Upload
nathaniel-compton
View
220
Download
1
Embed Size (px)
Citation preview
Central California Clean Energy Transmission Project
TSS Meeting #146Seattle, WA
August 15-17, 2007
2
Approach to Transmission Development
• Encourage resources to connect to areas where transmission capacity is available
• Focus on multi-purpose projects• Use existing R/W before developing new R/W• Focus on implementing smaller transmission projects
that can be placed in service quickly• Develop larger transmission projects • Maintain flexibility in developing transmission plans to
deliver maximum benefits to customers in an environmentally responsible manner
• Develop a California Sub-regional Transmission Plan through regional and sub-regional collaboration
3
Possible Future Transmission Corridors in California
Wind
Geo
Geo
Geo
Geo
Geo
Geo
Wind
Solar
Solar
Wind
Wind
SolarWind-- Major Load Centers in California
4
• Project Scope– Construct ~ 140 - 180 miles of new
500 kV Double Circuit Tower Line from Midway to a new Substation east of Fresno on new R/W
• Project Objective:– Facilitate efficient management of
renewables to meet CA 20% RPS Goal
– Increase Path 15 transfer capability by ~1,250 MW
– Increase transfer of base load & as available renewable resources from S CA to N CA
– Increase utilization of the Helms PSP to enhance the value of off-peak generation
– Increase reliability to Yosemite/Fresno area
– Reduce Fresno Area LCR• Expected Operation Date: Dec. 2012• Defers need for Gates-Gregg
indefinitely
Central California Clean Energy Transmission Project
Central California Clean Energy Transmission Project
To Southern California Edison
Company
Pacific Gas & Electric Company
Gregg
Panoche
Helms PSP
Gates
San Luis
Los Banos
Moss Landing
Morro Bay
Diablo Canyon
Midway
Bellota
Tesla
Kings River
McCall
Arco
PATH 15
PATH 26
New Sub E2
5
Potential Routes
C3ET Project – East Route
To Southern California Edison
Company
Pacific Gas & Electric Company
Gregg
PanocheHelms PSP
Gates
San Luis
Los Banos
Moss Landing
Morro Bay
Diablo Canyon
Midway
Bellota
Tesla
Kings RiverMcCall
PATH 15
PATH 26
New Sub E2
C3ET Project – West Route
Arco
East Route:• ~140 miles• Runs along the foothills – less
impacts on farm lands, avoid urban areas
• Potential use of SCE access roads
• Lower probability of multiple 500 kV line outages than West Route
– No 500 kV line crossing
West Route:• ~180 miles• Crosses farm lands and urban
areas• Lower probability of multiple 500
kV line outages– Crosses Four existing 500 kV lines
6
Project Description
• Expected Operation Date - December 2012:– Build a 500 kV double circuit tower line (about 140 – 180 miles
in length) with two 2,300 kcmil AAL conductors (bundled), with both circuits strung.
– Build a new 500 kV Substation (E2) with one 500/230 kV 1,120 MVA transformer bank,
– Loop the Helms – Gregg #1 and #2 230 kV lines into the E2 Substation,
– Build two 500 kV line terminations each at Midway and E2– Install additional voltage supports in the Fresno area. The
amount and location of the voltage support will be evaluated in a voltage stability study.
7
Project Implementation Plan
Phase I:– Prepare PEA pursuant to the CEQA and the CPUC
permitting requirements.– Perform the necessary engineering and design work
required to prepare the PEA.– Coordinate WECC Regional Planning and Path Rating
Process with external interested parties.
Phase II:– File an application in December 2008 with the CPUC for a
CPCN.
Phase III:– Assuming the CPUC grants a CPCN by December 2009,
land acquisition and project construction would start immediately to achieve a December 2012 completion date.
8
Potential Future Expansion
C3ET Project must be designed and sited to allow for rational, cost-effective future expansion of the 500 kV grid as required by future load growth and RPS procurement
• Expected Operation Date ~ 2020:– Install a second 500/230 kV 1,120 MVA transformer bank at E2– Install additional voltage supports in the Fresno area. The
amount and location of the voltage support will be evaluated in a voltage stability study.
• Other expansion possibilities:– Potential expansion north of E2 to San Francisco Bay Area and
Sacramental Valley– Potential expansion south of Midway to Southern California and
Desert SW
9
• Potential projects south of Tesla -support – renewables in the southern portion of the
PG&E service territory– Renewables imported from the South– Load growth in Fresno and SF Bay Area
• Projects north of Tesla - support based on Option CA2 (other options possible)
– Renewables in the northern portion of the PG&E service territory
– Renewables imported from the NW and Canada at proposed Raven Substation
– Load growth in Sacramento Valley and SF Bay Area
Possible Long-Term Transmission Expansion
Path 66To NW and
Canada
LakeTahoe
MalinCaptain Jack
Gates
Los Banos
DiabloMidway
COTP
Tracy
Bonneville Power Administrative (BPA)
Sierra Pacific (SPP)
Southern California Edison (SCE)Vincent
Tesla
Metcalf
Moss Landing
Path 15
Also includes 4-230 kV lines terminated at Gates
Path 26
Helms
Gregg
Bellota
Tehachapi Area
Raven Sub
Table Mt.
140 mi
60 mi
40 mi 105 miles
Raven New Sub
125 mi
C3ET Project
Elverta
• Connection to Potential projects south of Midway - support– renewables in the southern CA
and Desert SW– Load growth in S CA and
seasonal exchange
10
Questions?