57
Challenges of Large Diameter TBM Tunnels Sept 9 th , 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun Chek Lap Kok Link (TM - CLK) Hong Kong 17.6m

Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

  • Upload
    others

  • View
    29

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Challenges of Large Diameter TBM Tunnels

Sept 9th, 2019

Nasri Munfah, PEAECOM

Director of Tunneling and Underground Engineering

Tuen Mun –Chek Lap Kok Link (TM-CLK) Hong Kong – 17.6m

Page 2: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Challenges of Large Diameter Soft Ground TBM Tunnels

Presentation Outline Background and Historical

Perspective Challenges and Mitigation

Measures Associated with Large Diameter TBMs

Case Histories: Alaskan Way Tunnel SR-99,

Seattle, USA Eurasia Tunnel

Conclusions and Future Outlook

“Bertha” – Alaskan way Tunnel, Seattle, USA 17.5 m diameter – Second largest TBM in the world

Page 3: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Historical PerspectiveWhat was before mechanized excavation (TBM)? 19th Century and up to 1950s and 60s soft ground tunneling was done by hand

excavation, open shield, or compressed air Brunel Shield (1818) - Never open more than is needed, can be excavated

rapidly, and supported quickly Nearly all soft ground tunnels built up to the early 1970’s were mostly

constructed using the basic concepts of the Brunel tunnel shield, with compressed air; compartmentalization, face breasting with timber and lots of hand labor.

Marc Brunel 1818 Patent Application“Open… the ground in such a manner that no more earth shall be displaced than is to be filled by the shell or body of the tunnel.”

Thames River Tunnel, London, 1843

Page 4: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Historical Perspective (cont’d) Late 1950’s and 1960’s

Emergence of mechanical mining Rock Tunnel Boring Machines (TBMs) Rotating Cutter Head (The Robbins TBM)

Changes for Tunnel Shields in 1960’s Mechanical excavators start being used

replaced hand excavation and miners replaced at tunnel face

Starts in 1960’s Tunnel Face Closed to Control Water UK, Europe, Japan, Canada Earth Pressure Balance (EPB), Slurry TBM,

Hydroshield, Mixshieldetc. Trenchless Technology - Microtunneling

Pressurized Face Tunneling

EPB TBM

Slurry TBM

Page 5: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

TBMs are Getting Bigger and Bigger… Microtunneling (usually less than 3 m) Metro/subway size (6 to 7 m) Railroad single tracks (8 to 10 m) Railroad double tracks (10 to 12 m) Road tunnels 2 or 3 lanes > 12m

M-30 Madrid – 15.2 m dia. (2005)

4th Elbe River tunnel, Hamburg –14.2m dia. (1997)

Page 6: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Large Diameter TBMs (courtesy TunnelTalk)

First TBM larger than 14m Tokyo Bay Tunnel (1994)

Page 7: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Large Diameter Soft Ground TBMs

Courtesy of Herrenknecht

Page 8: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

More Challenges with Large Diameter

Courtesy of Herrenknecht

TBM Torque - EBP / Slurry

Page 9: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

And the World Largest TBM…

Tuen Mun –Chek Lap Kok Link (TM-CLK) Hong Kong – 17.6m (2015)

Page 10: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Large Diameter TBM Challenges Large Diameter Tunnel Configuration

Differential pressure within the excavation chamber Gap size Potential over-excavation TBM maneuverability and maintaining horizontal and

vertical alignments

Geological and Geotechnical Conditions and Potential Mixed Face Condition Variable ground conditions within the excavation and

around excavation Mixed face conditions (rock/soil ; clay/sand; fractured/solid

rock; intrusions; etc.)

