Ch 6 Piles-modified

Embed Size (px)

Citation preview

  • 8/12/2019 Ch 6 Piles-modified

    1/39

    Chapter 5

    Piles

    6th

    Semester

    Compiled by

    Dr. Irshad Ahmad

    Department of Civil Engineering

    N-W.F.P. University of Engineering & Technology

    Peshawar

    Peshawar, N-W.F.P., Pakistan, 2008

    Irshad 2008

  • 8/12/2019 Ch 6 Piles-modified

    2/39

    ii

    Table of Contents

    Table of Contents ................................................................................................................................... iiChapter 5 foundation settlement ............................................................................................................ 1

    5.1 Piles .............................................................................................................................................. 15.2 Uses of Piles ................................................................................................................................. 15.3 Classification of Piles .................................................................................................................. 2

    5.3.1 Classification according to the mechanism of load transfer ................................................. 25.3.2 Classification of piles according to their method of installation ........................................... 45.3.3 Classification of Piles according to Materials ....................................................................... 5

    5.4 Load Capacity of Piles ................................................................................................................. 75.5 Driven Piles .................................................................................................................................. 7

    5.5.1 Dynamic Pile Formulas ......................................................................................................... 75.5.2 PILE DRIVING EQUIPMENT ............................................................................................ 85.5.3 HAMMER SELECTION ...................................................................................................... 9

    5.6 STATIC PILE FORMULAS ..................................................................................................... 115.6.1 COHESIONLESS SOILS ................................................................................................... 12

    5.7 COHESIVE SOILS .................................................................................................................... 155.7.1 Driven Piles ......................................................................................................................... 155.7.2 Bored Piles .......................................................................................................................... 15

    5.8 FACTOR OF SAFETY .............................................................................................................. 185.9 NEGATIVE SKIN FRICTION .................................................................................................. 185.10 PILE GROUP........................................................................................................................... 19

    5.10.1 Load Distribution in Pile Group........................................................................................ 205.10.2 Efficiency of Pile Group ................................................................................................... 205.10.3 Pile Group in Cohesionless Soils ...................................................................................... 205.10.4 Pile Group in Cohesive Soils ............................................................................................ 21

    5.11 Settlement of Pile Group .......................................................................................................... 225.12 Pile Load Test .......................................................................................................................... 27

    5.12.1 Ultimate Load ................................................................................................................... 305.12.2 Disadvantages ................................................................................................................... 31

  • 8/12/2019 Ch 6 Piles-modified

    3/39

    CHAPTER 5

    FOUNDATION SETTLEMENT

    5.1 Piles

    For piles the length to width (diameter) ratio i.e. Lp/d 4 , where Lp is the pile length and d ispile diameter.

    The basic situation for a pile foundation is where soft soil exists near the ground surface whichunderlain by rock formation e.g.

    Figure 5-1 Pile foundation resting on hard stratum underlying a soft soil layer

    5.2 Uses of Piles

    Piles are commonly used for the following purposes (Figure 5-2).

    To carry superstructure loads into or through a soil stratum. Both vertical and lateral loads may beinvolved.

    To resist uplift or overturning forces such as for basement mats below the W.T. or to support thetower legs subjected to overturning from lateral loads such as wind.

    To compact loose, cohesionless deposits through a combination of pile volume displacement anddriving vibration, thus increasing their bearing capacity.

    Building

    Soft Soil

    Piles

    Firm Soil

  • 8/12/2019 Ch 6 Piles-modified

    4/39

    2

    To carry the foundation through the depth of scour to provide safety in the event the soil is erodedaway.

    To stiffen the soil beneath machine foundations to control both amplitudes of vibration and thenatural frequency of the system.

    In offshore construction to transmit the loads above the water surface through the water and intothe underlying soil. This case is one in which partially embedded piling is subjected to vertical

    (and buckling) as well as lateral loads.

    5.3 Classification of Piles

    5.3.1 Classification according to the mechanism of load transfer

    End/Point Beari ng Piles

    Figure 5-2 (a) Tension pile to resist overturning movements in tall buildings (b) Shear pile to

    resist horizontal forces or movements Friction pile (c) raking piles in harbor and river

    (a) (b) (c)tension com ression

    Wind

  • 8/12/2019 Ch 6 Piles-modified

    5/39

    3

    If a bedrock or rocklike material is present at a site within a reasonable depth, piles can be extended

    to the rock surface (figure 5-3(a)). In this case, the ultimate bearing capacity of the pile depends

    entirely of the underlying material; thus the piles are called end or point bearing piles. In most of

    these cases the necessary length of the pile can be fairly well established.

    Instead of bedrock, if a fairly compact and hard stratum of soil is encountered at a reasonable depth,

    piles can be extended a few meters into the hard stratum.

    Fri ction Piles (fi gure 5-3 b)

    When no layer of rock or rocklike material is present at a reasonable depth at a site, point/end bearing

    piles become very long and uneconomical. For this type of subsoil condition, piles are driven through

    the softer material to specified depth. These types of piles are called friction piles because the load on

    the pile is resisted mainly by skin/friction resistance along the side of the pile (pile shaft). Pure

    friction piles tend to be quite long, since the load-carrying capacity is a function of the shaft area in

    contact with the soil.

