Upload
others
View
9
Download
0
Embed Size (px)
Citation preview
Central Kitchen Stakeholder Meeting
June 7, 2017Hiram Johnson Cafeteria6879 14th Avenue
Central Kitchen Stakeholder Meeting
Welcome and Introductions Project Scope / Central Kitchen Project Schedule Conceptual Design / Planning Options Community Input Session Additional Topic Development Breakout Discussion / Input / Priorities Dot Polling Exercise Next Steps
Welcome and Introductions
Jessie Ryan1st Vice President, Board of EducationCo-Chair, Central Kitchen Taskforce
José L. BandaSuperintendent
Central Kitchen Stakeholder Meeting
Project Scope / Central Kitchen Project Schedule Conceptual Design / Planning Options Community Input Session Additional Topic Development Breakout Discussion / Input / Priorities Dot Polling Exercise Next Steps
San Joaquin Street
Redding Ave SiteWarehouseNutrition ServicesPrint ShopGroundsTransportationPurchasingLibrary Services10.2 Acres
Red
din
g A
ven
ue
Overall Project Scope / Central Kitchen
• Kitchen Adjacent to Warehouse
• Transportation Relocated
• New Parking for all functions
• Storm water Treatment
• Community Garden
• CTE Opportunity
Overall Project Scope / Central Kitchen
Programming Phase April – May ‘17
CEQA, CDE, DTSC Evaluations May ‘17
Design Process (P/SD/DD/CD) June ‘17 – June ‘18
Permitting July ‘18 – Jan ‘19
Bidding Jan – April ‘19
Phase 1 Construction (San Joaquin) May – Dec ‘19
Phase 2 Construction (Redding) Jan ‘20 – June ‘21
Schedule
Conceptual Design / Planning Process
• Site Assessment• Bldg Assessment• Context• Space Inventory• Space Needs• Program Developed• Adjacencies• Relationships• Infrastructure• Cost • Prioritization• Design
Community Input Session
Central Kitchen Transportation Community Questions / Concerns Sustainability Architectural Design Others?
Dot Polling
Next Steps
Review / Analyze Input Document Findings Schedule Follow-up Meetings Finalize Program Begin Design Continue Community Dialogue
Central Kitchen Stakeholder Meeting
June 7, 2017Hiram Johnson Cafeteria6879 14th Avenue