Page 11: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Large Diameter TBM Challenges (Cont’d) Ground Water

High ground water pressure Quantity of water intake Ground water control – transient lowering water table level on

adjoining facilities Large Overcut

Accommodate thickness of shield, brushes, gap, outer gage cutters, etc…

For 15m (50ft) dia tunnel the gap can be about 38 cubic meter/meter (15 CY/ft) – 3 times bigger than a typical metro tunnel – 90 CY/shove

Need to fill the gap Potential settlement

Page 12: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Large Diameter TBM Risk Issues (Cont’d) Ground Loss

Ground and ground water control 1% of ground loss on a 15m diameter will yield 1.8 cubic

meter/meter of ground loss – over 4.5 times ground loss from a metro size TBM

Potential significant settlement Wider settlement trough Impact on existing structures and utilities

Other Potential Issues: Transition areas near surface Break-in and break-out Operation and maintenance of the TBM – “safe havens” and

maintenance in free air Potential needs for saturation diving Required cover over the TBM

Page 13: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Controlling Ground Behavior at the Source Control overcut gap

Minimize the shield gap Bentonite injection & pressurization immediately and as close to

the face as possible Pressure cells on shield perimeter Tail shield grouting

Close spacing of extensometers and piezometers to determine ground behavior at the source

Continuous monitoring Correlate the TBM performance parameters and ground

behavior – impact on facilities Construction “Monitoring Task Force” for collaboration

Collaboration among contractor, designer, owner, and stakeholders

Page 14: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Controlling Overcut Gap Control the face pressure to prevent over-excavation Monitor for evidence of larger volumes of over-excavation and

void formation: ‒ Reconcile weight and volume of excavated material with volume of

advance - Targets +2 to -4 %. This requires accurate measure of additives and more accurate belt measurements

‒ Large diameter tunnels may yield 1000 tons per shove, this may represents 100 tons over excavation (10%) and a large void

Check grouting (use secondary grouting) through the segmental lining to fill all gaps as soon as possible if needed.

Polymer additives for EPBs to control sands and significant bentonite conditioning to make sand and water form a viscous fluid could add significant bentonite solids

‒ On a 1000 tons excavated per advance: up to 2 tons of bentonite solids could added

Page 15: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Case HistoryAlaskan Way Tunnel – SR99 – Seattle, USA

Alaskan Way Tunnel - Seattle

Page 16: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

New SR 99 Corridor - Alignment

South Holgate Street to South King Street Project

Alaskan Way Tunnel Project alignment

158 buildings within influence zone Passes under historic building zone Under freight rail tunnel Passes under significant utilities

Page 17: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Cross Section

Electrical rooms

Equipment rooms

Egress corridor

Pump station

Utility corridor

Ventilation duct

Excavation diameter (TBM)

17.48 m (57’4”)

Internaldiameter

15.85 m (52’)

Segmentthickness

610 mm (24”)

Grouting thickness

200 mm (8”)

Average ring length

2 m (6’ 6”)

Number of segments

7+2+1

Tunnel length 2800 m (9300’)

Page 18: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Tunnel Profile and Geological Setting

Poor, unconsolidated soils

Till depositsCohesionless sand and gravel – regional aquiferCohesionless silt and fine sandCohesive clay and siltTill-like deposits

Page 19: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

“Big Bertha” – Hitachi Zosen EPB Diameter: Ø17.480 m (57.35

ft) Length: 110.642m (363 ft) Total weight: 6,700 t Design pressure : 7 bar (10 bar

emergency) Max Thrust: 392,000 kN Max Torque: 147,400 kNm Breakout torque: 206,360 kNm Total installed power:22,600

kW Ribbon Screw Conveyor 2 x

Ø1,500 mm Design cycle: 62 min. (32 min

exc.+ 30 min ring building)

“Big Bertha” named after Bertha Knight Landes, the first woman mayor of a major city in the US, Seattle, 1926 to 1928

Page 20: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Cutterhead Features Weight: 886 t Opening rate: 37% rotational speed: 0.8 to 1.2 rpm Max. size boulder to pass: Ø 1m Max. CHD thrust allowed: 196,000 kN 55 face double disc cutters 17”, 47 of

them to be changed at atmosphericpressure

4 copy cutters (50 mm) 10 center disc cutters 101 fixed pre-cutting bit 260 cutter bits 12 Bucket teeth (trim bits) 32 scraper bits 45 emergency bits (150 mm) 34 foam injection ports

Page 21: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Sequence of Precarious EventsDate Event