    In cohesionless soils, such as sands of medium to low density, friction piles are often used to increase

    the density and thus the shear strength.

    Fri ction cum end bearing piles

    In the majority of cases, however, the load-carrying capacity is dependent on both end-bearing and

    shaft friction (figure 5-3 c).

  • 8/12/2019 Ch 6 Piles-modified

    6/39

    4

    5.3.2 Classification of piles according to their method of installation (figure 5-4)

    Dr iven or displacement pi les

    They are usually preformed before being driven, jacked, screwed or hammered into ground. This

    category consists of driven piles of steel or precast concrete and piles formed by driving tubes or

    shells which are fitted with a driving shoe. The tubes or shells which are filled with concrete after

    driving. Also included in this category are piles formed by placing concrete as the driven piles are

    withdrawn.

    Bored or Replacement pi les

    They require a hole to be first bored into which the pile is then formed usually of reinforced concrete.

    The shaft (bore) may be cased or uncased depending upon type of soil.

    Soft

    ground

    hard

    Soft to

    firm

    Soft to

    firm

    Firm to

    hard

    Soft

    Figure 5-3(a) End bearing pile (b) Friction pile (c) friction cum end bearing pile

    (a) (b) (c)

  • 8/12/2019 Ch 6 Piles-modified

    7/39

    5

    5.3.3 Classification of Piles according to Materials

    Timber piles

    Timber piles are made of tree trunks driven with small end as a point Maximum length: 35 m; optimum length: 9 20m Max load for usual conditions: 450 kN; optimum load range = 80240 kN Disadvantages: difficult to splice, vulnerable to damage in hard driving, vulnerable to decay

    unless treated with preservatives (If timber is below permanent W.T. it will apparently lastfor ever), if subjected to alternate wetting & drying, the useful life will be short, partly

    embedded piles or piles above W.T. are susceptible to damage from wood borers and other

    insects unless treated.

    Advantages: comparatively low initial cost, permanently submerged piles are resistant todecay, easy to handle, best suited for friction piles in granular material.

    (a) (b) (c) (d) (e) (f)

    Figure 5-4 Principal types of pile: (a) precast RC pile (b) steel H pile (c) shell

    pile (d) concrete pile cast as driven tube withdrawn (e) bored pile (cast in

    situ), (f) under-reamed bored pile (cast in situ)

  • 8/12/2019 Ch 6 Piles-modified

    8/39

    6

    Steel Piles

    Max length: practically unlimited, optimum length: 1250 m load for usual conditions = maximum allowable stress x-section area, Optimum load range = 3501050 kN The members are usually rolled HP shapes/pipe piles. Wide flange beams & I beams

    proportioned to withstand the hard driving stress to which the pile may be subjected, In HP

    pile the flange thickness= web thickness, pipe piles are either welded or seamless steel pipes,

    which may be driven either open ended or closed end. Closed end piles are usually filled with

    concrete after driving. Open end piles may be filled but this is not often necessary.

    Advantages: easy to splice, high capacity, small displacement, able to penetrate through lightobstructions, best suited for end bearing on rock, reduce allowable capacity for corrosivelocations or provide corrosion protection.

    Disadvantages: Vulnerable to corrosion, HP section may be damaged/deflected by majorobstruction

    Concrete Pi les

    Concrete piles may be precast, prestressed, cast in place, or of composite construction. Precast concrete pilesmay be made using ordinary reinforcement or they may be prestressed.

    Pecast piles using ordinary reinforcement are designed to resist bending stresses duringpicking up & transport to the site & bending moments from lateral loads and to provide

    sufficient resistance to vertical loads and any tension forces developed during driving.

    Prestressed piles are formed by tensioning high strength steel prestress cables, and castingthe concrete about the cable. When the concrete hardens, the prestress cables are cut, with the

    tension force in the cables now producing compressive stress in the concrete pile. It is

    common to higher-strength concrete (35 to 55 MPa) in prestressed piles because of the large

    initial compressive stresses from prestressing. Prestressing the pile tends to counteract any

    tension stresses during either handling or driving.

    Max length: 1015 m for precast, 2030 m for prestressed Optimum length: 1012 m for precast, 1825m prestressed Loads for usual conditions 900 for precast, 8500 kN for prestressed Optimum load range: 3503500 kN Disadvantages: difficult to handle unless prestressed, high initial cost, considerable

    displacement, prestressed piles are difficult to splice.

  • 8/12/2019 Ch 6 Piles-modified

    9/39

    7

    Advantages: high load capacities, corrosion resistance can be attained, hard driving possible Remarks: cylinder piles in particular are suited for bending resistance. Cast in place concrete piles are formed by drilling a hole in the ground & filling it with

    concrete. The hole may be drilled or formed by driving a shell or casing into the ground.

    Disadvantages of Concrete piles: Concrete piles are considered permanent, however, certainsoil (usually organic) contain materials that may form acids that can damage the concrete.

    Salt water may also adversely react with the concrete unless special precautions are taken

    when the mix proportions are designed. Additionally, concrete piles used for marine

    structures may undergo abrasion from wave action and floating debris in the water. Alternate

    freezing & thawing can cause concrete damage in any exposed situation.

    Composite pil es

    In general, a composite pile is made up of two or more sections of different materials ordifferent pile types. The upper portion could be cased cast-in-place concrete combined with alower portion of timber, steel H or concrete filled steel pipe pile. These piles have limited

    application and are employed under special conditions.

