilities (Contd) Accommodation, toilet and sanitary fittings

    Site personnelwho are stationed on site

    Foreign laboursthroughout the entire construction periods

    Storage

    Types of storage facilities depends on durability,vulnerability to damage & vulnerability to theft

    Ironmongery, hand toolsandpaint to be kept in lock hut

  • 8/12/2019 Chapter 2 Ctii 1

    15/28

    Cement,plasterand limein

    begrequire a drystore

    Aggregatessuch as sandand

    gravelrequire a clean firm base

  • 8/12/2019 Chapter 2 Ctii 1

    16/28

    Bricksandblocksshould be

    stackedin stable piles on a level

    & well-drainedsurface

    Roof tileshave a greater

    resistanceto load when it is

    imposed on the edge

  • 8/12/2019 Chapter 2 Ctii 1

    17/28

    Timberis a hygroscopic

    material and therefore to

    prevent undue moisturemovement

  • 8/12/2019 Chapter 2 Ctii 1

    18/28

    2.2 Temporary Facilities (Contd)

    Security

    Spotlight, hoarding, fencingand guardhouse

    Artificial lighting

    Reduces the risk of accident and injury

    Increases the production hour on site, allowwork to proceed at night

    Deliveries and collection of materials or plantcan be made outside normal site working hours

    Improve the general security on site

  • 8/12/2019 Chapter 2 Ctii 1

    19/28

    2.2 Temporary Facilities (Contd)

    Laboratory

    A place for testingof the materialon site

    Eg, cube test for concrete, tensile test for steel

    Which is essential under certain government

    projectsof infrastructureworks Services

    Waterconcreting, plastering and painting

    Electricityto provide the power to drive small

    and large items of plant, provide lighting Electricityportable self-powered generators &

    metered supply from the local area electricityboard

  • 8/12/2019 Chapter 2 Ctii 1

    20/28

    2.2 Temporary Facilities (Contd)

    Fencing Fencing is used to define the limit of the site or

    compoundand toprevent theft and vandalism

    A fencecan be constructed to provide aphysicalbarrier of solid construction or visual barrier of

    open work construction Type of fencing depends on the degree of security,

    cost implication, type of neighbourhood, durationof contract

    A security fence around the site or compoundshould be at least 1.8m high above the ground

    It should include the minimum number of accesspoints which should have a lockable barrieror gate

  • 8/12/2019 Chapter 2 Ctii 1

    21/28

  • 8/12/2019 Chapter 2 Ctii 1

    22/28

  • 8/12/2019 Chapter 2 Ctii 1

    23/28

  • 8/12/2019 Chapter 2 Ctii 1

    24/28

    2.2 Temporary Facilities (Contd)

    Hoarding

    Hoarding is close boarded fenceserected

    adjacent to a highwayorpublic footpath

    It can prevent unauthorised personobtaining

    accessto the site It provides a degree ofprotectionfor thepublic

    from the dustand noiseassociated with the

    construction works

    There are two forms of hoardings in common

    use; vertical hoardingand fan hoarding

  • 8/12/2019 Chapter 2 Ctii 1

    25/28

    2.2 Temporary Facilities (Contd)

    Vertical hoarding

    Consists of a series of closed boarded panels

    securely fixed to resist wind loads & accidental

    impact loads

    Can be free standing or fixed by stays toexternal walls of existing structures

  • 8/12/2019 Chapter 2 Ctii 1

    26/28

  • 8/12/2019 Chapter 2 Ctii 1

    27/28

    2.2 Temporary Facilities (Contd)

    Fan hoarding

    Is placed at a level above normal traffic height

    Arranged in a manner that any falling debris is

    directed back towards the site

  • 8/12/2019 Chapter 2 Ctii 1