20 July 2013 TBM Launch

20 Aug 2013Breakout of labor dispute with Longshoremen’s union over muck handling at the wharf

23 Sep 2013 Drive restarts

31 Oct 2013Stoppage for machine adjustments and fitting new cutting tools

14 Nov 2013 Drive restarts

03 Dec 2013“Bertha” hit a piezometer steel casing (left in place from the investigation phase).

05 Dec 2013 TBM reaches 1,000ft (300m) milestone

06 Dec 2013High temperature readings prompt precautionary machine shutdown and 158 hours worth of hyperbaric inspections are carried out between Jan 17–28

28 Jan 2014 Drive restarts

Page 22: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Sequence of Precarious EventsDate Event

29 Jan 2014TBM advances 2ft (60cm) before same heat readings prompt shutdown. Main bearing seal damage is diagnosed, plus possible damage to main bearing itself

May 2014Excavation of 36.5m x 24.4m (120ft x 80ft) recovery shaft begins

02 Sep 2014TBM advanced 3ft (1m) to rest against the outside of the piles of the recovery shaft

18 Feb 2015 Drive restarts

02 Mar 2015TBM shut down after being driven through 57ft (9 rings) into recovery shaft

30 Mar 2015TBM lifted out of recovery shaft over a 2-day period using specialist hoisting equipment

05 Jun 2015Newly designed outer and inner seal systems installation begins; repairs include a new main bearing plus other major modifications

April 2014 - Repair• Replace broken seal• Replace main bearing• Install enhanced motoring

systems • Add steel to stiffen the TBM

Page 23: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Sequence of Precarious EventsDate Event

25 Aug–8 Sept 2015

TBM lowered in pieces back into recovery shaft

12 Nov 2015TBM testing program begins – on Nov 24 the cutterhead is tested to sustained rotation

22 Dec 2015Drive resumes, with TBM breaking out of the recovery shaft –progress of 12 rings is made

12 Jan 2016Sinkhole 4.6mx10.7m (15x35ft) 250 m3 of concrete after 100ft (30m) advance made by the TBM out of the recovery shaft

14 Jan 2016WSDOT issues a forced stop order, pending an independent safety and operational review

23 Feb 2016Drive resumes after STP’s management modifications and additional operational protocols

Total Days Lost = 817 days

Page 24: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

TBM Recovery and Repair Shaft 24.3m (80ft) diameter x 36.5 m (120ft) recovery shaft Secant piles in conjunction with the existing protection piles and

closed with jet grouting Compression ring Dewatering to reduce pressure Started shaft construction May 2014

Page 25: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

TBM RepairHeavy Lift – 2000 tons

Page 26: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Damage

Main bearing seal Damaged Pinion Damaged RollersDamaged Disk Cutters

Main bearing

Page 27: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Repair

Page 28: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

TBM Crosses the Viaduct May 11th, 2016 TBM mined the full reach of 171m (385ft) 4.5m (15ft) below the viaduct’s foundation piles Run 12 days of 2-12 hrs shifts Settlement of the viaduct was 1.5 to 3 mm

Page 29: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Instrumentation and Monitoring

Total Stationing Settlement points Inclinometers Deep Extensometers

Tiltmeters Liquid Level sensor Crack gauges Compensation Grouting

Page 30: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Surface Settlement

TILL

SILT

6th Ave.PIONEER SQUARE

BNSF TUNNEL

1st Ave.SAND

SAND

60 m10 m

SAFE

HAV

EN 3

AL

ASKA

NW

AY

VIAD

UCT

24 m17.5 m DiaCLAY

SAND

Surface Settlement Criteria

Sett

lem

ent,

mm

13 mm 25 mm

APRI

L 29

, 201

6

APRI

L 4,

201

7

Measured Surface Settlement varied from 0 mm to 2.5 mm

Ground Loss 0.5%Courtesy Prof. Edward Cording Muir Wood Lecture April 2018

Page 31: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Deep Extensometer settlement 1.5 m above TBM

TILL

SILT

6th Ave.PIONEER SQUARE

BNSF TUNNEL

1st Ave.SAND

SAND

60 m10 m

SAFE

HAV

EN 3

AL

ASKA

NW

AY

VIAD

UCT

24 m17.5 m DiaCLAY

SANDAPRI

L 29

, 201

6

APRI

L 4,

201

7

bb

EXTENSOMETER SETTLEMENT

1.5 m ABOVE TBMSett

lem

ent,

mm 0

510152025

SURFACE SETTLEMENT 0 - 2.5 mm

Courtesy Prof. Edward Cording Muir Wood Lecture April 2018

Page 32: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Why Measured Settlement Was Less than Predicted?