    5.4 Load Capacity of Piles

    Three general methods are available to establish load capacity:

    (1) Static Analysis (2) Dynamic Analysis (3) Load Testing (4) Correlation with field tests (SPT,CPT etc)

    Dynamic formulae are used for driven piles. Static formulae are used both for bored and driven piles.

    Load testing is the most reliable method to determine the load capacity of the pile in the field. They

    should be performed on all piling projects. However, they are considerably more expensive than the

    other methods used to determine pile capacity, and economic consideration sometimes preclude their

    use on projects. Field tests like SPT, CPT are also used to correlate to load carrying capacity

    particularly for cohesionless soils.

    5.5 Driven Piles

    5.5.1 Dynamic Pile Formulas

    Piles are usually forced into the ground by a pile driver or pile hammer. In medieval times piles were

    driven by men manually swinging hammer, which consists of a weight raised by ropes or cables and

    allowed to drop freely striking the top of the pile. After the drop hammer came the single acting

    hammer, double acting hammer, differential acting hammer, diesel pile hammer, vibratory driver.

    Dynamic pile formulas are widely used to determine the static capacity of the driven pile. These

    formulas are derived starting with the relation

    Energy Input = Energy Used + Energy Lost

  • 8/12/2019 Ch 6 Piles-modified

    10/39

    8

    The Energy used equals the driving resistance (Pu) the pile movement (s).

    Energy lost is due to friction, heat, hammer rebound, vibration and elastic compression of the pile, the

    pacing assembly, and the soil.

    5.5.2 PILE DRIVING EQUIPMENT

    Piles are installed by a special pile driving device know as a pile hammer. The hammer may be

    suspended from the boom of a crawler crane, supported on a large frame called a pile driver or carried

    on a barge for construction in water. In all cases, the hammer is guided between two parallel steel

    members called leads. The leads may be adjusted at various angles for driving vertical and batter

    piles.

    Several types of hammers are in use and each of which are different sizes. The hammer types are:

    Drop hammer

    The drop hammer consists of a heavy ram in between the leads. The ram is lifted up to a certainheight and released to drop on the pile. This type is slow and therefore not in common use. It is used

    in the cases where only a small number of piles are driven.

    Single-acting hammer

    In single acting hammer a heavy ram is lifted up by steam or compressed air but dropped by its own

    weight. The energy of a single acting hammer is equal to the weight of the ram times the height of

    fall.

    Double-acting hammer

    The double-acting hammer employs steam or air for lifting the ram and for accelerating thedownward stroke. The energy of a double-acting hammer is equal to the (weight of the ram + mean

    effective pressure x the effective area of ram) x times the height of fall.

    Di esel hammer

    The diesel hammer is a small, light weight and highly mobile. They use gasoline for fuel. To start the

    operation, the ram is raised, and the fuel is injected. As the ram is released, the ram falls and

    compresses air and fuel. The air and fuel becomes hot because of the compression and the air-fuel

    mixture is ignited. The resulting explosion (1) advances the pile and (2) lifts the ram. If the pile

    advance is very great as in soft soils, the ram is not lifted by the explosion sufficiently to ignite the

    air-fuel mixture on the next cycle, requiring that the ram be again manually lifted.

    Vibratory hammer

    The principle of the vibratory driver is two counter-rotating eccentric weights. The driving unit

    vibrates at high frequency and provides two vertical impulses-one up and one down. The downward

    pulse acts with the pile weight to increase the apparent gravity force. These hammers have reduced

    driving vibrations, reduced noise, and great speed of penetration.

  • 8/12/2019 Ch 6 Piles-modified

    11/39

    9

    5.5.3 HAMMER SELECTION

    Generally the size of hammer is more important factor than type of hammer.

    A heavy pile should be driven by a heavy hammer delivering large energy. Preferably the weight of

    the hammer should be at least on-half the total weight of the pile, and the deriving energy should be atleast one foot-pound for each pound of pile weight.

    Each type of hammer has its use under suitable conditions. The advantages and disadvantages of each

    type are summarized below:

    Single-acting hammer

    They are advantageous when driving heavy piles in compact or hard soils; the heavy ram striking at

    low velocity produces least damage due to impact. The disadvantages are low driving speed and

    large headroom requirement.

    Double-acting hammer

    They are generally used to drive piles of light or moderate weight in soils of average resistance

    against driving. This type of hammer can drive piles at fast speed, requires less headroom and can be

    used to extract piles by turning them [i.e. the double-acting hammer] upside down.

    Diesel hammer

    They are similar in application as double-acting hammers, but driving may become difficult in

    extremely soft ground.

    Vibratory hammer

    They have fairly good results in silty and clayey deposits. They are used in heavy clays or soils with

    appreciable numbers of boulders. These hammers have reduced driving vibrations, reduced noise, and

    great speed of penetration.

  • 8/12/2019 Ch 6 Piles-modified

    12/39

    10

  • 8/12/2019 Ch 6 Piles-modified

    13/39

    11

    5.6 STATIC PILE FORMULAS

    The ultimate load which can be carried by a pile is equal to the sum of the base resistance and theshaft resistance (figure 5-5).

