Cep-construction and Design of Multistorey Building by Abhimanyu Parida

Embed Size (px)

Citation preview

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    1/39

    Thanks For Choosing

    www.engineeringcivil.com

    We hope that this presentation is useful to you. If you

    also have any presentation which can be useful toother civil engineers then please contact us via our

    website.

    Thanks

    KJS

    http://www.engineeringcivil.com/http://www.engineeringcivil.com/
  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    2/39

    CONSTRUCTION AND DESIGN OF

    MULTISTOREY BUILDING

    AT

    UNITECH LTD

    SUBMITTED BY: UNDER THE GUINDANCE OF

    ABHIMANYU PARIDA RAJIV GUPTA

    1040241 FACULTY COORDINATOR

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    3/39

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    4/39

    Projects Undertaken

    1. Construction of residential building (escape)1.1 Excavation, Layout and Foundation

    1.2 Column layout, shuttering and casting

    1.3 Slab, Beam shuttering and casting

    1.4 Important Components

    2. Introduction to bonded slab post tensioning2.1 Post tensioning

    2.2 benefits

    2.3 Tendons and stressing

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    5/39

    Projects Undertaken

    3. Design of building component

    3.1 Formwork design

    3.2 Staircase design3.3 Deep Beams

    3.4 Slabs

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    6/39

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    7/39

    Excavation, Layout and Foundation

    Excavation is a process of making trenches by digging up

    of earth for the construction of foundations and

    basements.

    Excavation level at escape site is 219.825 mm

    Excavation is done by the JCB on the hourly basis

    After the excavation the surface is leveled called surface

    dressing

    Layout is done on the PCC poured over leveled surface.

    Column and foundation (raft ) steel is then laid as perdrawings.

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    8/39

    Points to take care:-

    layout should be checked properly.

    Check any difference between architectural and structural

    drawings regarding location of column.

    After excavation check the stability of temporary structures built

    near the excavated ground. Before laying raft reinforcement, shuttering wall which is mainly

    brick wall should be built and should be filled with soil on other

    side.

    Check the direction of chair bars in the raft

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    9/39

    EXCAVATION

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    10/39

    LAYOUT

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    11/39

    RAFT FOUNDATION

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    12/39

    COULMN CASTING

    On the raft the column layout is done.

    Layout for starter.

    The column ties and link bars are provided as per column

    reinforcement drawings and general specifications.

    Displacement of main bars should be provided with L bar The plumb of formwork should be checked.

    Height of cast should be calculated accurately.

    Avoid caps as far as possible.

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    13/39

    LAYOUT , PEDESTAL & STARTER

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    14/39

    LINKS & TIES

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    15/39

    PLUMB & FORMWORK, CASTING,CURING

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    16/39

    SLAB, BEAM SHUTTERING & CASTING

    beam bottom is first laid on the column and then slab formwork

    is laid

    After the reinforcement, the slab is checked for steel as per

    drawings and level required.

    A camber of 5 mm in provided in the center of slab.

    Casting of slab should be discontinue at l/3 from the support.

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    17/39

    SLAB STAGES

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    18/39

    IMPORTANT COMPONENTS

    Key in column

    Water bar

    Binding materials

    Expansion joint

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    19/39

    KEY IN COLUMN

    since the height of column is very large,

    hence it is not possible to cast the column at

    one time, to cast the column later the key is

    made at the junction so that the proper bondbetween the old concrete and new concrete

    is formed.

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    20/39

    KEY IN COLUMN

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    21/39

    EXPANSION JOINT

    Since concrete is subjected to volume change. Provision must

    be made to cater for the volume change by way of joint to

    relieve the stresses produced.

    Expansion joint is function of length

    Buildings longer than 45 m are generally provided with one ormore expansion joints.

    Material used as expansion joint material is armour board

    whose thickness is 25 mm.

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    22/39

    EXPANSION JOINT

    Expansion joint

    material, size is 25 mm

    Expansion joint inbuilding

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    23/39

    WATER BAR

    Water bar is provided in the retaining wall o

    that the moisture cant move from the soil to

    the joint. Water bar is basically provided at

    the constructions joints of retaining wall of twodifferent towers

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    24/39

    WATER BAR

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    25/39

    BINDING MATERIALS

    Since the thermal expansion of concrete is different from that ofmasonry. The interface between the concrete and the masonry isliable to crack. To avoid this crack the chicken wire mesh is used toavoid the crack and also provides the better grip for Masonry withconcrete.

    Similarly when the drainage pipes are laid along with the outer wallthen again the connection between the pipe and the wall hasdifferent coefficient of temperature change hence they are joint tothe concrete by lead keys.

    In the toilets and kitchen sunken portion the joints in any case are

    packed by water proof and non shrinkable material.