CHAMBER PRESSURIZED WITH CONDITIONED MUCK

BENTONITE SLURRY INJECTED THROUGH PORTS INTO 30-mm GAP

Overcut gap closure Bentonite injection &

pressurization Pressure cells on shield

perimeter Immediate and

continuous grouting Shield gap pressure:

volume injected to fill 30 mm gap + 35%

Borehole Extensometers 50 ft(16m) on center to measure settlement at the source

Piezometers in all extensometer boreholes

Construction Monitoring Task Force Courtesy Prof. Edward Cording Muir Wood Lecture April 2018

Page 33: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Construction Monitoring Task Force – Collaborative Approach

GROUT VOLUME

10 to 14 40% to 100%

to 3% to 5%

1.85478 884

Target CHD Rotation Speed (rev/min):

TBM PARAMETERS

1.0 Penetration Rate (mm/rev): 40

Mostly ESU 5

Geologic Comments:

General Comments:

TBM Parameters can only be changed after consultation with Tunnel Superintendent, General Superintendent, and Tunnel Manager according to the TWP Appendix #42, Decision Making Process, Submittal #01264-03

OTHERS

Coverage (m) 60 PIEZO PRESSURE closest to CHD:

Present Soil Unit:

(As per GBR)

NumberPS095_258_45_0

95(06 07 25845 09

Pressure Value (bar)

1.45

Slump Range: 5 7 Concentration Target:

2.85

SOIL CONDITIONING

Planned Ground Conditioning Recipe: Recipe 1 SLF (3.0%) plus Rehosoil 211 (0.5%)

FER Target: FIR Target:FER Range:12

GBR Density:Bank m3:

Target. Belt Scale Weight

(ton):Comments: Dens i ty/Slump tests to be carried out at least once per shi ft.

Except when cons is tency i s too wet that i t wi l l be once per ring

Gap Volume Target (m3): 4.14 Green Range N/A to 5.4GAP

TOP Target Gap Line Pressure (bar): 4.0 Green Range N/A to

Gap Keep Settings (bar):(based on gap sensors #6 and #3) Lower 2.80 Upper

Grout Volume Target (m3): 26 Green Range 22.1 to 31.2

5.8

MID. TOP Target Grout Line Pressure (bar): 6.1 5.8 6.6

MID. BOT. Target Grout Line Pressure (bar): 7.1 6.8 7.6

GROUT PRESSURE

TOP Target Grout Line Pressure (bar): 5.3

Green Range

5

to

BOTTOM Target Grout Line Pressure (bar): 7.5 7.2

WORKING PRESSURE

TOP Target Earth Pressure (bar):(average of sensors 11 &12)

3.2 Green Range 3 to 3.5

Keep System Settings (bar):(based on average of sensors 11 &12)

Lower 3 Upper 3.05

Target Advance Speed(mm/min): 40 Target Total CHD Force (kN): 45,000

Target CHD Torque (%): 40%

Start Station: 25838 Current Ring #: 977

Date From: 12/9/16 Time From: 5:00 AM

Date To:

Target Total Thrust Force (kN): 155,000

Daily TBM Parameter LogReport #: 135 revision #: 1

FIR Range:85%

3.0% C(%) Range

12/10/16 Time To: 4:59 AM

8.0

8.0

TBM Work Plan Daily TBM

Parameter Log‒ TBM Torque, Thrust,

Rotation, Penetration Rate, etc.