    Pu+ Wp= Abqb(gross)+ Asqs

    Pu is the ultimate load that can be carried at top of pile, qbultimate (gross) bearing capacity at base

    level, Ab= base area of pile, qs=ultimate shearing/skin resistance per unit area, As= perimeter area of

    pile, and Wp = weight of the pile.

    Subtracting Ws from both sides of the equation. Where Ws is effective soil weight replaced/displaced

    due to pile volume. Ws = LAb where is the effective weight of soil, and L is pile length.

    Pu+ (WpWs)= Abqb(gross)+ Asqs-Ws

    Pu+ (WpWs) = Abqb(gross)+ Asqs - LAb

    Pu+ (WpWs) = (qb(gross)- L)Ab+ Asqs

    Pu+ (WpWs) = (qb(gross)- o)Ab+ Asqs

    Where o=L is effective vertical stress at pile base

    Pu+(WpWs) = Abqb+ Asqs

    Pu= Abqb+ Asqs(WpWs)

    Pu= Abqb+ AsqsW

    Pu is the ultimate load that can be carried at top of pile, qb ultimate (net) bearing capacity at base

    level, Ab= base area of pile, qs=ultimate shearing/skin resistance per unit area, As= perimeter area of

    pile, W= WpWs = weight of the pile effective weight of soil replaced. In most cases WpWsand hence W0.

    Pu= Abqb+ Asqs

    However in the case of under-reamed piles (figure 5-4 f) the reduction in pressure on the soil at base

    level due to the removal of soil is greater than the subsequent increase in pressure due to the weight of

    the pile and hence use equation-1 (i.e. do not assume that WpWs)

  • 8/12/2019 Ch 6 Piles-modified

    14/39

    12

    5.6.1 COHESIONLESS SOILS

    End beari ng Resistance (qb)

    The ultimate B.C. and settlement of a pile depends mainly on the relative density of sand. However, ifa pile is driven into sand the relative density adjoining the pile is increased by compaction due to soil

    displacement (except in dense sands, which may be loosened). The soil characteristics governing

    ultimate bearing capacity and settlement, therefore, are different from the original characteristics prior

    to driving. This fact, in addition to the heterogeneous nature of sand deposits, makes the prediction of

    pile behavior by analytical methods extremely difficult.

    The ultimate (net) B.C. at base level can be expressed as

    qb= cNc+ oNq+ B N-o[ois subtracted to get net value of qb]

    Where ois the effective overburden pressure at base level of pile.

    qb= cN

    c+

    o(N

    q-1) + B N

    c=0 for sand and 1/2BN term can be neglected because the B (width/diameter of pile) is smallcompared to the length of pile. so

    qb= o(Nq-1) oNq (Nq-1) Nq [because reduction of Nq by 1 is a substantialrefinement not justified by estimated soil parameters]. Nqis a B.C. factor (figure 5-6)

    qs

    qb

    WP

    Figure 5-5 Free body diagram of a pile

    Pu

  • 8/12/2019 Ch 6 Piles-modified

    15/39

    13

    Figure 5-6: Values of Nq for pile formulae (Meyerhof, 1976)

    Fri ction/Shaft Resistance (qs):

    The average value of skin resistance (qs) over the length of pile embedded in sand can be expressed as

    tan''cqs

    Where'' osK and c=0

    tan'oss Kq

    Ksa coefficient of earth pressure dependent largely on the relative density of the soil, ' = averageeffective pressure in the layer perpendicular to qs (i.e. horizontal).

    '

    o = average effective vertical

    overburden pressure in the layer, and =angle of friction between the pile and the soil.

    Table 5-1 Ksand values

    Pile TypeKs

    Loose Sand Dense Sand

    Concrete 3/4 1.0 2.0

    Steel 20 0.5 1.0

    Wood 2/3 1.5 4.0

    Bored or Jetted

    pile0.5

  • 8/12/2019 Ch 6 Piles-modified

    16/39

    14

    Variation of qband qswith depth

    The above equations for qband qsindicate a linear increase with depth of qband qs. However, tests on

    full scale and model piles have shown that these equations are valid up to certain depth called critical

    depth (zc). Below this depth zc(=15d to 20d, conservatively take zc= 15 d), base (qb) and shaft/skin(qs) resistances do not develop linearly [i.e. become constant]. This is because the vertical effective

    stress adjacent to the pile is not necessarily equal to the effective overburden pressure (away from the

    effect of pile) but reaches a limiting value at critical depth zc(figure 5-7).

    qband qsfr om SPT Test

    Ultimate base resistance qb

    Due to the critical depth limitation and to the difficulty of obtaining values of the required parameters,

    the above equations are difficult to apply in practice. It is preferable to use empirical correlations

    The following empirical correlations have been proposed by Meyerhof for driven piles in sand.

    qb= (40N55)Lb/B 400N55 (kN/m2)

    N= is the value of standard penetration resistance in the vicinity of the pile base. Use any applicable

    SPT N corrections discussed in earlier chapter-3.

    B = width or diameter of pile point

    Lb= the length of pile embedded in sand

    W.T.

    d

    oc

    d

    oc

    zc=15 dzc=15d

    Figure 5-7 Effective vertical stress distribution diagram adjacent to pile

  • 8/12/2019 Ch 6 Piles-modified

    17/39

    15

    Skin f ri ction resistance

    Skin friction resistance is Nqs 2 [kN/m2]

    WhereN

    is the average value of standard penetration resistance over the embedded length of the pilewithin the sand stratum.

