Center Grove High School
Addition & Remodeling
Project Update
July 21, 2008
Phase 1 Complete
Cafeteria
Main
Entry
Small
Learning
Communities
Art &
Music
Addition
Administration
Guidance
Nurse
PE /Health
Center
Special
Services
Existing Auditorium
Existing
Media
Center
Existing
Vandermeer Gym
& Natatorium
Reference: April 28, 2008
Additional
Core
Academic
SpaceExpanded
Cafeteria
Seating
Future
Natatorium
Weight
Training
Relocation
Expanded Music Department
Future AdditionsReference: April 28, 2008
Recent Activities
• Schematic Design– Optimizing use of existing building
– Integration of Level Changes
– Coordination of Site Design
– Refinement of Design Elements
– Understanding Phasing Implications
• Schematic Design Estimate– A Work-in-Progress
Phase I: Existing Building
Existing
Media
Center
Existing
Academic
Departments
Existing
Art & Music
Spaces
Administration
Cafeteria
Existing
Auditorium
Phase I: Existing Building
Existing
Media
Center
Existing
Academic
Departments
1953
Addition
Existing
Art & Music
SpacesExisting
NatatoriumHall of
Excellence
Administration
Cafeteria
Existing
Vandermeer
Gym
Existing
Auditorium
Phase I: Expansion – New East/West Concourse
Existing
Media
Center
Existing
Academic
Departments
1953
Addition
Existing
Art & Music
SpacesHall of
Excellence
Administration
Cafeteria
Existing
Natatorium
Existing
Vandermeer
Gym New
East / West
Concourse
Existing
Auditorium
Existing
Media
Center
Existing
Academic
Departments
1953
Addition
Existing
Art & Music
SpacesHall of
Excellence
Administration
Cafeteria
Existing
Natatorium
Existing
Vandermeer
Gym New
East / West
Concourse
Phase I: Demolish 1953 Addition
Existing
Auditorium
Existing
Media
Center
Existing
Academic
Departments
Existing
Art & Music
SpacesHall of
Excellence
Administration
Cafeteria
Existing
Natatorium
Existing
Vandermeer
Gym New
East / West
Concourse
Phase I: Addition & Renovation: New North/South Concourse
New
North / South
Concourse
Existing
Auditorium
Existing
Media
Center
Existing
Academic
Departments
Existing
Art & Music
SpacesHall of
Excellence
Existing
Natatorium
Existing
Vandermeer
Gym New
East / West
Concourse
Phase I: Main Level: Cafeteria & Community PE Center
New
North / South
Concourse
Nutritional
Services
New
PE / Health
Center
Kitchen
Serving Dining
Existing
Auditorium
Existing
Media
Center
Existing
Academic
Departments
Existing
Art & Music
SpacesHall of
Excellence
Existing
Natatorium
Existing
Vandermeer
Gym
Phase I: Upper Level: Main Entry & Administration
New
North / South
Concourse
Nutritional
Services
New
PE / Health
Center
Visitor Parking
and
Main Entry
Administration
Guidance
Health
Existing
Auditorium
Existing
Media
Center
Existing
Academic
Departments
Existing
Art & Music
SpacesHall of
Excellence
Existing
Natatorium
Existing
Vandermeer
Gym
Phase I: Academic Additions
New
North / South
Concourse
Nutritional
Services
Visitor Parking
and
Main Entry
Administration
Guidance
Health
Art & Music
Addition
New
Tech High &
Business SLC
Special
Services
New
PE / Health
Center
Existing
Auditorium
Existing
Media
Center
Existing
Academic
Departments
Existing
Auditorium
Existing
Art & Music
SpacesHall of
Excellence
Existing
Natatorium
Existing
Vandermeer
Gym
Phase I: Academic Remodeling (Phase I Project Completed)
New
North / South
Concourse
Nutritional
Services
Visitor Parking
and
Main Entry
Administration
Guidance
Health
Art & Music
Addition
New
Tech High &
Business SLC
Special
Services
New
PE / Health
Center
Small Learning Communities
Traditional
Humanities
Health
STEM
Early College
Future Phases
Existing
Media
Center
Existing
Art & Music
Spaces
Existing
Vandermeer
Gym
Relocated
Weight TrainingHall of
Excellence
New
Natatorium
New
Technology
High SLC
Academy
Of Business
Addition
New
East / West
Concourse
New
North / South
Concourse
Special
Services
Nutritional
Services
Visitor Parking
and
Main Entry
Administration
Guidance
Health
New
PE / Health
Center
Art & Music
AdditionExisting
Auditorium
Small Learning Communities
Traditional
Humanities
Health
STEM
Early College
Music Expansion
Example: Current Status of Design Detail
Next Steps
• July – August– Complete Schematic Design Estimate
– Building Level Design Review
– Form Final Scope & Budget Options &
Recommendation
• September - October– Board Work Session
– Determine Final Scope & Budget to be presented
in a Public Hearing
Thank You.