‒ Face Pressure ‒ Shield gap ‒ Pressure between

advances‒ Tail grout injection and

volume‒ Soil conditioning‒ Muck weight and

volume

Daily TBM Parameter Log

Real time machine instrumentation

Ground and structure displacements

Correlated with TBM pressures

Courtesy Prof. Edward Cording Muir Wood Lecture April 2018

Page 34: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

TBM Face and Shield Pressure

1.52.02.53.03.54.04.55.05.5

1/16

3/16

5/16

7/16

9/16

1/16

3/16

PRES

SURE

, BAR

S

Shield Pressure (Crown)Automatic bentonite injection into chamber between advances, 0.2 bars below target pressure

Lower Face Pressure

Upper Face Pressure

Courtesy Prof. Edward Cording Muir Wood Lecture April 2018

Pressure across full face of ~ 2 bars

Upper face pressure controls

Between advances: maintained at 0.2 bars below target by pumping bentonite slurry which replaces air coming out of foam so that density and pressure in lower face increase

Page 35: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Closely spaced instrumentation provides unique assessment of the tunnel performance

Ground movement & dynamic groundwater pressures to be monitored at the source

Bentonite injection through the shield: Shield pressures and volumes as indictors

Minimize ground loss Gaps filled & pressurized immediately Elastic Settlement, settlement at the

surface is minimal (0 to 2.5 mm) Deep settlement is proportional to

differential between overburden & TBM face/shield Pressure

April 4th, 2017

Lessons Learned on SR-99

Page 36: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Case HistoryIstanbul Strait Crossing

Eurasia Tunnel - Istanbul

Page 37: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Model: Build – Operate – Transfer Total Investment: ~$1.3 Billion Construction Period: 55 Months Operation Period: ~ 26 Years

Total Project Length: 14.6 km•Part-1: Europe side (5.4 km)

•Part-2: Bosphorus Crossing (5.4 km)

•Part-3: Asian side (3.8 km)

1st and 2nd bridges (total 7x2 lanes)• 180,000 (1st) and 220,000 (2nd) crossings

per day Eurasia Tunnel (2x2 lanes)

• 110,000 crossings per day (both directions)

Project Description

Page 38: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Connectivity of Istanbul Provides shortcut between Bakirkoy and Fatih regions in the

European side and Uskudar and Kadikoy regions in the Asian side Considerable relief of traffic on the Bosphorus bridges Significant time savings for travelers - Reduce travel time from 100

min to 15 min each way Significant net savings in fuel consumption, emission, air pollution Shortest distance between Ataturk and Sabiha Gokcen airports Minimal visual impact - No effect on the appearance or the

silhouette of Istanbul Respect to cultural heritage (UNESCO Surveillance) Shortest distance and significant time saving for

travelers

Page 39: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Upper Roadway

Deck (Cast in Situ)

Lower Roadway Deck

(Precast)

Upper Corbel

Lower Corbel Utility

Gallery

Precast Segment Lining(t=600mm)

12.000600 60013.200

TBM Bored Tunnel Tunnel Cross Section

13.2m (43’-4”) outer diameter and 12.0m (39’-4”) inner diameter Double Deck

Water Pressure 11.0 bar

Tunnel Alignment ±5% - Depth 106m

Seismic Design

Consideration of Mw= 7.5 on main Marmara fault

Design Life 100 years

Segment Liner

60 cm precast concrete (8+1 configuration) (C50)

Upper RoadDeck

Cast in-situ concrete (C40)

Lower Road Deck

Precast concrete(C40)

Tunnel Ventilation

Longt.Ventilation: Jet-fans and Vent Shafts at Portals20Km/hr vehiclespeed

Emergency Egress

1.12m wide Emergency Walkway / Escape Stairways at every 200m

Emergency Stops At every 600m

Page 40: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Challenges Large-diameter/double-deck tunnel configuration Complex and variable geology and hydrology Mixed face conditions High water pressure (11 bars) High seismic zone Complex Transition Structures on Both Sides

Utility Gallery

12.00013.200

Page 41: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

-106m-62m

TRAKYA Formation (Bedrock) TRAKYA Formation(Bedrock)

Soft Ground

Bedrock: Trakya formation sedimentary inter-layered sandstone, siltstone and mudstone. Highly fractured, folded, faulted, weathered, and intruded with volcanic dykes

Soft ground: is alluvial deposits consisting of coarse-grained soils (gravels and sands) to fine-grained soils (silts and clays) with beds of gravel and cobbles