    The values of qsshould be halved in the case of small displacement piles such as steel H piles. For

    bored piles the values of qband qsare approximately 1/3 and 1/2, respectively, of the corresponding

    values for driven piles.

    5.7 COHESIVE SOILS

    5.7.1 Driven Piles

    In the case of driven piles, the clay adjacent to the pile is displaced both laterally and vertically.

    Upward displacement of the clay results in heaving of the ground surface around the pile and cancause a reduction in the bearing capacity of adjacent piles already installed. The clay in the disturbed

    zone around the pile is completely remoulded during driving. The excess porewater pressure set up by

    the driving stresses dissipates within a few months as the disturbed zone is relatively narrow (of the

    order B): in general, dissipation is virtually complete before significant structural load is applied to

    the pile. Dissipation is accompanied by an increase in skin friction. Thus the skin friction at the end of

    dissipation is normally appropriate in design.

    5.7.2 Bored Piles

    In the case of bored piles, a thin layer of clay (of the order of 25 mm) immediately adjoining the

    shaft will be remoulded during boring. In addition, a gradual softening of the clay will take place

    adjacent to the shaft due to stress release, pore water seeping from the surrounding clay towards the

    shaft. Water can also be absorbed from wet concrete when it comes in contact with the clay.

    Softening is accompanied by a reduction in shear strength and a reduction in skin friction.

    Construction of a bored pile, therefore, should be completed as quickly as possible. Limited

    reconsolidation of the remoulded and softened clay takes place after installation of the pile.

    Base Resistance

    The relavent shear strength for the determination of the base resistance of a pile in clay is the

    undrained strength at base level. The ultimate bearing capacity is expressed as

    qb= cuNc+ oNq+ B N-o [ois subtracted to get net value of qb]

    1/2BNterm can be neglected because the B (width/diameter of pile) is small compared to the lengthof pile and for u=0, Nq=1, we get

    qb= cuNc where Nc= 9, and cu is undrained shear strength at pile base

    Skin Resistance

  • 8/12/2019 Ch 6 Piles-modified

    18/39

    16

    Total Stress (Undrained Conditions u=0)

    Total stress analyses are relevant, for example, for a short-term loading conditions such as from wind

    or earthquake loads. These loads are so rapidly applied that excess pore water pressure is developed

    in the clay- the clay is under undrained condition. In such cases-total stress parameters are used.

    )tan( uas cq [where cais average adhesion]

    0)tan( u as u=0

    Hence uas ccq is a coefficient depending on type of clay, the method of installation, and the

    pile material. The appropriate value of is obtained from load tests. Values of range from 0.3 to 1.

    uc is the average undrained shear strength. One difficulty with this approach is that there is usually a

    considerable scatter in the plot of undrained shear strength against depth and it may be difficult to

    define the value ofu

    c . See figure 5-8 for different values of .

    Effective Stress (drained conditions)

    An alternative approach is to express skin friction in terms of effective stress. The zone of soil

    disturbance around the pile is relatively thin, therefore dissipation of the positive or negative excess

    pore water pressure set up during installation should virtually be complete by the time the structural

    load is applied. In principle, therefore, an effective stress approach has more justification than one

    based on total stress. In terms of effective stress the skin friction can be expressed as

    )'tan(' ' oss Kcq

    )'tan(' oss Kq [c=0 for saturated clay under drained conditions]

    Where Ks is the average coefficient of earth pressure and 'o is the average effective overburden

    pressure adjacent to the pile shaft. Failure is assumed to take place in the remoulded soil close to the

    pile shaft, therefore the angle of friction between the pile and the soil is represented by the angle of

    shearing resistance in terms of effective stress () for the remoulded clay: the cohesion intercept forremoulded clay will be zero. The above equation can also be written as

    '

    osq [where )'tan( sK ]

    Approximate value of can be deduced by making assumptions regarding the value of Ks, especiallyin the case of normally consolidated clays. However, the coefficient is generally obtained empirically

    from the results of load test carried out a few months after installation. Correlations with loading tests

    have shown that for soft clays falls within a narrow range of values (0.25 to 0.4), irrespective of theclay type.

  • 8/12/2019 Ch 6 Piles-modified

    19/39

    17

    Figure 5-8 Relationship between the adhesion factor and undrained shear strength su

  • 8/12/2019 Ch 6 Piles-modified

    20/39

    18

    5.8 FACTOR OF SAFETY

    The base resistance requires a larger deformation for full mobilization than the shaft resistance,

    therefore different values of load factor may be appropriate for the two components, the higher factor

    being applied to the base resistance.

    In the case of large-diameter bored piles, including underreamed piles, the shaft resistance may be

    fully mobilized at working load and it is advisable to ensure a load factor of 3 for base resistance,

    with a factor of 1 for shaft resistance, in addition to the specified over all load factor (generally 2) for

    the pile.

    5.9 NEGATIVE SKIN FRICTION

    When piles are driven through a layer of fill material which slowly compacts or consolidates due to

    its own weight, or if the layers underlying the fill consolidate under the weight of the fill, a downward

    drag is imposed in the pile shaft (figure 5-9).