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    26/39

    BINDING MATERIALS

    Chicken wire mesh between

    brick masonry and concrete

    Connection of pipes withconcrete

    Chicken wire mesh in

    conduits through concrete

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    27/39

    WATER PROOFING

    Water proofing has remained as an unsolved complex problem

    Use of plasticizers, super plasticizers, air-entraining agents

    helps in reducing the permeability of concrete by reducing the

    requirement of mixing water, hence can be also be regarded aswaterproof material.

    Some of approved water-proofing compound by the company

    are:- pidilite, cico, fosroe, baushimine, unitile.

    Water-proofing cement paint:- super snoweem

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    28/39

    WATER PROOFING

    Water proofing in sunken

    portion of kitchen and

    bathroom WP in sunken portion at

    ground level

    WP in retaining wall

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    29/39

    WATER PROOFING IN GARDEN AREA

    For water proofing in garden area the soil is first leveled and

    then rammed to achieve the maximum density

    The PCC is then laid down mixed with tape Crete (a water

    proofing compound)

    After PCC the plaster of fibrous material is done. the bituminous sheets are laid by heating it with the welder. On

    those sheets the drainage pipes are laid down with suitable

    slope and these pipes are covered with geo-fabric sheets.

    Again the plaster is done. On the plaster the 40 mm aggregates

    are laid. On the aggregate the geo-fabric sheets are laid down on which

    the sand is placed & on the sand the soil ,along with fertilizers,

    is placed on which the gardening is done for the non tower area.

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    30/39

    WATER PROOFING IN GARDEN AREA

    Sandy soil

    PCC mixed with tape

    Crete (water proof

    compound)

    Texas (bitumen) sheet

    Drainage pipe

    40 mm aggregate

    Geo-fabric sheet

    Sand

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    31/39

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    32/39

    INTRODUCTION/BENEFITS

    Post-tensioning is a method of reinforcing (strengthening)

    concrete or other materials with high-strength steel strands or

    bars, typically referred to as tendons

    allows longer clear spans, thinner slabs

    lower overall building height for the same floor-to-floor height.

    allows a high degree of flexibility in the column layout, span

    lengths and ramp configurations

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    33/39

    POST TENSIONING

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    34/39

    PLACEMENT OF TENDONS

    Positioning and fixing of casting and block-outs to the edge formworkor construction joint formwork

    The support bars shall be prepared in advance.

    Lay tendons according to tendon layout in accordance with thedrawings.

    Fix tendons to correct profiles with support bars and chairs and the

    tendons are made with provisions for grouting using grout using groutvents and grout hoses

    Prepare installation report for every installation as per the enclosedformat.

    tolerance of tendon profiles is recommended as follows:

    **vertical: + 5 mm (at lowest and highest points)

    Horizontal: + 100 mm

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    35/39

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    36/39

    LOADS ON FALSEWORK

    Loads on Falsework are any combinations of

    the following:

    Dead loads,

    Imposed loads, Environmental loads,

    Incidental loads during erection and

    operation, and Lateral pressure.

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    37/39

    DIFFERENT LOAD DATA

    Self load shall be determined by either actual measurement or inaccordance with IS 875 (Part I) the unit weight of wet concreteincluding reinforcement shall be taken as 26 kN/m. However, inabsence of the data, load may be assumed as 500 N/M2 for thepurpose of initial calculations .

    Loads during constructional operation shall constitute the imposedloads [see IS 875 (Part 2 ) Where allowance has only to be made foraccess and inspection purposes, a loading of 750 N/m should beadequate

    The lateral pressure due to fresh concrete depends on the temperatureof concrete as placed, the rate of placing of concrete and the concretemix proportion

    Wind loads should be taken for design in accordance with IS 875 (Part3 ) subject to a minimum horizontal load equal to 3 percent of thevertical loads at critical level.

    Snow loads should be assumed in accordance with IS 875(4) . Themaximum density of ice may be assumed to be 900 kg/m.

  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    38/39

    OUTPUT OF EXCEL SHEET(DOFW)

    http://localhost/var/www/apps/conversion/releases/formwork%20design/MAXIMUM%20PRESSURE%20FOR%20FORMWORK.xlshttp://localhost/var/www/apps/conversion/releases/formwork%20design/MAXIMUM%20PRESSURE%20FOR%20FORMWORK.xls
  • 7/31/2019 Cep-construction and Design of Multistorey Building by Abhimanyu Parida

    39/39

    End Note

    This presentation is for educational use can

    use this as part of reference material and it

    should not be used directly as your own

    presentation.

    For more such presentation log on to

    www.engineeringcivil.com

    http://www.engineeringcivil.com/http://www.engineeringcivil.com/