Mixed Face Conditions: The tunnel passes through mixed face conditions rock to soft ground, soft ground to rock, and within the rock strata itself

Complex Geology

Page 42: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Geotechnical Investigations

Deepest point

0 m

10 m

20 m

30 m

40 m

50 m

60 m

70 m

80 m

90 m

100 m

110 m

0 m

10 m

20 m

30 m

40 m

50 m

Kum

Killi Siltli Kum

Çamurtaşı

Kumlu Kil Silt

SandSandy Clay

Clayey Silty Sand

Mud Stone

Depth: 19.00 m - 25.85 m

Depth: 26.40 m - 29.60 m

Rock Quality: RQD < 25% –very weak

Rock Mass based on Geological Strength Index (GSI): Fractured –Weak locked and extremely fractured rock mass with angular and round rock particles

GEOLOGICAL PROFILE OF BOREHOLE (BH1-2) EXPECTED HIGHEST FACE PRESSURE

Page 43: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Mixed Face Tunneling Rock/soft ground interfaces Volcanic Dyke Intrusions of diabase, andesite and dacite up

to 100m thick Highly variable rock strengths, abrasive mineralogy, and

presence of stiff blocks embedded in soft matrix Faults at various locations across the tunnel alignment Sand, Gravel, and Cobbles Soft Silts and Clays

Mixed Face

Mixed Face

(From The nearby MarmarayTunnel)

Volcanic Dyke

Sandstone

Page 44: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

In Trakya Formation, dykes (andesite and diabase) cut through the sandstone/Mudstone layers Such a geological setting creates a different rock mass medium with variable stiffness. Andesite/Diabase dykes have uniaxial compressive strengths more than 200 MPa. (30,000 psi) Cherchar Abrasive Index (CAI) is an indication of cutter disc/tools wear rate and in the case of dykes,

this index increases up to 4.5 (extremely abrasive). Pink color in geological profile corresponding to dyke zones faced during excavation.

Parameter Asia Side Trakya Formation Europe Side Trakya Formation Overall Trakya Formation

Number of Dyke Zones 6 23 29

Total Dyke Length (m) 28 397 425

Average Dyke Length (m) 5 17 15

Average Dyke Frequency (m) 113 83 90

Mixed Face Condition - Dykes

Note: Longest dyke is 120.0 m.

Page 45: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Tunnel Boring Machine (TBM)

Outer Diameter: 13.71m, Length : 120.0m, Weight : 3,300 ton, Water Pressure: 13 bar

Page 46: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Mix-Shield Slurry TBM

TBM ParametersTB

M -

GEN

ERAL

Maximum Face Pressure TBM Diameter Length of the TBM Weight of the TBM Installed Total Power Nominal Torque Thrust Force

13 bar13.7 m120.0 m~3,300 t10,330 kW23,289 kNm (17,000 K-ft)247,300 kN (55,600 K)

TBM

–SP

ECIA

L EQ

UIP

MEN

T Φ2000mm Man Lock Φ1600mm Center Lock Material Lock Shuttle (3200 x 1600 x 1600 mm)

2 units2 units3 units1 unit

CUTT

ING

TO

OLS Number of Total Disc Cutters

Diameter of Disc Cutters Atmospheric Changeable Cutting Knives Hyperbaric Changeable Cutting Knives Buckets

35 (double)19 inch4814412

ENTS

Outer Ring Diameter Inner Ring Diameter Ring Arrangement

13.2 m (43’-4”)12.0 m (39’-4”)8+1 keystone

Page 47: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

TBM Tunnel Designed to handle mixed-face conditions Operates in closed face mode to minimize

uncontrolled ground losses and to avoid potential loss of face stability

Most cutters can be replaced under atmospheric pressure

A special lock system allows access under pressurized air at over 5 bars

Launched on April 19, 2014; completed the drive on August 22nd, 2015

Average daily advancement (working days) is at 9 m (29.5 ft) – Maximum 18 m (59 ft)

Rock Disc Cutter (19 inch Monoblock) 35 pieces

Soil scrappers (192 pieces)

Jaw crusher

12 Buckets

Page 48: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Cutter Change under Atmospheric Condition

Spoke access underatmospheric conditions

Back knives cutting replacement

Tool exchange without working at tunnel face

Back loaded Disc cutter replacement

Double disk cutters (atmospherically changeable) 35qty Cutting knives (scrapers) (atmospherically changeable) 48qty Cutting knives (scrapers) (changeable under hyperbaric) 144qty Buckets (changeable under hyperbaric) 12qty

Page 49: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Saturation Diving

50

Page 50: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Saturation Diving 7 hyperbaric maintenance interventions and

repair. Some are:1. 10.8 bars (Suction grid)2. 10.3 bars (Cutter-head)3. 9.8 bars (Suction grid)4. 8.5 bars (Stone crusher)

Divers worked up to 12 days under hyperbaric conditions at a time

Up to 7 days decompression period was needed

Page 51: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

TBM is equipped with more than 300 sensors/parameters & online monitoring

Major monitored TBM excavation parameters Daily advance rates (m/day) Thrust forces (kN) Torque (kNm) Penetration (mm/rev) Revolution per minute (rpm) Face Pressure (bar) Utilization (%) Downtimes and root causes

TBM Performance

Page 52: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

0 0,2 0,4 0,6 0,8 1 1,2 1,4 1,6 1,8 2 2,2 2,4 2,6 2,8 3 3,2 3,4 3,6 3,8 4Kesici Kafanın Dönüş Sayısı (RPM)

0

4

8

12

16

20

24

28

32

36

40

Tork

(MNm

)

Prod

ucer

Lim

it =

3.2

rpm

Limit Torque

Nominal Torque

Cutterhead Torque and Speed

Cutt

erhe

ad To

rque

(MN

m)

Cutterhead Speed (revolution per minute)Source: Yapı Merkezi R&D Department, 2015©

Trakya Formation

Marine Sediments

Page 53: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

The picture can't be displayed.

Excavation Direction

3400

3300

3200

3100

3000

2900

2800

2700

2600

2500

2400

2300

2200

2100

2000

1900

1800

1700

1600

1500

1400

1300

1200

1100

1000 90

080

070

060

050

040

030

020

010

0 0

Tunnel Distance (m)

0

1

2

3

4

5

6

7

8

9

10

11

12

Pres

sure

at T

unne

l Axi

s (b

ar)

0

20000

40000

60000

80000

100000

120000

140000

160000

180000

200000

220000

240000

Tota

l Thr

ust F

orce

(kN)

PressureThrust 239000 kN

(97 % of design capacity)

10.8 bar(90 % of design capacity)

1st Hyperbaric Maintenancefor "Suction Grid Repair"

at 10.8 bar

2nd Hyperbaric Maintenancefor "Cutterhead Inspection"

at 10.3 bar

3rd Hyperbaric Maintenancefor "Suction Grid Repair"

at 9.8 bar

4th Hyperbaric Maintenancefor "Boulder Crusher Repair"

at 8.5 bar

Abov

e4.

5 ba

r, sa

tura

tion

divi

ngis

requ

ired

for

man

inte

nanc

e/re

pair

oper

atio

ns

Face Pressure and Thrust Force

Page 54: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

TBM Breakthrough August 22, 2015

Page 55: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Opening Day December 20th, 2016

Page 56: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Conclusions Tunnel construction technologies have advanced significantly

in the last 20 years -- Further advancements are anticipated Tunnels are becoming larger, longer, in more challenging

grounds and conditions Detailed risk assessment and risk management must be fully

implemented taking into consideration all potential risks Risks are best managed by design of mitigation and reduction

measures in a systematic way Aggressive, innovative thinking, and a cooperative partnering

approach among various project stakeholders are essential for a successful project

Set backs should not hinder the development or advancement of tunneling technologies or executing challenging projects

Page 57: Challenges of Large Diameter TBM Tunnels...Challenges of Large Diameter TBM Tunnels Sept 9th, 2019 Nasri Munfah, PE AECOM Director of Tunneling and Underground Engineering Tuen Mun

Thank YouQuestions?

“Open… the ground in such a manner that no more earth shall be displaced than is to be filled by the shell or the

body of the tunnel.” Marc Brunel