    The skin friction between the pile and soil therefore acts in a downward direction. The force due to

    this downward or negative skin friction is thus carried by the pile instead of helping to support the

    external load on the pile.

    Negative skin friction increases gradually as consolidation of the clay layer proceeds, the effective

    overburden pressure gradually increasing as the excess pore water pressure dissipates.

    qsN

    qb

    qsN

    qs

    Fill: consolidating

    under own weight

    Soft clay: consolidating

    under weight of fill

    Firm or Hard bearing

    layer

    Figure 5-9 Negative skin friction

    Pu

  • 8/12/2019 Ch 6 Piles-modified

    21/39

    19

    Pu+ qsNAs = qbAb+ qsAs where qsN is negative skin friction (downward), AsN is thecorresponding surface area of pile, qsis the skin friction (upward) and Asis the corresponding surface

    areas of pile, Abis the end bearing area of pile.

    To calculate negative skin friction equation

    '

    oNsq can be used. In normally consolidated clays,a value of =0.25 represents a reasonable upper limit to negative skin friction for preliminary design

    purposes.

    It should be noted that there will be a reduction in effective overburden pressure adjacent to the pile

    in the bearing stratum due to the transfer of part of the overlying soil weight to the pile: if the bearing

    stratum is sand, this will result in a reduction in bearing capacity above the critical depth.

    5.10 PILE GROUP

    Rarely is the foundation likely to consist of a single pile. Generally, there will be a minimum of two

    of three piles under a foundation element or footing to allow for misalignments and other inadvertent

    eccentricities.

    The group of piles is installed fairly close together (typically 2B-4B where B is the width or diameter

    of a single pile) and joined by a slab, known as the Pile Cap, cast on top of the piles.

    The cap is usually in contact with the soil in which case part of the structural load is carried directly

    on the soil immediately below the surface. The group of piles in this case is called piled foundation. If

    the cap is clear of the ground surface, the piles in the group are referred to as free-standing (figure 5-

    10).

    Pile CapPile Cap

    (a) (b)

    Figure 5-10 (a) A group of free-standing piles (b) A group of piled foundation

  • 8/12/2019 Ch 6 Piles-modified

    22/39

    20

    5.10.1 Load Distribution in Pile Group

    It is generally assumed that the load distribution between the piles in an axially loaded group is

    uniform.

    However experimental evidence indicates that for a group in sand the piles at the center of the groupcarry greater loads than those on the perimeter.

    In clay, on the other hand, the piles on the perimeter of the group carry greater loads than on those at

    the center.

    5.10.2 Efficiency of Pile Group

    In general the ultimate load which can be supported by a group of N piles is not equal to N times the

    ultimate load of a single isolated pile of the same dimensions in the same soil. Where N is the number

    of piles in a group. So

    [in general] Ultimate load of Pile Group N Ultimate load of a single pile

    The ratio of the average load per pile in a group at failure to the ultimate load for a single pile is

    defined as the efficiency of the group ().

    Average load per pile in a group at failure = Ultimate group load / N

    = ( Ultimate group load ] / ( N Ultimate Individual load )

    5.10.3 Pile Group in Cohesionless Soils

    Dr iven Piles

    The driving of a group of piles into loose sand or medium-dense sand causes compaction of the sand

    between the piles, provided that the spacing is less than about 8B: consequently the efficiency of thegroup is greater than unity. The maximum efficiency is reached at a spacing of 2 to 3 diameters and

    generally ranges between 1.3 to 2. It is recommended that in this case the design value of =1 betaken.

    In the case of piles driven into dense sand, the group efficiency is less than unity due to loosening of

    the sand and the overlapping of zones of shear (figure 5-11).

    Bored Pil es

    However, for a group of bored piles the efficiency may be as low as 2/3 because the sand between the

    piles is not compacted during installation but the zones of shear of adjacent piles will overlap.

  • 8/12/2019 Ch 6 Piles-modified

    23/39

    21

    Figure 5-11 Stress surrounding a friction pile and the summing effects of a pile group

    5.10.4 Pile Group in Cohesive Soils

    A closely spaced group of piles (spacing = 2B to 3B) in clay may fail as a unit, with shear failure

    taking place around the perimeter of the group and below the area covered by the piles and theenclosed soil. This is referred to as Block Failure. (figure 5-12)

    The ultimate load in the case of a pile group which fails as a block is given by

    usgbbgug cAqAP

    Four piles contributing

    to this stress zone

    Three piles contributing to

    this stress zone

    Two piles contributing to

    this stress zone

  • 8/12/2019 Ch 6 Piles-modified

    24/39

    22

    Abg = base are of the group = Bg Lg; Asg= perimeter area of the group = 2D(Bg + Lg); cu =undrained shear strength at depth D

    uc = average undrained shear strength between 0 and D below the ground.

    qb=cuNc where Nc=5.14(1+0.2Bg/Lg)[1 + (0.053D/Bg)]9

    )(2 gguggucug LBDcLBcNP

    Design Ul timate Load

    Piled Foundation

    The ultimate load should be taken as the lesser of the

    Block Failure value (2) The sum of the individual pile values

    Free Standing Group of Piles

    The ultimate load should be taken as the lesser of the

    (1) Block Failure value (2) 2/3 of the sum of the individual pile values

    5.11 Settlement of Pile Group

    The settlement of pile group is always greater than the settlement of a corresponding single pile, as a

    result of the overlapping of the individual zones of influence of the piles in the group. The bulbs of

    pressure of a single pile and a pile group (with piles of the same length as the single pile) are of the

    form illustrated in figure 5-13. The settlement ratio of a group is defined as the ratio of the settlement

    of the group to the settlement of a single pile when both are carrying the same proportion of theirultimate load.

