Upload
alex-iskandar
View
148
Download
0
Embed Size (px)
Citation preview
Changes / Variations / Deviations Lesson Learned – Minimizing
Changes Dispute Resolution Arising from
Changes
CHANGES / VARIATIONS /DEVIATIONS What’s Change :
• Base Assumptions on Scope, Specifications, Environment/Conditions, Social
Political, Rules and Regulations, Business Process etc. Existence of Instruction from Owner Cause – Effect – Entitlement - Damage
Business Process : • Change Management
Change Documentation Change Log / Register Change Notice Change Request
Governance :• Change Authority• Change Control Board
Outcome : Change Order / Purchase Order Amendment Change Cost and Schedule
Failure to adequately document the scope expectations of the parties in the contract
Owner’s actions/inactions during the work Contractor’s failure to understand local conditions Contractor’s inexperience with technology/type of work Contractor’s failure to adequately staff/departures of key personnel Owner’s or Contractor’s poor contracting strategy Unreasonable contractual allocation of risks Contractor’s poor subcontract management Financial weakness of Contractor Contractor’s poor accounting/estimating/control systems Owner/Contractor personality conflicts Contractor management personal/professional conflicts Contractor’s “lowball” bid approach – cost/schedule Labor issues Failure to understand the contract/law
Contract Change Claims Root Causesexamples:
Stage-Gate Project-Management Process in the Oil and Gas Industry – by G.W. Walkup Jr., SPE, SDG, and J.R. Ligon, SPE,
http://www.spe.org/spe-site/spe/spe/jpt/2006/12/Syn102926.pdf
AREAS OF DISCUSSIONS :• CONTRACTOR SELECTION
Bid Document Preparation Pre Qualification and Stage-1 Technical
Bid Commercial Bid
• CONTRACT AWARD, PREPARATION TO KICK OFF• PROJECT EXECUTION• CONTRACT CLOSE OUT
BID DOCUMENT PREPARATION• BEST PRACTICE:
SCOPE OF WORK AND CONTRACT T&C’s Proper Company Supplied Data ( Specifications, drawings, etc.) Concise Company requirement on HSE and Quality, facilities
performance, Established Project Management Of Change Defined responsibility and accountability among Company, EPC
Contractor, Government Authorities and other parties (i.e. LLI Vendor, etc.)
Aligned interfaces among stakeholders Established Warranty requirement No Ambiguity / Contradictive Statements in the Contract
(including Exhibits)
PRE QUALIFICATION AND STAGE-1 TECHNICAL BID :• BEST PRACTICE :
ENSURE CONCISE AND FOCUS CRITERIA Enable screening and selection of Qualified Registrants
DO NOT REVIEW AND ASSESS FROM THE SUBMITTED DOCUMENTS ONLY, PROOF THOSE INFORMATION WITH:
Scrutiny reviewing Contractor ‘s Proposal (Technical and Commercial)
(Stage-1) Interviews Bidder Key Personnel(s), (Stage-1) Site visits to Bidder Main Office and/or Fabrication
/Yard (Stage-1) Interview the Bidder (Main Contractor and/ member
of Consortium ), (Stage -1) Clarity of Scope, assurance of split Role &
Responsibility, and Interface (Main Contractor and/ member of Consortium)
PRE QUALIFICATION AND STAGE-1 TECHNICAL BID: (cont’d)
• BEST PRACTICE : ENSURE BIDDER (Main Contractor / Consortium) FULLY
UNDERSTAND THE SCOPE, REQUIREMENTS, AND LIABILITIES
Conduct Technical Bid Clarifications scrutiny, including Bidder HSE-MS and Quality Assurance/Control, Business Ethics, etc.
ENSURE BIDDER (Main Contractor / Consortium) FINANCIALLY CAPABLE TO PERFORM THE WORK CONTINUOUSLY AND ON TIMELY BASIS.
Proper Financial Due Diligence
COMMERCIAL BID:• BEST PRACTICE: EVALUATE THE SUBMITTED COMMERCIAL BID,
• Assurance of Capability to Perform the Contract ESTABLISHED WORK INSTRUCTION AND CRITERIA FOR
NEGOTIATION PROCESS, WHEN REQUIRED:• As per PTK 007, If all the Bid prices is above than EE,
then requires negotiation to all bidders started from 1st rank to the last rank. The Objectives is to have prices near to the Company EE.
• If the result is lower than Company EE, then re-assess the proposal – RED FLAG
BEST PRACTICE: Contract Effective Date:
LOI Date is the basis. Kick Off Meeting
Set-up series of meetings: HSE, project management, project control, procurement, contract, discipline engineering, quality assurance/control, construction.
Ensure all Contractor Key persons is mobilized and all changes of Key Personnel require Company approval.
BEST PRACTICE: Establishment of an agreed Project Master Schedule at the
earliest stage: Clear and “realistic” milestone targets. Constructability Review and Site Verification before AFC
Scheduled periodic-assessment of Contractor Performance Availability of Qualified HAZOP Facilitator Establish Procurement Management System at the earliest
stage: Assurance of Contractor’s personnel capability in
managing procurement Proper control and monitoring, include maintain updated
register MASTER LIST preparation at the earliest stage:
Assurance of Contractor’s personnel capability in managing logistic/formalities
Proper control and monitoring Master List and Custom Clearance process.
BEST PRACTICE: Shutdown and Tie-In Preparation:
Assurance of Contractor’s personnel capability in execution of SIMOPS (Simultaneously Operations)
Set-up detail plan, check list, joint walk through Implement Project Management of Change
Proper control and monitoring level Sufficient early discussion prior to issuance and execution Maintain updated register Settlement of claims to avoid dispute at contract close-out
Mechanical Completion, Pre-Comm. & Commissioning Assurance of Contractor’s personnel capability for Pre-Comm.,
clearing of punch-lists prior to Facilities Mechanical Acceptance & Hand-over
Sufficient Contractor’s experienced personnel to assist commissioning activities .
Set-up Company PMT and Discipline Engineers with sufficient competencies and experiences
to support lack of experiences / incompetence of Contractor’s Personnel(s
OBJECTIVES : Proper Close-out documentation to support Project
and AFE Close-out
BEST PRACTICE: “As Built” Documentation
Scheduled sufficient time for site verification (i.e. joint walk through)
Release of Leans Overall Final Documentation completion
• Make all reasonable efforts to resolve disputes by negotiation for mutual consent :
• Justifiable, Accountable, Auditable • Proper documentation
• Open and timely disclosure of relevant facts, information and documentation – without prejudice
• Outcome :• Justifiable compensable• Justifiable non compensable• Non justifiable
Litigation Non Litigation :
Negotiation Consultation Mediation Conciliation Arbitration
• Ref. : Undang-Undang No. 30, 1999: