Upload
neutron87
View
37
Download
2
Embed Size (px)
DESCRIPTION
Foamed Concrete
Citation preview
CHAPTER 1
INTRODUCTION
1.1 Background
The general idea of this project is to produce and test foamed concrete (FC) in
the laboratory. Preliminary, it involves the finding of a mix proportion for foamed
concrete which will produce hardened concrete that can sustain dynamic load.
The Star Online News quoted Mr. Faizal Parish of the Global Environment
Centre (Peat Expert) that road construction on the peat soil area is unavoidable
phenomena in Sarawak because 95% of peat land in Sarawak is categorized as deep
peat which is more than 3m deep ( The Star Online, August 9, 2009). Therefore, this
research is aimed to introduce the composite structure of foamed concrete to be a
preferred material for sub base used in road construction on the peat soil. The
conventional method of using the geotextile and the bakau log is the common practice
for such construction on peat soil.
Composite concrete can be described as combined structure of different types of
concrete. In this project, combination of different mix of foamed concrete is examined
1
in term of strength, volume and bonding in order to fulfill the required characteristics
of road sub base. Moreover, it will be compared to conventional method which is using
geotextile and bakau log. Thus, the required characteristics of the composite concrete
are determined through the experiments undertaken in this study.
1.2 Introducing Foamed Concrete
Foamed concrete is lightweight, free flowing material which consists
principally of a cement-based mortar or paste mixed at least 20% by volume air.
Foamed concrete is also known as aerated concrete, lightweight concrete or porous
concrete. The special characteristic of foamed concrete is it can be placed easily and
does not require compaction, vibration and leveling. It is first patented in 1923 and its
construction application as lightweight non- and semi- structural material are increasing
in the last few years.
1.3 Concept of Project
The concept of this project is to produce alternative way in replacing the
conventional way of constructing the sub base in road construction. Thus, it is proposed
to replace the conventional design which is using the bakau logs and geotextile with
anew design of using the composite model which combines the different mix of foamed
concrete.
2
The concept of sub base construction using composite material is found similar
to the floating foundation concept. The significant American architect, John Wellborn
Root, who protects against settlement and the liquefaction of soft soil due to seismic
activity, has invented the foating raft foundation or floating foundation which is a type
of land-based foundation. It was a necessary innovation in the development of tall
buildings in the wet soil of Chicago in the 19th century. (Wikipedia, 2009)
For a floating foundation, the foundation has a volume where it is filled with
soil so that it would be equal in weight to the total weight of the structure. When the
soil is so soft, where even friction piles will not support the building load, the floating
foundation will be the solution. The floating foundation will make the building like a
boat that obeys Archimedes’ principle where it is buoyed up by the weight of the earth
displaced in creating the foundation. (Wikipedia, 2009)
Thus, it is similar to the function of the composite material that is proposed to
be as the road sub base on the peat soil. The composite material is expected to take up
the load from Down Crusher Run (DCR) and vehicles without sinking into the peat soil
which can affect the road structure in future.The conventional design of sub base in the
road construction is shown as in Figure 1.1 and Figure 1.2.
3
Figure 1.1: Conventional design of sub base
Figure 1.2: Bakau arrangement prior to geotextile layering process
4
Load
DCRGeotextile
Peat Soil
Soil embankment
Bakau (refer to Figure 1.2)
Geotextile layered on the bakau that arranged on the peat soil
Bakau logs
The role of bakau logs arranged prior to geotextile layering process is to
distribute the load subjected on the peat soil. Furthermore, it functions as the separating
the layer between Down Crusher Run (DCR) and peat soil. Other than that, they keep
the DCR together and avoid the DCR from falling into the peat soil and being wasted.
While the geotextile is used to take up the load from DCR. It also becomes the
separating layer between DCR and bakau logs arranged and peat soil.
Figure 1.3: Geotextile is layered on the excavated pathway
5
Figure 1.4: Geotextile functions as the separator between aggregate and soil surface.
Thus, this conventional way is widely applied in the sub base construction on
the peat soil. Using the geotextile might cause longer construction period as it is
6
imported product, mostly from China. The availability of the material might cause the
construction process to be delayed if the material is insufficient. Besides that, the
installation of geotextile will require a number of manpower which is uncertain in
productivity especially if there is raining as the geotextile installation will be
terminated. This will extend the period of the road construction which is not good to
the project progress. Other than that, the bakau supplies might be a problem nowadays
as it is not as many as before.
Therefore, to replace the conventional method, it is proposed to use the
composite materials which are the self compacting concrete and foamed concrete as the
replacement of the geotextile and bakau logs functions. Furthermore, these two types of
concrete are widely used in the construction industries nowadays. Thus, the availability
of the concrete material is not an obstruction to the construction.
The proposed design of sub base in the road construction is shown as in Figure1.5.
7
Load
Peat Soil
Soil embankment
DCR
Composite Model
SCC
Foamed Concrete
Figure 1.5: Proposed design of sub base
Therefore, the proposed sub base made of composite model which is the SCC
and foamed concrete is able to replace the function of bakau and geotextile as shown in
Table 1.1.
Table 1.1: Conventional material functions substitution by composite material
Conventional
materials
Functions Foamed concrete
Bakau Distributing loading
Geotextile Take up load from DCR
Separating layer between
DCR and peat soil
1.4 Objectives of Project
The objectives of this project are:
a) To produce durable foamed concrete and test for its strength.
b) To examine the ability of structure to withstand dynamic load.
8
1.5 Summary
The outlines of the structure of this project are summarized as below:
Chapter 1 is the introduction to the project carried out where the aim, objectives
and purpose of the project are stated in this chapter. In addition, general information of
the project will be included for preliminary research of the project. Other than that, the
outline of the structure of the following chapters in the project report will be included
in the summary of chapter 1.
Chapter 2 is the literature review of the project. The references made are due to
the aims and objectives requirement in order to support the methodology that will be
carried out to fulfill the objectives requirement. Thus, references are regarding to
journals, books and many more which will be done due to APA (American
Psychological Association) style.
Chapter 3 is about the methodology of the project which refers to the preferred
options and approaches used to achieve the objectives.
Chapter 4 is the results, analysis and discussions of the testing method is stated
in this chapter. Data collected from the testing method will be stated systematically,
analyzed and discussed due to the project requirement.
Chapter 5 is the conclusions and recommendations of the project. This is the
synopsis of the analysis and discussions from Chapter 4 which will be related to
9
objectives of the project, whether it has satisfied the project requirements or not.
Recommendations will be stated in this chapter in order to improve the methodology
used so that better results can be achieved for future project research.
10