    5.11.1 Settlement of pile group in clay

    In order to estimate settlement for a pile group, it is assumed that the total load is carried by an

    Equivalent raft located at a depth of 2L/3 where L is the length of piles (figure 5-14). It may be

    assumed as shown in figure 5-14 that the load is spread from the perimeter of the pile group at a slope

    of 1 horizontal to 4 vertical to allow for that part of the load transferred to the soil by skin friction.

    The vertical stress increment at any depth below the equivalent raft may be estimated by assuming in

    turn that the total load is spread to the underlying soil at a slope of 1 horizontal to 2 vertical.

    It should be appreciated that settlement is normally the limiting design criterion for pile groups inboth sands and clays.

  • 8/12/2019 Ch 6 Piles-modified

    25/39

    23

    Pile CapPile Cap

    (a) A group of free-standing piles (b) A group of piled foundation

    Lg

    Bg

    DD

    Lg

    Bg

    D

    Figure 5-12Block failure of pile group in clay

    (c ) Dimensions of Failure block

  • 8/12/2019 Ch 6 Piles-modified

    26/39

    24

    Figure 5-13 Bulbs of pressure for a single and a pile group

    Figure 5-14 Equivalent raft concept

    5.11.2 Settlement of pile group in sand

  • 8/12/2019 Ch 6 Piles-modified

    27/39

    25

  • 8/12/2019 Ch 6 Piles-modified

    28/39

    26

    Solution

  • 8/12/2019 Ch 6 Piles-modified

    29/39

    27

    5.12 Pile Load Test

    The loading of a test pile enables the ultimate load to be determined directly and provides a means of

    assessing the accuracy of predicted values.

    Tests may also be carried out in which loading is stopped when the proposed working load has been

    exceeded by a specified percentage.

  • 8/12/2019 Ch 6 Piles-modified

    30/39

    28

    Figure 5-15 shows a schematic diagram of the pile load test arrangement for testing in axial

    compression in the field. The load is applied to the pile by a hydraulic jack. The load is applied in

    suitable increments, allowing sufficient time between increments for settlement to be substantially

    complete. According to ASTM D1143, the test pile is loaded in eight equal increments up to a

    maximum load, usually twice the predetermined working (allowable) load. Unloading stages arenormally included in the test program. This testing procedure is Maintained load test (or Controlled

    load test).

    In constant rate of penetration (CRP) test the pile is jacked into the soil at a constant speed, the

    load applied in order to maintain the penetration being continuously measured. Suitable rates of

    penetration for tests in sands and clays are 1.5 mm/min and 0.75 mm/min respectively.

    Another type of pile load test is cyclic loading, in which an increment load is repeatedly applied and

    removed.

    Driven piles in clays should not be tested for at least a month after installation to allow most of the

    increase in skin friction (a result of dissipation of the excess pore water pressure due to the driving

    stresses) to take place. Load tests on piles in sand can be carried out immediately after the piles aredriven.

  • 8/12/2019 Ch 6 Piles-modified

    31/39

    29

  • 8/12/2019 Ch 6 Piles-modified

    32/39

    30

    5.12.1 Ultimate Load

    Figure 5-15 shows load settlement diagram obtained from fried loading and unloading. For any load

    Q, the pile settlement can be calculated as follows. When Q=Q1,

    net settlement, snet(1)= st(1)se(1)

    When Q=Q2

    net settlement, snet(2)= st(2)se(2)

    and so on.

    Where snet= net settlement

    se= elastic settlement of the pile itself

  • 8/12/2019 Ch 6 Piles-modified

    33/39

    31

    st= total settlement

    These values of Q can be plotted in a graph against the corresponding net settlement, s netas shown in

    figure 5-15 (c). The ultimate load of the pile can be determined from this graph. Pile settlement may

    increase with load to a certain point, beyond which the load settlement curve becomes vertical. The

    load corresponding to the point where Q-snet becomes vertical is the ultimate load, Qu, for the pile. It

    is shown by curve 1 of the figure 5-15 (c ).

    In many cases, the latter stage of the load-settlement curve is almost linear, showing large degree of

    settlement for a small increment of load; it is shown by curve 2 in figure 5-15 ( c). The ultimate load

    for such cases is determined from the point of the curve where this steep linear portion starts.

    5.12.2 Disadvantages

    The performance of single pile does not correspond to actual conditions of performance underneath

    the structure within the entire group of piles. (2) The loading test must be performed at the actual

    construction site and under real conditions of the blueprint conditions which are often difficult to

    fulfill and to execute. (3) This method of test requires specially heavy, sturdy equipment and

    platforms, precise settlement measuring devices, large quantities of dead load, or powerful hydraulic

    jacks. (4) The aforementioned conditions and factors make this kind of pile bearing capacity test very

    expensive.

