Central Reservoir Replacement Project Central Reservoir Replacement Project Community Meeting #2 February 13, 2018 Community Meeting #2 February 13, 2018

Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Central Reservoir Replacement

Project

Central Reservoir Replacement

Project

Community Meeting #2February 13, 2018

Community Meeting #2February 13, 2018

Page 2: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Project Team

• EBMUD– David Rehnstrom, P.E., Division Manager– Bill Maggiore, P.E., Senior Engineer– Aaron Hope, P.E., Project Manager– Laura Luong, Community Affairs

• ConsultantsESA, Specialty CEQA ConsultantsDillingham Associates, Landscape ArchitectureMuller & Caulfield, Architecture

2

Page 3: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Agenda

3

• EBMUD Background

• Schedule

• Project Purpose & Need

• Site Plan

• Landscape Design

• Visual Simulations

• Environmental Review

• Q & A

Page 4: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Central Reservoir Replacement Schedule

September 2017Community Meeting #1Community input on

landscape design

February 2018Community Meeting #2Final Design PresentedCommunity input on

EIR scope

2018Start Environmental

Review Process

Summer 2019Draft EIR

Summer 2019EIR Public Meeting

Early 2020Final EIR & Project

Approval

2020-2023Engineering Design

2024-2025Demolition

2026-2029 Construction

4

Page 5: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

EBMUD Water System

167 Reservoirs

136 Pumping plants

4,200 mi. pipelines

Page 6: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

EBMUD Water System

Central Reservoir

Page 7: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

7

Project Purpose and Need

Page 8: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

8

• EBMUD’s largest distribution reservoir• 153 Million Gallons• 27 acre site• Provides emergency and operational storage to

about 52,000 of the District’s 382,000 meters• Open cut reservoir will be replaced with three

17 million gallon reservoirs

Page 9: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

9

Page 10: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Existing Cross Section of Central Reservoir

Auxiliary Dam Main DamI 580

25th Ave E. 29th St.

Page 11: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Existing Cross Section of Central Reservoir

Three 17 million gallon tanks

(third one not shown in section)

Page 12: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Why are we Replacing the Reservoir?

• The reservoir has reached the end of its useful life• Reduce water loss through the liner• Resize to meet existing & future demands• Improve water distribution system

Page 13: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

13

Site Plan

Page 14: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Conceptual Site Plan

14

Ardley Ave

25th AveE. 29th St

Central ReservoirRecreation Area

Three 17 Million Gallon Concrete Tanks

Page 15: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Conceptual Site Plan

15

Ardley Ave

25th AveE. 29th St

Central ReservoirRecreation Area

Page 16: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Conceptual Site Plan

16

Ardley Ave

25th AveE. 29th St

Central ReservoirRecreation Area

Vault Structure

Central Rate Control Station

Page 17: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Conceptual Site Plan

17

Ardley Ave

25th AveE. 29th St

Central ReservoirRecreation Area

Demo Material Storage Building

Page 18: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Conceptual Site Plan

18

Ardley Ave

25th AveE. 29th St

Central ReservoirRecreation Area

Access Roads

Page 19: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Conceptual Site Plan

19

Ardley Ave

25th AveE. 29th St

Central ReservoirRecreation Area

Page 20: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

20

Landscape Design

Page 21: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Comments on September 2017 Conceptual Designs

• Improve screening• Reduce distance between fence and

sidewalk• Murals• Access through the site

21

Page 22: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Final Site Plan

23

Page 23: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Final Site Plan

24

Page 24: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Final Site Plan

25

/ / / / / / / / / / /

Page 25: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Final Site Plan

26

Page 26: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

28

Visual Simulations

Page 27: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

29

Viewpoint 1

Viewpoint 2

Viewpoint 3

Viewpoint 4

Viewpoint 5

Page 28: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

30

Viewpoint 1

Page 29: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Viewpoint 1: Ardley Near Bridge

31

Page 30: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

September Meeting10-Year Simulation

32

Page 31: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

New 10-Year Simulation

33

Page 32: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

New 5-Year Simulation

34

Page 33: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

35

Viewpoint 2

Page 34: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Viewpoint 2: Ardley at E. 32nd St

36

Page 35: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

September Meeting10-Year Simulation

37

Page 36: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

New 10-Year Simulation

38

Page 37: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

New 5-Year Simulation

39

Page 38: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

40

Viewpoint 3

Page 39: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Viewpoint 3: Ardley & 23rd Ave

41

Page 40: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

September Meeting10-Year Simulation

42

Page 41: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

New 10-Year Simulation

43

Page 42: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

New 5-Year Simulation

44

Page 43: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

45Viewpoint 4

Page 44: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Viewpoint 4: 25th Ave & E. 29th St.

46

Page 45: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

September Meeting10-Year Simulation

47

Page 46: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

New 10-Year Simulation

48

Page 47: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

New 5-Year Simulation

49

Page 48: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

50

Viewpoint 5

Page 49: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Viewpoint 5: Redwood Day School

51

Page 50: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

September Meeting Simulation

52

Page 51: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

New Simulation

53

Page 52: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Plant Palette - Trees

Big-leaf Maple California Buckeye Elderberry

Valley OakCanyon Live Oak Coast Live Oak

Ginkgo

Page 53: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Plant Palette - Shrubs

Edmunds Manzanita

Wayside Manzanita Manzanita

McMinn Manzanita

Pajaro Manzanita

Skylark Ceanothus

Joyce Coulter Ceanothus

Page 54: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

56

Next Steps

Page 55: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

What is an EIR?

• Purpose: – To inform the public of the environmental

consequences of projects

• EIR is required: – When there is potential that a project may

have significant impacts

57

Page 56: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

EIR Analysis of Impacts

58

Environmental ResourceCategory

Less than Significant

Less than Significant

with Mitigation

Significant and Unavoidable

AestheticsAir QualityBiologicalCulturalGeologyGreenhouse GasesHazardsHydrologyNoiseTraffic

To be analyzedin the EIR

Page 57: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Central Reservoir Next Steps

59

• Start Environmental Review Process• Draft EIR Summer 2019• EIR Public Meeting

• Final EIR & Project Approval• Early 2020

• Engineering Design• 2020-2023

• Demolition & Construction• 2024-2029

Page 58: Central Reservoir Replacement Project · Central Reservoir Replacement Schedule September 2017 Community Meeting #1 ... 2018 Start Environmental Review Process Summer 2019 Draft EIR

Thank You

For comments or questions

[email protected]/central

Laura Luong, EBMUD375 11th Street,

MS 802, Oakland, CA 94607