  • 8/12/2019 Ch 6 Piles-modified

    34/39

    32

    Figure 5-15 (a) Schematic diagram of pile load test arrangement; (b) plot of load against total

    settlement (c) plot of load against net settlement

  • 8/12/2019 Ch 6 Piles-modified

    35/39

    33

    Figure 5-16 Schematic setup for applying vertical load to the test pile using a hydraulic jack

    acting against an anchored reaction frame

  • 8/12/2019 Ch 6 Piles-modified

    36/39

    34

    Problem 5-1Single Pile in Sand

    A 12m long, 305mm square section pile is to be embedded in sand. Water table is encountered at 2m

    depth below the ground surface. Sand has the following properties: =16.8 kN/m3above WT, sat=18kN/m3, =35. Angle of friction between soil and pile is taken to be =0.6, lateral earth pressure

    coefficient Ks=1.4. Calculate the ultimate compressive load.

    Solution:

    End-bearing resistance:

    qb= oNq (Nq=42 given)

    qb= 54.742=2297.4 kPa

    Friction resistance:

    tan'oss Kq

    First find average vertical effective stress along the pile length, it is equal to the area

    under vertical effective stress distribution diagram divided by the length of pile.

    2' kN/m46=4.575)-(1254.7+2)-(4.57554.7)/2+(33.6+2)/2(33.612/1 o

    kPakKq oss 7.24)356.0tan(464.1tan'

    Ultimate compressive load (Pu)

    Pu = Abqb+ Asqs

    Ab=0.3052= 0.093 m2, As= 40.30512= 14.64 m

    2

    Pu= 0.0932297.4 + 14.6424.7 = 213.6 + 361.6 = 575.2 kN

    L=12m

    zc=150.305=4.575 m

    16.82=33.6 kPa

    (18-9.81)(4.575-2)+33.6

    =54.7 kPa

    o=54.7 kPa

    2m

  • 8/12/2019 Ch 6 Piles-modified

    37/39

    35

    Example 5-2 Single Pil e Capacity in Sand using SPT

    A precast concrete pile 450 mm square in section and 9 m long is to be driven into a river bed which

    consists of a depth of sand. The standard penetration resistance (N) at the pile base is 24, and the

    average value of N along the pile length is 13. Calculate the ultimate compressive and tensile loadcarrying capacity of the pile.

    Solution

    N = 24

    13N

    Lb= 9.0 m

    Ultimate compressive load capacity = Abqb+ Asqs

    Ultimate tensile load capacity = Asqs +Wp (weight of pile)

    qb= (40N)Lb/B 400N (kN/m2)

    qb = 40 24 9/ 0.45 =

    Nqs 2 [kN/m2]

    =2 13 = 26 kN/m2

    Solve yourself

    Problem 5-3, Single Pile in Clay

    A 400mm, square section concrete pile is driven to an embedded depth of 12m in a cohesive soil,

    which has the following properties, u=0, =20 kN/m3both above & below W.T., cu at 12m depth is85.4 kPa. The water table is at a depth of 3m. Assume =0.4. Calculate safe load capacity for the pileadopting a FOS of 3 for the base shear and factor of safety of 2.5 for skin resistance.

    L=12m

    203=60 kPa

    (20-9.81)(12-3)+60=151.7 kPa

    3m

  • 8/12/2019 Ch 6 Piles-modified

    38/39

    36

    Solution

    End bearing resistance

    kPacNq cb 6.7684.8599c

    Skin/friction resistance:

    osq

    Let us find average effective overburden pressure

    kPao 9.86)]312(2/)607.151(2/)603[(12/1

    kPaq os 7.349.864.0

    Ultimate & Allowable Compressive loads:

    ssbbu qAqAP

    kNPu 7922.6668.1257.3412)4.04(6.786)4.04.0(

    kNPa 3085.2

    2.666

    3

    8.125

    Problem 5-4Pil e Group in Clay

    Determine the safe load capacity for a square group of 9 piles in cohesive soil. Safety factor 2.5

    against block failure. =20 kN/m3, cu at the base 85.4 kPa, average undrained shear strength =60.2kPa, u=0. Pu for single pile is equal to 819 kN.

    Given Data

    No of piles = n = 9, =20 kN/m3, cu (base) = 85.4 kN/m2, cu (avg.) = 60.2 kPa

    Pu(single pile) = 819 kN

    Required

    Safe Load Capacity of pile group = Pug

    Solution

    ssbbgpu qAqAP )(

  • 8/12/2019 Ch 6 Piles-modified

    39/39

    2/2.60 mkNcq us

    cub Ncq

    Find Ncby using the relation:-

    9053.012.0114.5

    gg

    g

    cB

    D

    L

    BN

    925.2

    12053.01

    25.2

    25.22.0114.5

    cN

    945.9 cN

    So take 9cN

    kPaNcq cub 6.76894.85

    20625.525.225.2 mAb

    depthParameterAs

    210812)25.225.2(2 mAs

    kNP gpu 103922.601086.7680625.5)(

    Ultimate load for piled foundation (Pile cap resting over group).(a) Base Failure Value=10392 kN(b) Such as of induced pile cap=8199=7371 kN

    Minimum of (a) & (b) is selected for Pu(group)= 7371 kN

    kNFOS

    PP uallowable 4.2948

    5.2

    7371

    12 m

    2.25 m

    2.25 m